WisDOT contract 20260414019 bid tabulation
Wisconsin Rapids - Plover; Biron/Plover Xing Approach Repairs (STH 054, Wood County Wisconsin Rapids - Biron/Plover Xing Approach Repairs). Let by Wisconsin DOT on April 14, 2026, Wood. 7 bids received; low bid $341,137 by Chippewa Concrete Services, Inc..
- Owner
- Wisconsin DOT
- Letting
- 14 APR 2026
- Pay items
- 52
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Chippewa Concrete Services, Inc. | $341,137 | Low |
| 2 | Relyco Plus, LLC | $403,937 | +18% |
| 3 | Norcon Corporation | $462,200 | +35% |
| 4 | Highway Landscapers, Inc. | $465,034 | +36% |
| 5 | Pember Companies, Inc. | $479,377 | +41% |
| 6 | Earth, Inc. | $492,919 | +44% |
| 7 | Integrity Grading and Excavating, Inc. | $512,630 | +50% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Chippewa Concrete Services, Inc. | 2. Relyco Plus, LLC | 3. Norcon Corporation | 4. Highway Landscapers, Inc. | 5. Pember Companies, Inc. | 6. Earth, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete pavement (204.0100) | SY | 320 | $6.46 | $3.00 | $34.75 | $30.00 | $20.90 | $22.50 |
| 2 | Removing curb & gutter (204.0150) | LF | 615 | $8.16 | $7.89 | $17.50 | $16.00 | $4.45 | $12.50 |
| 3 | Removing concrete sidewalk (204.0155) | SY | 25 | $20.44 | $9.00 | $46.00 | $25.00 | $13.75 | $26.50 |
| 4 | Excavation common (205.0100) | CY | 650 | $18.28 | $46.27 | $63.50 | $35.00 | $47.10 | $26.50 |
| 5 | Finishing roadway (project) 01. 1520-01-61 (213.0100) | EACH | 1 | $4,599.00 | $3,000.00 | $1,200.00 | $500.00 | $500.00 | $1,500.00 |
| 6 | Base aggregate dense 3/4-inch (305.0110) | TON | 110 | $33.91 | $45.15 | $67.90 | $60.00 | $32.50 | $46.00 |
| 7 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 880 | $22.83 | $18.90 | $49.00 | $16.00 | $28.85 | $35.00 |
| 8 | Select crushed material (312.0110) | TON | 930 | $31.43 | $23.50 | $50.80 | $18.00 | $33.70 | $34.00 |
| 9 | Tack coat (455.0605) | GAL | 65 | $17.23 | $16.86 | $16.86 | $16.86 | $17.90 | $18.00 |
| 10 | Asphaltic surface (465.0105) | TON | 410 | $189.83 | $185.74 | $185.74 | $185.74 | $227.80 | $210.00 |
| 11 | Concrete curb & gutter 30-inch type A (601.0409) | LF | 40 | $61.56 | $60.23 | $96.00 | $35.00 | $46.40 | $65.00 |
| 12 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 675 | $61.56 | $60.23 | $71.00 | $35.00 | $46.00 | $63.00 |
| 13 | Concrete sidewalk 4-inch (602.0405) | SF | 720 | $23.12 | $23.62 | $19.50 | $20.00 | $7.10 | $25.00 |
| 14 | Concrete sidewalk 6-inch (602.0415) | SF | 100 | $24.17 | $24.65 | $23.50 | $30.00 | $9.75 | $27.00 |
| 15 | Curb ramp detectable warning field natural patina (602.0515) | SF | 40 | $61.68 | $60.35 | $59.90 | $60.00 | $60.00 | $65.00 |
| 16 | Maintenance and repair of haul roads (project) 01. 1520-01-61 (618.0100) | EACH | 1 | $1,022.00 | $0.01 | $800.00 | $250.00 | $500.00 | $100.00 |
| 17 | Mobilization (619.1000) | EACH | 1 | $35,566 | $94,500 | $63,951 | $168,000 | $153,700 | $120,000 |
| 18 | Concrete median sloped nose (620.0300) | SF | 400 | $24.60 | $24.07 | $19.75 | $30.00 | $10.50 | $40.00 |
| 19 | Water (624.0100) | MGAL | 10 | $102.20 | $0.01 | $14.00 | $10.00 | $125.00 | $50.00 |
| 20 | Topsoil (625.0100) | SY | 450 | $8.05 | $17.62 | $21.00 | $18.00 | $14.40 | $10.00 |
| 21 | Silt fence (628.1504) | LF | 134 | $4.60 | $5.00 | $4.00 | $4.00 | $4.15 | $10.00 |
| 22 | Silt fence maintenance (628.1520) | LF | 67 | $0.10 | $0.01 | $0.01 | $1.00 | $0.10 | $1.00 |
| 23 | Mobilizations erosion control (628.1905) | EACH | 2 | $102.20 | $0.01 | $200.00 | $1,000.00 | $300.00 | $350.00 |
| 24 | Mobilizations emergency erosion control (628.1910) | EACH | 2 | $102.20 | $0.01 | $200.00 | $1.00 | $300.00 | $100.00 |
| 25 | Erosion mat urban class I type B (628.2008) | SY | 450 | $2.56 | $3.50 | $2.29 | $5.00 | $3.50 | $5.00 |
| 26 | Inlet protection type C (628.7015) | EACH | 17 | $70.01 | $100.00 | $90.00 | $100.00 | $110.00 | $150.00 |
| 27 | Fertilizer type B (629.0210) | CWT | 0.30 | $102.20 | $250.00 | $110.00 | $500.00 | $550.00 | $500.00 |
| 28 | Seeding mixture no. 40 (630.0140) | LB | 8 | $10.22 | $50.00 | $25.00 | $40.00 | $38.00 | $50.00 |
| 29 | Seed water (630.0500) | MGAL | 11 | $51.10 | $10.00 | $25.00 | $125.00 | $200.00 | $50.00 |
| 30 | Field office type C (642.5201) | EACH | 1 | $7,665.00 | $10,000 | $7,800.00 | $1.00 | $10,000 | $12,000 |
| 31 | Traffic control barricades type III (643.0420) | DAY | 120 | $2.04 | $2.00 | $2.00 | $2.00 | $2.10 | $2.20 |
| 32 | Traffic control signs (643.0900) | DAY | 2,510 | $0.26 | $0.25 | $0.25 | $0.25 | $0.25 | $0.30 |
| 33 | Traffic control covering signs type I (643.0910) | EACH | 5 | $255.50 | $250.00 | $250.00 | $250.00 | $265.00 | $260.00 |
| 34 | Traffic control covering signs type II (643.0920) | EACH | 6 | $102.20 | $100.00 | $100.00 | $100.00 | $107.00 | $110.00 |
| 35 | Traffic control signs fixed message (643.1000) | SF | 72 | $15.33 | $15.00 | $15.00 | $15.00 | $16.00 | $16.00 |
| 36 | Traffic control (643.5000) | EACH | 1 | $18,692 | $18,290 | $18,290 | $18,290 | $23,000 | $26,000 |
| 37 | Geotextile type sas (645.0140) | SY | 1,250 | $4.60 | $2.50 | $2.25 | $4.00 | $2.90 | $5.00 |
| 38 | Marking line epoxy 6-inch (646.2020) | LF | 970 | $5.38 | $0.53 | $5.26 | $0.53 | $5.60 | $2.00 |
| 39 | Marking railroad crossing epoxy (646.5320) | EACH | 8 | $1,226.40 | $2,106.93 | $1,200.00 | $2,106.93 | $1,275.00 | $1,800.00 |
| 40 | Marking curb epoxy (646.8120) | LF | 20 | $16.20 | $8.50 | $15.85 | $8.50 | $16.80 | $25.00 |
| 41 | Marking island nose epoxy (646.8220) | EACH | 1 | $357.70 | $319.18 | $350.00 | $319.18 | $370.00 | $450.00 |
| 42 | Marking removal special marking (646.9300) | EACH | 24 | $76.65 | $75.00 | $75.00 | $75.00 | $79.55 | $100.00 |
| 43 | Construction staking subgrade (650.4500) | LF | 420 | $0.77 | $0.01 | $0.75 | $1.00 | $0.50 | $3.00 |
| 44 | Construction staking base (650.5000) | LF | 420 | $1.28 | $0.01 | $1.25 | $2.00 | $0.50 | $3.00 |
| 45 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 675 | $1.79 | $1.75 | $1.75 | $3.00 | $2.00 | $3.50 |
| 46 | Construction staking resurfacing reference (650.8000) | LF | 420 | $0.15 | $0.15 | $0.15 | $0.10 | $0.15 | $0.50 |
| 47 | Construction staking curb ramps (650.9000) | EACH | 4 | $143.08 | $140.00 | $140.00 | $200.00 | $148.50 | $250.00 |
| 48 | Construction staking sidewalk (project) 01. 1520-01-61 (650.9500) | EACH | 1 | $1,533.00 | $1,500.00 | $1,500.00 | $2,000.00 | $1,600.00 | $2,500.00 |
| 49 | Construction staking supplemental control (project) 01. 1520-01-61 (650.9911) | EACH | 1 | $1,022.00 | $1,000.00 | $1,000.00 | $1,500.00 | $1,000.00 | $2,000.00 |
| 50 | Sawing asphalt (690.0150) | LF | 50 | $2.81 | $4.00 | $2.00 | $10.00 | $3.90 | $6.00 |
| 51 | Sawing concrete (690.0250) | LF | 300 | $2.81 | $4.00 | $3.00 | $10.00 | $5.45 | $8.00 |
| 52 | Special 01. reconstructing sanitary manholes (SPV.0060) | EACH | 1 | $4,599.00 | $2,000.00 | $8,400.00 | $7,500.00 | $2,500.00 | $4,800.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of April 14, 2026. Compiled by Mirage Metrics.