Earth, Inc.: WisDOT bid record
Earth, Inc. submitted 21 bids on Wisconsin DOT contracts in the data, from 12 APR 2022 to 13 OCT 2026, and was the low bidder on 3 of them (14%). When it was not low, its total sat a median +9.0% above the low bid.
- Owner
- Wisconsin DOT
- Low bid volume
- $9,828,071
- Latest bid
- 13 OCT 2026
- Data through
- 10 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 2 | 0 | 0% |
| 2023 | 2 | 1 | 50% |
| 2024 | 3 | 0 | 0% |
| 2025 | 8 | 1 | 13% |
| 2026 | 6 | 1 | 17% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| Wood | 8 | 2 | 25% |
| Marathon | 6 | 0 | 0% |
| Clark | 3 | 1 | 33% |
| Portage | 2 | 0 | 0% |
| Monroe | 1 | 0 | 0% |
| Adams | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| On-the-job training graduate at $5.00/HR | ASP.1T0G | HRS | 16 | 16 (100%) | $5.00 | $5.00 |
| On-the-job training apprentice at $5.00/HR | ASP.1T0A | HRS | 16 | 16 (100%) | $5.00 | $5.00 |
| Silt fence maintenance | 628.1520 | LF | 20 | 13 (65%) | $0.01 | $0.02 |
| Incentive density HMA pavement | 460.2000 | DOL | 13 | 13 (100%) | $1.00 | $1.00 |
| Incentive iri ride | 740.0440 | DOL | 13 | 13 (100%) | $1.00 | $1.00 |
| Mobilizations emergency erosion control | 628.1910 | EACH | 20 | 11 (55%) | $200.00 | $150.00 |
| Mobilizations erosion control | 628.1905 | EACH | 21 | 10 (48%) | $300.00 | $233.00 |
| Water | 624.0100 | MGAL | 19 | 9 (47%) | $40.00 | $32.00 |
| Tack coat | 455.0605 | GAL | 18 | 9 (50%) | $5.50 | $3.85 |
| Culvert pipe checks | 628.7555 | EACH | 17 | 9 (53%) | $17.00 | $20.00 |
| Construction staking base | 650.5000 | LF | 16 | 8 (50%) | $0.93 | $0.80 |
| Mobilization | 619.1000 | EACH | 21 | 7 (33%) | $150,000 | $136,364 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Integrity Grading and Excavating, Inc. | 10 | 3 of 10 |
| James Peterson Sons, Inc. | 8 | 4 of 8 |
| Haas Sons, Inc. | 8 | 4 of 8 |
| A-1 Excavating LLC | 8 | 2 of 8 |
| Gerke Excavating Inc | 7 | 3 of 7 |
| American Asphalt of Wisconsin | 6 | 6 of 6 |
| Hoffman Construction Company | 5 | 4 of 5 |
| McCabe Construction, Inc. | 4 | 1 of 4 |
| Mashuda Contractors, Inc. | 4 | 3 of 4 |
| Michels Road & Stone, Inc. | 3 | 2 of 3 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 13 OCT 2026 | 20261013016 | Adams | Adams - Wisconsin Rapids; STH 13/Apache Avenue Intersection (STH 013, Adams County Adams - Wisconsin Rapids; STH 13/Apache Avenue Intersecti | 3 of 4 | $428,361 | +12% |
| 11 AUG 2026 | 20260811017 | Marathon | Rudolph - Knowlton; Oak Hill Road to CTH Db (STH 034, Marathon County Rudolph - Knowlton) | 2 of 2 | $7,336,949 | +4.0% |
| 14 APR 2026 | 20260414019 | Wood | Wisconsin Rapids - Plover; Biron/Plover Xing Approach Repairs (STH 054, Wood County Wisconsin Rapids - Biron/Plover Xing Approach Repairs) | 6 of 7 | $492,919 | +44% |
| 10 MAR 2026 | 20260310025 | Wood | 1520-00-74 | 2 of 7 | $4,429,543 | +2.0% |
| 10 MAR 2026 | 20260310028 | Wood | V Biron, CTH U; Biron Drive South to Huffman Road (CTH U, Wood County V Biron, CTH U) | 1 of 6 | $6,235,820 | Low, 12% under the second |
| 13 JAN 2026 | 20260113007 | Monroe | T Christiana - T Portland (CTH Pc); Vernon Co Line to STH 33 (CTH PC, Monroe County T. Christiana - T. Portland (CTH PC)) | 8 of 8 | $8,173,151 | +27% |
| 09 DEC 2025 | 20251209032 | Marathon | V Marathon City, Main Street; CTH B to North Street (STH 107, Marathon County V Marathon City, Main Street; CTH B to North Street) | 2 of 2 | $1,397,532 | +8.0% |
| 11 NOV 2025 | 20251111022 | Marathon | V Spencer, East Willow Drive; S Lasalle St to S Monroe St (LOC STR, Marathon County V Spencer, East Willow Drive) | 3 of 3 | $634,338 | +15% |
| 11 NOV 2025 | 20251111023 | Portage | T Stockton, Standing Rocks Road; Custer Road to Town Line Road (LOC STR, Portage County T Stockton, Standing Rocks Road) | 2 of 4 | $1,454,209 | +10% |
| 11 NOV 2025 | 20251111024 | Wood | Wisconsin Rapids - Vesper; Town Hall Road to CTH Hh (CTH F, Wood County Wisconsin Rapids - Vesper) | 2 of 8 | $1,362,269 | +5.0% |
| 14 OCT 2025 | 20251014017 | Clark | Abbotsford - Medford; Porky Creek B-10-0250 & B-10-0251 (STH 013, Clark County Abbotsford - Medford) | 2 of 4 | $1,558,366 | 0.0% |
| 14 OCT 2025 | 20251014018 | Clark | Greenwood - Spencer; STH 73 to Helm Street (STH 098, Clark County Greenwood - Spencer) | 1 of 4 | $1,797,288 | Low, 3.0% under the second |
| 09 SEP 2025 | 20250909023 | Portage | Rudolph - Marshfield; 2nd Street North to CTH P (STH 013, Portage County Rudolph - Marshfield) | 4 of 4 | $9,042,719 | +8.0% |
| 11 MAR 2025 | 20250311036 | Marathon | STH 29 - STH 52; CTH N/CTH J Intersection (CTH N, Marathon County STH 29 - STH 52) | 3 of 4 | $327,148 | +28% |
| 10 DEC 2024 | 20241210024 | Wood | 6933-00-61 | 2 of 2 | $3,808,313 | +19% |
| 08 OCT 2024 | 20241008015 | Clark | Globe - East County Line; CTH K Intersection (CTH H, Clark County Globe - East County Line) | 3 of 10 | $1,030,488 | +1.0% |
| 13 FEB 2024 | 20240213031 | Marathon | C Wausau, Stewart Avenue; S 72nd Avenue to S 48th Avenue (LOC STR, Marathon County C Wausau, Stewart Avenue) | 5 of 5 | $8,208,055 | +16% |
| 12 SEP 2023 | 20230912009 | Wood | Necedah - Babcock; Juneau Co Line to STH 173 N (STH 080, Wood County Necedah - Babcock) | 2 of 4 | $5,359,821 | +4.0% |
| 09 MAY 2023 | 20230509021 | Wood | C Marshfield, S Lincoln Avenue; West 5th Street To Adler Road (LOC STR, Wood County City Marshfield, S Lincoln Ave) | 1 of 2 | $1,794,963 | Low, 51% under the second |
| 13 DEC 2022 | 20221213027 | Marathon | Abbotsford - Wausau; Cth E To Cth H, Eb (STH 029, Marathon County Abbotsford - Wausau) | 7 of 8 | $14,029,442 | +13% |
| 12 APR 2022 | 20220412026 | Wood | C Wisconsin Rapids, W Jackson St; W Riverview Exp To Jackson St Brdge (LOC STR, Wood County C Wisconsin Rapids, W Jackson St) | 3 of 3 | $4,077,480 | +7.0% |
How this record was read
WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
- Every bid counted here matched its published total to within one dollar; WisDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.