WisDOT contract 20261013016 bid tabulation
Adams - Wisconsin Rapids; STH 13/Apache Avenue Intersection (STH 013, Adams County Adams - Wisconsin Rapids; STH 13/Apache Avenue Intersection). Let by Wisconsin DOT on October 13, 2026, Adams. 4 bids received; low bid $382,740 by Hoffman Construction Company.
- Owner
- Wisconsin DOT
- Letting
- 13 OCT 2026
- Pay items
- 50
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Hoffman Construction Company | $382,740 | Low |
| 2 | S & N Incorporated | $391,743 | +2.0% |
| 3 | Earth, Inc. | $428,361 | +12% |
| 4 | James Peterson Sons, Inc. | $444,717 | +16% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Hoffman Construction Company | 2. S & N Incorporated | 3. Earth, Inc. | 4. James Peterson Sons, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Removing curb & gutter (204.0150) | LF | 67 | $20.00 | $10.00 | $20.00 | $25.00 |
| 2 | Removing (item description) 01. asphaltic flume (204.9060.S) | EACH | 1 | $500.00 | $250.00 | $1,000.00 | $750.00 |
| 3 | Excavation common (205.0100) | CY | 2,208 | $30.00 | $32.25 | $25.00 | $39.56 |
| 4 | Finishing roadway (project) 01. 6140-02-72 (213.0100) | EACH | 1 | $500.00 | $750.00 | $2,500.00 | $2,500.00 |
| 5 | Base aggregate dense 3/4-inch (305.0110) | TON | 81 | $80.00 | $38.50 | $38.00 | $55.12 |
| 6 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 2,210 | $35.00 | $27.21 | $24.70 | $29.63 |
| 7 | Tack coat (455.0605) | GAL | 144 | $10.40 | $10.40 | $12.00 | $10.40 |
| 8 | Incentive density HMA pavement (460.2000) | DOL | 450 | $1.00 | $1.00 | $1.00 | $1.00 |
| 9 | HMA pavement 4 MT 58-28 S (460.6224) | TON | 672 | $138.90 | $138.90 | $158.00 | $138.90 |
| 10 | Asphaltic surface temporary (465.0125) | TON | 29 | $230.82 | $230.82 | $300.00 | $230.82 |
| 11 | Asphaltic flumes (465.0315) | SY | 20 | $84.80 | $84.80 | $100.00 | $84.80 |
| 12 | Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557) | LF | 154 | $76.89 | $76.89 | $65.00 | $76.89 |
| 13 | Maintenance and repair of haul roads (project) 01. 6140-02-72 (618.0100) | EACH | 1 | $500.00 | $100.00 | $500.00 | $150.00 |
| 14 | Mobilization (619.1000) | EACH | 1 | $44,790 | $58,490 | $60,000 | $75,000 |
| 15 | Water (624.0100) | MGAL | 34 | $150.00 | $60.00 | $50.00 | $100.00 |
| 16 | Topsoil (625.0100) | SY | 2,652 | $2.00 | $4.95 | $5.00 | $8.33 |
| 17 | Mulching (627.0200) | SY | 2,076 | $0.75 | $0.75 | $1.00 | $0.75 |
| 18 | Silt fence (628.1504) | LF | 420 | $4.00 | $4.00 | $3.25 | $4.00 |
| 19 | Silt fence maintenance (628.1520) | LF | 420 | $0.01 | $0.01 | $0.10 | $0.01 |
| 20 | Mobilizations erosion control (628.1905) | EACH | 3 | $350.00 | $350.00 | $380.00 | $350.00 |
| 21 | Mobilizations emergency erosion control (628.1910) | EACH | 3 | $250.00 | $250.00 | $300.00 | $250.00 |
| 22 | Erosion mat urban class I type B (628.2008) | SY | 570 | $4.00 | $4.00 | $5.00 | $4.00 |
| 23 | Temporary ditch checks (628.7504) | LF | 30 | $9.50 | $9.50 | $15.00 | $9.50 |
| 24 | Fertilizer type A (629.0205) | CWT | 0.16 | $500.00 | $500.00 | $280.00 | $500.00 |
| 25 | Seeding mixture no. 40 (630.0140) | LB | 117 | $8.50 | $8.50 | $12.00 | $8.50 |
| 26 | Seed water (630.0500) | MGAL | 45 | $5.00 | $5.00 | $50.00 | $5.00 |
| 27 | Field office type B (642.5001) | EACH | 1 | $500.00 | $5,000.00 | $12,000 | $5,000.00 |
| 28 | Traffic control drums (643.0300) | DAY | 1,748 | $1.00 | $1.00 | $1.10 | $1.00 |
| 29 | Traffic control barricades type III (643.0420) | DAY | 288 | $2.00 | $2.00 | $2.25 | $2.00 |
| 30 | Traffic control warning lights type A (643.0705) | DAY | 144 | $0.25 | $0.25 | $0.35 | $0.25 |
| 31 | Traffic control warning lights type C (643.0715) | DAY | 240 | $0.35 | $0.35 | $0.45 | $0.35 |
| 32 | Traffic control signs (643.0900) | DAY | 442 | $3.50 | $3.50 | $3.60 | $3.50 |
| 33 | Traffic control signs fixed message (643.1000) | SF | 36 | $10.60 | $10.60 | $20.00 | $10.60 |
| 34 | Temporary marking line removable tape 6-inch (643.3180) | LF | 6,580 | $1.90 | $1.90 | $2.10 | $1.90 |
| 35 | Temporary marking stop line removable tape 18-inch (643.3850) | LF | 59 | $5.25 | $5.25 | $6.00 | $5.25 |
| 36 | Traffic control (643.5000) | EACH | 1 | $4,150.00 | $4,150.00 | $22,000 | $4,150.00 |
| 37 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 5,521 | $1.75 | $1.75 | $1.80 | $1.75 |
| 38 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 1,455 | $3.30 | $3.30 | $3.35 | $3.30 |
| 39 | Marking stop line epoxy 18-inch (646.6120) | LF | 50 | $15.00 | $15.00 | $20.00 | $15.00 |
| 40 | Marking chevron epoxy 12-inch (646.7320) | LF | 271 | $11.00 | $11.00 | $12.00 | $11.00 |
| 41 | Marking removal line 4-inch (646.9000) | LF | 4,898 | $0.40 | $0.40 | $0.45 | $0.40 |
| 42 | Construction staking subgrade (650.4500) | LF | 857 | $0.01 | $0.01 | $1.50 | $0.01 |
| 43 | Construction staking base (650.5000) | LF | 857 | $0.01 | $1.00 | $1.50 | $1.00 |
| 44 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 154 | $5.00 | $2.50 | $3.00 | $2.50 |
| 45 | Construction staking supplemental control (project) 01. 6140-02-72 (650.9911) | EACH | 1 | $750.00 | $1,200.00 | $5,000.00 | $1,200.00 |
| 46 | Construction staking slope stakes (650.9920) | LF | 857 | $0.01 | $1.30 | $1.50 | $1.30 |
| 47 | Public land survey monument verify and reset (680.0100) | EACH | 1 | $750.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 48 | Sawing asphalt (690.0150) | LF | 958 | $1.49 | $1.96 | $4.50 | $1.96 |
| 49 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 300 | $5.00 | $5.00 | $5.00 | $5.00 |
| 50 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 600 | $5.00 | $5.00 | $5.00 | $5.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of October 13, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.