WisDOT contract 20250909023 bid tabulation
Rudolph - Marshfield; 2nd Street North to CTH P (STH 013, Portage County Rudolph - Marshfield). Let by Wisconsin DOT on September 9, 2025, Portage. 4 bids received; low bid $8,382,897 by Mashuda Contractors, Inc..
- Owner
- Wisconsin DOT
- Letting
- 09 SEP 2025
- Pay items
- 128
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Mashuda Contractors, Inc. | $8,382,897 | Low |
| 2 | James Peterson Sons, Inc. | $8,808,484 | +5.0% |
| 3 | Integrity Grading and Excavating, Inc. | $8,817,126 | +5.0% |
| 4 | Earth, Inc. | $9,042,719 | +8.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Mashuda Contractors, Inc. | 2. James Peterson Sons, Inc. | 3. Integrity Grading and Excavating, Inc. | 4. Earth, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 133 | $764.88 | $800.00 | $764.88 | $720.00 |
| 2 | Clearing (201.0120) | ID | 144 | $21.10 | $25.00 | $21.10 | $15.00 |
| 3 | Grubbing (201.0205) | STA | 133 | $105.50 | $259.00 | $105.50 | $135.00 |
| 4 | Grubbing (201.0220) | ID | 144 | $5.28 | $25.00 | $5.28 | $10.00 |
| 5 | Removing small pipe culverts (203.0100) | EACH | 78 | $275.00 | $350.00 | $175.00 | $1,500.00 |
| 6 | Removing concrete pavement (204.0100) | SY | 110 | $15.00 | $20.00 | $9.00 | $40.00 |
| 7 | Removing asphaltic surface (204.0110) | SY | 6,110 | $2.00 | $2.42 | $2.35 | $8.00 |
| 8 | Removing guardrail (204.0165) | LF | 465 | $3.50 | $3.50 | $3.50 | $4.00 |
| 9 | Removing fence (204.0170) | LF | 2,160 | $1.75 | $1.75 | $1.75 | $3.50 |
| 10 | Removing (item description) 01. removing post (204.9060.S) | EACH | 30 | $50.00 | $50.00 | $50.00 | $100.00 |
| 11 | Excavation common (205.0100) | CY | 30,321 | $6.53 | $4.50 | $15.00 | $13.60 |
| 12 | Borrow (208.0100) | CY | 27,619 | $8.14 | $12.42 | $11.00 | $15.80 |
| 13 | Prepare foundation for asphaltic paving (project) 01. 6340-00-74 (211.0101) | EACH | 1 | $100.00 | $68,000 | $55,817 | $81,000 |
| 14 | Finishing roadway (project) 01. 6340-00-74 (213.0100) | EACH | 1 | $2,050.00 | $3,500.00 | $500.00 | $7,500.00 |
| 15 | Base aggregate dense 3/4-inch (305.0110) | TON | 18,020 | $24.69 | $23.56 | $24.50 | $23.55 |
| 16 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 53,600 | $23.70 | $19.60 | $19.00 | $19.34 |
| 17 | Select crushed material (312.0115) | CY | 172 | $70.00 | $100.00 | $75.00 | $70.00 |
| 18 | Pulverize and relay (325.0100) | SY | 109,200 | $1.24 | $1.51 | $0.89 | $1.69 |
| 19 | QMP pulverize and relay compaction (374.1020.S) | SY | 109,200 | $0.16 | $0.15 | $0.16 | $0.12 |
| 20 | Concrete pavement 6-inch (415.0060) | SY | 40 | $135.11 | $138.00 | $135.11 | $145.00 |
| 21 | Concrete pavement approach slab (415.0410) | SY | 80 | $320.31 | $359.00 | $320.31 | $330.00 |
| 22 | Tack coat (455.0605) | GAL | 20,630 | $3.40 | $3.40 | $3.40 | $3.40 |
| 23 | HMA percent within limits (PWL) test strip volumetrics (460.0105.S) | EACH | 2 | $4,500.00 | $4,500.00 | $4,500.00 | $5,000.00 |
| 24 | HMA percent within limits (PWL) test strip density (460.0110.S) | EACH | 3 | $4,500.00 | $4,500.00 | $4,500.00 | $5,000.00 |
| 25 | Incentive density PWL HMA pavement (460.2005) | DOL | 31,700 | $1.00 | $1.00 | $1.00 | $1.00 |
| 26 | Incentive density HMA pavement longitudinal joints (460.2007) | DOL | 20,140 | $1.00 | $1.00 | $1.00 | $1.00 |
| 27 | Incentive air voids HMA pavement (460.2010) | DOL | 40,280 | $1.00 | $1.00 | $1.00 | $1.00 |
| 28 | HMA pavement 3 MT 58-28 S (460.6223) | TON | 28,970 | $87.50 | $87.50 | $87.50 | $87.60 |
| 29 | HMA pavement 4 MT 58-28 S (460.6224) | TON | 11,360 | $92.30 | $92.30 | $92.30 | $92.40 |
| 30 | Asphaltic surface (465.0105) | TON | 990 | $147.15 | $147.15 | $147.15 | $148.00 |
| 31 | Asphaltic surface driveways and field entrances (465.0120) | TON | 111 | $221.00 | $221.00 | $221.00 | $225.00 |
| 32 | Asphaltic rumble strips, centerline (465.0560) | LF | 29,400 | $0.18 | $0.38 | $0.18 | $0.20 |
| 33 | Preparation decks type 1 (509.0301) | SY | 1 | $437.00 | $255.00 | $437.00 | $450.00 |
| 34 | Preparation decks type 2 (509.0302) | SY | 1 | $759.00 | $305.00 | $759.00 | $800.00 |
| 35 | Sawing pavement deck preparation areas (509.0310.S) | LF | 10 | $3.50 | $12.00 | $3.50 | $4.00 |
| 36 | Concrete surface repair (509.1500) | SF | 3 | $143.00 | $425.00 | $143.00 | $150.00 |
| 37 | Concrete masonry deck repair (509.2100.S) | CY | 1 | $3,500.00 | $2,500.00 | $3,500.00 | $3,800.00 |
| 38 | Polymer overlay (509.5100.S) | SY | 550 | $41.11 | $41.46 | $41.11 | $43.00 |
| 39 | Removing polymer overlay (structure) 01. B-49-0082 (509.9015.S) | SY | 550 | $23.68 | $20.60 | $16.55 | $18.00 |
| 40 | Apron endwalls for culvert pipe 18- inch (520.1018) | EACH | 60 | $435.00 | $330.06 | $700.00 | $410.00 |
| 41 | Apron endwalls for culvert pipe 24- inch (520.1024) | EACH | 42 | $528.00 | $468.88 | $774.00 | $550.00 |
| 42 | Culvert pipe class III-A non-metal 18-inch (520.3418) | LF | 1,260 | $55.00 | $53.19 | $60.00 | $98.00 |
| 43 | Culvert pipe class III-A non-metal 24-inch (520.3424) | LF | 992 | $71.50 | $74.47 | $73.15 | $112.00 |
| 44 | Culvert pipe class III-A non-metal 30-inch (520.3430) | LF | 254 | $97.25 | $64.45 | $83.00 | $130.00 |
| 45 | Apron endwalls for culvert pipe sloped side drains steel 30-inch 6 to 1 (521.1530) | EACH | 10 | $4,540.00 | $4,662.27 | $4,465.00 | $5,000.00 |
| 46 | Culvert pipe reinforced concrete class IV 24-inch (522.0424) | LF | 138 | $146.75 | $163.04 | $263.00 | $210.00 |
| 47 | Culvert pipe reinforced concrete class IV 30-inch (522.0430) | LF | 152 | $189.00 | $209.96 | $291.00 | $260.00 |
| 48 | Culvert pipe reinforced concrete class IV 36-inch (522.0436) | LF | 74 | $247.25 | $321.94 | $332.00 | $300.00 |
| 49 | Culvert pipe reinforced concrete class IV 42-inch (522.0442) | LF | 460 | $306.25 | $356.00 | $353.00 | $355.00 |
| 50 | Culvert pipe reinforced concrete class IV 48-inch (522.0448) | LF | 196 | $385.50 | $426.93 | $414.00 | $420.00 |
| 51 | Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024) | EACH | 6 | $1,331.00 | $1,235.61 | $1,820.00 | $1,400.00 |
| 52 | Apron endwalls for culvert pipe reinforced concrete 30-inch (522.1030) | EACH | 4 | $1,586.00 | $1,503.13 | $2,060.00 | $1,675.00 |
| 53 | Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036) | EACH | 2 | $2,270.00 | $2,241.85 | $3,250.00 | $2,425.00 |
| 54 | Apron endwalls for culvert pipe reinforced concrete 42-inch (522.1042) | EACH | 10 | $2,715.00 | $2,822.77 | $3,680.00 | $3,000.00 |
| 55 | Apron endwalls for culvert pipe reinforced concrete 48-inch (522.1048) | EACH | 4 | $3,058.00 | $3,525.02 | $3,973.00 | $3,500.00 |
| 56 | Culvert pipe reinforced concrete horizontal elliptical class HE-III 14X23-inch (522.2314) | LF | 122 | $144.50 | $237.50 | $144.00 | $235.00 |
| 57 | Culvert pipe reinforced concrete horizontal elliptical class HE-III 19X30-inch (522.2319) | LF | 60 | $169.50 | $291.35 | $163.00 | $264.00 |
| 58 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 14X23-inch (522.2614) | EACH | 6 | $1,182.00 | $1,095.33 | $1,940.00 | $1,375.00 |
| 59 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 19X30-inch (522.2619) | EACH | 4 | $1,420.00 | $1,344.09 | $2,150.00 | $1,680.00 |
| 60 | Riprap light (606.0100) | CY | 2 | $225.00 | $500.00 | $409.00 | $128.00 |
| 61 | Riprap medium (606.0200) | CY | 52 | $90.00 | $150.00 | $144.50 | $118.00 |
| 62 | Riprap heavy (606.0300) | CY | 92 | $85.00 | $150.00 | $144.50 | $116.00 |
| 63 | Storm sewer pipe reinforced concrete class IV 24-inch (608.0424) | LF | 68 | $142.50 | $152.68 | $102.50 | $180.00 |
| 64 | Manhole covers type J (611.0530) | EACH | 1 | $950.00 | $1,151.24 | $861.00 | $850.00 |
| 65 | Manholes 4-FT diameter (611.2004) | EACH | 1 | $3,207.00 | $3,198.67 | $3,900.00 | $3,800.00 |
| 66 | Guardrail mow strip emulsified asphalt (614.0397) | SY | 688 | $15.00 | $15.00 | $9.18 | $10.00 |
| 67 | MGS guardrail 3 (614.2300) | LF | 300 | $31.00 | $31.00 | $31.00 | $30.00 |
| 68 | MGS guardrail 3 K (614.2330) | LF | 1,100 | $38.00 | $38.00 | $38.00 | $40.00 |
| 69 | MGS thrie beam transition (614.2500) | LF | 157.60 | $89.00 | $89.00 | $89.00 | $95.00 |
| 70 | MGS guardrail terminal eat (614.2610) | EACH | 4 | $3,975.00 | $3,975.00 | $3,975.00 | $4,000.00 |
| 71 | Fence safety (616.0700.S) | LF | 410 | $4.50 | $4.50 | $4.50 | $5.00 |
| 72 | Maintenance and repair of haul roads (project) 01. 6340-00-74 (618.0100) | EACH | 1 | $100.00 | $1,250.00 | $500.00 | $10,000 |
| 73 | Mobilization (619.1000) | EACH | 1 | $422,397 | $498,168 | $287,000 | $300,000 |
| 74 | Landmark reference monuments (621.0100) | EACH | 52 | $105.77 | $105.77 | $105.77 | $113.00 |
| 75 | Water (624.0100) | MGAL | 2,022 | $30.00 | $46.00 | $43.50 | $30.00 |
| 76 | Topsoil (625.0100) | SY | 147,200 | $0.01 | $2.00 | $2.30 | $1.00 |
| 77 | Mulching (627.0200) | SY | 117,635 | $0.35 | $0.35 | $0.35 | $0.35 |
| 78 | Silt fence (628.1504) | LF | 21,250 | $1.80 | $1.80 | $1.80 | $1.85 |
| 79 | Silt fence maintenance (628.1520) | LF | 63,800 | $0.01 | $0.01 | $0.01 | $0.10 |
| 80 | Mobilizations erosion control (628.1905) | EACH | 20 | $100.00 | $100.00 | $100.00 | $150.00 |
| 81 | Mobilizations emergency erosion control (628.1910) | EACH | 6 | $100.00 | $100.00 | $100.00 | $200.00 |
| 82 | Erosion mat class I type B (628.2004) | SY | 35,580 | $1.00 | $1.00 | $1.00 | $1.10 |
| 83 | Erosion mat urban class I type B (628.2008) | SY | 19,340 | $1.55 | $1.55 | $1.55 | $1.60 |
| 84 | Soil stabilizer type B (628.6510) | ACRE | 0.28 | $1,500.00 | $1,500.00 | $1,500.00 | $1,000.00 |
| 85 | Temporary ditch checks (628.7504) | LF | 5,250 | $6.95 | $6.95 | $6.95 | $6.70 |
| 86 | Culvert pipe checks (628.7555) | EACH | 236 | $15.00 | $15.00 | $15.00 | $15.00 |
| 87 | Tracking pads (628.7560) | EACH | 3 | $3,000.00 | $3,000.00 | $1,000.00 | $1,500.00 |
| 88 | Rock bags (628.7570) | EACH | 856 | $15.00 | $15.00 | $15.00 | $15.00 |
| 89 | Fertilizer type B (629.0210) | CWT | 152 | $80.00 | $80.00 | $80.00 | $85.00 |
| 90 | Seeding mixture no. 30 (630.0130) | LB | 10,290 | $7.50 | $7.50 | $7.50 | $7.10 |
| 91 | Seeding temporary (630.0200) | LB | 6,500 | $3.25 | $3.25 | $3.25 | $2.00 |
| 92 | Seeding borrow pit (630.0300) | LB | 570 | $7.50 | $7.50 | $7.50 | $7.00 |
| 93 | Seed water (630.0500) | MGAL | 26,800 | $0.01 | $0.01 | $0.01 | $0.15 |
| 94 | Markers culvert end (633.5200) | EACH | 16 | $75.00 | $75.00 | $75.00 | $90.00 |
| 95 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 28 | $85.00 | $85.00 | $85.00 | $120.00 |
| 96 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 50 | $90.00 | $90.00 | $90.00 | $125.00 |
| 97 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 3 | $95.00 | $95.00 | $95.00 | $130.00 |
| 98 | Moving signs type II (638.2102) | EACH | 66 | $155.00 | $155.00 | $155.00 | $100.00 |
| 99 | Removing small sign supports (638.3000) | EACH | 81 | $30.00 | $30.00 | $30.00 | $50.00 |
| 100 | Field office type C (642.5201) | EACH | 1 | $12,000 | $18,000 | $20,000 | $10,000 |
| 101 | Traffic control drums (643.0300) | DAY | 12,025 | $0.40 | $0.40 | $0.40 | $0.45 |
| 102 | Traffic control barricades type III (643.0420) | DAY | 9,750 | $0.50 | $0.50 | $0.50 | $0.52 |
| 103 | Traffic control warning lights type A (643.0705) | DAY | 17,550 | $0.05 | $0.05 | $0.05 | $0.05 |
| 104 | Traffic control signs (643.0900) | DAY | 183,625 | $0.12 | $0.12 | $0.12 | $0.13 |
| 105 | Traffic control covering signs type I (643.0910) | EACH | 6 | $550.00 | $550.00 | $550.00 | $600.00 |
| 106 | Traffic control covering signs type II (643.0920) | EACH | 8 | $20.00 | $20.00 | $20.00 | $25.00 |
| 107 | Traffic control signs fixed message (643.1000) | SF | 30 | $10.90 | $10.90 | $10.90 | $12.00 |
| 108 | Traffic control (643.5000) | EACH | 1 | $3,401.00 | $3,401.00 | $3,401.00 | $5,000.00 |
| 109 | Geotextile type HR (645.0120) | SY | 287 | $6.05 | $10.00 | $2.30 | $5.00 |
| 110 | Geotextile type R (645.0130) | SY | 17 | $40.00 | $50.00 | $12.88 | $5.00 |
| 111 | Geotextile type sas (645.0140) | SY | 609 | $4.50 | $5.00 | $1.32 | $3.00 |
| 112 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 91,300 | $1.30 | $1.26 | $1.26 | $1.31 |
| 113 | Marking stop line epoxy 18-inch (646.6120) | LF | 45 | $20.00 | $15.80 | $15.80 | $22.00 |
| 114 | Locating no-passing zones (648.0100) | MI | 6.46 | $500.00 | $520.00 | $520.00 | $500.00 |
| 115 | Construction staking storm sewer (650.4000) | EACH | 3 | $66.67 | $66.67 | $66.67 | $250.00 |
| 116 | Construction staking base (650.5000) | LF | 34,109 | $0.51 | $0.51 | $0.51 | $0.51 |
| 117 | Construction staking pipe culverts (650.6000) | EACH | 72 | $69.44 | $69.44 | $69.44 | $110.00 |
| 118 | Construction staking concrete pavement (650.7000) | LF | 30 | $10.00 | $10.00 | $10.00 | $15.00 |
| 119 | Construction staking resurfacing reference (650.8000) | LF | 34,109 | $0.15 | $0.15 | $0.15 | $0.15 |
| 120 | Construction staking supplemental control (project) 01. 6340-00-74 (650.9911) | EACH | 1 | $7,884.00 | $6,500.00 | $6,500.00 | $8,000.00 |
| 121 | Construction staking slope stakes (650.9920) | LF | 34,109 | $0.47 | $0.47 | $0.47 | $0.50 |
| 122 | Sawing asphalt (690.0150) | LF | 2,047 | $1.80 | $1.80 | $1.80 | $2.80 |
| 123 | Incentive compressive strength concrete pavement (715.0720) | DOL | 500 | $1.00 | $1.00 | $1.00 | $1.00 |
| 124 | Incentive iri ride (740.0440) | DOL | 25,740 | $1.00 | $1.00 | $1.00 | $1.00 |
| 125 | Special 01. research and locate existing land parcel monuments (SPV.0060) | EACH | 41 | $43.90 | $43.90 | $43.90 | $48.00 |
| 126 | Special 02. verify and replace existing land parcel monuments (SPV.0060) | EACH | 41 | $31.71 | $31.71 | $31.71 | $35.00 |
| 127 | Special 03. reestablish section corner monuments (SPV.0060) | EACH | 13 | $153.85 | $153.85 | $153.85 | $160.00 |
| 128 | Special 04. mowing project ID 6340- 00-74 (SPV.0060) | EACH | 1 | $36,000 | $36,000 | $36,000 | $13,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of September 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.