WisDOT contract 20251111022 bid tabulation
V Spencer, East Willow Drive; S Lasalle St to S Monroe St (LOC STR, Marathon County V Spencer, East Willow Drive). Let by Wisconsin DOT on November 11, 2025, Marathon. 3 bids received; low bid $549,256 by American Asphalt of Wisconsin.
- Owner
- Wisconsin DOT
- Letting
- 11 NOV 2025
- Pay items
- 86
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | American Asphalt of Wisconsin | $549,256 | Low |
| 2 | Pember Companies, Inc. | $627,397 | +14% |
| 3 | Earth, Inc. | $634,338 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. American Asphalt of Wisconsin | 2. Pember Companies, Inc. | 3. Earth, Inc. |
|---|---|---|---|---|---|---|
| 1 | Removing concrete surface partial depth (204.0109.S) | SF | 1,744 | $1.65 | $2.30 | $8.50 |
| 2 | Removing asphaltic surface (204.0110) | SY | 6,228 | $4.66 | $5.35 | $7.50 |
| 3 | Removing asphaltic surface butt joints (204.0115) | SY | 92 | $13.52 | $11.35 | $20.00 |
| 4 | Removing asphaltic surface milling (204.0120) | SY | 1,621 | $3.43 | $4.75 | $12.00 |
| 5 | Removing curb & gutter (204.0150) | LF | 403 | $12.25 | $9.50 | $15.00 |
| 6 | Removing concrete sidewalk (204.0155) | SY | 658 | $13.15 | $13.00 | $12.00 |
| 7 | Removing storm sewer (size) 01. 8- inch (204.0245) | LF | 15 | $38.00 | $15.00 | $30.00 |
| 8 | Excavation common (205.0100) | CY | 120 | $20.50 | $90.00 | $50.00 |
| 9 | Prepare foundation for asphaltic paving (project) 01.6685-04-70 (211.0101) | EACH | 1 | $22,587 | $23,715 | $25,000 |
| 10 | Prepare foundation for asphaltic shoulders (211.0400) | STA | 2 | $594.00 | $357.50 | $500.00 |
| 11 | Finishing roadway (project) 01. 6685-04-70 (213.0100) | EACH | 1 | $5,000.00 | $500.00 | $5,000.00 |
| 12 | Base aggregate dense 3/4-inch (305.0110) | TON | 449 | $27.50 | $52.25 | $32.00 |
| 13 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 100 | $21.25 | $40.50 | $25.00 |
| 14 | Drilled tie bars (416.0610) | EACH | 18 | $20.00 | $7.00 | $10.00 |
| 15 | Tack coat (455.0605) | GAL | 488 | $5.32 | $5.60 | $5.50 |
| 16 | Incentive density HMA pavement (460.2000) | DOL | 1,125 | $1.00 | $1.00 | $1.00 |
| 17 | HMA pavement 3 MT 58-28 S (460.6223) | TON | 1,020 | $106.10 | $111.45 | $110.00 |
| 18 | HMA pavement 4 MT 58-28 S (460.6224) | TON | 740 | $116.80 | $122.65 | $120.00 |
| 19 | Asphaltic surface (465.0105) | TON | 35 | $279.80 | $293.80 | $300.00 |
| 20 | Asphaltic surface driveways and field entrances (465.0120) | TON | 52 | $251.05 | $263.65 | $260.00 |
| 21 | Apron endwalls for culvert pipe 12- inch (520.1012) | EACH | 1 | $250.00 | $640.00 | $350.00 |
| 22 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 192 | $43.00 | $45.00 | $50.00 |
| 23 | Concrete sidewalk 4-inch (602.0405) | SF | 4,582 | $7.50 | $6.50 | $7.10 |
| 24 | Curb ramp detectable warning field yellow (602.0505) | SF | 80 | $65.00 | $52.40 | $55.00 |
| 25 | Curb ramp detectable warning field radial yellow (602.0605) | SF | 30 | $70.00 | $74.00 | $80.00 |
| 26 | Concrete driveway 6-inch (602.0810) | SY | 204 | $81.00 | $82.65 | $85.00 |
| 27 | Concrete driveway 8-inch (602.0820) | SY | 290 | $90.00 | $101.00 | $108.00 |
| 28 | Riprap medium (606.0200) | CY | 5 | $120.00 | $232.50 | $200.00 |
| 29 | Storm sewer pipe class III-A 12- inch (608.3012) | LF | 24 | $14.25 | $91.00 | $120.00 |
| 30 | Reconstructing manholes (611.0420) | EACH | 2 | $1,500.00 | $2,865.00 | $1,500.00 |
| 31 | Reconstructing inlets (611.0430) | EACH | 3 | $1,200.00 | $1,400.00 | $1,200.00 |
| 32 | Adjusting inlet covers (611.8115) | EACH | 3 | $700.00 | $570.00 | $500.00 |
| 33 | Maintenance and repair of haul roads (project) 01. 6685-04-70 (618.0100) | EACH | 1 | $100.00 | $500.00 | $100.00 |
| 34 | Mobilization (619.1000) | EACH | 1 | $53,320 | $63,625 | $60,000 |
| 35 | Water (624.0100) | MGAL | 1.50 | $50.00 | $185.00 | $50.00 |
| 36 | Topsoil (625.0100) | SY | 320 | $5.75 | $19.55 | $10.00 |
| 37 | Mulching (627.0200) | SY | 285 | $1.25 | $1.30 | $1.25 |
| 38 | Silt fence (628.1504) | LF | 50 | $5.00 | $5.30 | $5.00 |
| 39 | Silt fence maintenance (628.1520) | LF | 50 | $0.01 | $0.01 | $1.00 |
| 40 | Mobilizations erosion control (628.1905) | EACH | 2 | $976.00 | $1,025.00 | $200.00 |
| 41 | Mobilizations emergency erosion control (628.1910) | EACH | 2 | $100.00 | $100.00 | $350.00 |
| 42 | Erosion mat urban class I type B (628.2008) | SY | 35 | $6.00 | $3.20 | $4.00 |
| 43 | Inlet protection type C (628.7015) | EACH | 9 | $79.50 | $83.50 | $125.00 |
| 44 | Culvert pipe checks (628.7555) | EACH | 22 | $17.65 | $18.55 | $20.00 |
| 45 | Rock bags (628.7570) | EACH | 5 | $17.65 | $18.55 | $20.00 |
| 46 | Seeding mixture no. 40 (630.0140) | LB | 16 | $24.50 | $25.75 | $30.00 |
| 47 | Seed water (630.0500) | MGAL | 6 | $100.00 | $105.00 | $100.00 |
| 48 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 3 | $98.55 | $103.50 | $200.00 |
| 49 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 5 | $109.75 | $115.25 | $200.00 |
| 50 | Signs type II reflective H (637.2210) | SF | 30.18 | $20.75 | $21.80 | $30.00 |
| 51 | Signs type II reflective F (637.2230) | SF | 18 | $25.35 | $26.65 | $32.50 |
| 52 | Removing signs type II (638.2602) | EACH | 8 | $22.25 | $23.35 | $50.00 |
| 53 | Removing small sign supports (638.3000) | EACH | 8 | $22.25 | $23.35 | $50.00 |
| 54 | Field office type C (642.5201) | EACH | 1 | $12,000 | $9,100.00 | $8,000.00 |
| 55 | Traffic control drums (643.0300) | DAY | 2,215 | $0.69 | $0.55 | $0.60 |
| 56 | Traffic control barricades type III (643.0420) | DAY | 304 | $1.01 | $1.05 | $1.00 |
| 57 | Traffic control warning lights type A (643.0705) | DAY | 608 | $0.10 | $0.10 | $0.25 |
| 58 | Traffic control warning lights type C (643.0715) | DAY | 153 | $0.10 | $0.10 | $0.25 |
| 59 | Traffic control signs (643.0900) | DAY | 508 | $1.01 | $1.05 | $1.00 |
| 60 | Traffic control signs fixed message (643.1000) | SF | 40 | $11.01 | $11.55 | $11.00 |
| 61 | Temporary marking line removable tape 6-inch (643.3180) | LF | 82 | $1.71 | $1.80 | $2.00 |
| 62 | Traffic control (643.5000) | EACH | 1 | $1,414.00 | $35,000 | $10,000 |
| 63 | Temporary pedestrian surface matting (644.1440) | SF | 25 | $5.05 | $5.35 | $6.00 |
| 64 | Temporary pedestrian curb ramp (644.1601) | DAY | 17 | $5.05 | $5.35 | $6.00 |
| 65 | Temporary pedestrian detectable warning field (644.1605) | SF | 10 | $5.05 | $5.35 | $6.00 |
| 66 | Temporary pedestrian barricade (644.1810) | LF | 208 | $5.05 | $5.35 | $6.00 |
| 67 | Geotextile type HR (645.0120) | SY | 17 | $79.53 | $6.80 | $10.00 |
| 68 | Marking line paint 6-inch (646.2005) | LF | 7,840 | $0.65 | $0.70 | $0.75 |
| 69 | Marking stop line paint 12-inch (646.6005) | LF | 17 | $20.00 | $21.20 | $25.00 |
| 70 | Marking crosswalk paint transverse line 6-inch (646.7405) | LF | 68 | $15.00 | $15.90 | $18.00 |
| 71 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 407 | $2.50 | $2.70 | $3.00 |
| 72 | Construction staking resurfacing reference (650.8000) | LF | 2,046 | $0.25 | $0.25 | $0.65 |
| 73 | Construction staking curb ramps (650.9000) | EACH | 10 | $275.00 | $292.00 | $300.00 |
| 74 | Construction staking sidewalk (project) 01. 6685-04-70 (650.9500) | EACH | 1 | $800.00 | $850.00 | $1,000.00 |
| 75 | Construction staking supplemental control (project) 01.6685-04-70 (650.9911) | EACH | 1 | $800.00 | $850.00 | $3,000.00 |
| 76 | Sawing asphalt (690.0150) | LF | 1,068 | $5.00 | $3.50 | $5.00 |
| 77 | Sawing concrete (690.0250) | LF | 32 | $15.91 | $9.50 | $10.00 |
| 78 | Incentive iri ride (740.0440) | DOL | 1,440 | $1.00 | $1.00 | $1.00 |
| 79 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 300 | $5.00 | $5.00 | $5.00 |
| 80 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 600 | $5.00 | $5.00 | $5.00 |
| 81 | Special 01. fertilizer for lawn type turf (SPV.0030) | CWT | 0.60 | $300.00 | $315.00 | $250.00 |
| 82 | Special 01. adjusting water main valve box (SPV.0060) | EACH | 3 | $750.00 | $305.00 | $500.00 |
| 83 | Special 02. adjusting sanitary manhole covers (SPV.0060) | EACH | 1 | $900.00 | $865.00 | $1,500.00 |
| 84 | Special 03. apron endwalls for culvert pipe salvaged horizontal elliptical 19X30-inch (SPV.0060) | EACH | 4 | $1,850.00 | $1,165.00 | $1,500.00 |
| 85 | Special 01. concrete curb & gutter 30-inch type A modified (SPV.0090) | LF | 215 | $45.00 | $45.00 | $48.00 |
| 86 | Special 01. preparing topsoil for lawn type turf (SPV.0180) | SY | 320 | $0.88 | $0.90 | $5.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of November 11, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.