Temporary pedestrian curb ramp, WisDOT 644.1601
Low bidders on WisDOT contracts carried a median of $10.45 per DAY for this item, over the 24 months to 10 NOV 2026, across 176 low bids. Half of all 581 bids fell between $6.00 and $16.07.
- Owner
- Wisconsin DOT
- Item
- 644.1601
- Unit
- DAY
- Data through
- 10 NOV 2026
WisDOT prints this item as “Temporary Pedestrian Curb Ramp”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 63 | 59 | $17.00 | 139 | $18.50 |
| 2023 | 67 | 65 | $19.56 | 186 | $15.00 |
| 2024 | 80 | 70 | $15.00 | 259 | $15.00 |
| 2025 | 92 | 90 | $10.05 | 271 | $10.00 |
| 2026 | 67 | 66 | $10.00 | 227 | $10.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Milwaukee | 24 | $7.75 | 90 | $10.00 |
| Dane | 12 | $8.88 | 66 | $9.75 |
| Waukesha | 7 | $6.00 | 27 | $5.22 |
| Outagamie | 8 | $9.00 | 27 | $11.79 |
| Racine | 6 | $10.75 | 24 | $10.70 |
| Walworth | 5 | $12.68 | 18 | $11.32 |
| La Crosse | 5 | $26.15 | 16 | $25.57 |
| Dodge | 4 | $12.25 | 16 | $24.83 |
| Jefferson | 3 | $15.00 | 14 | $7.88 |
| Rock | 6 | $13.68 | 14 | $12.00 |
| Columbia | 3 | $10.40 | 13 | $11.00 |
| Washington | 4 | $26.25 | 13 | $17.50 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (DAY) | Low bids | Low-bid median |
|---|---|---|
| 5 to 50 | 44 | $19.48 |
| 50 to 210 | 44 | $11.25 |
| 210 to 560 | 44 | $11.14 |
| 572 to 9,500 | 44 | $6.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Zignego Company, Inc. | 101 | 68 (67%) |
| Rock Road Companies, Inc. | 66 | 42 (64%) |
| James Peterson Sons, Inc. | 64 | 36 (56%) |
| Lalonde Contractors Incorporated | 68 | 33 (49%) |
| Payne and Dolan, Inc | 59 | 33 (56%) |
| Vinton Construction Company | 47 | 30 (64%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 10 NOV 2026 | 20261110012 | Dane | 31 | $15.00 | $15.00 | 6 | R.G. Huston Company, Inc. | WisDOT |
| 10 NOV 2026 | 20261110014 | Milwaukee | 9,500 | $1.50 | $1.50 | 3 | Lalonde Contractors Incorporated | WisDOT |
| 10 NOV 2026 | 20261110017 | Walworth | 500 | $10.00 | $5.00 | 5 | James Peterson Sons, Inc. | WisDOT |
| 10 NOV 2026 | 20261110020 | Manitowoc | 336 | $5.00 | $5.00 | 2 | Northeast Asphalt, Inc | WisDOT |
| 10 NOV 2026 | 20261110021 | Waupaca | 220 | $8.00 | $8.00 | 2 | American Asphalt of Wisconsin | WisDOT |
| 10 NOV 2026 | 20261110030 | Ashland | 105 | $10.00 | $10.00 | 1 | Northwoods Paving, A Div. of Mathy Construction610 | WisDOT |
| 10 NOV 2026 | 20261110035 | Eau Claire | 28 | $13.00 | $13.00 | 1 | Monarch Paving Company | WisDOT |
| 10 NOV 2026 | 20261110037 | Eau Claire | 10 | $5.00 | $12.60 | 5 | Haas Sons, Inc. | WisDOT |
| 13 OCT 2026 | 20261013006 | Milwaukee | 270 | $15.00 | $15.00 | 2 | Zenith Tech., Inc. - Waukesha | WisDOT |
| 13 OCT 2026 | 20261013012 | Calumet | 178 | $30.00 | $19.55 | 2 | Northeast Asphalt, Inc | WisDOT |
| 13 OCT 2026 | 20261013013 | Sheboygan | 224 | $14.75 | $12.38 | 2 | Northeast Asphalt, Inc | WisDOT |
| 13 OCT 2026 | 20261013022 | Dunn | 50 | $30.00 | $20.00 | 2 | Lunda Construction Company | WisDOT |
| 13 OCT 2026 | 20261013031 | Polk | 120 | $5.50 | $5.50 | 1 | Monarch Paving Company | WisDOT |
| 15 SEP 2026 | 20260915003 | Dane | 300 | $3.60 | $4.50 | 6 | Parisi Construction, LLC | WisDOT |
| 15 SEP 2026 | 20260915007 | Milwaukee | 4,945 | $3.47 | $3.47 | 3 | Payne and Dolan, Inc | WisDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the WisDOT explorer.
How these prices were read
WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WisDOT's own: this item is compared with WisDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the WisDOT letting of 10 NOV 2026 and was rebuilt on 26 NOV 2026.