| 1 | Removing small pipe culverts (203.0100) | EACH | 2 | $1,459.00 | $1,459.00 |
| 2 | Removing asphaltic surface (204.0110) | SY | 230 | $18.00 | $18.00 |
| 3 | Removing asphaltic surface butt joints (204.0115) | SY | 200 | $36.70 | $8.85 |
| 4 | Removing asphaltic surface milling (204.0120) | SY | 118,100 | $2.05 | $1.65 |
| 5 | Removing curb (204.0130) | LF | 110 | $18.00 | $18.00 |
| 6 | Removing curb & gutter (204.0150) | LF | 870 | $18.00 | $18.00 |
| 7 | Removing concrete sidewalk (204.0155) | SY | 460 | $30.00 | $25.00 |
| 8 | Removing delineators and markers (204.0180) | EACH | 12 | $15.00 | $26.00 |
| 9 | Excavation common (205.0100) | CY | 700 | $37.40 | $37.40 |
| 10 | Prepare foundation for asphaltic paving (project) 01. 4540-35-71 (211.0101) | EACH | 1 | $14,750 | $24,855 |
| 11 | Finishing roadway (project) 01. 4540-35-71 (213.0100) | EACH | 1 | $2,800.00 | $2,363.00 |
| 12 | Base aggregate dense 3/4-inch (305.0110) | TON | 3,050 | $29.85 | $28.20 |
| 13 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 500 | $19.47 | $19.47 |
| 14 | Tack coat (455.0605) | GAL | 14,630 | $3.00 | $2.20 |
| 15 | HMA percent within limits (PWL) test strip volumetrics (460.0105.S) | EACH | 1 | $2,350.00 | $2,922.00 |
| 16 | HMA percent within limits (PWL) test strip density (460.0110.S) | EACH | 2 | $3,450.00 | $3,187.00 |
| 17 | Incentive density PWL HMA pavement (460.2005) | DOL | 16,520 | $1.00 | $1.00 |
| 18 | Incentive density HMA pavement longitudinal joints (460.2007) | DOL | 12,360 | $1.00 | $1.00 |
| 19 | Incentive air voids HMA pavement (460.2010) | DOL | 23,920 | $1.00 | $1.00 |
| 20 | HMA pavement 4 MT 58-28 S (460.6224) | TON | 23,920 | $73.90 | $78.10 |
| 21 | Asphaltic surface (465.0105) | TON | 100 | $174.70 | $235.00 |
| 22 | Asphaltic surface patching (465.0110) | TON | 150 | $164.90 | $292.40 |
| 23 | Asphaltic surface driveways and field entrances (465.0120) | TON | 5 | $352.40 | $193.30 |
| 24 | Asphaltic rumble strips, shoulder (465.0520) | LF | 35,800 | $0.27 | $0.22 |
| 25 | Asphaltic rumble strips, centerline (465.0560) | LF | 18,950 | $0.28 | $0.22 |
| 26 | Cleaning culvert pipes (520.8700) | EACH | 4 | $1,400.00 | $1,200.00 |
| 27 | Apron endwalls for culvert pipe steel 24-inch (521.1024) | EACH | 4 | $738.13 | $738.13 |
| 28 | Culvert pipe reinforced concrete class IV 24-inch (522.0424) | LF | 68 | $140.60 | $140.60 |
| 29 | Culvert pipe reinforced concrete class IV 30-inch (522.0430) | LF | 70 | $199.09 | $199.09 |
| 30 | Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024) | EACH | 2 | $2,555.58 | $2,555.58 |
| 31 | Apron endwalls for culvert pipe reinforced concrete 30-inch (522.1030) | EACH | 2 | $3,850.00 | $3,850.00 |
| 32 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 870 | $68.00 | $81.86 |
| 33 | Concrete curb pedestrian (601.0600) | LF | 180 | $55.00 | $81.86 |
| 34 | Concrete sidewalk 4-inch (602.0405) | SF | 4,890 | $13.00 | $14.96 |
| 35 | Curb ramp detectable warning field yellow (602.0505) | SF | 250 | $35.00 | $55.00 |
| 36 | Curb ramp detectable warning field radial yellow (602.0605) | SF | 82 | $62.00 | $85.00 |
| 37 | Adjusting manhole covers (611.8110) | EACH | 17 | $450.00 | $450.00 |
| 38 | Adjusting inlet covers (611.8115) | EACH | 2 | $300.00 | $300.00 |
| 39 | Cover plates temporary (611.8120.S) | EACH | 28 | $240.77 | $241.00 |
| 40 | Maintenance and repair of haul roads (project) 01. 4540-35-71 (618.0100) | EACH | 1 | $1.00 | $1.00 |
| 41 | Mobilization (619.1000) | EACH | 1 | $187,450 | $191,117 |
| 42 | Water (624.0100) | MGAL | 53 | $60.00 | $70.00 |
| 43 | Topsoil (625.0100) | SY | 750 | $10.77 | $5.00 |
| 44 | Mulching (627.0200) | SY | 180 | $1.00 | $1.00 |
| 45 | Silt fence (628.1504) | LF | 380 | $2.85 | $3.00 |
| 46 | Silt fence maintenance (628.1520) | LF | 760 | $0.10 | $0.01 |
| 47 | Mobilizations erosion control (628.1905) | EACH | 4 | $300.00 | $100.00 |
| 48 | Mobilizations emergency erosion control (628.1910) | EACH | 2 | $300.00 | $1.00 |
| 49 | Erosion mat urban class I type B (628.2008) | SY | 470 | $2.20 | $3.00 |
| 50 | Inlet protection type A (628.7005) | EACH | 2 | $95.00 | $140.00 |
| 51 | Inlet protection type C (628.7015) | EACH | 8 | $35.00 | $75.00 |
| 52 | Culvert pipe checks (628.7555) | EACH | 8 | $18.00 | $30.00 |
| 53 | Fertilizer type B (629.0210) | CWT | 1 | $150.00 | $100.00 |
| 54 | Seeding mixture no. 10 (630.0110) | LB | 14 | $22.00 | $40.00 |
| 55 | Seeding mixture no. 40 (630.0140) | LB | 8 | $22.00 | $40.00 |
| 56 | Seeding mixture no. 60 (630.0160) | LB | 1 | $75.00 | $100.00 |
| 57 | Seed water (630.0500) | MGAL | 17 | $5.00 | $30.00 |
| 58 | Markers culvert end (633.5200) | EACH | 12 | $58.00 | $75.00 |
| 59 | Moving small sign supports (638.4000) | EACH | 4 | $35.00 | $80.00 |
| 60 | Field office type B (642.5001) | EACH | 1 | $14,490 | $14,227 |
| 61 | Traffic control drums (643.0300) | DAY | 1,890 | $0.15 | $0.50 |
| 62 | Traffic control signs (643.0900) | DAY | 3,782 | $0.25 | $1.50 |
| 63 | Traffic control signs PCMS (643.1050) | DAY | 14 | $35.00 | $85.00 |
| 64 | Temporary marking line paint 4- inch (643.3105) | LF | 2,790 | $0.25 | $0.30 |
| 65 | Temporary marking line paint 6- inch (643.3165) | LF | 156,020 | $0.25 | $0.36 |
| 66 | Temporary marking line epoxy 6- inch (643.3170) | LF | 30,770 | $0.51 | $0.80 |
| 67 | Traffic control (643.5000) | EACH | 1 | $44,500 | $18,500 |
| 68 | Temporary pedestrian surface matting (644.1440) | SF | 670 | $2.75 | $12.00 |
| 69 | Temporary pedestrian curb ramp (644.1601) | DAY | 224 | $14.75 | $10.00 |
| 70 | Temporary pedestrian detectable warning field (644.1605) | SF | 300 | $4.50 | $7.50 |
| 71 | Temporary pedestrian barricade (644.1810) | LF | 2,420 | $5.00 | $8.50 |
| 72 | Temporary audible message devices (644.1900.S) | DAY | 546 | $10.00 | $4.50 |
| 73 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 92,400 | $1.22 | $1.10 |
| 74 | Marking stop line epoxy 18-inch (646.6120) | LF | 75 | $17.70 | $15.00 |
| 75 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 1,490 | $14.07 | $12.00 |
| 76 | Marking curb epoxy (646.8120) | LF | 590 | $8.50 | $7.00 |
| 77 | Marking removal line 4-inch (646.9000) | LF | 1,990 | $1.10 | $0.95 |
| 78 | Marking removal line 6-inch (646.9002) | LF | 1,310 | $1.90 | $0.96 |
| 79 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 870 | $0.91 | $0.91 |
| 80 | Construction staking pipe culverts (650.6000) | EACH | 2 | $116.49 | $116.49 |
| 81 | Construction staking resurfacing reference (650.8000) | LF | 30,688 | $0.10 | $0.10 |
| 82 | Construction staking curb ramps (650.9000) | EACH | 23 | $143.43 | $143.43 |
| 83 | Construction staking sidewalk (project) 01. 4540-35-71 (650.9500) | EACH | 1 | $889.98 | $889.98 |
| 84 | Construction staking supplemental control (project) 01. 4540-35-71 (650.9911) | EACH | 1 | $462.62 | $462.62 |
| 85 | Public land survey monument verify and reset (680.0100) | EACH | 8 | $856.15 | $856.15 |
| 86 | Sawing asphalt (690.0150) | LF | 1,356 | $1.35 | $1.35 |
| 87 | Sawing concrete (690.0250) | LF | 252 | $2.35 | $2.35 |
| 88 | Incentive iri ride (740.0440) | DOL | 46,500 | $1.00 | $1.00 |
| 89 | Special 01. foundation backfill (SPV.0035) | CY | 370 | $36.00 | $36.00 |
| 90 | Special 01. adjusting sanitary manhole covers (SPV.0060) | EACH | 9 | $600.00 | $600.00 |