WisDOT contract 20260915003 bid tabulation

5992-10-74. Let by Wisconsin DOT on September 15, 2026, Dane. 6 bids received; low bid $2,119,322 by Parisi Construction, LLC.

Owner
Wisconsin DOT
Letting
15 SEP 2026
Pay items
165
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Parisi Construction, LLC$2,119,322Low
2James Peterson Sons, Inc.$2,368,151+12%
3Hoffman Construction Company$2,483,046+17%
4Rock Road Companies, Inc.$2,572,436+21%
5R.G. Huston Company, Inc.$2,607,400+23%
6Zignego Company, Inc.$4,246,960+100%
WisDOT contract 20260915003: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Parisi Construction, LLC2. James Peterson Sons, Inc.3. Hoffman Construction Company4. Rock Road Companies, Inc.5. R.G. Huston Company, Inc.6. Zignego Company, Inc.
1Clearing (201.0105)STA13$540.00$530.00$530.00$530.00$190.00$530.00
2Clearing (201.0120)ID40$1.00$1.00$1.00$1.00$70.00$1.00
3Grubbing (201.0205)STA13$360.00$450.00$350.00$350.00$370.00$350.00
4Grubbing (201.0220)ID40$1.00$1.00$1.00$1.00$60.00$1.00
5Removing small pipe culverts (203.0100)EACH2$660.00$750.00$500.00$708.00$800.00$1,000.00
6Removing curb & gutter (204.0150)LF1,260$8.50$3.50$4.50$6.41$7.00$10.00
7Removing concrete sidewalk (204.0155)SY250$19.00$10.00$6.50$9.40$7.00$30.00
8Removing fence (204.0170)LF560$2.00$2.00$2.00$2.00$2.00$3.00
9Removing concrete bases (204.0195)EACH1$340.00$500.00$500.00$652.42$700.00$500.00
10Removing manholes (204.0210)EACH1$660.00$600.00$650.00$652.42$700.00$1,000.00
11Removing inlets (204.0220)EACH1$660.00$500.00$650.00$652.42$600.00$1,000.00
12Removing storm sewer (size) 01. 12-inch (204.0245)LF72$27.00$23.00$18.00$27.47$26.00$50.00
13Removing storm sewer (size) 02. 21-inch (204.0245)LF42$30.75$25.00$18.00$27.47$42.00$50.00
14Excavation common (205.0100)CY12,900$16.75$11.76$10.50$20.27$20.30$29.00
15Excavation rock (205.0200)CY59$58.00$65.00$200.00$80.18$200.00$300.00
16Finishing roadway (project) 01. 5992-10-74 (213.0100)EACH1$500.00$2,500.00$100.00$5,388.88$3,100.00$1,000.00
17Base aggregate dense 3/4-inch (305.0110)TON215$35.75$30.84$60.00$41.37$47.00$50.00
18Base aggregate dense 1 1/4-inch (305.0120)TON4,100$19.50$25.14$25.00$19.58$22.00$20.00
19Base aggregate dense 3-inch (305.0130)TON4,000$17.00$19.24$25.00$21.81$20.50$26.00
20Coloring concrete wisdot red (405.0100)CY97$155.00$120.00$155.00$120.00$121.21$200.00
21Concrete truck apron 12-inch (415.2010)SY290$110.00$106.40$110.00$106.40$107.47$124.00
22Tack coat (455.0605)GAL380$2.00$2.00$2.00$5.00$2.00$2.00
23Incentive density HMA pavement (460.2000)DOL1,600$1.00$1.00$1.00$1.00$1.00$1.00
24HMA pavement 4 LT 58-28 S (460.5224)TON130$97.00$95.00$95.00$105.00$95.00$95.00
25HMA pavement 3 MT 58-28 S (460.6223)TON1,615$85.00$83.00$83.00$85.00$83.00$83.00
26HMA pavement 4 MT 58-28 S (460.6224)TON755$88.00$86.25$86.25$90.00$86.25$86.25
27Asphaltic surface driveways and field entrances (465.0120)TON23$160.00$160.00$160.00$220.00$160.00$160.00
28Asphaltic flumes (465.0315)SY8$40.75$40.00$40.00$67.00$40.00$40.00
29Apron endwalls for culvert pipe steel 12-inch (521.1012)EACH4$840.00$264.00$650.00$745.82$600.00$1,000.00
30Culvert pipe corrugated steel 12- inch (521.3112)LF63$75.00$73.00$65.00$106.67$55.00$120.00
31Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024)EACH1$2,000.00$1,518.00$1,750.00$1,935.94$3,300.00$1,250.00
32Concrete curb & gutter 18-inch type A (601.0405)LF173$40.00$27.70$40.00$27.70$27.98$80.00
33Concrete curb & gutter 4-inch sloped 30-inch type R (601.0581)LF258$37.00$30.30$37.00$30.30$30.61$80.00
34Concrete curb pedestrian (601.0600)LF123$60.00$55.00$60.00$55.00$55.56$80.00
35Concrete sidewalk 5-inch (602.0410)SF15,300$7.50$7.60$7.50$7.60$7.68$9.22
36Concrete sidewalk 7-inch (602.0420)SF195$16.50$9.20$16.50$9.20$9.29$10.00
37Curb ramp detectable warning field natural patina (602.0515)SF272$50.00$45.00$50.00$45.00$45.45$50.00
38Riprap heavy (606.0300)CY6$130.00$161.00$200.00$228.32$155.00$300.00
39Storm sewer rock excavation (608.0005)CY100$110.00$145.00$122.00$90.20$200.00$500.00
40Storm sewer pipe reinforced concrete class III 12-inch (608.0312)LF506$72.00$91.00$75.00$127.76$95.00$203.21
41Storm sewer pipe reinforced concrete class III 24-inch (608.0324)LF1,006$100.00$104.00$100.00$120.53$118.00$308.67
42Manhole covers type J-special (611.0535)EACH10$890.00$1,135.00$800.00$1,654.96$900.00$1,000.00
43Inlet covers type H (611.0624)EACH15$1,100.00$1,480.00$1,100.00$1,984.18$1,200.00$1,000.00
44Inlet covers type MS (611.0642)EACH1$880.00$600.00$830.00$1,213.36$900.00$1,000.00
45Inlet covers type T (611.0652)EACH2$1,400.00$1,450.00$1,500.00$2,340.29$1,500.00$1,000.00
46Catch basins 5-FT diameter (611.1005)EACH1$4,700.00$6,068.00$5,800.00$6,413.13$7,700.00$16,126
47Manholes 4-FT diameter (611.2004)EACH1$2,700.00$2,453.00$3,400.00$3,268.43$4,900.00$5,584.37
48Manholes 5-FT diameter (611.2005)EACH5$3,400.00$4,176.00$4,700.00$4,224.92$6,600.00$6,766.03
49Inlets 4-FT diameter (611.3004)EACH6$2,700.00$2,609.00$3,200.00$3,231.37$4,800.00$5,504.04
50Inlets 2X2.5-FT (611.3225)EACH1$2,100.00$1,188.00$2,000.00$2,700.08$2,000.00$3,001.54
51Inlets 2X3-FT (611.3230)EACH7$2,100.00$1,715.00$2,100.00$2,619.76$2,200.00$3,855.32
52Inlets median 1 grate (611.3901)EACH1$3,200.00$3,321.00$3,700.00$3,317.76$2,800.00$5,854.87
53Pipe grates (size) 01. 24-inch (611.9850.S)EACH1$700.00$1,981.00$850.00$593.07$2,100.00$2,500.00
54Insulation board polystyrene (inch) 01. 2-inch (612.0902.S)SY28.48$57.00$30.00$40.00$22.74$40.00$35.00
55Mobilization (619.1000)EACH1$90,000$179,901$281,368$209,287$289,854$384,000
56Concrete median sloped nose (620.0300)SF320$12.00$15.00$12.00$15.00$15.15$20.00
57Water (624.0100)MGAL95$31.75$70.00$95.00$0.01$42.00$30.00
58Topsoil (625.0100)SY11,400$4.90$2.45$3.50$3.70$0.01$5.95
59Topsoil (625.0105)CY90$45.00$60.00$35.00$65.65$35.00$75.00
60Silt fence (628.1504)LF1,250$2.30$2.25$2.25$2.25$2.25$2.05
61Silt fence maintenance (628.1520)LF1,250$0.01$0.01$0.01$0.01$0.01$0.01
62Mobilizations erosion control (628.1905)EACH6$100.00$100.00$100.00$100.00$100.00$250.00
63Mobilizations emergency erosion control (628.1910)EACH4$100.00$100.00$100.00$100.00$100.00$250.00
64Erosion mat urban class I type B (628.2008)SY11,400$1.80$1.75$1.75$1.75$1.75$1.75
65Turbidity barriers (628.6005)SY50$46.00$45.00$45.00$45.00$45.00$40.00
66Inlet protection type A (628.7005)EACH18$97.00$95.00$95.00$95.00$95.00$95.00
67Inlet protection type C (628.7015)EACH23$71.00$70.00$70.00$70.00$70.00$65.00
68Temporary ditch checks (628.7504)LF80$9.20$9.00$9.00$9.00$9.00$6.75
69Culvert pipe checks (628.7555)EACH3$25.50$25.00$25.00$25.00$25.00$18.00
70Tracking pads (628.7560)EACH2$1,000.00$1,500.00$500.00$950.00$2,900.00$2,000.00
71Fertilizer type B (629.0210)CWT7.50$97.00$95.00$95.00$95.00$95.00$80.00
72Seeding mixture no. 40 (630.0140)LB240$14.25$14.00$14.00$14.00$14.00$10.95
73Seeding mixture no. 70 (630.0170)LB25$130.00$125.00$125.00$125.00$125.00$150.00
74Seed water (630.0500)MGAL640$1.00$1.00$1.00$1.00$1.00$10.00
75Signs type II reflective H (637.2210)SF99.04$22.50$22.00$22.00$22.00$22.00$22.00
76Signs type II reflective F (637.2230)SF100$23.50$23.00$23.00$23.00$23.00$24.00
77Moving signs type II (638.2102)EACH1$260.00$250.00$250.00$250.00$250.00$110.00
78Removing signs type II (638.2602)EACH11$35.75$35.00$35.00$35.00$35.00$25.00
79Removing small sign supports (638.3000)EACH11$35.75$35.00$35.00$35.00$35.00$25.00
80Moving small sign supports (638.4000)EACH1$100.00$100.00$100.00$100.00$100.00$100.00
81Field office type D (642.5401)EACH1$9,500.00$15,000$5,000.00$8,100.00$25,000$20,000
82Traffic control drums (643.0300)DAY1,400$0.15$0.25$0.14$0.20$0.20$0.20
83Traffic control barricades type III (643.0420)DAY2,600$0.45$0.70$0.44$0.60$0.60$0.65
84Traffic control warning lights type A (643.0705)DAY4,150$0.10$0.07$0.10$0.11$0.11$0.10
85Traffic control signs (643.0900)DAY9,300$0.15$0.50$0.16$0.30$0.30$0.45
86Traffic control signs fixed message (643.1000)SF72$12.75$18.00$12.50$12.00$12.00$12.00
87Traffic control signs PCMS (643.1050)DAY30$12.25$55.00$12.00$60.00$60.00$55.00
88Temporary marking line removable tape 6-inch (643.3180)LF70$2.00$2.00$2.00$5.00$5.00$2.50
89Traffic control (643.5000)EACH1$22,700$16,000$22,290$12,000$12,000$11,923
90Temporary pedestrian surface matting (644.1440)SF160$8.20$12.00$8.00$10.00$10.00$8.00
91Temporary pedestrian curb ramp (644.1601)DAY300$3.60$4.00$3.50$5.00$5.00$6.00
92Temporary pedestrian detectable warning field (644.1605)SF20$13.25$15.00$13.00$12.00$12.00$20.00
93Temporary pedestrian barricade (644.1810)LF150$7.70$4.00$7.50$6.00$6.00$8.00
94Temporary audible message devices (644.1900.S)DAY850$9.70$3.45$9.50$2.25$2.25$1.25
95Geotextile type HR (645.0120)SY18$40.00$16.00$5.00$2.84$5.00$10.00
96Marking line epoxy 4-inch (646.1020)LF6,000$0.40$0.75$0.39$0.39$0.39$0.75
97Marking line epoxy 6-inch (646.2020)LF2,750$0.55$1.15$0.53$0.53$0.54$1.15
98Marking line epoxy 8-inch (646.3020)LF210$1.10$1.50$1.05$1.05$1.06$1.50
99Marking arrow epoxy (646.5020)EACH4$230.00$230.00$229.38$229.38$231.70$230.00
100Marking dotted extension epoxy 18-inch (646.6320)LF70$19.00$19.00$18.60$18.60$18.79$19.00
101Marking diagonal epoxy 12-inch (646.7120)LF120$18.50$9.75$18.15$18.15$18.33$9.75
102Marking crosswalk epoxy transverse line 6-inch (646.7420)LF275$12.25$11.50$11.95$11.95$12.07$11.50
103Marking curb epoxy (646.8120)LF30$9.10$7.75$8.92$8.92$9.01$7.75
104Marking island nose epoxy (646.8220)EACH3$340.00$325.00$333.36$333.36$336.73$325.00
105Marking removal line 4-inch (646.9000)LF700$0.80$1.00$0.80$0.80$1.70$0.75
106Construction staking storm sewer (650.4000)EACH23$200.00$200.00$200.00$15.00$200.00$200.00
107Construction staking subgrade (650.4500)LF2,024$0.10$0.01$0.01$0.01$0.01$0.01
108Construction staking base (650.5000)LF2,024$1.00$1.25$0.01$0.01$1.25$1.25
109Construction staking curb gutter and curb & gutter (650.5500)LF1,624$1.50$2.00$2.00$1.00$2.00$2.00
110Construction staking pipe culverts (650.6000)EACH2$260.00$300.00$300.00$100.00$300.00$300.00
111Construction staking electrical installations (project) 01. 5992-10- 74 (650.8501)EACH1$2,600.00$5,000.00$5,000.00$5,000.00$5,000.00$5,000.00
112Construction staking sidewalk (project) 01. 5992-10-74 (650.9500)EACH1$1,500.00$10,000$10,000$5,000.00$10,000$10,000
113Construction staking supplemental control (project) 01. 5992-10-74 (650.9911)EACH1$1,000.00$10,000$10,000$5,000.00$10,000$10,000
114Construction staking slope stakes (650.9920)LF2,039$1.50$2.00$2.00$0.80$2.00$2.00
115Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF1,505$8.20$8.00$8.00$8.00$10.61$8.00
116Conduit rigid nonmetallic schedule 40 3-inch (652.0235)LF1,180$10.25$10.00$10.00$10.00$13.38$10.00
117Conduit rigid nonmetallic schedule 80 2-inch (652.0325)LF300$10.25$10.00$10.00$10.00$12.12$10.00
118Conduit rigid nonmetallic schedule 80 3-inch (652.0335)LF155$14.25$14.00$14.00$14.00$14.65$14.00
119Install conduit into existing item (652.0700.S)EACH3$100.00$100.00$100.00$100.00$505.05$100.00
120Removing pull boxes (653.0905)EACH3$200.00$200.00$200.00$200.00$505.05$200.00
121Electrical wire lighting 10 AWG (655.0615)LF1,770$1.50$1.50$1.50$1.50$1.46$1.50
122Electrical wire lighting 8 AWG (655.0620)LF9,070$1.80$1.75$1.75$1.75$1.87$1.75
123Lamp, ballast, LED, switch disposal by contractor (659.5000.S)EACH1$150.00$150.00$150.00$150.00$505.05$150.00
124Sawing asphalt (690.0150)LF620$2.10$1.55$1.55$1.47$1.55$1.55
125Sawing concrete (690.0250)LF58.50$15.00$2.55$2.55$9.14$2.55$2.55
126Incentive compressive strength concrete pavement (715.0720)DOL500$1.00$1.00$1.00$1.00$1.00$1.00
127On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,000$5.00$5.00$5.00$5.00$5.00$5.00
128On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS1,320$5.00$5.00$5.00$5.00$5.00$5.00
129Special 01. sanitary sewer rock excavation (SPV.0035)CY250$99.00$108.00$103.50$90.20$200.00$900.00
130Special 02. water main rock excavation (SPV.0035)CY100$110.00$145.00$103.50$90.20$200.00$900.00
131Special 01. street light removal (SPV.0060)EACH1$510.00$500.00$500.00$500.00$757.58$500.00
132Special 02. construction staking roundabout (SPV.0060)EACH1$20,400$25,000$25,000$2,500.00$25,000$25,000
133Special 03. precast sign post base (SPV.0060)EACH16$230.00$225.00$225.00$225.00$225.00$500.00
134Special 04. sign post base for concrete installation (SPV.0060)EACH11$230.00$225.00$225.00$225.00$225.00$500.00
135Special 05. electrical pullbox, type (SPV.0060)IEACH8$1,000.00$1,000.00$1,000.00$1,000.00$1,515.15$1,000.00
136Special 06. electrical pullbox, type V (SPV.0060)EACH9$1,300.00$1,250.00$1,250.00$1,250.00$1,666.67$1,250.00
137Special 07. concrete base type LB- 3R (SPV.0060)EACH15$1,200.00$1,200.00$1,200.00$1,200.00$1,616.16$1,200.00
138Special 08. pole 30-foot, 11 gauge (SPV.0060)EACH15$2,600.00$2,530.00$2,530.00$2,530.00$2,575.76$2,530.00
139Special 09. LED light assembly type 1 (SPV.0060)EACH11$830.00$810.00$810.00$810.00$732.32$810.00
140Special 10. LED light assembly type 2 (SPV.0060)EACH4$830.00$810.00$810.00$810.00$732.32$810.00
141Special 11. sanitary sewer access structure, 4-foot diameter (SPV.0060)EACH6$5,600.00$4,827.00$7,625.00$5,975.35$6,600.00$16,289
142Special 12. doghouse manhole (SPV.0060)EACH1$47,500$17,573$8,120.00$39,308$28,000$69,309
143Special 13. construction staking sanitary sewer (SPV.0060)EACH1$2,600.00$5,000.00$5,000.00$2,500.00$5,000.00$5,000.00
144Special 14. cut-in or connect-to existing water system (SPV.0060)EACH3$3,400.00$2,779.00$4,610.00$8,902.13$6,700.00$6,000.00
145Special 15. remove, salvage and reinstall existing hydrant (SPV.0060)EACH2$4,000.00$3,500.00$2,150.00$5,802.82$1,200.00$7,000.00
146Special 16. furnish and install hydrant (SPV.0060)EACH1$7,100.00$7,142.00$7,090.00$8,530.92$7,700.00$12,000
147Special 17. adjust water valve box section (SPV.0060)EACH2$490.00$350.00$500.00$355.47$300.00$1,000.00
148Special 18. furnish and install 6- inch valve (SPV.0060)EACH3$4,200.00$2,669.00$2,350.00$3,118.28$3,100.00$3,000.00
149Special 19. furnish and install 12- inch valve (SPV.0060)EACH3$8,200.00$6,566.00$9,110.00$6,653.62$6,800.00$9,000.00
150Special 20. construction staking water main (SPV.0060)EACH1$2,600.00$5,000.00$5,000.00$2,500.00$5,000.00$5,000.00
151Special 21. manhole covers type J- special - MMSD (SPV.0060)EACH1$1,600.00$1,298.00$900.00$1,734.35$900.00$1,000.00
152Special 22. sanitary sewer internal chimney seal (SPV.0060)EACH3$370.00$567.00$1,200.00$0.01$500.00$1,000.00
153Special 23. utility line opening (ulo) (SPV.0060)EACH3$850.00$750.00$500.00$1,250.00$1,600.00$2,000.00
154Special 24. manhole liner (SPV.0060)EACH1$9,200.00$9,926.00$4,200.00$8,977.00$9,000.00$10,000
155Special 25. wastewater control MMSD (SPV.0060)EACH1$2,200.00$12,500$5,000.00$8,120.21$7,400.00$10,000
156Special 26. external sewer access structure joint seal (SPV.0060)EACH2$360.00$350.00$450.00$689.44$500.00$1,000.00
157Special 01. reflective sign post (SPV.0090)LF238$20.50$20.00$20.00$20.00$20.00$35.00
158Special 02. concrete curb & gutter 30-inch type D special (SPV.0090)LF4,138$25.50$20.90$25.50$20.90$21.11$44.51
159Special 03. electrical wire lighting, 14-3 grounded (SPV.0090)LF600$1.80$1.75$1.75$1.75$1.72$1.75
160Special 04. sanitary sewer pipe PVC, 8-inch (SPV.0090)LF1,599$79.00$82.00$124.00$148.53$142.00$290.17
161Special 05. select fill for sanitary sewer (SPV.0090)LF1,599$0.50$100.00$51.00$49.16$0.01$53.33
162Special 06. furnish & install 6-inch pipe & fittings (SPV.0090)LF52$140.00$146.00$127.00$135.37$116.00$228.64
163Special 07. furnish & install 12-inch pipe & fittings (SPV.0090)LF855$130.00$169.00$184.00$165.47$175.00$318.72
164Special 08. select fill for water main (SPV.0090)LF907$0.50$38.00$15.50$26.03$0.01$44.44
165Special 01. construct outside drop, 8-inch (SPV.0200)VF3.58$750.00$796.00$1,075.42$2,149.59$523.00$4,000.00
WisDOT contract 20260915003: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of September 15, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy