WisDOT contract 20261110037 bid tabulation
C Eau Claire, E Hamilton Ave; Horlacher Ln to Gateway Dr (LOC STR, Eau Claire County C Eau Claire, E Hamilton Ave). Let by Wisconsin DOT on November 10, 2026, Eau Claire. 5 bids received; low bid $797,744 by Haas Sons, Inc..
- Owner
- Wisconsin DOT
- Letting
- 10 NOV 2026
- Pay items
- 101
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Haas Sons, Inc. | $797,744 | Low |
| 2 | McCabe Construction, Inc. | $909,909 | +14% |
| 3 | Gerke Excavating Inc | $975,604 | +22% |
| 4 | A-1 Excavating LLC | $982,222 | +23% |
| 5 | Stout Construction, Inc. | $1,047,407 | +31% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Haas Sons, Inc. | 2. McCabe Construction, Inc. | 3. Gerke Excavating Inc | 4. A-1 Excavating LLC | 5. Stout Construction, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 8 | $550.00 | $1,235.00 | $1,102.28 | $200.00 | $1,250.00 |
| 2 | Grubbing (201.0205) | STA | 8 | $625.00 | $450.00 | $886.55 | $1,500.00 | $1,100.00 |
| 3 | Removing asphaltic surface (204.0110) | SY | 479 | $7.25 | $5.00 | $6.00 | $6.00 | $5.50 |
| 4 | Removing curb & gutter (204.0150) | LF | 303 | $3.50 | $5.00 | $4.74 | $7.00 | $9.10 |
| 5 | Removing concrete sidewalk (204.0155) | SY | 69 | $8.00 | $13.00 | $6.35 | $10.00 | $16.50 |
| 6 | Removing manholes (204.0210) | EACH | 3 | $560.00 | $1,050.00 | $473.66 | $1,100.00 | $475.00 |
| 7 | Removing catch basins (204.0215) | EACH | 2 | $575.00 | $525.00 | $358.11 | $750.00 | $650.00 |
| 8 | Removing storm sewer (size) 01. 12-inch (204.0245) | LF | 118 | $18.80 | $13.00 | $12.14 | $22.00 | $35.00 |
| 9 | Removing storm sewer (size) 02. 15-inch (204.0245) | LF | 12 | $26.30 | $17.00 | $59.68 | $28.00 | $125.00 |
| 10 | Removing storm sewer (size) 03. 18-inch (204.0245) | LF | 406 | $18.25 | $20.00 | $10.58 | $22.00 | $42.00 |
| 11 | Excavation common (205.0100) | CY | 4,292 | $13.10 | $16.00 | $10.63 | $15.00 | $17.50 |
| 12 | Prepare foundation for asphaltic paving (project) 01. 7995-02-76 (211.0101) | EACH | 1 | $1,500.00 | $5,630.00 | $8,426.12 | $5,000.00 | $15,000 |
| 13 | Finishing roadway (project) 01. 7995-02-76 (213.0100) | EACH | 1 | $0.01 | $1,700.00 | $1,426.34 | $1,000.00 | $6,000.00 |
| 14 | Base aggregate dense 3/4-inch (305.0110) | TON | 5 | $140.00 | $156.00 | $106.72 | $130.00 | $133.00 |
| 15 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 3,890 | $19.50 | $21.00 | $23.91 | $25.00 | $21.25 |
| 16 | Tack coat (455.0605) | GAL | 394 | $1.00 | $1.00 | $1.05 | $1.05 | $1.05 |
| 17 | Incentive density HMA pavement (460.2000) | DOL | 820 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 18 | HMA pavement 3 LT 58-28 S (460.5223) | TON | 705 | $83.08 | $83.08 | $87.23 | $89.00 | $87.25 |
| 19 | HMA pavement 4 LT 58-34 S (460.5244) | TON | 552 | $83.08 | $83.08 | $87.23 | $89.00 | $87.25 |
| 20 | Asphaltic surface (465.0105) | TON | 6 | $220.00 | $220.00 | $231.00 | $325.00 | $231.00 |
| 21 | Asphaltic surface driveways and field entrances (465.0120) | TON | 31 | $220.00 | $220.00 | $231.00 | $250.00 | $231.00 |
| 22 | Concrete collars for pipe (520.8000) | EACH | 3 | $385.00 | $1,065.00 | $1,484.42 | $780.00 | $1,750.00 |
| 23 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 195 | $24.00 | $32.00 | $33.60 | $37.00 | $25.25 |
| 24 | Concrete curb pedestrian (601.0600) | LF | 81 | $40.00 | $65.00 | $68.25 | $68.00 | $42.00 |
| 25 | Concrete sidewalk 4-inch (602.0405) | SF | 9,900 | $6.75 | $6.77 | $7.11 | $8.00 | $6.10 |
| 26 | Concrete sidewalk 6-inch (602.0415) | SF | 1,620 | $7.05 | $8.00 | $8.40 | $9.00 | $7.15 |
| 27 | Curb ramp detectable warning field natural patina (602.0515) | SF | 150 | $45.00 | $65.00 | $68.25 | $68.00 | $50.00 |
| 28 | Curb ramp detectable warning field radial natural patina (602.0615) | SF | 18 | $60.00 | $70.00 | $73.50 | $74.00 | $65.00 |
| 29 | Concrete driveway 6-inch (602.0810) | SY | 275 | $61.20 | $75.00 | $78.75 | $85.00 | $65.00 |
| 30 | Storm sewer pipe reinforced concrete class III 12-inch (608.0312) | LF | 169 | $65.00 | $63.00 | $71.02 | $66.00 | $93.00 |
| 31 | Storm sewer pipe reinforced concrete class III 15-inch (608.0315) | LF | 43 | $67.90 | $75.65 | $76.31 | $77.00 | $175.00 |
| 32 | Storm sewer pipe reinforced concrete class III 24-inch (608.0324) | LF | 647 | $89.50 | $110.50 | $89.05 | $99.00 | $110.00 |
| 33 | Storm sewer pipe reinforced concrete class IV 18-inch (608.0418) | LF | 6 | $87.25 | $121.00 | $236.23 | $190.00 | $210.00 |
| 34 | Storm sewer pipe reinforced concrete class IV 24-inch (608.0424) | LF | 605 | $106.75 | $135.00 | $105.44 | $130.00 | $157.00 |
| 35 | Manhole covers type J (611.0530) | EACH | 3 | $901.00 | $835.00 | $994.49 | $1,100.00 | $1,150.00 |
| 36 | Inlet covers type BW (611.0610) | EACH | 1 | $835.00 | $1,070.00 | $1,078.28 | $1,500.00 | $1,450.00 |
| 37 | Inlet covers type H (611.0624) | EACH | 9 | $702.50 | $935.00 | $1,055.00 | $1,500.00 | $1,300.00 |
| 38 | Manholes 3-FT diameter (611.2003) | EACH | 1 | $3,610.00 | $3,650.00 | $4,009.98 | $3,600.00 | $4,425.00 |
| 39 | Manholes 4-FT diameter (611.2004) | EACH | 2 | $3,610.00 | $4,210.00 | $4,007.51 | $6,800.00 | $4,525.00 |
| 40 | Inlets 4-FT diameter (611.3004) | EACH | 7 | $3,475.00 | $3,760.00 | $4,133.05 | $4,900.00 | $4,300.00 |
| 41 | Inlets 2X3-FT (611.3230) | EACH | 3 | $1,725.00 | $1,800.00 | $2,517.02 | $2,400.00 | $2,325.00 |
| 42 | Adjusting manhole covers (611.8110) | EACH | 4 | $550.00 | $715.00 | $686.63 | $750.00 | $650.00 |
| 43 | Maintenance and repair of haul roads (project) 01. 7995-02-76 (618.0100) | EACH | 1 | $1.00 | $100.00 | $1.00 | $500.00 | $16,000 |
| 44 | Mobilization (619.1000) | EACH | 1 | $23,000 | $24,951 | $95,556 | $58,000 | $49,000 |
| 45 | Water (624.0100) | MGAL | 61 | $50.25 | $49.00 | $24.02 | $30.00 | $55.00 |
| 46 | Topsoil (625.0100) | SY | 2,365 | $5.25 | $8.00 | $13.15 | $7.00 | $15.50 |
| 47 | Silt fence (628.1504) | LF | 100 | $2.50 | $2.50 | $3.15 | $3.15 | $3.15 |
| 48 | Silt fence maintenance (628.1520) | LF | 100 | $0.01 | $0.01 | $0.03 | $0.03 | $0.05 |
| 49 | Mobilizations erosion control (628.1905) | EACH | 2 | $100.00 | $100.00 | $160.65 | $160.00 | $160.00 |
| 50 | Mobilizations emergency erosion control (628.1910) | EACH | 2 | $100.00 | $100.00 | $213.15 | $213.00 | $215.00 |
| 51 | Erosion mat urban class I type B (628.2008) | SY | 2,365 | $1.60 | $1.60 | $2.10 | $2.10 | $2.10 |
| 52 | Inlet protection type C (628.7015) | EACH | 11 | $55.00 | $55.00 | $78.75 | $79.00 | $80.00 |
| 53 | Fertilizer type B (629.0210) | CWT | 1.51 | $145.00 | $145.00 | $105.00 | $105.00 | $105.00 |
| 54 | Seeding mixture no. 40 (630.0140) | LB | 108 | $50.00 | $50.00 | $9.45 | $10.00 | $9.50 |
| 55 | Seeding temporary (630.0200) | LB | 6 | $3.25 | $3.25 | $21.00 | $21.00 | $21.00 |
| 56 | Seed water (630.0500) | MGAL | 55 | $3.00 | $3.00 | $5.25 | $5.00 | $5.25 |
| 57 | Posts tubular steel 2X2-inch X 8-FT (634.0808) | EACH | 3 | $125.00 | $125.00 | $210.00 | $210.00 | $210.00 |
| 58 | Posts tubular steel 2X2-inch X 14- FT (634.0814) | EACH | 10 | $150.00 | $150.00 | $262.50 | $265.00 | $265.00 |
| 59 | Signs type II reflective H (637.2210) | SF | 59.40 | $23.00 | $23.00 | $26.25 | $30.00 | $30.00 |
| 60 | Moving signs type II (638.2102) | EACH | 1 | $150.00 | $150.00 | $157.50 | $160.00 | $160.00 |
| 61 | Removing signs type II (638.2602) | EACH | 10 | $15.00 | $15.00 | $26.25 | $30.00 | $30.00 |
| 62 | Removing small sign supports (638.3000) | EACH | 10 | $15.00 | $15.00 | $26.51 | $30.00 | $30.00 |
| 63 | Moving small sign supports (638.4000) | EACH | 1 | $75.00 | $75.00 | $157.50 | $160.00 | $160.00 |
| 64 | Field office type B (642.5001) | EACH | 1 | $8,500.00 | $7,000.00 | $10,201 | $8,000.00 | $5,500.00 |
| 65 | Traffic control drums (643.0300) | DAY | 2,420 | $0.69 | $0.20 | $0.21 | $0.25 | $0.25 |
| 66 | Traffic control barricades type III (643.0420) | DAY | 1,260 | $0.89 | $0.50 | $0.53 | $0.55 | $0.55 |
| 67 | Traffic control warning lights type A (643.0705) | DAY | 2,520 | $0.10 | $0.11 | $0.12 | $0.15 | $0.15 |
| 68 | Traffic control signs (643.0900) | DAY | 3,270 | $2.02 | $0.25 | $0.26 | $0.30 | $0.25 |
| 69 | Temporary marking line removable tape 6-inch (643.3180) | LF | 190 | $1.69 | $2.25 | $2.36 | $2.50 | $2.50 |
| 70 | Traffic control (643.5000) | EACH | 1 | $1,954.00 | $7,000.00 | $7,350.00 | $10,000 | $11,000 |
| 71 | Temporary pedestrian surface plate (644.1430) | SF | 660 | $11.38 | $10.00 | $10.50 | $11.00 | $10.50 |
| 72 | Temporary pedestrian curb ramp (644.1601) | DAY | 10 | $5.00 | $12.00 | $12.60 | $13.00 | $13.00 |
| 73 | Temporary pedestrian detectable warning field (644.1605) | SF | 80 | $5.00 | $9.50 | $9.98 | $10.00 | $10.00 |
| 74 | Temporary pedestrian barricade (644.1810) | LF | 400 | $4.32 | $3.75 | $3.94 | $4.00 | $4.00 |
| 75 | Temporary audible message devices (644.1900.S) | DAY | 20 | $12.00 | $4.00 | $4.20 | $5.00 | $4.20 |
| 76 | Marking crosswalk epoxy block style 24-inch (646.7520) | LF | 133 | $44.00 | $44.00 | $46.20 | $46.00 | $46.25 |
| 77 | Construction staking storm sewer (650.4000) | EACH | 13 | $200.00 | $200.00 | $210.00 | $210.00 | $210.00 |
| 78 | Construction staking subgrade (650.4500) | LF | 1,558 | $0.01 | $1.00 | $1.05 | $0.01 | $1.05 |
| 79 | Construction staking base (650.5000) | LF | 1,558 | $1.00 | $1.00 | $1.05 | $1.05 | $1.05 |
| 80 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 2,749 | $1.25 | $1.25 | $1.31 | $1.30 | $1.30 |
| 81 | Construction staking curb ramps (650.9000) | EACH | 14 | $160.00 | $150.00 | $157.50 | $160.00 | $160.00 |
| 82 | Construction staking sidewalk (project) 01. 7995-02-76 (650.9500) | EACH | 1 | $2,000.00 | $2,000.00 | $2,100.00 | $2,100.00 | $2,100.00 |
| 83 | Construction staking supplemental control (project) 01. 7995-02-76 (650.9911) | EACH | 1 | $2,000.00 | $2,000.00 | $2,100.00 | $2,100.00 | $2,100.00 |
| 84 | Construction staking slope stakes (650.9920) | LF | 1,529 | $1.00 | $1.00 | $1.05 | $1.05 | $1.05 |
| 85 | Geodetic survey monument (682.0200) | EACH | 1 | $3,475.00 | $2,500.00 | $849.48 | $2,100.00 | $3,150.00 |
| 86 | Sawing asphalt (690.0150) | LF | 379 | $3.25 | $3.45 | $2.47 | $4.00 | $2.50 |
| 87 | Sawing concrete (690.0250) | LF | 64 | $4.25 | $6.90 | $3.15 | $5.00 | $3.50 |
| 88 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 300 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 89 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 300 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 90 | Special 01. connect to existing storm sewer manhole (SPV.0060) | EACH | 1 | $1,374.25 | $1,000.00 | $1,301.78 | $1,800.00 | $1,550.00 |
| 91 | Special 02. connect to existing storm sewer pipe (SPV.0060) | EACH | 3 | $1,149.40 | $250.00 | $1,298.53 | $1,000.00 | $700.00 |
| 92 | Special 03. sanitary manholes & castings 4-FT diameter (SPV.0060) | EACH | 1 | $4,501.46 | $4,710.00 | $4,347.20 | $5,300.00 | $5,250.00 |
| 93 | Special 04. sanitary sewer service wye, 8-inch X 4-inch (SPV.0060) | EACH | 6 | $160.84 | $220.00 | $1,213.14 | $375.00 | $400.00 |
| 94 | Special 05. connect to existing sanitary manhole (SPV.0060) | EACH | 1 | $2,249.07 | $1,700.00 | $2,106.81 | $1,400.00 | $1,850.00 |
| 95 | Special 06. remove and replace hydrant (SPV.0060) | EACH | 3 | $2,836.99 | $8,060.00 | $9,087.43 | $5,300.00 | $10,550 |
| 96 | Special 07. cut and cap existing watermain (SPV.0060) | EACH | 3 | $1,279.91 | $1,150.00 | $1,688.76 | $1,100.00 | $1,900.00 |
| 97 | Special 08. adjusting valve boxes (SPV.0060) | EACH | 12 | $270.89 | $380.00 | $353.50 | $400.00 | $200.00 |
| 98 | Special 01. concrete curb & gutter 24-inch type D (SPV.0090) | LF | 2,554 | $15.50 | $18.00 | $18.90 | $20.00 | $16.50 |
| 99 | Special 02. 8-inch sanitary sewer (SPV.0090) | LF | 400 | $43.46 | $68.00 | $58.51 | $44.00 | $60.00 |
| 100 | Special 03. 4-inch sanitary sewer service (SPV.0090) | LF | 92 | $101.71 | $175.00 | $84.82 | $96.00 | $185.00 |
| 101 | Special 04. hydrant lead 6-inch (SPV.0090) | LF | 48 | $291.83 | $93.00 | $112.75 | $133.00 | $200.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of November 10, 2026. Compiled by Mirage Metrics.