Removing catch basins, WisDOT 204.0215

Low bidders on WisDOT contracts carried a median of $483.57 per EACH for this item, over the 24 months to 10 NOV 2026, across 28 low bids. Half of all 112 bids fell between $421.25 and $750.00.

Owner
Wisconsin DOT
Item
204.0215
Unit
EACH
Data through
10 NOV 2026

WisDOT prints this item as “Removing Catch Basins”.

$483.57Low bidder's median, per EACH
$534.00Median of all bids, per EACH
28Contracts in the window

By year of letting

Removing catch basins, WisDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202288$527.6720$500.00
20231313$550.0048$600.00
20241212$582.4048$538.40
20251313$474.0949$500.00
20261111$500.0044$540.75

Bid prices as published, not adjusted for inflation.

By county

CountyLow bidsLow-bid medianAll bidsMedian, all bids
Milwaukee10$430.0036$465.00
Waukesha3$616.1618$610.00
Removing catch basins, WisDOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Quantity (EACH)Low bidsLow-bid median
1 to 27$500.00
2 to 47$638.98
4 to 117$375.00
12 to 607$492.15
Removing catch basins, WisDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

Removing catch basins, WisDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
10 NOV 202620261110014Milwaukee27$400.00$500.003Lalonde Contractors IncorporatedWisDOT
10 NOV 202620261110037Eau Claire2$575.00$575.005Haas Sons, Inc.WisDOT
13 OCT 202620261013007Milwaukee1$1,200.00$1,200.004Wandel Contractors IncWisDOT
11 AUG 202620260811007Dane1$1,600.00$683.193Payne and Dolan, IncWisDOT
11 AUG 202620260811009Walworth9$438.00$470.986Musson Bros., Inc.WisDOT
10 MAR 202620260310016Milwaukee60$350.00$556.505Hoffman Construction CompanyWisDOT
10 MAR 202620260310031Forest1$500.00$500.005S & N IncorporatedWisDOT
10 FEB 202620260210003Dane4$300.00$470.006James Peterson Sons, Inc.WisDOT
10 FEB 202620260210009Milwaukee37$460.00$380.004Lalonde Contractors IncorporatedWisDOT
10 FEB 202620260210014Milwaukee29$600.00$600.001Lalonde Contractors IncorporatedWisDOT
10 FEB 202620260210018Kenosha1$925.00$971.122Musson Bros., Inc.WisDOT
09 DEC 202520251209032Marathon3$450.00$600.002American Asphalt of WisconsinWisDOT
11 NOV 202520251111010Milwaukee3$300.00$300.004Lalonde Contractors IncorporatedWisDOT
14 OCT 202520251014029Waukesha2$805.00$805.006Payne and Dolan, IncWisDOT
13 MAY 202520250513011Milwaukee11$750.00$500.004Zignego Company, Inc.WisDOT
Latest WisDOT contracts carrying Removing catch basins

Filter this item by your own quantity, county and period, or check your price against it, in the WisDOT explorer.

How these prices were read

WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WisDOT's own: this item is compared with WisDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the WisDOT letting of 10 NOV 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way