WisDOT contract 20251111010 bid tabulation

2984-21-71. Let by Wisconsin DOT on November 11, 2025, Milwaukee. 4 bids received; low bid $2,860,142 by Lalonde Contractors Incorporated.

Owner
Wisconsin DOT
Letting
11 NOV 2025
Pay items
167
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Lalonde Contractors Incorporated$2,860,142Low
2Zenith Tech., Inc. - Waukesha$2,950,343+3.0%
3Wandel Contractors Inc$2,989,160+5.0%
4Zignego Company, Inc.$2,997,191+5.0%
WisDOT contract 20251111010: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Lalonde Contractors Incorporated2. Zenith Tech., Inc. - Waukesha3. Wandel Contractors Inc4. Zignego Company, Inc.
1Clearing (201.0120)ID75$44.00$104.78$104.78$40.00
2Grubbing (201.0220)ID75$4.00$10.60$10.60$40.00
3Removing concrete pavement (204.0100)SY1,080$23.00$19.43$19.75$20.00
4Removing asphaltic surface (204.0110)SY44$17.71$11.88$15.00$20.00
5Removing curb & gutter (204.0150)LF250$18.50$30.49$10.50$10.00
6Removing concrete sidewalk (204.0155)SY832$18.00$15.36$18.65$10.00
7Removing concrete bases (204.0195)EACH12$483.33$900.00$400.00$500.00
8Removing catch basins (204.0215)EACH3$300.00$300.00$300.00$936.00
9Abandoning catch basins (204.0255)EACH2$300.00$300.00$300.00$936.00
10Abandoning culvert pipes (204.0270)EACH2$800.00$800.00$800.00$937.00
11Removing (item description) 001. aerial cable (204.9090.S)LF3,000$12.99$12.99$12.99$12.99
12Excavation common (205.0100)CY67$83.35$184.03$140.50$100.00
13Finishing roadway (project) 001. 2984-21-71 (213.0100)EACH1$1,940.00$1,103.92$1,775.00$1,000.00
14Finishing roadway (project) 002. 2984-21-72 (213.0100)EACH1$1,940.00$1,085.34$3,550.00$1,000.00
15Base aggregate dense 3/4-inch (305.0110)TON51$54.17$76.50$70.75$100.00
16Base aggregate dense 1 1/4-inch (305.0120)TON254$56.80$76.57$35.75$80.00
17Concrete base 9-inch (320.0155)SY72$94.30$116.86$86.15$140.00
18Concrete pavement 9-inch (415.0090)SY843$93.10$112.46$107.75$140.00
19Drilled tie bars (416.0610)EACH544$18.00$20.06$15.50$15.00
20Drilled dowel bars (416.0620)EACH170$25.00$25.46$20.00$15.00
21Tack coat (455.0605)GAL6$1.00$1.00$1.00$1.00
22Asphaltic surface (465.0105)TON15$235.00$235.00$235.00$235.00
23Concrete curb & gutter 22-inch (601.0322)LF100$57.83$64.32$60.75$60.00
24Concrete curb & gutter 31-inch (601.0331)LF326$65.00$67.82$66.00$60.00
25Concrete sidewalk 5-inch (602.0410)SF7,902$12.85$13.35$10.50$10.72
26Curb ramp detectable warning field natural patina (602.0515)SF200$43.97$42.05$55.00$50.00
27Concrete driveway 8-inch (602.0820)SY27$141.35$133.60$113.75$140.00
28Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF96$150.00$150.00$150.00$246.00
29Storm sewer pipe composite 8-inch (608.6008)LF15$130.00$130.00$130.00$446.00
30Inlets 2X2.5-FT (611.3225)EACH9$3,000.00$3,000.00$3,000.00$1,541.00
31Mobilization (619.1000)EACH1$276,696$280,058$383,004$371,000
32Water (624.0100)MGAL0.20$251.00$56.05$2,500.00$1,000.00
33Topsoil (625.0100)SY166$12.00$12.00$18.00$15.00
34Mobilizations erosion control (628.1905)EACH3$125.00$125.00$200.00$150.00
35Mobilizations emergency erosion control (628.1910)EACH3$1.00$1.00$200.00$150.00
36Inlet protection type C (628.7015)EACH20$70.00$70.00$62.50$65.00
37Inlet protection type D (628.7020)EACH12$130.00$130.00$120.00$95.00
38Sod water (631.0300)MGAL4.50$101.00$101.00$40.00$150.00
39Sod lawn (631.1000)SY166$30.00$30.00$12.00$25.00
40Signs type II reflective SH (637.2220)SF30$30.00$30.00$33.00$45.00
41Field office type C (642.5201)EACH1$18,864$28,033$5,500.00$20,000
42Traffic control drums (643.0300)DAY19,760$0.19$0.19$0.19$0.19
43Traffic control barricades type III (643.0420)DAY2,201$0.51$0.51$0.51$0.51
44Traffic control flexible tubular marker posts (643.0500)EACH119$22.19$22.19$22.19$22.19
45Traffic control flexible tubular marker bases (643.0600)EACH119$9.43$9.43$9.43$9.43
46Traffic control warning lights type A (643.0705)DAY4,402$0.21$0.21$0.21$0.21
47Traffic control warning lights type C (643.0715)DAY6,320$0.21$0.21$0.21$0.21
48Traffic control signs (643.0900)DAY16,184$0.36$0.36$0.36$0.36
49Traffic control signs PCMS (643.1050)DAY60$33.50$33.50$33.50$33.50
50Temporary marking line removable tape 4-inch (643.3150)LF19,252$0.66$0.66$0.66$0.66
51Temporary marking line removable tape 6-inch (643.3180)LF1,215$1.59$1.59$1.59$1.59
52Temporary marking line removable tape 8-inch (643.3250)LF552$2.10$2.10$2.10$2.10
53Temporary marking crosswalk removable tape 6-inch (643.3350)LF298$4.36$4.36$4.36$4.36
54Temporary marking arrow removable tape (643.3550)EACH9$167.67$167.67$167.67$167.67
55Temporary marking stop line removable tape 18-inch (643.3850)LF212$6.22$6.22$6.22$6.22
56Traffic control (643.5000)EACH1$14,827$14,827$14,827$14,827
57Temporary pedestrian barricade (644.1810)LF414$5.77$5.77$5.77$5.77
58Temporary audible message devices (644.1900.S)DAY3,708$2.08$2.08$2.08$2.08
59Marking line epoxy 4-inch (646.1020)LF17,138$0.85$0.85$0.38$0.85
60Marking line epoxy 8-inch (646.3020)LF1,718$1.70$1.70$1.00$1.70
61Marking arrow epoxy (646.5020)EACH24$235.00$235.00$402.00$235.00
62Marking symbol epoxy (646.5220)EACH12$215.00$215.00$391.00$215.00
63Marking diagonal epoxy 12-inch (646.7120)LF656$10.00$10.00$16.45$10.00
64Marking crosswalk epoxy transverse line 6-inch (646.7420)LF1,183$10.50$10.50$16.00$10.50
65Marking removal line 4-inch (646.9000)LF6,951$0.55$0.55$0.55$0.55
66Marking removal line 6-inch (646.9002)LF740$1.00$1.00$1.00$1.00
67Marking removal line wide (646.9200)LF142$2.52$2.52$2.52$2.52
68Marking removal special marking (646.9300)EACH16$116.50$116.50$116.50$116.50
69Construction staking storm sewer (650.4000)EACH12$125.00$150.00$160.00$150.00
70Construction staking curb gutter and curb & gutter (650.5500)LF1,016$2.00$1.75$5.00$1.75
71Construction staking electrical installations (project) 001. 2984-21- 71 (650.8501)EACH1$500.00$2,000.00$1,875.00$2,000.00
72Construction staking electrical installations (project) 002. 2984-21- 72 (650.8501)EACH1$500.00$3,000.00$3,675.00$3,000.00
73Construction staking curb ramps (650.9000)EACH20$125.00$275.00$220.00$275.00
74Construction staking sidewalk (project) 001. 2984-21-71 (650.9500)EACH1$1,000.00$1,000.00$2,000.00$1,000.00
75Construction staking sidewalk (project) 002. 2984-21-72 (650.9500)EACH1$1,500.00$1,500.00$3,400.00$1,500.00
76Construction staking supplemental control (project) 001. 2984-21-71 (650.9911)EACH1$750.00$1,500.00$2,000.00$1,500.00
77Construction staking supplemental control (project) 002. 2984-21-72 (650.9911)EACH1$750.00$2,500.00$3,500.00$2,500.00
78Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF35$14.32$14.32$14.32$14.32
79Conduit rigid nonmetallic schedule 40 3-inch (652.0235)LF2,545$15.66$15.66$15.66$15.66
80Conduit special 3-inch (652.0615)LF1,560$48.40$48.40$48.40$48.40
81Removing pull boxes (653.0905)EACH16$203.00$203.00$203.00$203.00
82Concrete bases type 1 (654.0101)EACH1$1,080.00$1,080.00$1,080.00$1,080.00
83Concrete bases type 10 (654.0110)EACH10$9,732.00$9,732.00$9,732.00$9,732.00
84Concrete bases type 10-special (654.0120)EACH2$11,214$11,214$11,214$11,214
85Cable traffic signal 5-14 AWG (655.0230)LF2,355$3.39$3.39$3.39$3.39
86Cable traffic signal 9-14 AWG (655.0250)LF20$4.36$4.36$4.36$4.36
87Cable traffic signal 19-14 AWG (655.0280)LF1,715$6.83$6.83$6.83$6.83
88Cable traffic signal 21-14 AWG (655.0290)LF1,250$7.40$7.40$7.40$7.40
89Cable type UF 2-12 AWG grounded (655.0305)LF4,795$2.65$2.65$2.65$2.65
90Cable type UF 2-10 AWG grounded (655.0320)LF400$3.59$3.59$3.59$3.59
91Electrical wire traffic signals 10 AWG (655.0515)LF1,935$2.62$2.62$2.62$2.62
92Traffic signal evp detector cable (655.0900)LF2,075$2.96$2.96$2.96$2.96
93Pedestal bases (657.0100)EACH1$310.00$310.00$310.00$310.00
94Transformer bases breakaway 11 1/2-inch bolt circle (657.0255)EACH5$726.00$726.00$726.00$726.00
95Poles type 10 (657.0350)EACH10$12,923$12,923$12,923$12,923
96Poles type 10-special (657.0352)EACH2$14,073$14,073$14,073$14,073
97Traffic signal standards aluminum 3.5-FT (657.0405)EACH1$309.00$309.00$309.00$309.00
98Monotube arms 20-FT (657.0520)EACH1$6,825.00$6,825.00$6,825.00$6,825.00
99Monotube arms 25-FT (657.0525)EACH1$7,400.00$7,400.00$7,400.00$7,400.00
100Monotube arms 30-FT (657.0530)EACH8$8,060.00$8,060.00$8,060.00$8,060.00
101Monotube arms 35-FT-special (657.0536)EACH2$8,517.00$8,517.00$8,517.00$8,517.00
102Traffic signal face 3S 12-inch (658.0173)EACH56$1,472.00$1,472.00$1,472.00$1,472.00
103Pedestrian signal face 12-inch (658.0412)EACH24$1,249.00$1,249.00$1,249.00$1,249.00
104Signal mounting hardware (location) 001. W center ST (658.5070)EACH1$7,870.00$7,870.00$7,870.00$7,870.00
105Signal mounting hardware (location) 002. W lisbon ave (658.5070)EACH1$6,352.00$6,352.00$6,352.00$6,352.00
106Signal mounting hardware (location) 003. W north ave (658.5070)EACH1$7,645.00$7,645.00$7,645.00$7,645.00
107Lamp, ballast, LED, switch disposal by contractor (659.5000.S)EACH60$9.10$9.10$9.10$9.10
108Temporary traffic signals for intersections (location) 001. W center ST (661.0201)EACH1$61,500$61,500$61,500$61,500
109Temporary traffic signals for intersections (location) 002. W lisbon ave (661.0201)EACH1$62,017$62,017$62,017$62,017
110Temporary traffic signals for intersections (location) 003. W north ave (661.0201)EACH1$62,362$62,362$62,362$62,362
111Remove cable (674.0300)LF200$3.65$3.65$3.65$3.65
112Sawing asphalt (690.0150)LF92$1.15$1.15$2.00$1.15
113Sawing concrete (690.0250)LF1,749$2.25$2.25$2.00$2.25
114Incentive compressive strength concrete pavement (715.0720)DOL1,000$1.00$1.00$1.00$1.00
115On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,400$5.00$5.00$5.00$5.00
116On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS4,800$5.00$5.00$5.00$5.00
117Special 001. utility line opening (SPV.0060)EACH3$1,703.03$800.00$800.00$2,000.00
118Special 002. adjusting water valve boxes (SPV.0060)EACH9$700.00$700.00$700.00$289.00
119Special 003. section corner monuments (SPV.0060)EACH2$1,692.00$2,860.25$1,500.00$1,950.00
120Special 004. water main protection (SPV.0060)EACH3$500.00$500.00$500.00$1.00
121Special 102. inlet covers type MS 57 (SPV.0060)EACH12$900.00$900.00$900.00$966.00
122Special 103. manhole covers type MS 58-A (SPV.0060)EACH9$1,050.00$1,050.00$1,050.00$954.00
123Special 110. catch basin type 44A (SPV.0060)EACH3$6,000.00$6,000.00$6,000.00$4,531.00
124Special 201. install city precast controller base (SPV.0060)EACH3$1,322.00$1,322.00$1,322.00$1,322.00
125Special 205. atc controller and cabinet installed (SPV.0060)EACH3$39,662$39,662$39,662$39,662
126Special 212. fiber optic patch panel (SPV.0060)EACH3$4,516.00$4,516.00$4,516.00$4,516.00
127Special 213. ethernet switch (SPV.0060)EACH3$5,746.00$5,746.00$5,746.00$5,746.00
128Special 215. electrical service pedestal (SPV.0060)EACH3$2,150.00$2,150.00$2,150.00$2,150.00
129Special 218. evp 1 direction detector (SPV.0060)EACH12$1,445.00$1,445.00$1,445.00$1,445.00
130Special 221. evp phase selector card 4 channel (SPV.0060)EACH3$5,616.00$5,616.00$5,616.00$5,616.00
131Special 223. evp confirmation light (SPV.0060)EACH12$434.00$434.00$434.00$434.00
132Special 228. electrical riser (SPV.0060)EACH8$811.00$811.00$811.00$811.00
133Special 243 remove traffic signals (W center ST) (SPV.0060)EACH1$8,610.00$8,610.00$8,610.00$8,610.00
134Special 244. remove traffic signals (W lisbon ave) (SPV.0060)EACH1$8,610.00$8,610.00$8,610.00$8,610.00
135Special 245. remove traffic signals (W north ave) (SPV.0060)EACH1$8,610.00$8,610.00$8,610.00$8,610.00
136Special 267. pedestrian countdown signal face 12-inch (SPV.0060)EACH24$1,187.00$1,187.00$1,187.00$1,187.00
137Special 268. voice instruction audible pushbutton (SPV.0060)EACH24$865.00$865.00$865.00$865.00
138Special 269. voice instruction audible control unit (SPV.0060)EACH3$3,401.00$3,401.00$3,401.00$3,401.00
139Special 291. street name sign mounting hardware on mast arm (SPV.0060)EACH4$30.00$30.00$250.00$300.00
140Special 302. pull boxes 13-inch X 24-inch X 24-inch (SPV.0060)EACH26$2,280.00$2,280.00$2,280.00$2,280.00
141Special 303. pull boxes 17-inch X 30-inch X 24-inch (SPV.0060)EACH26$2,526.00$2,526.00$2,526.00$2,526.00
142Special 310. remove poles complete (SPV.0060)EACH23$587.20$587.20$587.20$587.20
143Special 321. poles type 30-AL-BD (SPV.0060)EACH5$2,732.00$2,732.00$2,732.00$2,732.00
144Special 324. 40 FT. wood pole (SPV.0060)EACH16$2,269.00$2,269.00$2,269.00$2,269.00
145Special 334. inline 5A fast acting fuse with holder (SPV.0060)EACH31$182.00$182.00$182.00$182.00
146Special 339. primary or secondary riser (SPV.0060)EACH14$1,454.00$1,454.00$1,454.00$1,454.00
147Special 345. luminaire arms single member 6-FT. (SPV.0060)EACH9$347.00$347.00$347.00$347.00
148Special 346. luminaire arms single member 6-FT. WP mount (SPV.0060)EACH17$386.00$386.00$386.00$386.00
149Special 353. equipment grounding electrode (SPV.0060)EACH24$179.00$179.00$179.00$179.00
150Special 357. luminaire arms mounting clamps poles type -3 single bracket (SPV.0060)EACH11$1,204.00$1,204.00$1,204.00$1,204.00
151Special 360. water tight splices and connections (SPV.0060)EACH130$190.00$190.00$190.00$190.00
152Special 376. luminaire utility 3LED2 (SPV.0060)EACH22$2,195.00$2,195.00$2,195.00$2,195.00
153Special 400. adjusting cuc manhole cover (SPV.0060)EACH6$1,500.00$1,500.00$1,500.00$653.00
154Special 801. poles type H17 (SPV.0060)EACH3$4,700.00$4,700.00$4,700.00$4,700.00
155Special 819. poles type A31-BD (SPV.0060)EACH11$7,224.00$7,224.00$7,224.00$7,224.00
156Special 820. concrete base type 5 modified (SPV.0060)EACH5$1,178.00$1,178.00$1,178.00$1,178.00
157Special 821. concrete base type 2 modified (SPV.0060)EACH11$1,390.00$1,390.00$1,390.00$1,390.00
158Special 865. luminaire historic milwaukee harp LED 1 (SPV.0060)EACH3$3,221.00$3,221.00$3,221.00$3,221.00
159Special 867. luminaire historic milwaukee lantern LED 3 (SPV.0060)EACH19$3,204.00$3,204.00$3,204.00$3,204.00
160Special 001. marking stop line epoxy 24-inch (SPV.0090)LF329$18.00$18.00$17.30$18.00
161Special 011. concrete curb & gutter integral 31-inch (SPV.0090)LF590$27.80$72.73$66.50$60.00
162Special 240. electrical cable 3#4/1#8 XLP (SPV.0090)LF440$15.11$15.11$15.11$15.11
163Special 302. electrical cable type 3#6 AL (SPV.0090)LF800$9.22$9.22$9.22$9.22
164Special 304. electrical cable type 2#2/1#4 AL (SPV.0090)LF1,450$9.52$9.52$9.52$9.52
165Special 319. liquidtight flexible nonmetallic 1 ½ - inch conduit (SPV.0090)LF295$48.00$48.00$48.00$48.00
166Special 324. electrical cable type 4#2/1#8 XLP (SPV.0090)LF4,515$21.05$21.05$21.05$21.05
167Special 325. conduit 3-inch HDPE schedule 40 (SPV.0090)LF3,535$24.80$24.80$24.80$24.80
WisDOT contract 20251111010: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of November 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy