Concrete curb & gutter 31-inch, WisDOT 601.0331

Low bidders on WisDOT contracts carried a median of $43.00 per LF for this item, over the 24 months to 10 NOV 2026, across 32 low bids. Half of all 121 bids fell between $30.00 and $60.00.

Owner
Wisconsin DOT
Item
601.0331
Unit
LF
Data through
10 NOV 2026

WisDOT prints this item as “Concrete Curb & Gutter 31-Inch”.

$43.00Low bidder's median, per LF
$42.00Median of all bids, per LF
34Contracts in the window

By year of letting

Concrete curb & gutter 31-inch, WisDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20221414$28.6840$32.50
20231110$31.2636$41.20
20241212$42.4848$35.67
20252120$43.0075$42.00
20261211$42.0041$40.77

Bid prices as published, not adjusted for inflation.

By quantity

Quantity (LF)Low bidsLow-bid median
26 to 3268$68.63
344 to 1,2698$52.74
1,281 to 5,6718$31.09
6,636 to 28,5128$29.90
Concrete curb & gutter 31-inch, WisDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

Concrete curb & gutter 31-inch, WisDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
10 NOV 202620261110014Milwaukee18,100$35.30$35.303Lalonde Contractors IncorporatedWisDOT
10 NOV 202620261110015Milwaukee1,152$53.00$49.255Payne and Dolan, IncWisDOT
13 OCT 202620261013006Milwaukee2,873$34.00$57.002Zenith Tech., Inc. - WaukeshaWisDOT
13 OCT 202620261013007Milwaukee35$66.00$83.004Wandel Contractors IncWisDOT
15 SEP 202620260915007Milwaukee6,636$42.00$56.183Payne and Dolan, IncWisDOT
14 JUL 202620260714004Milwaukee6,765$48.80$39.006Lalonde Contractors IncorporatedWisDOT
10 MAR 202620260310016Milwaukee18,315$25.15$27.085Hoffman Construction CompanyWisDOT
10 FEB 202620260210009Milwaukee7,160$29.35$24.844Lalonde Contractors IncorporatedWisDOT
10 FEB 202620260210010Milwaukee344$63.12$66.363Lalonde Contractors IncorporatedWisDOT
10 FEB 202620260210013Milwaukee282n/a$28.001WisDOT
10 FEB 202620260210014Milwaukee8,908$30.45$30.451Lalonde Contractors IncorporatedWisDOT
10 FEB 202620260210015Milwaukee1,387$65.79$55.814Wandel Contractors IncWisDOT
11 NOV 202520251111010Milwaukee326$65.00$65.504Lalonde Contractors IncorporatedWisDOT
14 OCT 202520251014007Milwaukee1,012$66.55$64.004Lalonde Contractors IncorporatedWisDOT
14 OCT 202520251014029Waukesha179$71.26$62.506Payne and Dolan, IncWisDOT
Latest WisDOT contracts carrying Concrete curb & gutter 31-inch

Filter this item by your own quantity, county and period, or check your price against it, in the WisDOT explorer.

How these prices were read

WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WisDOT's own: this item is compared with WisDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the WisDOT letting of 10 NOV 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy