WisDOT contract 20260210010 bid tabulation
C Greenfield, Cudahy, Layton Ave; Intersections 84th, 68th, Nicholson (CTH Y, Milwaukee County C Greenfield, Cudahy, Layton Ave). Let by Wisconsin DOT on February 10, 2026, Milwaukee. 3 bids received; low bid $978,509 by Lalonde Contractors Incorporated.
- Owner
- Wisconsin DOT
- Letting
- 10 FEB 2026
- Pay items
- 139
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Lalonde Contractors Incorporated | $978,509 | Low |
| 2 | Zenith Tech., Inc. - Waukesha | $1,018,160 | +4.0% |
| 3 | Zignego Company, Inc. | $1,154,058 | +18% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Lalonde Contractors Incorporated | 2. Zenith Tech., Inc. - Waukesha | 3. Zignego Company, Inc. |
|---|---|---|---|---|---|---|
| 1 | Removing concrete pavement (204.0100) | SY | 98 | $21.14 | $30.00 | $28.00 |
| 2 | Removing curb & gutter (204.0150) | LF | 235 | $14.99 | $25.00 | $40.00 |
| 3 | Removing concrete sidewalk (204.0155) | SY | 197 | $15.63 | $20.00 | $40.00 |
| 4 | Removing concrete bases (204.0195) | EACH | 14 | $350.00 | $297.10 | $300.00 |
| 5 | Removing (item description) 01. traffic signal equipment at CTH Y and 84TH (204.9060.S) | EACH | 1 | $5,198.00 | $5,318.81 | $5,318.81 |
| 6 | Removing (item description) 02. traffic signal equipment at CTH Y and 68TH (204.9060.S) | EACH | 1 | $2,789.00 | $405.93 | $405.93 |
| 7 | Removing (item description) 03. traffic signal equipment at CTH Y and nicholson (204.9060.S) | EACH | 1 | $5,198.00 | $5,318.81 | $5,318.81 |
| 8 | Removing (item description) 04. concrete base bolts (204.9060.S) | EACH | 4 | $2,315.00 | $326.31 | $326.31 |
| 9 | Excavation common (205.0100) | CY | 130 | $76.10 | $65.00 | $100.00 |
| 10 | Excavation, hauling, and disposal of petroleum contaminated soil (205.0501.S) | TON | 44.50 | $515.07 | $300.00 | $200.00 |
| 11 | Finishing roadway (project) 01. 2070-03-77 (213.0100) | EACH | 1 | $3,110.00 | $1,904.97 | $1,000.00 |
| 12 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 137 | $46.51 | $46.00 | $50.00 |
| 13 | Base aggregate open-graded (310.0110) | TON | 59 | $50.44 | $46.00 | $50.00 |
| 14 | Stamping colored concrete (405.1000) | CY | 3 | $381.99 | $634.02 | $500.00 |
| 15 | Concrete pavement 9-inch (415.0090) | SY | 47 | $147.93 | $262.85 | $260.00 |
| 16 | Drilled tie bars (416.0610) | EACH | 202 | $17.96 | $7.93 | $30.00 |
| 17 | Concrete curb & gutter 31-inch (601.0331) | LF | 344 | $63.12 | $66.36 | $110.00 |
| 18 | Concrete curb pedestrian (601.0600) | LF | 65 | $54.23 | $63.11 | $110.00 |
| 19 | Concrete sidewalk 7-inch (602.0420) | SF | 2,025 | $14.33 | $15.55 | $26.00 |
| 20 | Curb ramp detectable warning field natural patina (602.0515) | SF | 172 | $43.20 | $33.01 | $60.00 |
| 21 | Pipe underdrain wrapped 4-inch (612.0404) | LF | 135 | $49.47 | $8.47 | $40.00 |
| 22 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 86 | $50.33 | $12.69 | $60.00 |
| 23 | Mobilization (619.1000) | EACH | 1 | $76,096 | $62,600 | $165,000 |
| 24 | Concrete median sloped nose (620.0300) | SF | 114 | $32.76 | $29.22 | $50.00 |
| 25 | Topsoil (625.0100) | SY | 178 | $5.95 | $8.00 | $8.00 |
| 26 | Mobilizations erosion control (628.1905) | EACH | 2 | $150.00 | $100.00 | $100.00 |
| 27 | Mobilizations emergency erosion control (628.1910) | EACH | 2 | $150.00 | $100.00 | $100.00 |
| 28 | Soil stabilizer type B (628.6510) | ACRE | 0.04 | $1,500.00 | $1.00 | $1.00 |
| 29 | Inlet protection type B (628.7010) | EACH | 24 | $55.00 | $60.00 | $60.00 |
| 30 | Inlet protection type C (628.7015) | EACH | 13 | $55.00 | $70.00 | $70.00 |
| 31 | Fertilizer type B (629.0210) | CWT | 0.12 | $950.00 | $80.00 | $80.00 |
| 32 | Sod water (631.0300) | MGAL | 5 | $65.00 | $50.00 | $50.00 |
| 33 | Sod lawn (631.1000) | SY | 178 | $9.95 | $7.00 | $7.50 |
| 34 | Posts tubular steel 2X2-inch X 11- FT (634.0811) | EACH | 9 | $205.00 | $215.00 | $215.00 |
| 35 | Signs type II reflective H (637.2210) | SF | 154.26 | $23.00 | $24.00 | $24.00 |
| 36 | Signs type II reflective H folding (637.2215) | SF | 93.24 | $28.00 | $28.00 | $28.00 |
| 37 | Removing signs type II (638.2602) | EACH | 18 | $28.00 | $20.00 | $20.00 |
| 38 | Removing small sign supports (638.3000) | EACH | 2 | $25.00 | $20.00 | $20.00 |
| 39 | Field office type B (642.5001) | EACH | 1 | $26,864 | $11,473 | $15,000 |
| 40 | Traffic control drums (643.0300) | DAY | 20,700 | $0.19 | $0.14 | $0.19 |
| 41 | Traffic control barricades type III (643.0420) | DAY | 2,775 | $0.60 | $0.21 | $0.60 |
| 42 | Traffic control warning lights type A (643.0705) | DAY | 5,550 | $0.13 | $0.05 | $0.13 |
| 43 | Traffic control warning lights type C (643.0715) | DAY | 2,910 | $0.13 | $0.05 | $0.13 |
| 44 | Traffic control signs (643.0900) | DAY | 11,215 | $0.49 | $0.32 | $0.49 |
| 45 | Traffic control signs PCMS (643.1050) | DAY | 70 | $45.00 | $39.14 | $45.00 |
| 46 | Temporary marking line removable tape 6-inch (643.3180) | LF | 260 | $1.76 | $1.87 | $1.76 |
| 47 | Traffic control (643.5000) | EACH | 1 | $16,560 | $31,818 | $16,560 |
| 48 | Temporary pedestrian surface matting (644.1440) | SF | 145 | $6.99 | $9.93 | $6.99 |
| 49 | Temporary pedestrian curb ramp (644.1601) | DAY | 55 | $16.81 | $15.15 | $16.81 |
| 50 | Temporary pedestrian detectable warning field (644.1605) | SF | 46 | $10.24 | $20.20 | $10.24 |
| 51 | Temporary pedestrian barricade (644.1810) | LF | 735 | $3.73 | $6.06 | $3.73 |
| 52 | Temporary audible message devices (644.1900.S) | DAY | 1,185 | $3.75 | $5.05 | $3.75 |
| 53 | Geotextile type DF schedule A (645.0111) | SY | 163 | $2.71 | $9.03 | $5.00 |
| 54 | Marking line epoxy 6-inch (646.2020) | LF | 650 | $1.25 | $2.32 | $1.25 |
| 55 | Marking line epoxy 10-inch (646.4020) | LF | 130 | $1.70 | $3.89 | $1.70 |
| 56 | Marking arrow epoxy (646.5020) | EACH | 21 | $320.00 | $237.37 | $320.00 |
| 57 | Marking word epoxy (646.5120) | EACH | 11 | $350.00 | $267.68 | $350.00 |
| 58 | Marking stop line epoxy 18-inch (646.6120) | LF | 350 | $16.25 | $12.27 | $16.25 |
| 59 | Marking yield line epoxy 18-inch (646.6220) | EACH | 20 | $28.50 | $45.45 | $28.50 |
| 60 | Cold weather marking epoxy 6-inch (646.6466) | LF | 650 | $2.75 | $5.05 | $2.75 |
| 61 | Cold weather marking epoxy 10- inch (646.6470) | LF | 110 | $3.50 | $8.33 | $3.50 |
| 62 | Marking diagonal epoxy 12-inch (646.7120) | LF | 40 | $14.75 | $10.10 | $14.75 |
| 63 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 1,410 | $10.50 | $11.36 | $10.50 |
| 64 | Marking removal line 4-inch (646.9000) | LF | 520 | $0.50 | $0.66 | $0.50 |
| 65 | Marking removal line 6-inch (646.9002) | LF | 1,420 | $0.66 | $0.76 | $0.66 |
| 66 | Marking removal line 8-inch (646.9100) | LF | 90 | $1.15 | $1.01 | $1.15 |
| 67 | Marking removal line wide (646.9200) | LF | 85 | $1.83 | $1.01 | $1.83 |
| 68 | Marking removal special marking (646.9300) | EACH | 2 | $78.83 | $101.01 | $78.83 |
| 69 | Construction staking subgrade (650.4500) | LF | 93 | $1.50 | $1.91 | $1.50 |
| 70 | Construction staking base (650.5000) | LF | 93 | $1.50 | $1.91 | $1.50 |
| 71 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 344 | $2.50 | $3.19 | $2.50 |
| 72 | Construction staking concrete pavement (650.7000) | LF | 93 | $4.00 | $5.10 | $4.00 |
| 73 | Construction staking electrical installations (project) 01. 2070-03- 77 (650.8501) | EACH | 1 | $1,900.00 | $2,422.09 | $1,900.00 |
| 74 | Construction staking curb ramps (650.9000) | EACH | 15 | $200.00 | $254.96 | $200.00 |
| 75 | Construction staking sidewalk (project) 01. 2070-03-77 (650.9500) | EACH | 1 | $1,650.00 | $2,103.39 | $1,650.00 |
| 76 | Construction staking supplemental control (project) 01. 2070-03-77 (650.9911) | EACH | 1 | $1,500.00 | $1,912.18 | $1,500.00 |
| 77 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 95 | $10.68 | $10.12 | $10.12 |
| 78 | Conduit rigid nonmetallic schedule 40 3-inch (652.0235) | LF | 115 | $11.74 | $11.87 | $11.87 |
| 79 | Install conduit into existing item (652.0700.S) | EACH | 17 | $432.00 | $302.15 | $302.15 |
| 80 | Adjusting pull boxes (653.0900) | EACH | 4 | $498.00 | $671.22 | $671.22 |
| 81 | Concrete bases type 1 (654.0101) | EACH | 7 | $1,168.00 | $932.13 | $932.13 |
| 82 | Concrete bases type 2 (654.0102) | EACH | 3 | $1,434.00 | $1,133.23 | $1,133.23 |
| 83 | Concrete bases type 10 (654.0110) | EACH | 1 | $8,976.00 | $9,168.78 | $9,168.78 |
| 84 | Concrete bases type 13 (654.0113) | EACH | 1 | $14,565 | $15,327 | $15,327 |
| 85 | Concrete bases type 10-special (654.0120) | EACH | 6 | $9,908.00 | $10,948 | $10,948 |
| 86 | Cable traffic signal 3-14 AWG (655.0210) | LF | 1,495 | $1.76 | $1.73 | $1.73 |
| 87 | Cable traffic signal 5-14 AWG (655.0230) | LF | 1,776 | $1.98 | $1.83 | $1.83 |
| 88 | Cable traffic signal 7-14 AWG (655.0240) | LF | 975 | $2.48 | $2.52 | $2.52 |
| 89 | Cable traffic signal 12-14 AWG (655.0260) | LF | 1,995 | $3.62 | $3.65 | $3.65 |
| 90 | Cable traffic signal 15-14 AWG (655.0270) | LF | 340 | $3.74 | $4.69 | $4.69 |
| 91 | Cable traffic signal 19-14 AWG (655.0280) | LF | 160 | $3.92 | $6.40 | $6.40 |
| 92 | Cable type UF 2-12 AWG grounded (655.0305) | LF | 645 | $1.67 | $1.62 | $1.62 |
| 93 | Electrical wire traffic signals 10 AWG (655.0515) | LF | 1,915 | $1.33 | $1.68 | $1.68 |
| 94 | Electrical wire lighting 12 AWG (655.0610) | LF | 699 | $1.08 | $0.94 | $0.94 |
| 95 | Traffic signal evp detector cable (655.0900) | LF | 1,615 | $1.74 | $1.40 | $1.40 |
| 96 | Pedestal bases (657.0100) | EACH | 16 | $345.00 | $430.11 | $430.11 |
| 97 | Transformer bases breakaway 11 1/2-inch bolt circle (657.0255) | EACH | 3 | $698.00 | $716.61 | $716.61 |
| 98 | Poles type 2 (657.0305) | EACH | 2 | $4,133.00 | $3,066.50 | $3,066.50 |
| 99 | Poles type 4 (657.0315) | EACH | 1 | $3,851.00 | $2,768.86 | $2,768.86 |
| 100 | Poles type 9 - over height special (657.0348) | EACH | 1 | $11,465 | $13,029 | $13,029 |
| 101 | Poles type 10 (657.0350) | EACH | 1 | $9,717.00 | $11,024 | $11,024 |
| 102 | Poles type 10-special (657.0352) | EACH | 4 | $12,517 | $14,402 | $14,402 |
| 103 | Poles type 10 - over height special (657.0353) | EACH | 1 | $12,778 | $14,638 | $14,638 |
| 104 | Poles type 13 (657.0360) | EACH | 1 | $16,578 | $19,738 | $19,738 |
| 105 | Traffic signal standards aluminum 3.5-FT (657.0405) | EACH | 1 | $399.00 | $531.22 | $531.22 |
| 106 | Traffic signal standards aluminum 15-FT (657.0425) | EACH | 9 | $790.00 | $1,176.90 | $1,176.90 |
| 107 | Traffic signal standards aluminum 10-FT (657.0430) | EACH | 6 | $730.00 | $971.22 | $971.22 |
| 108 | Monotube arms 30-FT (657.0530) | EACH | 1 | $5,856.00 | $6,804.44 | $6,804.44 |
| 109 | Monotube arms 40-FT-special (657.0541) | EACH | 1 | $6,935.00 | $6,798.67 | $6,798.67 |
| 110 | Monotube arms 45-FT-special (657.0546) | EACH | 5 | $7,123.00 | $7,090.88 | $7,090.88 |
| 111 | Monotube arms 55-FT (657.0555) | EACH | 1 | $16,978 | $17,890 | $17,890 |
| 112 | Trombone arms 15-FT (657.0585) | EACH | 1 | $1,879.00 | $2,199.70 | $2,199.70 |
| 113 | Trombone arms 25-FT (657.0595) | EACH | 1 | $2,079.00 | $3,048.09 | $3,048.09 |
| 114 | Luminaire arms single member 4- inch clamp 8-FT (657.0614) | EACH | 1 | $543.00 | $478.16 | $478.16 |
| 115 | Luminaire arms steel 15-FT (657.0815) | EACH | 8 | $996.00 | $1,168.86 | $1,168.86 |
| 116 | Traffic signal face 3S 12-inch (658.0173) | EACH | 31 | $740.00 | $783.63 | $783.63 |
| 117 | Traffic signal face 4S 12-inch (658.0174) | EACH | 14 | $900.00 | $988.14 | $988.14 |
| 118 | Pedestrian signal face 16-inch (658.0416) | EACH | 18 | $560.00 | $528.27 | $528.27 |
| 119 | Signal mounting hardware (location) 01. CTH Y and 84TH (658.5070) | EACH | 1 | $6,754.00 | $6,490.42 | $6,490.42 |
| 120 | Signal mounting hardware (location) 02. CTH Y and 68TH (658.5070) | EACH | 1 | $3,421.00 | $2,698.38 | $2,698.38 |
| 121 | Signal mounting hardware (location) 03. CTH Y and nicholson (658.5070) | EACH | 1 | $4,700.00 | $5,076.44 | $5,076.44 |
| 122 | Luminaires utility LED C (659.1125) | EACH | 5 | $425.00 | $587.67 | $587.67 |
| 123 | Temporary traffic signals for intersections (location) 01. CTH Y and 84TH (661.0201) | EACH | 1 | $46,000 | $51,054 | $51,054 |
| 124 | Temporary traffic signals for intersections (location) 02. CTH Y and nicholson (661.0201) | EACH | 1 | $46,000 | $53,960 | $53,960 |
| 125 | Sawing concrete (690.0250) | LF | 571 | $2.25 | $1.65 | $2.00 |
| 126 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 3,000 | $5.00 | $5.00 | $5.00 |
| 127 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 5,700 | $5.00 | $5.00 | $5.00 |
| 128 | Special 01. backfill slurry (SPV.0035) | CY | 20 | $150.50 | $456.03 | $300.00 |
| 129 | Special 01. adjusting water valve boxes (SPV.0060) | EACH | 3 | $463.00 | $1,350.67 | $1,000.00 |
| 130 | Special 02. remove and reinstall video detection system (SPV.0060) | EACH | 3 | $3,248.00 | $6,375.26 | $6,375.26 |
| 131 | Special 03. remove and reinstall evp detectors (SPV.0060) | EACH | 3 | $2,180.00 | $2,358.79 | $2,358.79 |
| 132 | Special 04. remove and reinstall accessible pedestrian push button system, 8 buttons (SPV.0060) | EACH | 1 | $2,567.00 | $3,566.02 | $3,566.02 |
| 133 | Special 05. transport and install traffic signal cabinet (SPV.0060) | EACH | 1 | $3,498.00 | $4,538.91 | $4,538.91 |
| 134 | Special 06. cored sign post holes 12-inch (SPV.0060) | EACH | 4 | $115.00 | $400.00 | $400.00 |
| 135 | Special 07. accessible pedestrian push button system, 8 buttons (SPV.0060) | EACH | 1 | $9,764.00 | $11,665 | $11,665 |
| 136 | Special 08. utility line opening (ulo) (SPV.0060) | EACH | 9 | $1,300.00 | $1,382.68 | $0.01 |
| 137 | Special 09. cabinet modification (SPV.0060) | EACH | 2 | $2,543.00 | $3,852.18 | $3,852.18 |
| 138 | Special 10. section corner monuments (SPV.0060) | EACH | 2 | $1,624.00 | $2,718.70 | $2,000.00 |
| 139 | Special 01. furnish and install camera cable (SPV.0090) | LF | 2,045 | $1.98 | $2.76 | $2.76 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of February 10, 2026. Compiled by Mirage Metrics.