Low bidders on WisDOT contracts carried a median of $76.00 per TON for this item, over the 24 months to 10 NOV 2026, across 34 low bids. Half of all 131 bids fell between $60.00 and $139.50.

Owner
Wisconsin DOT
Item
205.0501.S
Unit
TON
Data through
10 NOV 2026

WisDOT prints this item as “Excavation, Hauling, and Disposal of Petroleum Contaminated Soil”.

$76.00Low bidder's median, per TON
$83.00Median of all bids, per TON
34Contracts in the window

By year of letting

Excavation, hauling, and disposal of petroleum contaminated soil, WisDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20221111$64.0034$56.77
20231717$81.6247$100.00
20241414$69.1055$75.00
20251515$65.4258$66.21
20261515$90.0057$91.20

Bid prices as published, not adjusted for inflation.

By county

CountyLow bidsLow-bid medianAll bidsMedian, all bids
Milwaukee12$144.5045$125.00
Outagamie4$82.5013$88.00
Excavation, hauling, and disposal of petroleum contaminated soil, WisDOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Quantity (TON)Low bidsLow-bid median
12 to 30.508$150.00
36 to 1449$94.00
150 to 8138$75.00
853 to 6,9009$48.00
Excavation, hauling, and disposal of petroleum contaminated soil, WisDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

Excavation, hauling, and disposal of petroleum contaminated soil, WisDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
10 NOV 202620261110030Ashland90$94.00$94.001Northwoods Paving, A Div. of Mathy Construction610WisDOT
13 OCT 202620261013006Milwaukee36$466.12$333.062Zenith Tech., Inc. - WaukeshaWisDOT
13 OCT 202620261013007Milwaukee479.50$90.00$87.504Wandel Contractors IncWisDOT
13 OCT 202620261013010Outagamie150$95.50$95.505Zignego Company, Inc.WisDOT
11 AUG 202620260811007Dane20$150.00$126.003Payne and Dolan, IncWisDOT
14 APR 202620260414027Trempealeau200$75.00$88.697McCabe Construction, Inc.WisDOT
10 MAR 202620260310004Crawford255$140.55$141.882Gerke Excavating IncWisDOT
10 MAR 202620260310018Racine853$68.20$45.004Lalonde Contractors IncorporatedWisDOT
10 MAR 202620260310023Outagamie2,690$56.00$50.523Vinton Construction CompanyWisDOT
10 FEB 202620260210010Milwaukee44.50$515.07$300.003Lalonde Contractors IncorporatedWisDOT
10 FEB 202620260210015Milwaukee25$350.00$162.504Wandel Contractors IncWisDOT
10 FEB 202620260210022Outagamie500$75.00$74.003Michels Road & Stone, Inc.WisDOT
10 FEB 202620260210047Dane30$77.00$150.007Integrity Grading and Excavating, Inc.WisDOT
13 JAN 202620260113021Racine813$58.00$60.484A.W. Oakes & Son, Inc.WisDOT
13 JAN 202620260113054Oconto80$75.00$92.005Peters Concrete CompanyWisDOT
Latest WisDOT contracts carrying Excavation, hauling, and disposal of petroleum contaminated soil

Filter this item by your own quantity, county and period, or check your price against it, in the WisDOT explorer.

How these prices were read

WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WisDOT's own: this item is compared with WisDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the WisDOT letting of 10 NOV 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy