WisDOT contract 20260811007 bid tabulation
5992-11-37. Let by Wisconsin DOT on August 11, 2026, Dane. 3 bids received; low bid $6,447,026 by Payne and Dolan, Inc.
- Owner
- Wisconsin DOT
- Letting
- 11 AUG 2026
- Pay items
- 254
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Payne and Dolan, Inc | $6,447,026 | Low |
| 2 | Rock Road Companies, Inc. | $6,598,184 | +2.0% |
| 3 | Hoffman Construction Company | $6,705,305 | +4.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Payne and Dolan, Inc | 2. Rock Road Companies, Inc. | 3. Hoffman Construction Company |
|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 3 | $2,110.00 | $2,110.00 | $2,110.00 |
| 2 | Clearing (201.0120) | ID | 143 | $40.09 | $40.09 | $40.09 |
| 3 | Grubbing (201.0205) | STA | 3 | $1,582.50 | $1,582.50 | $1,582.50 |
| 4 | Grubbing (201.0220) | ID | 143 | $5.28 | $5.28 | $5.28 |
| 5 | Removing concrete pavement (204.0100) | SY | 285 | $11.50 | $13.92 | $25.00 |
| 6 | Removing asphaltic surface (204.0110) | SY | 2,370 | $5.80 | $9.40 | $7.50 |
| 7 | Removing asphaltic surface milling (204.0120) | SY | 56,955 | $5.15 | $4.65 | $5.65 |
| 8 | Removing curb (204.0130) | LF | 1,505 | $9.30 | $27.66 | $9.00 |
| 9 | Removing curb & gutter (204.0150) | LF | 5,465 | $13.00 | $24.76 | $9.00 |
| 10 | Removing concrete sidewalk (204.0155) | SY | 2,495 | $23.50 | $20.86 | $9.00 |
| 11 | Removing guardrail (204.0165) | LF | 225 | $5.00 | $5.00 | $5.00 |
| 12 | Removing concrete bases (204.0195) | EACH | 45 | $550.00 | $550.00 | $500.00 |
| 13 | Removing manholes (204.0210) | EACH | 1 | $1,600.00 | $683.19 | $500.00 |
| 14 | Removing catch basins (204.0215) | EACH | 1 | $1,600.00 | $683.19 | $500.00 |
| 15 | Removing inlets (204.0220) | EACH | 3 | $1,600.00 | $683.19 | $500.00 |
| 16 | Removing storm sewer (size) 01. 12-inch (204.0245) | LF | 555 | $30.25 | $28.63 | $15.00 |
| 17 | Removing storm sewer (size) 02. 15-inch (204.0245) | LF | 65 | $35.25 | $28.63 | $15.00 |
| 18 | Removing storm sewer (size) 03. 18-inch (204.0245) | LF | 120 | $35.25 | $28.63 | $15.00 |
| 19 | Removing (item description) 01. removing street light assembly (204.9060.S) | EACH | 2 | $1,500.00 | $1,500.00 | $1,500.00 |
| 20 | Removing (item description) 02. removing traffic signal (CTH MM/rimrock road & moorland road) (204.9060.S) | EACH | 1 | $10,000 | $10,000 | $10,000 |
| 21 | Removing (item description) 03. removing traffic signal (CTH MM/rimrock road & badger road) (204.9060.S) | EACH | 1 | $12,000 | $12,000 | $12,000 |
| 22 | Removing (item description) 04. removing traffic signal (CTH MM/rimrock road & rusk avenue) (204.9060.S) | EACH | 1 | $7,500.00 | $7,500.00 | $7,500.00 |
| 23 | Removing (item description) 05. removing traffic signal (CTH MM/rimrock road & alliant energy center way) (204.9060.S) | EACH | 1 | $10,000 | $10,000 | $10,000 |
| 24 | Removing (item description) 06. bus shelter (204.9060.S) | EACH | 1 | $2,000.00 | $3,562.82 | $1,100.00 |
| 25 | Excavation common (205.0100) | CY | 4,374 | $38.25 | $29.81 | $26.00 |
| 26 | Excavation, hauling, and disposal of petroleum contaminated soil (205.0501.S) | TON | 20 | $150.00 | $36.41 | $126.00 |
| 27 | Prepare foundation for asphaltic paving (project) 01. 5992-11-37 (211.0101) | EACH | 1 | $10,000 | $0.01 | $100.00 |
| 28 | Prepare foundation for asphaltic paving (project) 02. 5992-11-62 (211.0101) | EACH | 1 | $15,000 | $0.01 | $100.00 |
| 29 | Finishing roadway (project) 01. 5992-11-37 (213.0100) | EACH | 1 | $100.00 | $5,684.47 | $100.00 |
| 30 | Finishing roadway (project) 02. 5992-11-62 (213.0100) | EACH | 1 | $100.00 | $5,684.47 | $100.00 |
| 31 | Base aggregate dense 3/4-inch (305.0110) | TON | 642 | $30.25 | $35.84 | $39.00 |
| 32 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 4,989 | $21.75 | $27.31 | $41.00 |
| 33 | Base aggregate open-graded (310.0110) | TON | 6 | $70.00 | $25.07 | $400.00 |
| 34 | Select crushed material (312.0110) | TON | 2,623 | $20.25 | $22.06 | $29.00 |
| 35 | Concrete pavement 7-inch (415.0070) | SY | 20 | $100.00 | $89.04 | $89.04 |
| 36 | Concrete truck apron 12-inch (415.2010) | SY | 23 | $170.00 | $131.35 | $131.35 |
| 37 | Drilled tie bars (416.0610) | EACH | 158 | $17.50 | $10.46 | $10.46 |
| 38 | Concrete pavement replacement (416.1720) | SY | 25 | $200.00 | $172.02 | $172.02 |
| 39 | Tack coat (455.0605) | GAL | 3,839 | $1.75 | $3.53 | $2.50 |
| 40 | Incentive density HMA pavement (460.2000) | DOL | 16,910 | $1.00 | $1.00 | $1.00 |
| 41 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 386 | $90.25 | $106.30 | $96.55 |
| 42 | HMA pavement 3 MT 58-28 S (460.6223) | TON | 11,581 | $89.25 | $77.62 | $78.15 |
| 43 | HMA pavement 4 MT 58-28 S (460.6224) | TON | 7,639 | $91.25 | $80.85 | $84.10 |
| 44 | Asphaltic surface driveways and field entrances (465.0120) | TON | 62 | $255.00 | $183.43 | $138.15 |
| 45 | Asphaltic surface temporary (465.0125) | TON | 107 | $300.00 | $106.30 | $177.60 |
| 46 | Asphaltic surface safety islands (465.0305) | TON | 8 | $215.00 | $362.49 | $230.00 |
| 47 | Concrete collars for pipe (520.8000) | EACH | 2 | $1,800.00 | $554.27 | $2,000.00 |
| 48 | Concrete curb & gutter 18-inch type D (601.0407) | LF | 1,108 | $32.50 | $24.43 | $24.43 |
| 49 | Concrete curb & gutter 30-inch type A (601.0409) | LF | 468 | $56.00 | $80.56 | $80.56 |
| 50 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 5,238 | $47.25 | $39.33 | $39.33 |
| 51 | Concrete curb & gutter 6-inch sloped 30-inch type J (601.0415) | LF | 60 | $49.75 | $56.04 | $56.04 |
| 52 | Concrete curb pedestrian (601.0600) | LF | 543 | $74.00 | $67.59 | $67.59 |
| 53 | Concrete sidewalk 5-inch (602.0410) | SF | 16,165 | $11.75 | $8.49 | $8.49 |
| 54 | Concrete sidewalk 7-inch (602.0420) | SF | 2,250 | $15.00 | $15.19 | $15.19 |
| 55 | Curb ramp detectable warning field yellow (602.0505) | SF | 928 | $49.00 | $49.43 | $49.43 |
| 56 | Curb ramp detectable warning field radial yellow (602.0605) | SF | 280 | $71.00 | $68.54 | $68.54 |
| 57 | Concrete driveway 7-inch (602.0815) | SY | 30 | $96.00 | $85.84 | $85.84 |
| 58 | Concrete safety islands (602.2400) | SF | 3,535 | $7.10 | $7.03 | $7.03 |
| 59 | Concrete surface drains (602.3010) | CY | 0.80 | $1,600.00 | $1,495.19 | $1,495.19 |
| 60 | Riprap medium (606.0200) | CY | 2 | $120.00 | $238.89 | $300.00 |
| 61 | Storm sewer pipe reinforced concrete class IV 12-inch (608.0412) | LF | 606 | $91.00 | $119.41 | $64.00 |
| 62 | Storm sewer pipe reinforced concrete class IV 15-inch (608.0415) | LF | 64 | $110.00 | $175.00 | $68.00 |
| 63 | Storm sewer pipe reinforced concrete class IV 18-inch (608.0418) | LF | 110 | $110.00 | $177.23 | $76.00 |
| 64 | Storm sewer pipe reinforced concrete horizontal elliptical class HE-IV 24X38-inch (608.2424) | LF | 6 | $410.00 | $329.15 | $300.00 |
| 65 | Manhole covers type J (611.0530) | EACH | 1 | $880.00 | $1,357.24 | $850.00 |
| 66 | Inlet covers type C (611.0612) | EACH | 2 | $1,200.00 | $1,357.24 | $860.00 |
| 67 | Inlet covers type H (611.0624) | EACH | 1 | $1,100.00 | $1,605.63 | $1,200.00 |
| 68 | Inlet covers type HM-GJ-S (611.0633) | EACH | 1 | $1,200.00 | $1,605.63 | $1,500.00 |
| 69 | Inlet covers type H-S (611.0639) | EACH | 2 | $1,200.00 | $1,617.02 | $1,200.00 |
| 70 | Inlet covers type MS (611.0642) | EACH | 3 | $890.00 | $1,394.84 | $850.00 |
| 71 | Catch basins 4-FT diameter (611.1004) | EACH | 1 | $3,100.00 | $4,664.33 | $3,100.00 |
| 72 | Manholes 3-FT diameter (611.2003) | EACH | 1 | $2,100.00 | $3,293.63 | $1,800.00 |
| 73 | Inlets 3-FT diameter (611.3003) | EACH | 2 | $2,100.00 | $3,293.63 | $1,700.00 |
| 74 | Inlets 4-FT diameter (611.3004) | EACH | 2 | $2,600.00 | $3,613.85 | $2,500.00 |
| 75 | Inlets median 1 grate (611.3901) | EACH | 1 | $3,200.00 | $3,822.94 | $2,400.00 |
| 76 | Adjusting manhole covers (611.8110) | EACH | 20 | $1,400.00 | $1,427.64 | $2,100.00 |
| 77 | Adjusting inlet covers (611.8115) | EACH | 57 | $750.00 | $1,202.27 | $2,100.00 |
| 78 | Cover plates temporary (611.8120.S) | EACH | 20 | $780.00 | $1,014.14 | $500.00 |
| 79 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 130 | $39.25 | $74.57 | $10.00 |
| 80 | Barrier system grading shaping finishing (614.0010) | EACH | 2 | $3,500.00 | $4,579.37 | $6,100.00 |
| 81 | Steel plate beam guard class A (614.0305) | LF | 141 | $35.00 | $35.00 | $35.00 |
| 82 | Steel plate beam guard energy absorbing terminal (614.0370) | EACH | 4 | $4,500.00 | $4,500.00 | $4,500.00 |
| 83 | Mobilization (619.1000) | EACH | 1 | $68,400 | $463,000 | $451,635 |
| 84 | Concrete median sloped nose (620.0300) | SF | 597 | $12.75 | $13.78 | $13.78 |
| 85 | Water (624.0100) | MGAL | 155 | $39.50 | $0.01 | $135.00 |
| 86 | Topsoil (625.0100) | SY | 6,100 | $11.50 | $13.13 | $12.00 |
| 87 | Silt fence (628.1504) | LF | 2,020 | $2.25 | $2.25 | $2.25 |
| 88 | Silt fence maintenance (628.1520) | LF | 3,090 | $0.01 | $0.01 | $0.01 |
| 89 | Mobilizations erosion control (628.1905) | EACH | 7 | $100.00 | $100.00 | $100.00 |
| 90 | Mobilizations emergency erosion control (628.1910) | EACH | 5 | $100.00 | $100.00 | $100.00 |
| 91 | Erosion mat urban class I type B (628.2008) | SY | 5,985 | $2.25 | $2.25 | $2.25 |
| 92 | Inlet protection type A (628.7005) | EACH | 4 | $150.00 | $150.00 | $150.00 |
| 93 | Inlet protection type B (628.7010) | EACH | 2 | $60.00 | $60.00 | $60.00 |
| 94 | Inlet protection type C (628.7015) | EACH | 115 | $65.00 | $65.00 | $65.00 |
| 95 | Inlet protection type D (628.7020) | EACH | 78 | $120.00 | $120.00 | $120.00 |
| 96 | Temporary ditch checks (628.7504) | LF | 12 | $15.00 | $15.00 | $15.00 |
| 97 | Culvert pipe checks (628.7555) | EACH | 10 | $25.00 | $25.00 | $25.00 |
| 98 | Fertilizer type B (629.0210) | CWT | 4.50 | $125.00 | $125.00 | $125.00 |
| 99 | Seeding mixture no. 40 (630.0140) | LB | 305 | $15.00 | $15.00 | $15.00 |
| 100 | Seeding temporary (630.0200) | LB | 185 | $5.00 | $5.00 | $5.00 |
| 101 | Seed water (630.0500) | MGAL | 165 | $10.00 | $10.00 | $10.00 |
| 102 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 14 | $85.00 | $85.00 | $85.00 |
| 103 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 4 | $90.00 | $90.00 | $90.00 |
| 104 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 4 | $95.00 | $95.00 | $95.00 |
| 105 | Posts tubular steel 2X2-inch X 11- FT (634.0811) | EACH | 22 | $185.00 | $185.00 | $185.00 |
| 106 | Signs type II reflective H (637.2210) | SF | 180.93 | $22.00 | $22.00 | $22.00 |
| 107 | Signs type II reflective F (637.2230) | SF | 30 | $24.00 | $24.00 | $24.00 |
| 108 | Moving signs type II (638.2102) | EACH | 54 | $175.00 | $175.00 | $175.00 |
| 109 | Removing signs type II (638.2602) | EACH | 10 | $35.00 | $35.00 | $35.00 |
| 110 | Removing small sign supports (638.3000) | EACH | 22 | $35.00 | $35.00 | $35.00 |
| 111 | Moving small sign supports (638.4000) | EACH | 10 | $125.00 | $125.00 | $125.00 |
| 112 | Field office type C (642.5201) | EACH | 1 | $5,000.00 | $3,500.00 | $20,000 |
| 113 | Traffic control drums (643.0300) | DAY | 76,100 | $0.20 | $0.20 | $0.15 |
| 114 | Traffic control barricades type III (643.0420) | DAY | 6,775 | $0.60 | $0.60 | $0.40 |
| 115 | Traffic control flexible tubular marker posts (643.0500) | EACH | 78 | $25.00 | $25.00 | $36.61 |
| 116 | Traffic control flexible tubular marker bases (643.0600) | EACH | 78 | $5.00 | $5.00 | $12.68 |
| 117 | Traffic control warning lights type A (643.0705) | DAY | 12,100 | $0.10 | $0.10 | $0.10 |
| 118 | Traffic control warning lights type C (643.0715) | DAY | 1,650 | $0.10 | $0.10 | $0.30 |
| 119 | Traffic control connected arrow boards (643.0810) | DAY | 70 | $22.00 | $22.00 | $10.00 |
| 120 | Traffic control signs (643.0900) | DAY | 15,650 | $0.40 | $0.40 | $0.15 |
| 121 | Traffic control signs PCMS (643.1050) | DAY | 180 | $35.00 | $35.00 | $30.00 |
| 122 | Traffic control cones 42-inch (643.1070) | DAY | 25,950 | $0.15 | $0.15 | $0.15 |
| 123 | Traffic control connected work zone start and end location markers (643.1220) | DAY | 70 | $14.00 | $14.00 | $12.95 |
| 124 | Temporary marking line removable tape 6-inch (643.3180) | LF | 31,885 | $2.00 | $2.00 | $2.00 |
| 125 | Temporary marking line removable tape 10-inch (643.3280) | LF | 585 | $3.50 | $3.50 | $4.00 |
| 126 | Temporary marking crosswalk removable tape 6-inch (643.3350) | LF | 5,170 | $2.15 | $2.15 | $2.25 |
| 127 | Temporary marking arrow removable tape (643.3550) | EACH | 4 | $145.00 | $145.00 | $185.00 |
| 128 | Temporary marking stop line removable tape 18-inch (643.3850) | LF | 316 | $6.00 | $6.00 | $7.25 |
| 129 | Traffic control (643.5000) | EACH | 1 | $62,000 | $62,000 | $192,125 |
| 130 | Temporary pedestrian surface matting (644.1440) | SF | 5,530 | $7.30 | $7.30 | $3.34 |
| 131 | Temporary pedestrian curb ramp (644.1601) | DAY | 3,190 | $15.00 | $15.00 | $7.61 |
| 132 | Temporary pedestrian detectable warning field (644.1605) | SF | 1,130 | $18.00 | $18.00 | $6.04 |
| 133 | Temporary pedestrian barricade (644.1810) | LF | 9,490 | $5.75 | $5.75 | $5.25 |
| 134 | Temporary audible message devices (644.1900.S) | DAY | 4,200 | $5.00 | $5.00 | $4.25 |
| 135 | Geotextile type HR (645.0120) | SY | 12 | $3.70 | $2.09 | $100.00 |
| 136 | Geogrid type SR (645.0220) | SY | 4,810 | $2.40 | $3.53 | $2.50 |
| 137 | Marking line epoxy 4-inch (646.1020) | LF | 29,475 | $0.35 | $0.75 | $0.35 |
| 138 | Marking line epoxy 8-inch (646.3020) | LF | 4,310 | $0.96 | $1.50 | $0.96 |
| 139 | Marking line epoxy 10-inch (646.4020) | LF | 35 | $4.00 | $1.90 | $4.00 |
| 140 | Marking arrow epoxy (646.5020) | EACH | 97 | $207.80 | $250.00 | $207.80 |
| 141 | Marking word epoxy (646.5120) | EACH | 22 | $329.50 | $275.00 | $329.50 |
| 142 | Marking symbol epoxy (646.5220) | EACH | 32 | $196.54 | $375.00 | $196.54 |
| 143 | Marking stop line epoxy 18-inch (646.6120) | LF | 891 | $13.25 | $12.00 | $13.25 |
| 144 | Marking diagonal epoxy 12-inch (646.7120) | LF | 318 | $12.84 | $9.75 | $12.84 |
| 145 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 486 | $11.57 | $11.00 | $11.57 |
| 146 | Marking crosswalk epoxy block style 24-inch (646.7520) | LF | 2,596 | $21.18 | $17.00 | $21.18 |
| 147 | Marking curb epoxy (646.8120) | LF | 3,058 | $8.08 | $7.75 | $8.08 |
| 148 | Marking island nose epoxy (646.8220) | EACH | 18 | $302.00 | $305.00 | $302.00 |
| 149 | Marking removal line 4-inch (646.9000) | LF | 7,330 | $0.55 | $0.55 | $1.00 |
| 150 | Marking removal line 6-inch (646.9002) | LF | 275 | $0.75 | $0.75 | $1.75 |
| 151 | Marking removal line 8-inch (646.9100) | LF | 1,130 | $1.00 | $1.00 | $2.00 |
| 152 | Marking removal line wide (646.9200) | LF | 94 | $10.00 | $10.00 | $3.50 |
| 153 | Construction staking storm sewer (650.4000) | EACH | 7 | $250.00 | $15.00 | $250.00 |
| 154 | Construction staking subgrade (650.4500) | LF | 2,070 | $0.01 | $0.01 | $0.01 |
| 155 | Construction staking base (650.5000) | LF | 2,070 | $2.00 | $0.01 | $2.00 |
| 156 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 6,956 | $2.00 | $0.50 | $2.00 |
| 157 | Construction staking electrical installations (project) 01. 5992-11- 37 (650.8501) | EACH | 1 | $10,000 | $5,000.00 | $10,000 |
| 158 | Construction staking electrical installations (project) 02. 5992-11- 62 (650.8501) | EACH | 1 | $10,000 | $5,000.00 | $10,000 |
| 159 | Construction staking curb ramps (650.9000) | EACH | 95 | $300.00 | $450.00 | $300.00 |
| 160 | Construction staking sidewalk (project) 01. 5992-11-37 (650.9500) | EACH | 1 | $10,000 | $5,000.00 | $10,000 |
| 161 | Construction staking sidewalk (project) 02. 5992-11-62 (650.9500) | EACH | 1 | $10,000 | $5,000.00 | $10,000 |
| 162 | Construction staking supplemental control (project) 01. 5992-11-37 (650.9911) | EACH | 1 | $15,000 | $4,000.00 | $15,000 |
| 163 | Construction staking supplemental control (project) 02. 5992-11-62 (650.9911) | EACH | 1 | $15,000 | $4,000.00 | $15,000 |
| 164 | Construction staking slope stakes (650.9920) | LF | 3,250 | $2.00 | $0.50 | $2.00 |
| 165 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 3,608 | $12.00 | $12.00 | $12.00 |
| 166 | Conduit rigid nonmetallic schedule 40 3-inch (652.0235) | LF | 2,335 | $15.00 | $15.00 | $15.00 |
| 167 | Conduit special 2-inch (652.0605) | LF | 1,754 | $22.00 | $22.00 | $22.00 |
| 168 | Conduit special 3-inch (652.0615) | LF | 2,427 | $35.00 | $35.00 | $35.00 |
| 169 | Install conduit into existing item (652.0700.S) | EACH | 9 | $250.00 | $250.00 | $250.00 |
| 170 | Adjusting pull boxes (653.0900) | EACH | 1 | $800.00 | $800.00 | $800.00 |
| 171 | Removing pull boxes (653.0905) | EACH | 13 | $350.00 | $350.00 | $350.00 |
| 172 | Concrete bases type 1 (654.0101) | EACH | 7 | $1,100.00 | $1,100.00 | $1,100.00 |
| 173 | Concrete bases type 10 (654.0110) | EACH | 4 | $9,000.00 | $9,000.00 | $9,000.00 |
| 174 | Concrete bases type 13 (654.0113) | EACH | 1 | $18,000 | $18,000 | $18,000 |
| 175 | Concrete bases type 10-special (654.0120) | EACH | 5 | $15,000 | $15,000 | $15,000 |
| 176 | Cable traffic signal 5-14 AWG (655.0230) | LF | 3,927 | $1.65 | $1.65 | $1.65 |
| 177 | Cable traffic signal 7-14 AWG (655.0240) | LF | 11,364 | $2.10 | $2.10 | $2.10 |
| 178 | Cable traffic signal 9-14 AWG (655.0250) | LF | 341 | $2.45 | $2.45 | $2.45 |
| 179 | Cable traffic signal 12-14 AWG (655.0260) | LF | 5,949 | $3.25 | $3.25 | $3.25 |
| 180 | Cable traffic signal 15-14 AWG (655.0270) | LF | 153 | $4.15 | $4.15 | $4.15 |
| 181 | Cable type UF 2-12 AWG grounded (655.0305) | LF | 3,176 | $2.00 | $2.00 | $2.00 |
| 182 | Electrical wire traffic signals 10 AWG (655.0515) | LF | 7,510 | $1.37 | $1.37 | $1.37 |
| 183 | Electrical wire lighting 12 AWG (655.0610) | LF | 3,142 | $1.00 | $1.00 | $1.00 |
| 184 | Loop detector lead in cable (655.0700) | LF | 14,078 | $1.85 | $1.85 | $1.85 |
| 185 | Traffic signal evp detector cable (655.0900) | LF | 3,902 | $2.00 | $2.00 | $2.00 |
| 186 | Pedestal bases (657.0100) | EACH | 35 | $254.00 | $254.00 | $254.00 |
| 187 | Poles type 9 (657.0345) | EACH | 4 | $9,500.00 | $9,500.00 | $9,500.00 |
| 188 | Poles type 9-special (657.0347) | EACH | 5 | $12,000 | $12,000 | $12,000 |
| 189 | Poles type 12 (657.0355) | EACH | 1 | $12,000 | $12,000 | $12,000 |
| 190 | Traffic signal standards aluminum 3.5-FT (657.0405) | EACH | 2 | $400.00 | $400.00 | $400.00 |
| 191 | Traffic signal standards aluminum 13-FT (657.0420) | EACH | 6 | $750.00 | $750.00 | $750.00 |
| 192 | Traffic signal standards aluminum 15-FT (657.0425) | EACH | 7 | $850.00 | $850.00 | $850.00 |
| 193 | Traffic signal standards aluminum 10-FT (657.0430) | EACH | 20 | $640.00 | $640.00 | $640.00 |
| 194 | Monotube arms 25-FT (657.0525) | EACH | 1 | $5,000.00 | $5,000.00 | $5,000.00 |
| 195 | Monotube arms 30-FT (657.0530) | EACH | 3 | $6,500.00 | $6,500.00 | $6,500.00 |
| 196 | Monotube arms 35-FT-special (657.0536) | EACH | 2 | $7,000.00 | $7,000.00 | $7,000.00 |
| 197 | Monotube arms 40-FT-special (657.0541) | EACH | 2 | $7,500.00 | $7,500.00 | $7,500.00 |
| 198 | Monotube arms 45-FT-special (657.0546) | EACH | 1 | $8,000.00 | $8,000.00 | $8,000.00 |
| 199 | Monotube arms 50-FT (657.0550) | EACH | 1 | $14,000 | $14,000 | $14,000 |
| 200 | Traffic signal face 3S 12-inch (658.0173) | EACH | 1 | $750.00 | $750.00 | $750.00 |
| 201 | Pedestrian signal face 16-inch (658.0416) | EACH | 8 | $610.00 | $610.00 | $610.00 |
| 202 | Pedestrian push buttons (658.0500) | EACH | 10 | $410.00 | $410.00 | $410.00 |
| 203 | Fiber optic termination (678.0400) | EACH | 16 | $1,050.00 | $1,050.00 | $1,050.00 |
| 204 | Sawing asphalt (690.0150) | LF | 4,895 | $1.59 | $1.39 | $1.35 |
| 205 | Sawing concrete (690.0250) | LF | 1,560 | $2.95 | $2.25 | $2.35 |
| 206 | Incentive iri ride (740.0440) | DOL | 10,790 | $1.00 | $1.00 | $1.00 |
| 207 | Installing and maintaining climbing turtle exclusion fence (999.2100.S) | LF | 600 | $5.00 | $5.00 | $5.00 |
| 208 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,400 | $5.00 | $5.00 | $5.00 |
| 209 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 2,160 | $5.00 | $5.00 | $5.00 |
| 210 | Special 01. electrical pull box type III (SPV.0060) | EACH | 4 | $550.00 | $550.00 | $550.00 |
| 211 | Special 02. electrical pull box type V (SPV.0060) | EACH | 45 | $850.00 | $850.00 | $850.00 |
| 212 | Special 03. electrical pull box type VII (SPV.0060) | EACH | 7 | $1,800.00 | $1,800.00 | $1,800.00 |
| 213 | Special 04. concrete bases type P (SPV.0060) | EACH | 4 | $2,500.00 | $2,500.00 | $2,500.00 |
| 214 | Special 05. concrete bases type LB-3R (SPV.0060) | EACH | 19 | $1,500.00 | $1,500.00 | $1,500.00 |
| 215 | Special 06. concrete bases type LB-8R (SPV.0060) | EACH | 5 | $2,200.00 | $2,200.00 | $2,200.00 |
| 216 | Special 07. concrete bases type GR (SPV.0060) | EACH | 29 | $1,100.00 | $1,100.00 | $1,100.00 |
| 217 | Special 08. pole 20-foot, 7 gauge (SPV.0060) | EACH | 5 | $2,200.00 | $2,200.00 | $2,200.00 |
| 218 | Special 09. pole 30-foot, 7 gauge single mount (SPV.0060) | EACH | 1 | $2,450.00 | $2,450.00 | $2,450.00 |
| 219 | Special 10. pole 30-foot, 11 gauge single mount (SPV.0060) | EACH | 13 | $2,200.00 | $2,200.00 | $2,200.00 |
| 220 | Special 11. pole 30-foot, 11 gauge twin mount (SPV.0060) | EACH | 6 | $2,270.00 | $2,270.00 | $2,270.00 |
| 221 | Special 12. traffic signal trombone arm aluminum 18-foot (SPV.0060) | EACH | 5 | $2,550.00 | $2,550.00 | $2,550.00 |
| 222 | Special 13. traffic signal trombone arm aluminum 25-foot (SPV.0060) | EACH | 1 | $3,000.00 | $3,000.00 | $3,000.00 |
| 223 | Special 14. traffic signal heads 12- inch, 3-section with backplate (SPV.0060) | EACH | 48 | $1,025.00 | $1,025.00 | $1,025.00 |
| 224 | Special 15. traffic signal heads 12- inch, 4-section with backplate (SPV.0060) | EACH | 27 | $1,060.00 | $1,060.00 | $1,060.00 |
| 225 | Special 16. traffic signal heads 12- inch, 5-section with backplate (SPV.0060) | EACH | 4 | $1,300.00 | $1,300.00 | $1,300.00 |
| 226 | Special 17. traffic signal heads 16- inch pedestrian signal with countdown (SPV.0060) | EACH | 42 | $610.00 | $610.00 | $610.00 |
| 227 | Special 18. install city furnished traffic signal control cabinet and controller (SPV.0060) | EACH | 4 | $2,500.00 | $2,500.00 | $2,500.00 |
| 228 | Special 19. optical signal preempt (SPV.0060) | EACH | 4 | $14,500 | $14,500 | $14,500 |
| 229 | Special 20. temporary traffic signals (rimrock road & moorland road) (SPV.0060) | EACH | 1 | $75,000 | $75,000 | $75,000 |
| 230 | Special 21. temporary traffic signals (rimrock road & badger road) (SPV.0060) | EACH | 1 | $75,000 | $75,000 | $75,000 |
| 231 | Special 22. temporary traffic signals (rimrock road & rusk avenue) (SPV.0060) | EACH | 1 | $75,000 | $75,000 | $75,000 |
| 232 | Special 23. temporary traffic signals (rimrock road & alliant energy center way) (SPV.0060) | EACH | 1 | $75,000 | $75,000 | $75,000 |
| 233 | Special 24. transformer base 16- inch steel (SPV.0060) | EACH | 25 | $870.00 | $870.00 | $870.00 |
| 234 | Special 25. fiber optic fusion splice - 1 to 12 per location (SPV.0060) | EACH | 6 | $700.00 | $700.00 | $700.00 |
| 235 | Special 26. ussl luminaire and mounting bracket type 1 (SPV.0060) | EACH | 26 | $1,600.00 | $1,600.00 | $1,600.00 |
| 236 | Special 27. furnish & install APS system (rimrock road & moorland road) (SPV.0060) | EACH | 1 | $12,000 | $12,000 | $12,000 |
| 237 | Special 28. furnish & install APS system (rimrock road & badger road) (SPV.0060) | EACH | 1 | $12,000 | $12,000 | $12,000 |
| 238 | Special 29. furnish and install APS system (rimrock road & rusk avenue) (SPV.0060) | EACH | 1 | $11,000 | $11,000 | $11,000 |
| 239 | Special 30. furnish & install APS system (rimrock road & alliant energy center way) (SPV.0060) | EACH | 1 | $12,000 | $12,000 | $12,000 |
| 240 | Special 31. traffic signal ethernet switch (SPV.0060) | EACH | 4 | $7,000.00 | $7,000.00 | $7,000.00 |
| 241 | Special 32. non-intrusive vehicle detection system (SPV.0060) | EACH | 4 | $32,000 | $32,000 | $32,000 |
| 242 | Special 33. adjusting water valve box (SPV.0060) | EACH | 34 | $580.00 | $450.74 | $700.00 |
| 243 | Special 34. adjusting water manhole frame & cover (SPV.0060) | EACH | 1 | $600.00 | $2,045.21 | $2,400.00 |
| 244 | Special 35. adjust sanitary sewer access structure, city of fitchburg (SPV.0060) | EACH | 4 | $600.00 | $1,641.45 | $2,400.00 |
| 245 | Special 36. utility line opening (ulo) (SPV.0060) | EACH | 10 | $1,500.00 | $1,250.00 | $700.00 |
| 246 | Special 37. concrete pipe support (SPV.0060) | EACH | 1 | $1,900.00 | $1,138.27 | $2,300.00 |
| 247 | Special 38. apron endwalls for culvert pipe salvage 24X38-inch (SPV.0060) | EACH | 1 | $3,200.00 | $846.12 | $1,100.00 |
| 248 | Special 39. manhole covers type J- special mad logo lid (SPV.0060) | EACH | 9 | $900.00 | $1,438.14 | $850.00 |
| 249 | Special 40. reconstructing MMSD manhole (SPV.0060) | EACH | 1 | $3,000.00 | $4,639.90 | $3,000.00 |
| 250 | Special 41. adjust sanitary sewer access structure, city of madison (SPV.0060) | EACH | 17 | $3,200.00 | $2,003.79 | $3,000.00 |
| 251 | Special 01. fiber optic cable 24- count (SPV.0090) | LF | 3,455 | $5.00 | $5.00 | $5.00 |
| 252 | Special 02. cut in bicycle loop detection (SPV.0090) | LF | 486 | $25.00 | $25.00 | $25.00 |
| 253 | Special 03. concrete curb & gutter 24-inch type D (SPV.0090) | LF | 380 | $42.75 | $76.92 | $76.92 |
| 254 | Special 01. directional guidance plates (SPV.0165) | SF | 13 | $71.00 | $55.00 | $60.28 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of August 11, 2026. Compiled by Mirage Metrics.