Cable traffic signal 7-14 AWG, WisDOT 655.0240
Low bidders on WisDOT contracts carried a median of $2.21 per LF for this item, over the 24 months to 10 NOV 2026, across 78 low bids. Half of all 300 bids fell between $2.00 and $2.52.
- Owner
- Wisconsin DOT
- Item
- 655.0240
- Unit
- LF
- Data through
- 10 NOV 2026
WisDOT prints this item as “Cable Traffic Signal 7-14 AWG”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 28 | 26 | $1.99 | 72 | $2.00 |
| 2023 | 37 | 34 | $2.10 | 137 | $2.10 |
| 2024 | 28 | 26 | $2.25 | 105 | $2.25 |
| 2025 | 42 | 41 | $2.21 | 152 | $2.22 |
| 2026 | 29 | 29 | $2.25 | 117 | $2.25 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Milwaukee | 25 | $2.22 | 98 | $2.22 |
| Waukesha | 7 | $2.12 | 36 | $2.12 |
| Dane | 5 | $1.85 | 21 | $2.10 |
| Outagamie | 5 | $2.75 | 17 | $2.75 |
| Walworth | 5 | $2.08 | 16 | $2.10 |
| Racine | 3 | $2.27 | 13 | $2.27 |
| Winnebago | 3 | $2.25 | 11 | $2.25 |
| Kenosha | 3 | $1.95 | 11 | $1.95 |
| Washington | 3 | $2.00 | 10 | $2.11 |
| La Crosse | 3 | $2.14 | 7 | $2.14 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 31 to 415 | 19 | $2.25 |
| 463 to 975 | 20 | $2.35 |
| 1,054 to 2,445 | 19 | $2.16 |
| 2,878 to 12,905 | 20 | $2.15 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Zignego Company, Inc. | 87 | 77 (89%) |
| Lalonde Contractors Incorporated | 58 | 53 (91%) |
| Vinton Construction Company | 36 | 33 (92%) |
| Payne and Dolan, Inc | 34 | 30 (88%) |
| Michels Road & Stone, Inc. | 32 | 30 (94%) |
| Zenith Tech., Inc. - Waukesha | 33 | 28 (85%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 10 NOV 2026 | 20261110012 | Dane | 519 | $1.75 | $1.75 | 6 | R.G. Huston Company, Inc. | WisDOT |
| 10 NOV 2026 | 20261110014 | Milwaukee | 498 | $2.90 | $2.56 | 3 | Lalonde Contractors Incorporated | WisDOT |
| 10 NOV 2026 | 20261110017 | Walworth | 3,854 | $1.94 | $1.94 | 5 | James Peterson Sons, Inc. | WisDOT |
| 13 OCT 2026 | 20261013006 | Milwaukee | 2,445 | $4.03 | $4.03 | 2 | Zenith Tech., Inc. - Waukesha | WisDOT |
| 13 OCT 2026 | 20261013007 | Milwaukee | 615 | $3.99 | $3.99 | 4 | Wandel Contractors Inc | WisDOT |
| 15 SEP 2026 | 20260915007 | Milwaukee | 3,469 | $2.44 | $2.44 | 3 | Payne and Dolan, Inc | WisDOT |
| 15 SEP 2026 | 20260915008 | Waukesha | 1,862 | $1.93 | $1.93 | 9 | Zignego Company, Inc. | WisDOT |
| 11 AUG 2026 | 20260811007 | Dane | 11,364 | $2.10 | $2.10 | 3 | Payne and Dolan, Inc | WisDOT |
| 11 AUG 2026 | 20260811009 | Walworth | 1,881 | $2.89 | $2.82 | 6 | Musson Bros., Inc. | WisDOT |
| 14 JUL 2026 | 20260714002 | Dane | 965 | $1.85 | $3.00 | 5 | R.G. Huston Company, Inc. | WisDOT |
| 14 JUL 2026 | 20260714004 | Milwaukee | 295 | $2.37 | $2.37 | 6 | Lalonde Contractors Incorporated | WisDOT |
| 09 JUN 2026 | 20260609001 | Waukesha | 4,312 | $2.92 | $2.92 | 2 | Payne and Dolan, Inc | WisDOT |
| 12 MAY 2026 | 20260512007 | Sauk | 3,083 | $3.91 | $3.91 | 3 | Zignego Company, Inc. | WisDOT |
| 14 APR 2026 | 20260414015 | Racine | 463 | $2.00 | $1.95 | 5 | A.W. Oakes & Son, Inc. | WisDOT |
| 10 MAR 2026 | 20260310016 | Milwaukee | 2,021 | $1.99 | $1.99 | 5 | Hoffman Construction Company | WisDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the WisDOT explorer.
How these prices were read
WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WisDOT's own: this item is compared with WisDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the WisDOT letting of 10 NOV 2026 and was rebuilt on 26 NOV 2026.