Cable type UF 2-10 AWG grounded, WisDOT 655.0320
Low bidders on WisDOT contracts carried a median of $2.28 per LF for this item, over the 24 months to 10 NOV 2026, across 34 low bids. Half of all 130 bids fell between $2.02 and $2.53.
- Owner
- Wisconsin DOT
- Item
- 655.0320
- Unit
- LF
- Data through
- 10 NOV 2026
WisDOT prints this item as “Cable Type UF 2-10 AWG Grounded”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 12 | 12 | $2.23 | 36 | $2.25 |
| 2023 | 26 | 23 | $2.31 | 104 | $2.27 |
| 2024 | 10 | 10 | $2.23 | 36 | $2.42 |
| 2025 | 23 | 22 | $2.17 | 80 | $2.15 |
| 2026 | 9 | 9 | $2.52 | 39 | $2.52 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Milwaukee | 12 | $2.44 | 45 | $2.44 |
| Waukesha | 5 | $2.12 | 24 | $2.12 |
| Kenosha | 3 | $2.12 | 11 | $2.12 |
| Walworth | 3 | $2.00 | 5 | $2.00 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 30 to 527 | 8 | $2.29 |
| 565 to 1,180 | 9 | $2.12 |
| 1,194 to 2,108 | 8 | $2.22 |
| 2,631 to 7,333 | 9 | $2.34 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Zignego Company, Inc. | 44 | 41 (93%) |
| Lalonde Contractors Incorporated | 34 | 32 (94%) |
| Payne and Dolan, Inc | 22 | 19 (86%) |
| Michels Road & Stone, Inc. | 19 | 19 (100%) |
| Stark Pavement Corporation | 18 | 15 (83%) |
| James Peterson Sons, Inc. | 16 | 15 (94%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 10 NOV 2026 | 20261110012 | Dane | 295 | $2.00 | $2.00 | 6 | R.G. Huston Company, Inc. | WisDOT |
| 13 OCT 2026 | 20261013006 | Milwaukee | 6,634 | $3.69 | $3.69 | 2 | Zenith Tech., Inc. - Waukesha | WisDOT |
| 13 OCT 2026 | 20261013007 | Milwaukee | 1,150 | $3.52 | $3.52 | 4 | Wandel Contractors Inc | WisDOT |
| 15 SEP 2026 | 20260915008 | Waukesha | 4,670 | $2.22 | $2.22 | 9 | Zignego Company, Inc. | WisDOT |
| 09 JUN 2026 | 20260609001 | Waukesha | 6,585 | $2.52 | $2.52 | 2 | Payne and Dolan, Inc | WisDOT |
| 10 MAR 2026 | 20260310017 | Racine | 506 | $2.53 | $2.53 | 5 | Stark Pavement Corporation | WisDOT |
| 10 MAR 2026 | 20260310029 | Portage | 1,044 | $2.41 | $2.40 | 6 | Chippewa Concrete Services, Inc. | WisDOT |
| 10 FEB 2026 | 20260210011 | Washington | 1,024 | $2.10 | $2.10 | 1 | Zenith Tech., Inc. - Waukesha | WisDOT |
| 13 JAN 2026 | 20260113021 | Racine | 4,748 | $2.80 | $2.78 | 4 | A.W. Oakes & Son, Inc. | WisDOT |
| 11 NOV 2025 | 20251111010 | Milwaukee | 400 | $3.59 | $3.59 | 4 | Lalonde Contractors Incorporated | WisDOT |
| 11 NOV 2025 | 20251111011 | Waukesha | 483 | $1.88 | $1.88 | 3 | Payne and Dolan, Inc | WisDOT |
| 11 NOV 2025 | 20251111012 | Kenosha | 244 | $2.12 | $2.12 | 5 | Stark Pavement Corporation | WisDOT |
| 11 NOV 2025 | 20251111034 | Chippewa | 4,076 | $3.07 | $3.07 | 3 | Chippewa Concrete Services, Inc. | WisDOT |
| 14 OCT 2025 | 20251014026 | Barron | 1,010 | $2.99 | $3.07 | 4 | Antczak Construction, Inc. | WisDOT |
| 09 SEP 2025 | 20250909006 | Milwaukee | 3,195 | n/a | $1.84 | 2 | WisDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the WisDOT explorer.
How these prices were read
WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WisDOT's own: this item is compared with WisDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the WisDOT letting of 10 NOV 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way