WisDOT contract 20260310017 bid tabulation

City Racine, Ohio St; Washington Ave to Graceland Blvd (LOC STR, Racine County City Racine, Ohio St). Let by Wisconsin DOT on March 10, 2026, Racine. 5 bids received; low bid $3,621,950 by Stark Pavement Corporation.

Owner
Wisconsin DOT
Letting
10 MAR 2026
Pay items
174
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Stark Pavement Corporation$3,621,950Low
2Lalonde Contractors Incorporated$3,754,862+4.0%
3A.W. Oakes & Son, Inc.$3,967,597+10%
4Musson Bros., Inc.$4,009,777+11%
5Zignego Company, Inc.$4,119,871+14%
WisDOT contract 20260310017: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Stark Pavement Corporation2. Lalonde Contractors Incorporated3. A.W. Oakes & Son, Inc.4. Musson Bros., Inc.5. Zignego Company, Inc.
1Clearing (201.0120)ID290$30.00$38.50$45.00$39.65$38.50
2Grubbing (201.0220)ID290$20.00$7.50$10.00$7.72$7.50
3Removing concrete pavement (204.0100)SY23,060$15.81$3.66$19.80$21.50$21.50
4Removing concrete sidewalk (204.0155)SY970$12.29$10.60$10.00$7.10$7.10
5Removing concrete bases (204.0195)EACH13$505.66$379.36$350.00$249.00$400.00
6Removing inlets (204.0220)EACH15$250.00$250.00$560.00$291.00$250.00
7Removing storm sewer (size) 01. 12-inch (204.0245)LF690$16.00$16.00$25.00$34.00$16.00
8Excavation common (205.0100)CY19,674$10.62$20.07$12.00$0.01$0.01
9Finishing roadway (project) 01. 2703-00-76 (213.0100)EACH1$5,000.00$2,510.00$2,500.00$1,000.00$1,000.00
10Base aggregate dense 1 1/4-inch (305.0120)TON10,309$11.20$21.64$16.00$11.50$11.50
11Breaker run (311.0110)TON12,620$6.06$24.51$0.01$11.50$11.50
12Concrete pavement 8-inch (415.0080)SY19,214$57.90$59.22$62.00$60.77$69.00
13Concrete pavement gaps (415.0210)EACH8$1,600.00$1,150.33$500.00$1,030.00$1.00
14Concrete pavement joint filling (415.4100)SY21,356$1.90$1.38$2.00$2.21$2.00
15Drilled tie bars (416.0610)EACH631$12.00$14.25$10.00$12.36$20.00
16Drilled dowel bars (416.0620)EACH546$16.00$18.30$20.00$22.66$20.00
17Asphaltic surface driveways and field entrances (465.0120)TON13$150.00$150.00$200.00$154.50$150.00
18Asphaltic surface temporary (465.0125)TON161$120.00$120.00$150.00$123.60$120.00
19Concrete collars for pipe (520.8000)EACH7$1,000.00$1,000.00$750.00$481.00$900.00
20Concrete curb type D (601.0110)LF5$200.00$65.27$35.00$30.90$38.36
21Concrete curb & gutter 30-inch type A (601.0409)LF5,426$24.25$26.79$25.00$23.69$29.57
22Concrete curb & gutter integral 30- inch type D (601.0452)LF4,153$29.10$17.65$17.00$23.69$24.18
23Concrete curb pedestrian (601.0600)LF50$45.00$58.73$50.00$46.35$33.50
24Concrete sidewalk 4-inch (602.0405)SF10,200$8.25$7.96$8.30$8.24$5.56
25Concrete sidewalk 5-inch (602.0410)SF9,100$9.75$8.48$8.30$8.50$9.65
26Curb ramp detectable warning field yellow (602.0505)SF360$44.00$43.06$55.00$46.35$34.53
27Concrete driveway 6-inch (602.0810)SY1,001$72.00$69.00$72.00$72.10$68.81
28Concrete driveway 8-inch (602.0820)SY57$85.00$91.76$77.00$77.25$105.60
29Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF970$71.00$71.00$110.00$95.00$71.00
30Storm sewer pipe reinforced concrete class IV 15-inch (608.0415)LF16$108.00$108.00$185.00$149.00$108.00
31Reconstructing manholes (611.0420)EACH7$600.00$600.00$2,500.00$1,580.00$600.00
32Manhole covers type J-special (611.0535)EACH1$600.00$600.00$700.00$827.00$600.00
33Inlet covers type H (611.0624)EACH16$895.00$895.00$1,000.00$1,160.00$895.00
34Inlet covers type H-S (611.0639)EACH4$895.00$895.00$1,000.00$1,160.00$895.00
35Manholes 4-FT diameter (611.2004)EACH1$4,250.00$4,250.00$4,400.00$4,070.00$4,250.00
36Manholes 5-FT diameter (611.2005)EACH1$5,250.00$5,250.00$4,600.00$4,200.00$5,250.00
37Inlets 4-FT diameter (611.3004)EACH13$2,115.00$2,115.00$3,400.00$2,010.00$2,115.00
38Inlets 2X3-FT (611.3230)EACH6$1,400.00$1,400.00$3,100.00$1,330.00$1,400.00
39Adjusting manhole covers (611.8110)EACH1$700.00$700.00$1,200.00$606.00$700.00
40Mobilization (619.1000)EACH1$189,370$124,850$269,000$524,254$530,000
41Concrete median sloped nose (620.0300)SF192$14.00$22.44$16.00$17.51$25.32
42Dust control surface treatment (623.0200)SY26,900$0.10$0.01$0.01$0.01$0.01
43Water (624.0100)MGAL210$42.41$0.01$65.00$0.01$0.01
44Topsoil (625.0100)SY3,062$5.00$4.95$5.50$8.50$4.95
45Mulching (627.0200)SY610$0.50$0.55$1.00$0.77$0.55
46Mobilizations erosion control (628.1905)EACH9$100.00$200.00$100.00$206.00$200.00
47Mobilizations emergency erosion control (628.1910)EACH6$50.00$200.00$50.00$257.50$200.00
48Erosion mat urban class I type A (628.2006)SY650$5.00$1.90$2.00$2.32$1.90
49Soil stabilizer type B (628.6510)ACRE0.20$100.00$750.00$200.00$1,287.50$750.00
50Inlet protection type A (628.7005)EACH22$50.00$95.00$1.00$46.35$95.00
51Inlet protection type C (628.7015)EACH42$70.00$55.00$75.00$72.10$55.00
52Inlet protection type D (628.7020)EACH4$100.00$90.00$120.00$97.85$90.00
53Tracking pads (628.7560)EACH6$1.09$0.01$100.00$100.00$1,600.00
54Fertilizer type B (629.0210)CWT6$80.00$85.00$80.00$123.60$85.00
55Seeding mixture no. 40 (630.0140)LB28$12.00$12.75$10.00$15.45$12.75
56Seeding temporary (630.0200)LB16$5.00$5.00$1.00$7.21$5.00
57Seed water (630.0500)MGAL15$1.00$40.00$0.01$41.20$40.00
58Sod water (631.0300)MGAL63$30.00$40.00$35.00$66.95$40.00
59Sod lawn (631.1000)SY2,880$8.00$7.95$8.00$7.72$7.95
60Posts tubular steel 2X2-inch X 16- FT (634.0816)EACH30$215.00$230.00$225.00$247.20$230.00
61Signs type II reflective H (637.2210)SF372.40$21.00$22.00$23.00$24.72$22.00
62Signs type II reflective H folding (637.2215)SF20.72$27.00$25.00$25.00$46.35$25.00
63Removing signs type II (638.2602)EACH55$20.00$25.00$15.00$36.05$25.00
64Removing small sign supports (638.3000)EACH15$20.00$25.00$15.00$51.50$25.00
65Field office type B (642.5001)EACH1$14,000$16,064$22,000$25,000$20,000
66Traffic control drums (643.0300)DAY37,207$0.25$0.25$0.30$0.26$0.25
67Traffic control barricades type III (643.0420)DAY12,032$0.50$0.50$0.55$0.51$0.50
68Traffic control flexible tubular marker posts (643.0500)EACH294$22.00$22.00$25.00$22.66$22.00
69Traffic control flexible tubular marker bases (643.0600)EACH294$6.00$6.00$7.00$6.18$6.00
70Traffic control warning lights type A (643.0705)DAY23,590$0.10$0.10$0.15$0.10$0.10
71Traffic control warning lights type C (643.0715)DAY9,552$0.10$0.10$0.15$0.10$0.10
72Traffic control connected arrow boards (643.0810)DAY514$20.00$20.00$20.00$20.60$20.00
73Traffic control signs (643.0900)DAY28,173$0.20$0.20$0.25$0.21$0.20
74Traffic control signs PCMS (643.1050)DAY21$100.00$100.00$100.00$103.00$100.00
75Temporary marking line paint 4- inch (643.3105)LF6,939$0.75$0.75$1.00$0.77$0.75
76Temporary marking line removable tape 4-inch (643.3150)LF14,484$1.00$1.00$1.10$1.03$1.00
77Temporary marking line removable tape 6-inch (643.3180)LF4,963$1.50$1.50$1.60$1.54$1.50
78Temporary marking line removable tape 8-inch (643.3250)LF195$1.65$1.65$2.00$1.70$1.65
79Temporary marking arrow removable tape (643.3550)EACH5$50.00$50.00$75.00$51.50$50.00
80Temporary marking word removable tape (643.3650)EACH3$100.00$100.00$110.00$103.00$100.00
81Temporary marking stop line removable tape 18-inch (643.3850)LF186$5.00$5.00$5.00$5.15$5.00
82Traffic control (643.5000)EACH1$10,000$10,000$22,000$10,300$10,000
83Temporary pedestrian surface matting (644.1440)SF372$5.00$5.00$6.00$5.15$5.00
84Temporary pedestrian curb ramp (644.1601)DAY644$7.00$7.00$8.00$7.21$7.00
85Temporary pedestrian detectable warning field (644.1605)SF128$5.00$5.00$6.00$5.15$5.00
86Temporary pedestrian barricade (644.1810)LF2,181$4.00$4.00$4.00$4.12$4.00
87Temporary audible message devices (644.1900.S)DAY608$3.00$3.00$3.00$3.09$3.00
88Geotextile type SR (645.0135)SY11,770$2.39$2.81$0.01$0.01$0.01
89Marking line epoxy 4-inch (646.1020)LF11,983$0.76$0.98$1.10$1.01$0.98
90Marking line epoxy 8-inch (646.3020)LF575$1.52$1.20$1.35$1.24$1.20
91Marking arrow epoxy (646.5020)EACH31$227.25$270.00$300.00$278.10$270.00
92Marking symbol epoxy (646.5220)EACH30$303.00$255.00$300.00$262.65$255.00
93Marking stop line epoxy 18-inch (646.6120)LF127$12.63$14.10$15.00$14.52$14.10
94Marking diagonal epoxy 12-inch (646.7120)LF66$10.10$11.50$12.00$11.84$11.50
95Marking chevron epoxy 24-inch (646.7220)LF12$14.14$19.75$20.00$20.34$19.75
96Marking crosswalk epoxy transverse line 6-inch (646.7420)LF1,719$11.11$9.25$10.00$9.53$9.25
97Marking curb epoxy (646.8120)LF80$7.83$12.10$13.00$12.46$12.10
98Marking island nose epoxy (646.8220)EACH8$303.00$235.00$275.00$242.05$235.00
99Marking removal line 4-inch (646.9000)LF3,242$0.51$0.51$0.60$0.53$0.65
100Marking removal line 8-inch (646.9100)LF200$0.65$0.65$1.00$0.67$1.00
101Marking removal line wide (646.9200)LF50$1.00$1.00$1.00$1.03$100.00
102Marking removal special marking (646.9300)EACH5$100.00$100.00$100.00$103.00$100.00
103Construction staking storm sewer (650.4000)EACH40$120.00$120.00$125.00$123.60$120.00
104Construction staking subgrade (650.4500)LF6,261$0.01$0.01$0.01$0.01$0.01
105Construction staking concrete pavement (650.7000)LF6,261$0.01$0.01$2.00$0.01$0.01
106Construction staking electrical installations (project) 01. 2703-00- 76 (650.8501)EACH1$3,000.00$3,000.00$7,500.00$3,090.00$3,000.00
107Construction staking curb ramps (650.9000)EACH30$130.00$130.00$100.00$133.90$130.00
108Construction staking sidewalk (project) 01. 2703-00-76 (650.9500)EACH1$4,800.00$4,800.00$5,000.00$4,944.00$4,800.00
109Construction staking supplemental control (project) 01. 2703-00-76 (650.9911)EACH1$12,000$12,000$5,000.00$12,360$12,000
110Construction staking slope stakes (650.9920)LF6,261$0.75$0.75$1.00$0.77$0.75
111Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF561$10.50$10.50$11.00$10.81$10.50
112Conduit rigid nonmetallic schedule 40 3-inch (652.0235)LF913$12.42$12.42$13.00$12.79$12.42
113Pull boxes steel 24X36-inch (653.0135)EACH1$1,234.00$1,234.00$1,300.00$1,271.02$1,234.00
114Pull boxes steel 24X42-inch (653.0140)EACH8$1,350.20$1,350.20$1,500.00$1,390.71$1,350.20
115Removing pull boxes (653.0905)EACH9$170.00$170.00$200.00$175.10$170.00
116Concrete bases type 1 (654.0101)EACH3$1,175.80$1,175.80$1,200.00$1,211.07$1,175.80
117Concrete bases type 2 (654.0102)EACH1$1,424.80$1,424.80$1,500.00$1,467.54$1,424.80
118Concrete bases type 5 (654.0105)EACH2$1,412.80$1,412.80$1,500.00$1,455.18$1,412.80
119Concrete bases type 10 (654.0110)EACH2$7,169.00$7,169.00$7,400.00$7,384.07$7,169.00
120Concrete bases type 10-special (654.0120)EACH2$8,558.00$8,558.00$9,000.00$8,814.74$8,558.00
121Concrete control cabinet bases type 9 special (654.0217)EACH1$3,360.00$3,360.00$3,500.00$3,460.80$3,360.00
122Cable traffic signal 5-14 AWG (655.0230)LF811$1.90$1.90$2.00$1.96$1.90
123Cable traffic signal 12-14 AWG (655.0260)LF1,331$3.53$3.53$4.00$3.64$3.53
124Cable type UF 2-10 AWG grounded (655.0320)LF506$2.53$2.53$3.00$2.61$2.53
125Electrical wire traffic signals 10 AWG (655.0515)LF1,211$1.25$1.25$2.00$1.29$1.25
126Electrical wire lighting 12 AWG (655.0610)LF576$1.21$1.21$1.50$1.25$1.21
127Electrical wire lighting 8 AWG (655.0620)LF573$1.80$1.80$2.00$1.85$1.80
128Electrical wire lighting 4 AWG (655.0630)LF1,146$2.95$2.95$3.30$3.04$2.95
129Electrical service meter breaker pedestal (location) 01. ohio street and kinzie avenue (656.0201)EACH1$1,980.00$1,980.00$2,000.00$2,039.40$1,980.00
130Pedestal bases (657.0100)EACH3$281.00$281.00$300.00$289.43$281.00
131Transformer bases breakaway 11 1/2-inch bolt circle (657.0255)EACH1$716.00$716.00$800.00$737.48$716.00
132Poles type 3 (657.0310)EACH1$3,514.20$3,514.20$3,700.00$3,619.63$3,514.20
133Poles type 9 (657.0345)EACH1$8,160.80$8,160.80$8,500.00$8,405.62$8,160.80
134Poles type 10 (657.0350)EACH1$9,650.80$9,650.80$10,300$9,940.32$9,650.80
135Poles type 10-special (657.0352)EACH2$12,697$12,697$13,500$13,078$12,697
136Traffic signal standards aluminum 13-FT (657.0420)EACH2$640.00$640.00$700.00$659.20$640.00
137Traffic signal standards aluminum 15-FT (657.0425)EACH2$724.00$724.00$800.00$745.72$724.00
138Monotube arms 25-FT (657.0525)EACH2$5,011.00$5,011.00$5,500.00$5,161.33$5,011.00
139Monotube arms 45-FT-special (657.0546)EACH2$6,768.00$6,768.00$7,000.00$6,971.04$6,768.00
140Luminaire arms single member 4- inch clamp 6-FT (657.0609)EACH1$332.00$332.00$350.00$341.96$332.00
141Luminaire arms steel 6-FT (657.0806)EACH3$849.00$849.00$900.00$874.47$849.00
142Traffic signal face 3S 12-inch (658.0173)EACH18$763.40$763.40$800.00$786.30$763.40
143Traffic signal face 4S 12-inch (658.0174)EACH2$1,034.20$1,034.20$1,200.00$1,065.23$1,034.20
144Pedestrian signal face 16-inch (658.0416)EACH8$432.00$432.00$500.00$444.96$432.00
145Pedestrian push buttons (658.0500)EACH8$364.00$364.00$400.00$374.92$364.00
146Signal mounting hardware (location) 01. ohio street and kinzie avenue (658.5070)EACH1$5,892.00$5,892.00$6,000.00$6,068.76$5,892.00
147Luminaires utility LED C (659.1125)EACH4$292.00$292.00$300.00$300.76$292.00
148Temporary traffic signals for intersections (location) 01. ohio street and kinzie avenue (661.0201)EACH1$44,892$44,892$49,000$46,239$44,892
149Field system integrator (670.0101)EACH1$22,644$22,644$26,000$23,323$22,644
150ITS documentation (670.0201)EACH1$6,264.00$6,264.00$7,000.00$6,451.92$6,264.00
151Remove cable (674.0300)LF539$2.04$2.04$2.30$2.10$2.04
152Reinstall cable (674.0400)LF539$2.48$2.48$3.00$2.55$2.48
153Fiber optic termination (678.0400)EACH4$286.00$286.00$300.00$294.58$286.00
154Communication system testing (678.0501)EACH1$4,512.00$4,512.00$5,000.00$4,647.36$4,512.00
155Sawing asphalt (690.0150)LF83$2.02$1.95$2.00$2.01$1.39
156Sawing concrete (690.0250)LF3,861$2.12$2.55$2.00$2.63$2.50
157Incentive compressive strength concrete pavement (715.0720)DOL5,764$1.00$1.00$1.00$1.00$1.00
158Incentive iri ride (740.0440)DOL6,736$1.00$1.00$1.00$1.00$1.00
159On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS1,200$5.00$5.00$5.00$5.00$5.00
160On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS2,400$5.00$5.00$5.00$5.00$5.00
161Special 01. sealing manhole openings (SPV.0060)EACH10$150.00$150.00$400.00$392.00$150.00
162Special 02. storm sewer tap (SPV.0060)EACH10$500.00$500.00$800.00$312.00$500.00
163Special 03. maintenance of lighting (SPV.0060)EACH1$6,834.00$6,834.00$7,500.00$7,039.02$6,834.00
164Special 04. adjust sanitary sewer manhole covers (SPV.0060)EACH8$700.00$700.00$1,100.00$243.00$700.00
165Special 05. traffic signal controller and cabinet (SPV.0060)EACH1$27,246$27,246$30,000$28,063$27,246
166Special 06. utility line opening (ulo) (SPV.0060)EACH4$1,200.00$1,200.00$1,250.00$926.00$1,200.00
167Special 07. section corner monuments (SPV.0060)EACH1$750.00$500.00$500.00$467.00$1,000.00
168Special 08. relocating existing lighting unit (SPV.0060)EACH2$986.00$986.00$1,000.00$1,015.58$986.00
169Special 09. remove and salvage traffic signal equipment; ohio street and kinzie avenue (SPV.0060)EACH1$5,610.00$5,610.00$6,000.00$5,778.30$5,610.00
170Special 10. ethernet switches (SPV.0060)EACH1$4,605.00$4,605.00$5,000.00$4,743.15$4,605.00
171Special 11. traffic signal detection system; ohio street and kinzie avenue (SPV.0060)EACH1$39,323$39,323$44,000$40,503$39,323
172Special 12. fiber optic termination panel (SPV.0060)EACH1$1,443.00$1,443.00$1,600.00$1,486.29$1,443.00
173Special 13. adjust street lighting pull box covers (SPV.0060)EACH2$412.00$412.00$500.00$424.36$412.00
174Special 01. street sweeping (SPV.0075)HRS50$200.00$114.00$250.00$206.00$300.00
WisDOT contract 20260310017: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of March 10, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy