WisDOT contract 20261013007 bid tabulation
2568-00-71. Let by Wisconsin DOT on October 13, 2026, Milwaukee. 4 bids received; low bid $3,871,977 by Wandel Contractors Inc.
- Owner
- Wisconsin DOT
- Letting
- 13 OCT 2026
- Pay items
- 188
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Wandel Contractors Inc | $3,871,977 | Low |
| 2 | Lalonde Contractors Incorporated | $3,959,451 | +2.0% |
| 3 | Zignego Company, Inc. | $4,054,630 | +5.0% |
| 4 | Parisi Construction, LLC | $4,174,400 | +8.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Wandel Contractors Inc | 2. Lalonde Contractors Incorporated | 3. Zignego Company, Inc. | 4. Parisi Construction, LLC |
|---|---|---|---|---|---|---|---|
| 1 | Removing concrete pavement (204.0100) | SY | 2,334 | $17.00 | $15.17 | $25.00 | $14.75 |
| 2 | Removing concrete sidewalk (204.0155) | SY | 1,193 | $12.00 | $14.70 | $25.00 | $60.00 |
| 3 | Removing concrete bases (204.0195) | EACH | 22 | $350.00 | $376.00 | $500.00 | $510.00 |
| 4 | Removing catch basins (204.0215) | EACH | 1 | $1,200.00 | $1,200.00 | $1,000.00 | $1,800.00 |
| 5 | Removing storm sewer (size) 01. 8- inch (204.0245) | LF | 23 | $44.00 | $44.00 | $50.00 | $120.00 |
| 6 | Abandoning manholes (204.0250) | EACH | 1 | $2,100.00 | $2,100.00 | $1,000.00 | $2,700.00 |
| 7 | Abandoning catch basins (204.0255) | EACH | 7 | $1,200.00 | $1,200.00 | $1,000.00 | $2,100.00 |
| 8 | Abandoning sewer (204.0291.S) | CY | 7 | $524.00 | $524.00 | $400.00 | $440.00 |
| 9 | Removing (item description) 01. poles (204.9060.S) | EACH | 36 | $750.40 | $750.40 | $750.40 | $770.00 |
| 10 | Removing (item description) 01. aerial cable (204.9090.S) | LF | 3,900 | $1.70 | $1.70 | $1.70 | $1.70 |
| 11 | Excavation common (205.0100) | CY | 640 | $46.00 | $69.10 | $60.00 | $66.00 |
| 12 | Excavation, hauling, and disposal of petroleum contaminated soil (205.0501.S) | TON | 479.50 | $90.00 | $91.20 | $80.00 | $85.00 |
| 13 | Finishing roadway (project) 01. 2568-00-71 (213.0100) | EACH | 1 | $4,200.00 | $3,092.00 | $1,000.00 | $500.00 |
| 14 | Finishing roadway (project) 02. 2568-00-72 (213.0100) | EACH | 1 | $2,800.00 | $3,092.00 | $1,000.00 | $500.00 |
| 15 | Base aggregate dense 3/4-inch (305.0110) | TON | 369 | $25.00 | $40.28 | $50.00 | $71.00 |
| 16 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 1,237 | $31.00 | $31.18 | $50.00 | $55.00 |
| 17 | Concrete base 8-inch (320.0145) | SY | 1,396 | $73.00 | $89.32 | $111.00 | $97.00 |
| 18 | Concrete pavement 8-inch (415.0080) | SY | 138 | $124.00 | $107.59 | $111.00 | $160.00 |
| 19 | Concrete pavement 11-inch (415.0110) | SY | 319 | $151.00 | $141.96 | $126.00 | $160.00 |
| 20 | Drilled tie bars (416.0610) | EACH | 1,015 | $18.00 | $19.28 | $15.00 | $18.75 |
| 21 | Drilled dowel bars (416.0620) | EACH | 319 | $10.00 | $23.81 | $30.00 | $28.25 |
| 22 | Tack coat (455.0605) | GAL | 99 | $4.00 | $4.00 | $4.00 | $4.10 |
| 23 | Asphaltic surface (465.0105) | TON | 310 | $158.51 | $158.51 | $158.51 | $160.00 |
| 24 | Concrete curb & gutter 19-inch (601.0319) | LF | 983 | $66.00 | $63.03 | $53.00 | $69.00 |
| 25 | Concrete curb & gutter 31-inch (601.0331) | LF | 35 | $66.00 | $64.11 | $100.00 | $140.00 |
| 26 | Concrete curb pedestrian (601.0600) | LF | 6 | $55.00 | $62.62 | $150.00 | $360.00 |
| 27 | Concrete sidewalk 5-inch (602.0410) | SF | 13,380 | $10.50 | $11.28 | $12.10 | $14.50 |
| 28 | Curb ramp detectable warning field natural patina (602.0515) | SF | 372 | $35.00 | $46.73 | $100.00 | $51.00 |
| 29 | Storm sewer pipe reinforced concrete class IV 12-inch (608.0412) | LF | 217 | $167.00 | $167.00 | $300.00 | $140.00 |
| 30 | Mobilization (619.1000) | EACH | 1 | $288,156 | $372,827 | $312,000 | $375,000 |
| 31 | Water (624.0100) | MGAL | 25 | $0.01 | $0.01 | $50.00 | $32.00 |
| 32 | Topsoil (625.0100) | SY | 110 | $7.95 | $12.20 | $7.95 | $31.75 |
| 33 | Mobilizations erosion control (628.1905) | EACH | 4 | $100.00 | $100.00 | $100.00 | $100.00 |
| 34 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $100.00 | $1.00 | $100.00 | $1.00 |
| 35 | Inlet protection type C (628.7015) | EACH | 8 | $65.00 | $72.00 | $65.00 | $73.00 |
| 36 | Inlet protection type D (628.7020) | EACH | 25 | $85.00 | $120.00 | $85.00 | $120.00 |
| 37 | Sod water (631.0300) | MGAL | 2.60 | $150.00 | $100.00 | $150.00 | $100.00 |
| 38 | Sod lawn (631.1000) | SY | 110 | $12.00 | $12.20 | $12.00 | $12.50 |
| 39 | Signs type II reflective H (637.2210) | SF | 19 | $22.00 | $31.00 | $22.00 | $31.50 |
| 40 | Signs type II reflective SH (637.2220) | SF | 193.20 | $24.00 | $29.80 | $24.00 | $30.50 |
| 41 | Moving signs type II (638.2102) | EACH | 13 | $110.00 | $80.00 | $110.00 | $82.00 |
| 42 | Removing signs type II (638.2602) | EACH | 25 | $25.00 | $20.00 | $25.00 | $20.50 |
| 43 | Removing small sign supports (638.3000) | EACH | 1 | $25.00 | $20.00 | $25.00 | $20.50 |
| 44 | Field office type C (642.5201) | EACH | 1 | $15,000 | $19,656 | $20,000 | $9,000.00 |
| 45 | Traffic control drums (643.0300) | DAY | 9,640 | $0.20 | $0.15 | $0.20 | $0.20 |
| 46 | Traffic control barricades type III (643.0420) | DAY | 2,688 | $0.60 | $0.50 | $0.60 | $0.60 |
| 47 | Traffic control warning lights type A (643.0705) | DAY | 5,366 | $0.10 | $0.11 | $0.10 | $0.10 |
| 48 | Traffic control signs (643.0900) | DAY | 7,040 | $0.35 | $0.25 | $0.35 | $0.35 |
| 49 | Traffic control signs PCMS (643.1050) | DAY | 120 | $45.00 | $60.00 | $45.00 | $46.00 |
| 50 | Temporary marking line removable tape 4-inch (643.3150) | LF | 4,470 | $1.40 | $1.50 | $1.40 | $1.40 |
| 51 | Traffic control (643.5000) | EACH | 1 | $27,825 | $21,000 | $27,825 | $28,400 |
| 52 | Temporary audible message devices (644.1900.S) | DAY | 2,800 | $4.25 | $2.75 | $4.25 | $4.30 |
| 53 | Marking line epoxy 4-inch (646.1020) | LF | 2,960 | $1.15 | $1.15 | $1.15 | $1.40 |
| 54 | Marking line epoxy 6-inch (646.2020) | LF | 1,690 | $1.70 | $1.70 | $1.70 | $2.10 |
| 55 | Marking line epoxy 8-inch (646.3020) | LF | 915 | $2.25 | $2.25 | $2.25 | $2.70 |
| 56 | Marking arrow epoxy (646.5020) | EACH | 30 | $235.00 | $235.00 | $235.00 | $290.00 |
| 57 | Marking symbol epoxy (646.5220) | EACH | 12 | $200.00 | $200.00 | $200.00 | $240.00 |
| 58 | Marking removal line 4-inch (646.9000) | LF | 3,080 | $1.25 | $1.35 | $1.25 | $1.30 |
| 59 | Marking removal line 6-inch (646.9002) | LF | 2,630 | $1.50 | $1.40 | $1.50 | $1.50 |
| 60 | Marking removal line 8-inch (646.9100) | LF | 960 | $2.00 | $2.35 | $2.00 | $2.00 |
| 61 | Marking removal line wide (646.9200) | LF | 420 | $3.00 | $4.00 | $3.00 | $3.10 |
| 62 | Marking removal special marking (646.9300) | EACH | 41 | $100.00 | $100.00 | $100.00 | $100.00 |
| 63 | Construction staking storm sewer (650.4000) | EACH | 10 | $150.00 | $150.00 | $0.01 | $0.01 |
| 64 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 1,378 | $2.00 | $2.00 | $0.01 | $0.01 |
| 65 | Construction staking electrical installations (project) 01. 2568-00- 71 (650.8501) | EACH | 1 | $3,575.00 | $3,000.00 | $0.01 | $0.01 |
| 66 | Construction staking electrical installations (project) 02. 2568-00- 72 (650.8501) | EACH | 1 | $3,575.00 | $1,000.00 | $0.01 | $0.01 |
| 67 | Construction staking curb ramps (650.9000) | EACH | 32 | $230.00 | $125.00 | $0.01 | $0.01 |
| 68 | Construction staking sidewalk (project) 01. 2568-00-71 (650.9500) | EACH | 1 | $2,500.00 | $3,000.00 | $0.01 | $0.01 |
| 69 | Construction staking sidewalk (project) 02. 2568-00-72 (650.9500) | EACH | 1 | $2,500.00 | $1,000.00 | $0.01 | $0.01 |
| 70 | Construction staking supplemental control (project) 01. 2568-00-71 (650.9911) | EACH | 1 | $1,800.00 | $3,000.00 | $13,660 | $13,900 |
| 71 | Construction staking supplemental control (project) 02. 2568-00-72 (650.9911) | EACH | 1 | $1,800.00 | $1,000.00 | $13,660 | $13,900 |
| 72 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 75 | $20.85 | $20.85 | $20.85 | $21.25 |
| 73 | Conduit rigid nonmetallic schedule 40 2 1/2-inch (652.0230) | LF | 150 | $22.03 | $22.03 | $22.03 | $22.50 |
| 74 | Conduit rigid nonmetallic schedule 40 3-inch (652.0235) | LF | 1,980 | $23.55 | $23.55 | $23.55 | $24.00 |
| 75 | Conduit special 3-inch (652.0615) | LF | 1,880 | $48.70 | $48.70 | $48.70 | $49.75 |
| 76 | Removing pull boxes (653.0905) | EACH | 16 | $288.00 | $288.00 | $288.00 | $290.00 |
| 77 | Concrete bases type 1 (654.0101) | EACH | 11 | $1,546.00 | $1,546.00 | $1,546.00 | $1,600.00 |
| 78 | Concrete bases type 10 (654.0110) | EACH | 2 | $7,356.00 | $7,356.00 | $7,356.00 | $7,500.00 |
| 79 | Concrete bases type 10-special (654.0120) | EACH | 10 | $9,614.00 | $9,614.00 | $9,614.00 | $9,800.00 |
| 80 | Cable traffic signal 5-14 AWG (655.0230) | LF | 2,470 | $3.34 | $3.34 | $3.34 | $3.40 |
| 81 | Cable traffic signal 7-14 AWG (655.0240) | LF | 615 | $3.99 | $3.99 | $3.99 | $4.10 |
| 82 | Cable traffic signal 15-14 AWG (655.0270) | LF | 2,555 | $6.57 | $6.57 | $6.57 | $6.70 |
| 83 | Cable traffic signal 19-14 AWG (655.0280) | LF | 1,105 | $7.91 | $7.91 | $7.91 | $8.10 |
| 84 | Cable type UF 2-12 AWG grounded (655.0305) | LF | 4,265 | $2.78 | $2.78 | $2.78 | $2.80 |
| 85 | Cable type UF 2-10 AWG grounded (655.0320) | LF | 1,150 | $3.52 | $3.52 | $3.52 | $3.60 |
| 86 | Electrical wire traffic signals 10 AWG (655.0515) | LF | 2,040 | $2.60 | $2.60 | $2.60 | $2.70 |
| 87 | Traffic signal evp detector cable (655.0900) | LF | 1,865 | $2.85 | $2.85 | $2.85 | $2.90 |
| 88 | Pedestal bases (657.0100) | EACH | 9 | $263.00 | $263.00 | $263.00 | $270.00 |
| 89 | Transformer bases breakaway 11 1/2-inch bolt circle (657.0255) | EACH | 7 | $672.00 | $672.00 | $672.00 | $690.00 |
| 90 | Poles type 10 (657.0350) | EACH | 2 | $12,038 | $12,038 | $12,037 | $12,300 |
| 91 | Poles type 10-special (657.0352) | EACH | 6 | $14,297 | $14,297 | $14,297 | $14,600 |
| 92 | Traffic signal standards aluminum 3.5-FT (657.0405) | EACH | 5 | $294.00 | $294.00 | $294.00 | $300.00 |
| 93 | Traffic signal standards aluminum 13-FT (657.0420) | EACH | 4 | $588.00 | $588.00 | $588.00 | $600.00 |
| 94 | Monotube arms 25-FT (657.0525) | EACH | 2 | $7,496.00 | $7,496.00 | $7,496.00 | $7,600.00 |
| 95 | Monotube arms 35-FT-special (657.0536) | EACH | 6 | $9,543.00 | $9,543.00 | $9,543.00 | $9,700.00 |
| 96 | Traffic signal face 3S 12-inch (658.0173) | EACH | 48 | $1,221.00 | $1,221.00 | $1,221.00 | $1,200.00 |
| 97 | Pedestrian signal face 12-inch (658.0412) | EACH | 24 | $993.00 | $993.00 | $993.00 | $1,000.00 |
| 98 | Signal mounting hardware (location) 01. MLK & wright (658.5070) | EACH | 1 | $10,085 | $10,085 | $10,085 | $10,300 |
| 99 | Signal mounting hardware (location) 02. MLK & clarke (658.5070) | EACH | 1 | $10,085 | $10,085 | $10,085 | $10,300 |
| 100 | Signal mounting hardware (location) 03. MLK & center (658.5070) | EACH | 1 | $10,085 | $10,085 | $10,085 | $10,300 |
| 101 | Lamp, ballast, LED, switch disposal by contractor (659.5000.S) | EACH | 110 | $4.10 | $4.10 | $4.10 | $4.20 |
| 102 | Temporary traffic signals for intersections (location) 01. MLK & wright (661.0201) | EACH | 1 | $58,704 | $58,704 | $58,704 | $59,900 |
| 103 | Temporary traffic signals for intersections (location) 02. MLK & clarke (661.0201) | EACH | 1 | $67,464 | $67,464 | $67,464 | $68,800 |
| 104 | Temporary traffic signals for intersections (location) 03. MLK & center (661.0201) | EACH | 1 | $67,464 | $67,464 | $67,464 | $68,800 |
| 105 | Temporary traffic signals for intersections (location) 04. MLK & north (661.0201) | EACH | 1 | $58,704 | $58,704 | $58,704 | $59,900 |
| 106 | Sawing asphalt (690.0150) | LF | 102 | $2.75 | $1.35 | $1.35 | $25.00 |
| 107 | Sawing concrete (690.0250) | LF | 2,347 | $2.75 | $2.35 | $2.35 | $2.40 |
| 108 | Incentive compressive strength concrete pavement (715.0720) | DOL | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 109 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 1,400 | $5.00 | $5.00 | $5.00 | $5.00 |
| 110 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 3,600 | $5.00 | $5.00 | $5.00 | $5.00 |
| 111 | Special 001. utility line opening (SPV.0060) | EACH | 15 | $700.00 | $1,624.24 | $1.00 | $1,100.00 |
| 112 | Special 002. adjusting water valve boxes (SPV.0060) | EACH | 40 | $1,200.00 | $435.00 | $800.00 | $820.00 |
| 113 | Special 102. inlet covers type MS 57 (SPV.0060) | EACH | 11 | $965.00 | $965.00 | $1,600.00 | $1,000.00 |
| 114 | Special 103. manhole covers type MS 58-A (SPV.0060) | EACH | 6 | $1,094.00 | $1,094.00 | $1,600.00 | $1,200.00 |
| 115 | Special 110. catch basin type 44A (SPV.0060) | EACH | 10 | $8,095.00 | $8,095.00 | $8,500.00 | $4,300.00 |
| 116 | Special 201. install city precast controller base (SPV.0060) | EACH | 4 | $1,833.00 | $1,833.00 | $1,833.00 | $1,900.00 |
| 117 | Special 205. atc controller and cabinet installed (SPV.0060) | EACH | 4 | $30,282 | $30,282 | $30,282 | $30,900 |
| 118 | Special 212. fiber optic patch panel (SPV.0060) | EACH | 4 | $4,698.00 | $4,698.00 | $4,698.00 | $4,800.00 |
| 119 | Special 213. ethernet switch (SPV.0060) | EACH | 4 | $5,370.00 | $5,370.00 | $5,370.00 | $5,500.00 |
| 120 | Special 215. electrical service pedestal (SPV.0060) | EACH | 2 | $2,150.00 | $2,150.00 | $2,150.00 | $2,200.00 |
| 121 | Special 218. evp 1 direction detector (SPV.0060) | EACH | 12 | $1,356.00 | $1,356.00 | $1,356.00 | $1,400.00 |
| 122 | Special 221. evp phase selector card 4 channel (SPV.0060) | EACH | 4 | $5,013.00 | $5,013.00 | $5,013.00 | $5,100.00 |
| 123 | Special 223. evp confirmation light (SPV.0060) | EACH | 12 | $684.00 | $684.00 | $684.00 | $700.00 |
| 124 | Special 224. vehicular video detection system 1-camera (SPV.0060) | EACH | 1 | $17,793 | $17,793 | $17,793 | $18,100 |
| 125 | Special 228. electrical riser (SPV.0060) | EACH | 12 | $607.00 | $607.00 | $607.00 | $620.00 |
| 126 | Special 243. removing traffic signals (MLK & wright) (SPV.0060) | EACH | 1 | $9,488.00 | $9,488.00 | $9,488.00 | $9,700.00 |
| 127 | Special 244. removing traffic signals (MLK & clarke) (SPV.0060) | EACH | 1 | $9,488.00 | $9,488.00 | $9,488.00 | $9,700.00 |
| 128 | Special 245. removing traffic signals (MLK & center) (SPV.0060) | EACH | 1 | $9,488.00 | $9,488.00 | $9,488.00 | $9,700.00 |
| 129 | Special 246. removing traffic signals (MLK & north) (SPV.0060) | EACH | 1 | $10,610 | $10,610 | $10,610 | $10,800 |
| 130 | Special 250. pedestal bases black (SPV.0060) | EACH | 2 | $320.00 | $320.00 | $320.00 | $330.00 |
| 131 | Special 251. poles type 10-special black (SPV.0060) | EACH | 4 | $15,685 | $15,685 | $15,685 | $16,000 |
| 132 | Special 252. traffic signal standards aluminum 3.5-FT black (SPV.0060) | EACH | 2 | $369.00 | $369.00 | $369.00 | $380.00 |
| 133 | Special 253. monotube arms 35-FT- special black (SPV.0060) | EACH | 4 | $10,216 | $10,216 | $10,216 | $10,400 |
| 134 | Special 254. traffic signal face 3S 12-inch black (SPV.0060) | EACH | 18 | $1,232.00 | $1,232.00 | $1,232.00 | $1,300.00 |
| 135 | Special 255. traffic signal face 4S 12-inch black (SPV.0060) | EACH | 2 | $1,475.00 | $1,475.00 | $1,475.00 | $1,500.00 |
| 136 | Special 256. pedestrian signal face 12-inch black (SPV.0060) | EACH | 8 | $993.00 | $993.00 | $993.00 | $1,000.00 |
| 137 | Special 257. pedestrian countdown signal face 12-inch black (SPV.0060) | EACH | 8 | $969.00 | $969.00 | $969.00 | $990.00 |
| 138 | Special 258. traffic signal mounting hardware black (location) MLK & north (SPV.0060) | EACH | 1 | $11,447 | $11,447 | $11,447 | $11,700 |
| 139 | Special 267. pedestrian countdown signal face 12-inch (SPV.0060) | EACH | 24 | $969.00 | $969.00 | $969.00 | $990.00 |
| 140 | Special 268. voice instruction audible push button (SPV.0060) | EACH | 32 | $962.00 | $962.00 | $962.00 | $980.00 |
| 141 | Special 269. voice instruction audible control unit (SPV.0060) | EACH | 4 | $3,333.00 | $3,333.00 | $3,333.00 | $3,400.00 |
| 142 | Special 280. round aluminum sign post system in soft surface 7-FT (SPV.0060) | EACH | 1 | $275.00 | $260.00 | $275.00 | $270.00 |
| 143 | Special 284. round aluminum sign post system in concrete surface 7- FT (SPV.0060) | EACH | 13 | $295.00 | $290.00 | $295.00 | $300.00 |
| 144 | Special 285. round aluminum sign post system in concrete surface 10-FT (SPV.0060) | EACH | 1 | $325.00 | $290.00 | $325.00 | $300.00 |
| 145 | Special 288. sign mounting hardware on existing pole (SPV.0060) | EACH | 8 | $175.00 | $15.00 | $175.00 | $15.25 |
| 146 | Special 290. street name sign mounting hardware on existing pole (SPV.0060) | EACH | 4 | $175.00 | $45.00 | $175.00 | $46.00 |
| 147 | Special 291. street name sign mounting hardware on mast arm (SPV.0060) | EACH | 12 | $175.00 | $45.00 | $175.00 | $46.00 |
| 148 | Special 292. sign mounting hardware on round aluminum sign post (SPV.0060) | EACH | 15 | $175.00 | $5.00 | $175.00 | $5.10 |
| 149 | Special 302. pull boxes 13-inch X 24-inch X 24-inch (SPV.0060) | EACH | 36 | $2,020.00 | $2,020.00 | $2,020.00 | $2,100.00 |
| 150 | Special 303. pull boxes 17-inch X 30-inch X 24-inch (SPV.0060) | EACH | 32 | $2,340.00 | $2,340.00 | $2,340.00 | $2,400.00 |
| 151 | Special 320. poles type 25-AL-BD aluminum (SPV.0060) | EACH | 4 | $4,428.40 | $4,428.40 | $4,428.40 | $4,500.00 |
| 152 | Special 321. poles type 25-AL-BD black (SPV.0060) | EACH | 1 | $4,739.40 | $4,739.40 | $4,739.40 | $4,800.00 |
| 153 | Special 322. poles type 30-AL-BD aluminum (SPV.0060) | EACH | 3 | $4,614.40 | $4,614.40 | $4,614.40 | $4,700.00 |
| 154 | Special 323. poles type 30-AL-BD black (SPV.0060) | EACH | 4 | $5,187.40 | $5,187.40 | $5,187.40 | $5,300.00 |
| 155 | Special 324. poles wood 40-FT (SPV.0060) | EACH | 20 | $3,002.40 | $3,002.40 | $3,002.40 | $3,100.00 |
| 156 | Special 334. inline 5A fast acting fuse with holder (SPV.0060) | EACH | 60 | $259.00 | $259.00 | $259.00 | $260.00 |
| 157 | Special 339. primary or secondary riser (SPV.0060) | EACH | 13 | $657.00 | $657.00 | $657.00 | $670.00 |
| 158 | Special 342. submersible multitap 3-port pre-insulated connector (SPV.0060) | EACH | 187 | $191.00 | $191.00 | $191.00 | $190.00 |
| 159 | Special 343. submersible multitap 4-port pre-insulated connector (SPV.0060) | EACH | 55 | $200.00 | $200.00 | $200.00 | $200.00 |
| 160 | Special 345. luminaire arms single member 6-FT (SPV.0060) | EACH | 7 | $309.00 | $309.00 | $309.00 | $320.00 |
| 161 | Special 346. luminaire arms single member 6-FT WP mount (SPV.0060) | EACH | 27 | $315.00 | $315.00 | $315.00 | $320.00 |
| 162 | Special 353. equipment grounding electrode (SPV.0060) | EACH | 46 | $135.00 | $135.00 | $135.00 | $140.00 |
| 163 | Special 355. install A21-A26 city furnished mounting clamp single bracket (SPV.0060) | EACH | 3 | $297.00 | $297.00 | $297.00 | $300.00 |
| 164 | Special 357. install A31 city furnished mounting clamp single bracket (SPV.0060) | EACH | 9 | $297.00 | $297.00 | $297.00 | $300.00 |
| 165 | Special 376. luminaire utility 3LED2 (SPV.0060) | EACH | 28 | $1,459.20 | $1,459.20 | $1,459.20 | $1,500.00 |
| 166 | Special 390. milwaukee light base type 1 (SPV.0060) | EACH | 5 | $1,946.00 | $1,946.00 | $1,946.00 | $2,000.00 |
| 167 | Special 399. transformer bases breakaway 11 1/2-inch bolt circle black (SPV.0060) | EACH | 5 | $748.00 | $748.00 | $748.00 | $760.00 |
| 168 | Special 425. installing conduit into existing manhole (SPV.0060) | EACH | 2 | $904.00 | $904.00 | $904.00 | $920.00 |
| 169 | Special 430. adjusting cuc manhole cover using epp system (SPV.0060) | EACH | 6 | $3,850.00 | $2,016.67 | $2,200.00 | $1,800.00 |
| 170 | Special 801. poles type H17 (SPV.0060) | EACH | 9 | $4,145.00 | $4,145.00 | $4,145.00 | $4,200.00 |
| 171 | Special 804. poles type 15-oct (SPV.0060) | EACH | 5 | $9,597.40 | $9,597.40 | $9,597.40 | $9,800.00 |
| 172 | Special 818. poles type A26-BD (SPV.0060) | EACH | 2 | $5,017.40 | $5,017.40 | $5,017.40 | $5,100.00 |
| 173 | Special 819. poles type A31-BD (SPV.0060) | EACH | 9 | $5,275.40 | $5,275.40 | $5,275.40 | $5,400.00 |
| 174 | Special 820. concrete base type 5 modified (SPV.0060) | EACH | 12 | $1,634.00 | $1,634.00 | $1,634.00 | $1,700.00 |
| 175 | Special 821. concrete base type 2 modified (SPV.0060) | EACH | 14 | $1,902.00 | $1,902.00 | $1,902.00 | $1,900.00 |
| 176 | Special 865. luminaire historic milwaukee harp LED 1 (SPV.0060) | EACH | 14 | $5,243.00 | $5,243.00 | $5,243.00 | $5,300.00 |
| 177 | Special 867. luminaire historic milwaukee lantern LED 3 (SPV.0060) | EACH | 28 | $5,139.00 | $5,139.00 | $5,139.00 | $5,200.00 |
| 178 | Special 010. concrete curb & gutter integral 19-inch (SPV.0090) | LF | 279 | $60.00 | $33.79 | $60.00 | $44.00 |
| 179 | Special 240. electrical cable 3#4/1#8 XLP (SPV.0090) | LF | 135 | $11.75 | $11.75 | $11.75 | $12.00 |
| 180 | Special 302. electrical cable type 3#6 AL (SPV.0090) | LF | 1,250 | $3.72 | $3.72 | $3.72 | $3.80 |
| 181 | Special 304. electrical cable type 2#2/1#4 AL (SPV.0090) | LF | 575 | $4.48 | $4.48 | $4.48 | $4.60 |
| 182 | Special 319. liquidtight flexible nonmetallic conduit 1 1/2-inch (SPV.0090) | LF | 700 | $42.00 | $42.00 | $42.00 | $42.75 |
| 183 | Special 322. electrical cable type 4#6/1#8 XLP (SPV.0090) | LF | 1,900 | $16.44 | $16.44 | $16.44 | $16.75 |
| 184 | Special 324. electrical cable type 4#2/1#8 XLP (SPV.0090) | LF | 1,950 | $24.85 | $24.85 | $24.85 | $25.25 |
| 185 | Special 325. conduit 3-inch HDPE schedule 40 (SPV.0090) | LF | 3,600 | $23.02 | $23.02 | $23.02 | $23.50 |
| 186 | Special 401. 1-duct conduit, cement encased, 4-inch rigid nonmetallic conduit DB-60 (SPV.0090) | LF | 83 | $147.00 | $147.00 | $147.00 | $150.00 |
| 187 | Special 705. marking crosswalk epoxy block style 12-inch (SPV.0090) | LF | 1,700 | $12.00 | $12.00 | $12.00 | $14.75 |
| 188 | Special 706. marking stop line epoxy 24-inch (SPV.0090) | LF | 435 | $18.00 | $18.00 | $18.00 | $22.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of October 13, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.