WisDOT contract 20260915008 bid tabulation

C New Berlin, Moorland Road; CTH D to STH 59 (CTH O, Waukesha County C New Berlin, Moorland Road). Let by Wisconsin DOT on September 15, 2026, Waukesha. 9 bids received; low bid $15,735,497 by Zignego Company, Inc..

Owner
Wisconsin DOT
Letting
15 SEP 2026
Pay items
354
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Zignego Company, Inc.$15,735,497Low
2Musson Bros., Inc.$16,215,140+3.0%
3Stark Pavement Corporation$17,205,097+9.0%
4Super Western, Inc.$17,346,084+10%
5Hoffman Construction Company$17,704,395+13%
6A.W. Oakes & Son, Inc.$17,776,862+13%
7James Peterson Sons, Inc.$18,339,949+17%
8Lalonde Contractors Incorporated$20,353,419+29%
9William Charles Construction, LLC$21,729,825+38%
WisDOT contract 20260915008: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Zignego Company, Inc.2. Musson Bros., Inc.3. Stark Pavement Corporation4. Super Western, Inc.5. Hoffman Construction Company6. A.W. Oakes & Son, Inc.
1CPM progress schedule (108.4400)EACH1$1,000.00$18,785$15,000$16,000$0.01$15,000
2Clearing (201.0105)STA20$850.00$850.00$858.50$850.00$850.00$850.00
3Clearing (201.0120)ID10$75.00$75.00$75.75$75.00$75.00$75.00
4Grubbing (201.0205)STA20$150.00$150.00$151.50$150.00$150.00$150.00
5Grubbing (201.0220)ID10$25.00$25.00$25.25$25.00$25.00$25.00
6Removing small pipe culverts (203.0100)EACH6$800.00$569.03$1,118.07$1,107.00$500.00$1,150.00
7Removing concrete pavement (204.0100)SY80,974$6.31$13.47$5.75$6.64$10.00$27.30
8Removing asphaltic surface butt joints (204.0115)SY23$30.00$30.00$60.00$30.00$26.00$21.00
9Removing asphaltic surface milling (204.0120)SY1,877$27.45$27.45$12.50$27.45$7.00$11.00
10Removing curb (204.0130)LF138$20.00$12.22$4.75$4.78$10.00$10.00
11Removing curb & gutter (204.0150)LF9,911$8.00$4.16$5.75$5.90$10.00$7.00
12Removing concrete sidewalk (204.0155)SY778$10.00$7.94$12.50$12.62$10.00$10.00
13Removing guardrail (204.0165)LF688$2.35$3.50$4.00$3.50$3.50$4.00
14Removing masonry (204.0185)CY1.20$1,000.00$1,316.02$2,000.00$1,500.00$2,500.00$1,700.00
15Removing surface drains (204.0190)EACH4$500.00$176.67$343.75$347.50$300.00$500.00
16Removing concrete bases (204.0195)EACH39$500.00$110.93$336.91$336.91$400.00$350.00
17Removing manholes (204.0210)EACH12$500.00$582.86$907.99$899.00$300.00$900.00
18Removing inlets (204.0220)EACH85$500.00$277.24$673.67$667.00$300.00$700.00
19Removing storm sewer (size) 001. 6-inch (204.0245)LF58$20.00$21.92$53.53$53.00$15.00$55.00
20Removing storm sewer (size) 002. 12-inch (204.0245)LF1,177$20.00$21.92$21.21$21.00$15.00$23.00
21Removing storm sewer (size) 003. 15-inch (204.0245)LF467$25.00$22.61$23.23$23.00$15.00$25.00
22Removing storm sewer (size) 004. 18-inch (204.0245)LF674$25.00$23.10$25.25$25.00$15.00$27.00
23Removing storm sewer (size) 005. 21-inch (204.0245)LF162$30.00$23.10$30.30$30.00$15.00$33.00
24Removing storm sewer (size) 006. 24-inch (204.0245)LF76$30.00$24.25$43.43$43.00$15.00$45.00
25Removing storm sewer (size) 007. 30-inch (204.0245)LF8$200.00$25.67$101.00$100.00$15.00$100.00
26Removing (item description) 101. traffic signals (CTH O & CTH D) (204.9060.S)EACH1$3,821.75$3,821.75$3,821.75$3,821.75$3,821.75$4,000.00
27Removing (item description) 102. traffic signals (CTH O & lincoln ave) (204.9060.S)EACH1$3,821.75$3,821.75$3,821.75$3,821.75$3,821.75$4,000.00
28Removing (item description) 103. traffic signals (CTH O & rogers DR) (204.9060.S)EACH1$3,184.79$3,184.79$3,184.79$3,184.79$3,184.79$3,500.00
29Excavation common (205.0100)CY80,700$11.00$6.78$15.75$17.29$55.00$0.01
30Finishing roadway (project) 001. 2722-04-71 (213.0100)EACH1$1,000.00$300.00$25,000$6,134.12$100.00$2,700.00
31Base aggregate dense 3/4-inch (305.0110)TON267$50.00$40.14$31.75$32.16$75.00$35.00
32Base aggregate dense 1 1/4-inch (305.0120)TON58,499$0.01$8.98$12.25$12.27$0.01$19.10
33Base aggregate open-graded (310.0110)TON199$50.00$36.85$36.50$36.84$25.00$35.00
34Select crushed material (312.0110)TON57,866$0.01$10.00$16.25$17.62$0.01$0.01
35Concrete pavement 9 1/2-inch (415.0095)SY78,618$60.59$62.78$63.25$62.78$62.78$62.00
36Concrete pavement gaps (415.0210)EACH10$1,000.00$857.05$2,400.00$857.05$857.05$1,500.00
37Concrete pavement hes 9 1/2-inch (415.1095)SY420$98.20$92.05$82.40$92.05$92.05$67.50
38Drilled tie bars (416.0610)EACH475$20.00$9.77$19.75$9.77$9.77$15.00
39Drilled dowel bars (416.0620)EACH125$20.00$14.12$20.95$14.12$14.12$30.00
40HMA cold weather paving (450.4000)TON50$10.00$10.00$6.00$10.00$5.00$10.00
41Tack coat (455.0605)GAL2,705$2.35$2.35$3.00$2.35$3.40$2.35
42Incentive density HMA pavement (460.2000)DOL6,250$1.00$1.00$1.00$1.00$1.00$1.00
43HMA pavement 4 LT 58-28 S (460.5224)TON117$197.50$197.50$274.00$197.50$210.00$200.00
44HMA pavement 3 MT 58-28 S (460.6223)TON4,708$86.75$86.75$89.60$86.75$75.50$87.00
45HMA pavement 4 MT 58-28 H (460.6424)TON2,213$108.00$108.00$103.00$108.00$90.00$108.00
46Asphaltic surface driveways and field entrances (465.0120)TON249$197.50$197.50$247.00$197.50$180.00$200.00
47Asphaltic surface temporary (465.0125)TON1,838$105.95$105.95$107.00$105.95$125.00$106.00
48Asphaltic flumes (465.0315)SY52$85.00$85.00$75.00$85.00$58.00$85.00
49Cold patch (495.1000.S)TON50$1.00$50.00$100.00$295.49$0.01$750.00
50Concrete collars for pipe (520.8000)EACH46$500.00$763.82$786.79$779.00$750.00$800.00
51Cleaning culvert pipes (520.8700)EACH1$1,600.00$2,000.00$2,020.00$3,000.00$1,750.00$2,500.00
52Apron endwalls for pipe arch steel 17X13-inch (521.1217)EACH2$750.00$492.22$559.54$554.00$500.00$600.00
53Apron endwalls for culvert pipe sloped side drains steel 24-inch 4 to 1 (521.1505)EACH4$2,000.00$2,737.31$1,803.86$1,786.00$2,500.00$1,800.00
54Culvert pipe corrugated steel 24- inch (521.3124)LF164$96.00$119.99$131.30$130.00$85.00$130.00
55Pipe arch corrugated steel 17X13- inch (521.3717)LF54$96.00$142.89$105.04$104.00$85.00$110.00
56Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012)EACH2$1,500.00$1,088.67$1,541.26$1,526.00$1,300.00$1,550.00
57Apron endwalls for culvert pipe reinforced concrete 15-inch (522.1015)EACH1$1,500.00$1,138.18$1,687.71$1,671.00$1,400.00$1,700.00
58Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024)EACH3$1,750.00$1,412.81$1,864.46$1,846.00$1,700.00$1,850.00
59Culvert pipe corrugated polyethylene 24-inch (530.0124)LF10$250.00$133.62$115.14$114.00$200.00$115.00
60Concrete curb type A (601.0105)LF11$60.00$33.00$65.00$33.00$33.00$100.00
61Concrete curb type D (601.0110)LF77$60.00$33.00$60.00$33.00$33.00$75.00
62Concrete curb & gutter 18-inch type A (601.0405)LF147$60.00$25.00$52.00$25.00$25.00$45.00
63Concrete curb & gutter 18-inch type D (601.0407)LF728$60.00$24.00$21.60$24.00$24.00$28.50
64Concrete curb & gutter 30-inch type A (601.0409)LF30,623$31.68$24.90$29.00$24.90$24.90$22.25
65Concrete curb & gutter 30-inch type D (601.0411)LF6,211$31.68$24.90$24.50$24.90$24.90$23.50
66Concrete sidewalk 5-inch (602.0410)SF16,357$8.01$12.00$8.20$12.00$12.00$6.80
67Curb ramp detectable warning field yellow (602.0505)SF36$100.00$50.00$55.00$50.00$50.00$62.00
68Curb ramp detectable warning field natural patina (602.0515)SF80$100.00$60.00$52.00$60.00$60.00$55.00
69Concrete driveway 7-inch (602.0815)SY196$100.00$72.00$86.00$72.00$72.00$75.00
70Concrete driveway 8-inch (602.0820)SY61$200.00$73.00$95.00$73.00$73.00$80.00
71Concrete driveway hes 7-inch (602.0865)SY182$120.00$88.00$95.00$88.00$88.00$82.00
72Concrete safety islands (602.2400)SF572$20.00$28.00$18.00$28.00$28.00$13.50
73Concrete surface drains (602.3010)CY3$1,000.00$1,100.00$825.00$1,100.00$1,100.00$1,375.00
74Riprap light (606.0100)CY13$300.00$208.38$165.00$166.87$200.00$250.00
75Riprap medium (606.0200)CY56$300.00$188.49$165.00$166.86$200.00$280.00
76Riprap heavy (606.0300)CY19$300.00$208.38$172.75$174.54$200.00$250.00
77Storm sewer pipe reinforced concrete class III 12-inch (608.0312)LF628$112.45$159.51$104.03$103.00$75.00$110.00
78Storm sewer pipe reinforced concrete class III 15-inch (608.0315)LF351$114.28$131.57$104.03$103.00$75.00$110.00
79Storm sewer pipe reinforced concrete class III 18-inch (608.0318)LF599$114.82$110.53$115.14$114.00$80.00$120.00
80Storm sewer pipe reinforced concrete class III 21-inch (608.0321)LF40$200.00$349.90$318.15$315.00$125.00$325.00
81Storm sewer pipe reinforced concrete class III 24-inch (608.0324)LF123$200.00$226.44$253.51$251.00$105.00$265.00
82Storm sewer pipe reinforced concrete class III 30-inch (608.0330)LF9$300.00$298.63$565.60$560.00$200.00$600.00
83Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF1,334$112.45$124.66$90.90$90.00$75.00$93.00
84Storm sewer pipe reinforced concrete class IV 15-inch (608.0415)LF685$114.28$107.41$101.00$100.00$75.00$105.00
85Storm sewer pipe reinforced concrete class IV 18-inch (608.0418)LF153$114.82$113.02$147.46$146.00$80.00$150.00
86Storm sewer pipe reinforced concrete class IV 24-inch (608.0424)LF191$200.00$148.82$174.73$173.00$105.00$180.00
87Storm sewer pipe reinforced concrete class IV 30-inch (608.0430)LF7$300.00$552.39$596.91$591.00$200.00$600.00
88Storm sewer pipe reinforced concrete class V 12-inch (608.0512)LF257$112.45$90.28$87.87$87.00$75.00$92.00
89Manhole covers type J (611.0530)EACH17$1,000.00$680.73$862.54$854.00$750.00$900.00
90Inlet covers type B (611.0606)EACH5$1,175.00$984.96$1,170.59$1,159.00$900.00$1,200.00
91Inlet covers type C (611.0612)EACH1$1,000.00$1,166.63$1,506.92$1,492.00$750.00$1,500.00
92Inlet covers type H (611.0624)EACH99$1,000.00$835.19$1,277.65$1,265.00$1,000.00$1,300.00
93Inlet covers type H-S (611.0639)EACH25$1,000.00$947.94$1,193.82$1,182.00$1,000.00$1,200.00
94Inlet covers type MS (611.0642)EACH11$1,000.00$550.14$825.17$817.00$750.00$850.00
95Inlet covers type S (611.0651)EACH3$1,000.00$941.41$1,258.46$1,246.00$1,200.00$1,300.00
96Inlet covers type WM (611.0660)EACH1$1,000.00$2,283.27$1,010.00$1,000.00$2,500.00$1,100.00
97Manholes 4-FT diameter (611.2004)EACH13$3,759.00$2,218.97$4,196.55$4,155.00$2,000.00$4,200.00
98Manholes 5-FT diameter (611.2005)EACH8$5,707.56$3,625.36$4,221.80$4,180.00$3,500.00$4,400.00
99Manholes 6-FT diameter (611.2006)EACH8$6,871.41$5,490.20$6,533.69$6,469.00$4,500.00$6,600.00
100Manholes 7-FT diameter (611.2007)EACH1$18,633$11,200$8,127.47$8,047.00$7,500.00$8,500.00
101Manholes 8-FT diameter (611.2008)EACH1$26,025$15,526$11,712$11,596$15,000$12,000
102Inlets 3-FT diameter (611.3003)EACH1$2,051.00$1,368.63$2,107.87$2,087.00$1,500.00$2,100.00
103Inlets 4-FT diameter (611.3004)EACH26$2,690.00$1,931.36$2,193.72$2,172.00$2,000.00$2,200.00
104Inlets 2X2-FT (611.3220)EACH1$2,103.80$1,579.35$1,881.63$1,863.00$1,400.00$2,000.00
105Inlets 2X3-FT (611.3230)EACH86$1,958.07$1,279.27$1,591.76$1,576.00$1,600.00$1,600.00
106Inlets median 1 grate (611.3901)EACH6$4,812.21$2,171.09$2,098.78$2,078.00$2,000.00$2,100.00
107Inlets median 2 grate (611.3902)EACH3$5,129.01$2,582.84$4,420.77$4,377.00$4,500.00$4,500.00
108Adjusting manhole covers (611.8110)EACH13$900.00$264.86$782.75$775.00$2,000.00$800.00
109Adjusting inlet covers (611.8115)EACH20$900.00$464.03$652.46$646.00$2,000.00$650.00
110Cover plates temporary (611.8120.S)EACH16$400.00$161.44$374.71$371.00$200.00$400.00
111Salvaged manhole covers (611.9705)EACH3$1.00$545.57$435.31$431.00$500.00$450.00
112Salvaged inlet covers (611.9710)EACH1$1.00$264.86$723.16$716.00$500.00$750.00
113Pipe underdrain 6-inch (612.0106)LF3,447$10.00$7.22$16.00$16.15$15.00$20.00
114Pipe underdrain unperforated 4- inch (612.0204)LF1,009$10.00$14.80$42.42$46.20$15.00$45.00
115Pipe underdrain unperforated 6- inch (612.0206)LF34$25.00$30.01$380.77$424.77$100.00$400.00
116Pipe underdrain unperforated 8- inch (612.0208)LF4$60.00$143.47$617.11$654.47$200.00$625.00
117Pipe underdrain unperforated 12- inch (612.0212)LF100$120.00$63.01$66.66$80.35$30.00$70.00
118Pipe underdrain unperforated 15- inch (612.0215)LF10$200.00$124.84$319.16$367.30$200.00$325.00
119Pipe underdrain wrapped 6-inch (612.0406)LF222$10.00$27.75$19.75$20.00$5.00$9.00
120Apron endwalls for underdrain reinforced concrete 6-inch (612.0806)EACH1$1.00$913.45$700.00$1,009.15$600.00$1,250.00
121Insulation board polystyrene (inch) 201. 2-inch (612.0902.S)SY40$30.00$37.45$24.24$24.00$80.00$25.00
122Guardrail mow strip emulsified asphalt (614.0397)SY433$20.05$17.65$26.50$17.65$17.65$18.00
123MGS guardrail 3 K (614.2330)LF857$40.00$46.00$52.72$46.00$46.00$46.00
124MGS guardrail terminal eat (614.2610)EACH4$3,750.00$3,925.00$3,817.80$3,925.00$3,925.00$4,000.00
125Fence chain link 4-FT (616.0204)LF224$50.00$50.00$50.00$104.00$50.00$60.00
126Fence safety (616.0700.S)LF58$3.65$3.30$8.50$3.30$3.30$3.30
127Mobilization (619.1000)EACH1$2,000,000$1,256,774$741,500$793,171$589,215$1,940,000
128Concrete median sloped nose (620.0300)SF554$20.00$18.00$19.00$18.00$18.00$16.25
129Dust control surface treatment (623.0200)SY39,520$0.01$0.10$0.05$0.01$0.01$0.01
130Water (624.0100)MGAL2,450$0.01$0.01$11.00$11.19$0.01$25.00
131Topsoil (625.0100)SY52,865$0.01$3.22$9.75$9.88$0.01$5.35
132Topsoil (625.0105)CY10$65.00$186.78$59.25$59.88$200.00$185.00
133Mulching (627.0200)SY240$0.55$2.50$0.81$2.50$2.50$2.50
134Erosion bales (628.1104)EACH20$12.00$20.00$13.13$20.00$20.00$20.00
135Silt fence (628.1504)LF4,945$1.85$1.79$1.86$1.79$1.79$2.00
136Silt fence maintenance (628.1520)LF4,945$0.01$0.05$0.10$0.05$0.05$0.01
137Mobilizations erosion control (628.1905)EACH9$100.00$50.00$303.00$50.00$50.00$50.00
138Mobilizations emergency erosion control (628.1910)EACH9$100.00$50.00$303.00$50.00$50.00$50.00
139Erosion mat urban class I type B (628.2008)SY13,299$1.75$1.76$1.98$1.76$1.76$1.80
140Erosion mat class II type C (628.2027)SY724$3.85$3.83$4.34$3.83$3.83$4.00
141Soil stabilizer type B (628.6510)ACRE7$775.00$850.00$808.00$850.00$850.00$850.00
142Inlet protection type A (628.7005)EACH271$90.00$65.00$88.88$65.00$65.00$2.00
143Inlet protection type B (628.7010)EACH32$55.00$55.00$37.37$55.00$55.00$55.00
144Inlet protection type C (628.7015)EACH8$60.00$55.00$37.37$55.00$55.00$55.00
145Inlet protection type D (628.7020)EACH316$85.00$99.00$82.82$99.00$99.00$100.00
146Temporary ditch checks (628.7504)LF365$5.95$6.35$11.92$6.35$6.35$6.50
147Culvert pipe checks (628.7555)EACH12$18.00$35.00$19.19$35.00$35.00$35.00
148Tracking pads (628.7560)EACH6$1.00$1,768.71$0.01$0.01$0.01$500.00
149Rock bags (628.7570)EACH200$10.00$15.15$16.16$15.15$15.15$16.00
150Fertilizer type B (629.0210)CWT56$80.00$110.00$93.93$110.00$110.00$110.00
151Seeding mixture no. 30 (630.0130)LB281$8.50$9.25$11.92$9.25$9.25$10.00
152Seeding mixture no. 40 (630.0140)LB7$12.00$15.00$26.26$15.00$15.00$15.00
153Seeding temporary (630.0200)LB480$2.00$4.50$4.65$4.50$4.50$5.00
154Seeding borrow pit (630.0300)LB49$7.00$10.00$14.14$10.00$10.00$10.00
155Seeding nurse crop (630.0400)LB65$7.00$10.00$4.65$10.00$10.00$10.00
156Seed water (630.0500)MGAL314$8.00$35.00$8.08$35.00$35.00$35.00
157Sod water (631.0300)MGAL435$30.00$35.00$40.40$35.00$35.00$35.00
158Sod lawn (631.1000)SY38,601$7.75$7.05$7.02$7.05$7.05$7.05
159Landscape planting surveillance and care cycles (632.9101)EACH3$1,200.00$2,005.00$959.50$2,005.00$2,005.00$2,005.00
160Markers culvert end (633.5200)EACH20$65.00$62.50$65.65$62.50$62.50$63.00
161Posts wood 4X6-inch X 16-FT (634.0616)EACH4$95.00$165.00$90.90$165.00$165.00$165.00
162Signs type II reflective H (637.2210)SF2,267.79$20.75$24.00$26.36$24.00$24.00$24.00
163Signs type II reflective H folding (637.2215)SF224.04$24.00$32.00$34.34$32.00$32.00$32.00
164Signs type II reflective F (637.2230)SF457.03$23.00$24.00$16.26$24.00$24.00$24.00
165Moving signs type II (638.2102)EACH10$110.00$165.00$99.99$165.00$165.00$165.00
166Removing signs type II (638.2602)EACH267$25.00$32.00$18.18$32.00$32.00$32.00
167Removing small sign supports (638.3000)EACH161$25.00$32.00$21.21$32.00$32.00$32.00
168Field office type D (642.5401)EACH1$30,000$67,571$78,000$48,808$35,000$25,000
169Traffic control drums (643.0300)DAY209,795$0.10$0.10$0.10$0.10$0.10$0.15
170Traffic control barricades type III (643.0420)DAY35,510$0.35$0.35$0.35$0.35$0.35$0.40
171Traffic control flexible tubular marker posts (643.0500)EACH587$25.00$25.00$25.00$25.00$25.00$27.00
172Traffic control flexible tubular marker bases (643.0600)EACH587$5.00$5.00$5.00$5.00$5.00$6.00
173Traffic control warning lights type A (643.0705)DAY71,019$0.10$0.10$0.10$0.10$0.10$0.15
174Traffic control warning lights type C (643.0715)DAY18,868$0.10$0.10$0.10$0.10$0.10$0.15
175Traffic control connected arrow boards (643.0810)DAY808$15.00$15.00$15.00$15.00$15.00$15.00
176Traffic control signs (643.0900)DAY49,631$0.25$0.25$0.25$0.25$0.25$0.30
177Traffic control covering signs type II (643.0920)EACH4$30.00$30.00$30.00$30.00$30.00$40.00
178Traffic control signs fixed message (643.1000)SF39$20.00$20.00$20.00$20.00$20.00$25.00
179Traffic control signs PCMS (643.1050)DAY213$43.00$43.00$43.00$43.00$43.00$45.00
180Traffic control connected work zone start and end location markers (643.1220)DAY942$7.25$7.25$7.25$7.25$7.25$8.00
181Temporary marking line paint 4- inch (643.3105)LF30,677$0.31$0.31$0.31$0.31$0.31$0.35
182Temporary marking line removable tape 4-inch (643.3150)LF33,800$1.25$1.25$1.25$1.25$1.25$1.40
183Temporary marking line paint 8- inch (643.3205)LF2,790$0.65$0.65$0.65$0.65$0.65$0.80
184Temporary marking line removable tape 8-inch (643.3250)LF4,951$2.30$2.30$2.30$2.30$2.30$2.50
185Temporary marking stop line paint 18-inch (643.3805)LF542$2.03$2.03$2.03$2.03$2.03$2.50
186Temporary marking stop line removable tape 18-inch (643.3850)LF782$5.05$5.05$5.05$5.05$5.05$6.00
187Traffic control (643.5000)EACH1$29,646$29,646$29,646$29,646$29,646$32,000
188Temporary pedestrian surface asphalt (644.1410)SF1,007$12.00$9.75$11.50$9.75$9.00$10.00
189Temporary pedestrian detectable warning field (644.1605)SF207$4.55$4.55$4.55$4.55$4.55$5.00
190Temporary pedestrian barricade (644.1810)LF949$4.89$4.89$4.89$4.89$4.89$5.00
191Geotextile type DF schedule A (645.0111)SY1,825$3.00$2.57$3.50$3.47$5.00$1.00
192Geotextile type HR (645.0120)SY42$10.00$13.57$5.75$5.79$25.00$25.00
193Geotextile type R (645.0130)SY27$10.00$19.27$5.25$5.28$25.00$40.00
194Geogrid type SR (645.0220)SY9,924$3.00$2.70$2.25$2.19$2.00$3.50
195Marking line epoxy 4-inch (646.1020)LF44,187$0.65$0.35$0.66$0.35$0.35$0.40
196Marking line epoxy 8-inch (646.3020)LF12,412$1.30$0.95$1.31$0.95$0.95$1.00
197Marking arrow epoxy (646.5020)EACH89$230.00$202.50$232.30$202.50$202.50$225.00
198Marking word epoxy (646.5120)EACH32$250.00$270.50$252.50$270.50$270.50$300.00
199Marking railroad crossing epoxy (646.5320)EACH4$1,600.00$1,954.00$1,616.00$1,954.00$1,954.00$2,200.00
200Marking stop line epoxy 18-inch (646.6120)LF792$12.00$13.90$12.12$13.90$13.90$15.00
201Cold weather marking epoxy 4-inch (646.6464)LF22,103$0.60$0.35$0.61$0.35$0.35$0.50
202Cold weather marking epoxy 8-inch (646.6468)LF6,211$1.20$0.95$1.21$0.95$0.95$1.10
203Marking diagonal epoxy 12-inch (646.7120)LF3,086$10.00$13.50$10.10$13.50$13.50$14.00
204Marking crosswalk epoxy transverse line 6-inch (646.7420)LF357$11.25$15.65$11.36$15.65$15.65$16.00
205Marking crosswalk epoxy block style 24-inch (646.7520)LF180$18.00$27.00$18.18$27.00$27.00$30.00
206Marking curb epoxy (646.8120)LF864$8.50$8.00$8.59$8.00$8.00$9.00
207Marking island nose epoxy (646.8220)EACH31$305.00$294.00$308.05$294.50$294.50$300.00
208Marking removal line 4-inch (646.9000)LF5,870$0.43$0.43$0.43$0.43$0.19$0.45
209Marking removal line water blasting 4-inch (646.9010)LF2,156$0.76$0.76$0.76$0.76$0.95$0.80
210Marking removal line 8-inch (646.9100)LF1,728$0.76$0.76$0.76$0.76$0.45$0.80
211Marking removal line wide (646.9200)LF1,265$1.08$1.08$1.08$1.08$3.00$1.20
212Marking removal line water blasting wide (646.9210)LF20$11.24$11.24$11.24$11.24$25.00$12.00
213Construction staking storm sewer (650.4000)EACH159$120.00$120.00$121.20$120.00$120.00$90.00
214Construction staking base (650.5000)LF3,297$1.10$1.10$1.11$1.10$1.10$1.00
215Construction staking curb gutter and curb & gutter (650.5500)LF7,045$1.20$1.20$1.21$1.20$1.20$2.00
216Construction staking pipe culverts (650.6000)EACH1$300.00$300.00$303.00$300.00$300.00$500.00
217Construction staking structure layout (structure) 401. R-67-173 (650.6501)EACH1$3,000.00$3,000.00$3,030.00$3,000.00$3,000.00$500.00
218Construction staking concrete pavement (650.7000)LF17,476$0.01$0.01$0.01$0.01$0.01$2.00
219Construction staking electrical installations (project) 001. 2722-04- 71 (650.8501)EACH1$4,000.00$4,000.00$4,040.00$4,000.00$4,000.00$5,000.00
220Construction staking curb ramps (650.9000)EACH7$200.00$200.00$202.00$200.00$200.00$150.00
221Construction staking sidewalk (project) 001. 2722-04-71 (650.9500)EACH1$650.00$650.00$656.50$650.00$650.00$5,000.00
222Construction staking supplemental control (project) 001. 2722-04-71 (650.9911)EACH1$50,000$50,000$50,500$50,000$50,000$7,500.00
223Construction staking slope stakes (650.9920)LF20,402$0.85$0.85$0.86$0.85$0.85$1.00
224Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF870$5.17$5.17$5.17$5.17$5.17$5.50
225Conduit rigid nonmetallic schedule 40 3-inch (652.0235)LF13,281$5.84$5.84$5.84$5.84$5.84$6.30
226Conduit special 3-inch (652.0615)LF330$15.21$15.21$15.21$15.21$15.21$16.00
227Pull boxes steel 24X42-inch (653.0140)EACH68$1,328.71$1,328.71$1,328.71$1,328.71$1,328.71$1,400.00
228Removing pull boxes (653.0905)EACH36$113.97$113.97$113.97$113.97$113.97$150.00
229Concrete bases type 1 (654.0101)EACH9$898.48$898.48$898.48$898.48$898.48$1,000.00
230Concrete bases type 2 (654.0102)EACH12$1,419.71$1,419.71$1,419.71$1,419.71$1,419.71$1,500.00
231Concrete bases type 5 (654.0105)EACH4$1,078.01$1,078.01$1,078.01$1,078.01$1,078.01$1,200.00
232Concrete bases type 10 (654.0110)EACH2$6,608.24$6,608.24$6,608.24$6,608.24$6,608.24$6,800.00
233Concrete bases type 13 (654.0113)EACH9$11,601$11,601$11,601$11,601$11,601$150.00
234Concrete bases type 10-special (654.0120)EACH5$8,481.14$8,481.14$8,481.14$8,481.14$8,481.14$9,000.00
235Concrete control cabinet bases type 9 special (654.0217)EACH4$2,499.41$2,499.41$2,499.41$2,499.41$2,499.41$2,800.00
236Cable traffic signal 3-14 AWG (655.0210)LF1,130$1.13$1.13$1.13$1.13$1.13$1.50
237Cable traffic signal 5-14 AWG (655.0230)LF2,673$1.50$1.50$1.50$1.50$1.50$1.70
238Cable traffic signal 7-14 AWG (655.0240)LF1,862$1.93$1.93$1.93$1.93$1.93$2.10
239Cable traffic signal 12-14 AWG (655.0260)LF7,190$3.08$3.08$3.08$3.08$3.08$3.30
240Cable traffic signal 15-14 AWG (655.0270)LF660$3.39$3.39$3.39$3.39$3.39$3.60
241Cable traffic signal 21-14 AWG (655.0290)LF235$4.44$4.44$4.44$4.44$4.44$5.00
242Cable type UF 2-12 AWG grounded (655.0305)LF730$1.31$1.31$1.31$1.31$1.31$1.50
243Cable type UF 2-10 AWG grounded (655.0320)LF4,670$2.22$2.22$2.22$2.22$2.22$2.50
244Electrical wire traffic signals 10 AWG (655.0515)LF7,499$1.12$1.12$1.12$1.12$1.12$1.30
245Electrical wire lighting 12 AWG (655.0610)LF4,834$0.96$0.96$0.96$0.96$0.96$1.00
246Traffic signal evp detector cable (655.0900)LF4,593$1.24$1.24$1.24$1.24$1.24$1.50
247Electrical service meter breaker pedestal (location) 101. CTH O & CTH D (656.0201)EACH1$1,718.20$1,718.20$1,718.20$1,718.20$1,718.20$1,900.00
248Electrical service meter breaker pedestal (location) 102. CTH O & lincoln ave (656.0201)EACH1$1,718.20$1,718.20$1,718.20$1,718.20$1,718.20$1,900.00
249Electrical service meter breaker pedestal (location) 103. CTH O & rogers DR (656.0201)EACH1$1,718.20$1,718.20$1,718.20$1,718.20$1,718.20$1,900.00
250Electrical service meter breaker pedestal (location) 501. CTH O & ridge RD (656.0201)EACH1$1,718.20$1,718.20$1,718.20$1,718.20$1,718.20$1,900.00
251Pedestal bases (657.0100)EACH9$330.02$330.02$330.02$330.02$330.02$350.00
252Transformer bases breakaway 11 1/2-inch bolt circle (657.0255)EACH16$771.58$771.58$771.58$771.58$771.58$800.00
253Poles type 3 (657.0310)EACH12$4,150.84$4,150.84$4,150.84$4,150.84$4,150.84$4,300.00
254Poles type 5-aluminum (657.0322)EACH4$2,371.38$2,371.38$2,371.38$2,371.38$2,371.38$2,500.00
255Poles type 10 (657.0350)EACH2$11,372$11,372$11,372$11,372$11,372$12,000
256Poles type 10-special (657.0352)EACH5$14,036$14,036$14,036$14,036$14,036$15,000
257Poles type 13 (657.0360)EACH9$19,220$19,220$19,220$19,220$19,220$20,000
258Traffic signal standards aluminum 3.5-FT (657.0405)EACH1$380.86$380.86$380.86$380.86$380.86$400.00
259Traffic signal standards aluminum 13-FT (657.0420)EACH4$937.78$937.78$937.78$937.78$937.78$1,000.00
260Traffic signal standards aluminum 15-FT (657.0425)EACH2$1,023.78$1,023.78$1,023.78$1,023.78$1,023.78$1,100.00
261Traffic signal standards aluminum 10-FT (657.0430)EACH2$706.51$706.51$706.51$706.51$706.51$800.00
262Monotube arms 25-FT (657.0525)EACH2$4,576.78$4,576.78$4,576.78$4,576.78$4,576.78$5,000.00
263Monotube arms 35-FT-special (657.0536)EACH1$6,848.99$6,848.99$6,848.99$6,848.99$6,848.99$7,000.00
264Monotube arms 40-FT (657.0540)EACH2$10,195$10,195$10,195$10,195$10,195$10,700
265Monotube arms 45-FT (657.0545)EACH2$12,264$12,264$12,264$12,264$12,264$13,000
266Monotube arms 50-FT (657.0550)EACH1$14,141$14,141$14,141$14,141$14,141$15,000
267Monotube arms 55-FT (657.0555)EACH8$16,426$16,426$16,426$16,426$16,426$17,000
268Luminaire arms single member 4- inch clamp 8-FT (657.0614)EACH12$430.01$430.01$430.01$430.01$430.01$500.00
269Luminaire arms single member 4 1/2-inch clamp 8-FT (657.0615)EACH4$415.26$415.26$415.26$415.26$415.26$480.00
270Luminaire arms steel 10-FT (657.0810)EACH12$1,284.84$1,284.48$1,284.84$1,284.84$1,284.84$1,400.00
271Luminaire arms steel 15-FT (657.0815)EACH6$1,350.94$1,350.94$1,350.94$1,350.94$1,350.94$1,450.00
272Traffic signal face 3S 12-inch (658.0173)EACH61$712.67$712.67$712.67$712.67$712.67$770.00
273Traffic signal face 4S 12-inch (658.0174)EACH19$911.34$911.34$911.34$911.34$911.34$1,000.00
274Traffic signal face 5S 12-inch (658.0175)EACH6$1,124.38$1,124.38$1,124.38$1,124.38$1,124.38$1,200.00
275Pedestrian signal face 16-inch (658.0416)EACH4$450.71$450.71$450.71$450.71$450.71$500.00
276Signal mounting hardware (location) 101. CTH O & CTH D (658.5070)EACH1$6,209.40$6,209.40$6,209.40$6,209.40$6,209.40$6,500.00
277Signal mounting hardware (location) 102. CTH O & lincoln ave (658.5070)EACH1$5,631.94$5,631.94$5,631.94$5,631.94$5,631.94$6,000.00
278Signal mounting hardware (location) 103. CTH O & rogers DR (658.5070)EACH1$5,300.21$5,300.21$5,300.21$5,300.21$5,300.21$5,500.00
279Signal mounting hardware (location) 501. CTH O & ridge RD (658.5070)EACH1$5,201.91$5,201.91$5,201.91$5,201.91$5,201.91$5,500.00
280Luminaires utility LED C (659.1125)EACH34$367.48$367.48$367.48$367.48$367.48$400.00
281Lamp, ballast, LED, switch disposal by contractor (659.5000.S)EACH56$25.48$25.48$25.48$25.48$25.48$30.00
282Temporary traffic signals for intersections (location) 101. CTH O & CTH D (661.0201)EACH1$40,840$40,840$40,840$40,840$40,840$44,000
283Temporary traffic signals for intersections (location) 102. CTH O & lincoln ave (661.0201)EACH1$40,840$40,840$40,840$40,840$40,840$44,000
284Temporary traffic signals for intersections (location) 103. CTH O & rogers DR (661.0201)EACH1$39,577$39,577$39,577$39,577$39,577$43,000
285Field system integrator (670.0101)EACH1$23,753$23,753$23,753$23,753$23,753$25,000
286ITS documentation (670.0201)EACH1$7,995.22$7,995.22$7,995.22$7,995.22$7,995.22$8,500.00
287Communication vault type 1 (673.0105)EACH6$2,989.92$2,989.92$2,989.92$2,989.92$2,989.92$3,100.00
288Remove cable (674.0300)LF1,078$0.81$0.81$0.81$0.81$0.81$1.00
289Reinstall cable (674.0400)LF1,066$0.81$0.81$0.81$0.81$0.81$1.00
290Fiber optic splice (678.0300)EACH96$190.50$190.50$190.50$190.50$190.50$200.00
291Communication system testing (678.0501)EACH1$7,995.22$7,995.22$7,995.22$7,995.22$7,995.22$8,000.00
292Sawing asphalt (690.0150)LF2,100$1.35$2.50$1.65$1.35$1.35$2.00
293Sawing concrete (690.0250)LF6,428$4.25$3.00$2.85$2.25$2.25$2.00
294Incentive flexural strength concrete pavement (715.0715)DOL23,720$1.00$1.00$1.00$1.00$1.00$1.00
295Incentive iri ride (740.0440)DOL18,060$1.00$1.00$1.00$1.00$1.00$1.00
296On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS4,900$5.00$5.00$5.00$5.00$5.00$5.00
297On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS8,640$5.00$5.00$5.00$5.00$5.00$5.00
298Special 001. engineered soil (SPV.0035)CY98$85.00$125.00$90.00$104.20$125.00$90.00
299Special 001. drain tile sump connection (SPV.0060)EACH10$100.00$600.14$1,593.78$549.68$1,000.00$1,650.00
300Special 002. posts tubular steel 1.75X1.75-inch X 11-FT (SPV.0060)EACH119$175.00$160.00$149.48$160.00$160.00$160.00
301Special 003. posts tubular steel 1.75X1.75-inch X 12-FT (SPV.0060)EACH114$175.00$160.00$154.53$160.00$160.00$160.00
302Special 004. posts tubular steel 1.75X1.75-inch X 14-FT (SPV.0060)EACH88$175.00$175.00$165.64$175.00$175.00$175.00
303Special 005. posts tubular steel 1.75X1.75-inch X 16-FT (SPV.0060)EACH2$175.00$225.00$198.97$225.00$225.00$225.00
304Special 006. utility line opening (ulo) (SPV.0060)EACH42$0.01$300.00$2,038.25$2,060.06$750.00$1,000.00
305Special 007. section corner monuments (SPV.0060)EACH3$1,000.00$3,000.00$100.00$2,000.00$200.00$500.00
306Special 008. construction staking bioswales (SPV.0060)EACH1$800.00$800.00$808.00$800.00$800.00$1,500.00
307Special 101. reinstall temporary evp equipment CTH O & CTH D (SPV.0060)EACH1$3,491.43$3,491.43$3,491.43$3,491.43$3,491.43$3,700.00
308Special 102. reinstall temporary evp equipment CTH O & lincoln ave (SPV.0060)EACH1$3,491.43$3,491.43$3,491.43$3,491.43$3,491.43$3,700.00
309Special 103. reinstall temporary evp equipment CTH O & rogers DR (SPV.0060)EACH1$3,491.43$3,491.43$3,491.43$3,491.43$3,491.43$3,700.00
310Special 104. furnish and install video detection system CTH O & CTH D (SPV.0060)EACH1$52,039$52,039$52,039$52,039$52,039$55,000
311Special 105. furnish and install video detection system CTH O & lincoln ave (SPV.0060)EACH1$52,039$52,039$52,039$52,039$52,039$55,000
312Special 106. furnish and install video detection system CTH O & rogers DR (SPV.0060)EACH1$52,039$52,039$52,039$52,039$52,039$55,000
313Special 107. traffic signal controller and cabinet, CTH O & CTH D (SPV.0060)EACH1$32,035$32,035$32,035$32,035$32,035$35,000
314Special 108. traffic signal controller and cabinet, CTH O & lincoln ave (SPV.0060)EACH1$32,035$32,035$32,035$32,035$32,035$35,000
315Special 109. traffic signal controller and cabinet, CTH O & rogers DR (SPV.0060)EACH1$32,035$32,035$32,035$32,035$32,035$35,000
316Special 110. temporary vehicle detection system CTH O & CTH D (SPV.0060)EACH1$4,353.93$4,353.93$4,353.93$4,353.93$4,353.93$4,500.00
317Special 111. temporary vehicle detection system CTH O & lincoln ave (SPV.0060)EACH1$4,353.93$4,353.93$4,353.93$4,353.93$4,353.93$4,500.00
318Special 112. temporary vehicle detection system CTH O & rogers DR (SPV.0060)EACH1$4,353.93$4,353.93$4,353.93$4,353.93$4,353.93$4,500.00
319Special 113. remove & reinstall evp equipment CTH O & CTH D (SPV.0060)EACH1$2,904.14$2,904.14$2,904.01$2,904.14$2,904.14$3,100.00
320Special 114. remove & reinstall evp equipment CTH O & lincoln ave (SPV.0060)EACH1$2,904.14$2,904.14$2,904.14$2,904.14$2,904.14$3,100.00
321Special 115. remove & reinstall evp equipment CTH O & rogers DR (SPV.0060)EACH1$2,904.14$2,904.14$2,904.14$2,904.14$2,904.14$3,100.00
322Special 116. pre-terminated patch panel with 6-ports (SPV.0060)EACH4$996.23$996.23$996.23$996.23$996.23$1,100.00
323Special 117. IP ethernet switch with single mode fiber ports (SPV.0060)EACH4$4,250.32$4,250.32$4,250.32$4,250.32$4,250.32$4,500.00
324Special 118. site mowing (SPV.0060)EACH1$2,500.00$4,150.00$8,080.00$4,765.03$4,150.00$4,150.00
325Special 119. furnish and install fiber optic splice enclosure (SPV.0060)EACH6$1,953.67$1,953.67$1,953.67$1,953.67$1,953.67$2,100.00
326Special 120. connect to existing storm sewer (SPV.0060)EACH7$1,000.00$937.51$1.01$1.00$1,500.00$100.00
327Special 121. temporary pipe connection, 12-inch (SPV.0060)EACH7$500.00$976.56$1,487.73$1,473.00$750.00$1,500.00
328Special 122. temporary pipe connection, 15-inch (SPV.0060)EACH1$500.00$1,026.56$2,194.73$2,173.00$750.00$2,200.00
329Special 123. temporary pipe connection, 24-inch (SPV.0060)EACH1$500.00$1,026.56$2,324.01$2,301.00$750.00$2,400.00
330Special 124. reconstructing manholes special (SPV.0060)EACH1$1,000.00$1,337.26$1,344.31$1,331.00$3,000.00$1,400.00
331Special 125. repair storm sewer structure (SPV.0060)EACH1$3,000.00$1,752.76$3,030.00$5,000.00$3,000.00$2,600.00
332Special 126. cleaning storm sewer pipe (SPV.0060)EACH8$800.00$1,176.72$2,525.00$1,200.00$2,400.00$1,100.00
333Special 127. cleaning storm sewer structure (SPV.0060)EACH6$500.00$1,176.72$505.00$750.00$1,500.00$1,000.00
334Special 201. adjusting water valve boxes (SPV.0060)EACH22$500.00$122.30$337.34$334.00$500.00$350.00
335Special 202. adjusting sanitary manholes (SPV.0060)EACH17$1,250.00$1,001.37$1,473.59$1,459.00$1,500.00$1,500.00
336Special 203. permanent connection to existing 16-inch water main (SPV.0060)EACH2$1.00$6,476.43$7,334.62$7,262.00$5,000.00$7,500.00
337Special 501. furnish & install video detection system CTH O & ridge RD (SPV.0060)EACH1$51,411$51,411$51,411$51,411$51,411$53,000
338Special 502. traffic signal controller and cabinet CTH O & ridge RD (SPV.0060)EACH1$32,035$32,035$32,035$32,035$32,035$35,000
339Special 503. furnish & install evp system with confirmation lights CTH O & ridge RD (SPV.0060)EACH1$14,188$14,188$14,188$14,188$14,188$15,000
340Special 504. furnish & install accessible pedestrian signal system CTH O & ridge RD (SPV.0060)EACH1$11,755$11,755$11,755$11,755$11,755$12,000
341Special 001. native pollinator seeding mixture no. 95A (SPV.0085)LB1$300.00$500.00$255.53$500.00$500.00$500.00
342Special 101. native seeding mixture no. 75 updated (SPV.0085)LB20$125.00$130.00$169.68$130.00$130.00$130.00
343Special 001. concrete curb & gutter 24-inch type D (SPV.0090)LF71$100.00$40.00$75.00$40.00$40.00$75.00
344Special 002. construction staking fence (SPV.0090)LF282$3.00$3.00$3.03$3.00$3.00$3.00
345Special 006. concrete curb & gutter hes 30-inch type A (SPV.0090)LF132$100.00$50.00$95.00$50.00$50.00$35.00
346Special 007. concrete curb & gutter hes 30-inch type D (SPV.0090)LF29$100.00$70.00$95.00$70.00$70.00$35.00
347Special 101. furnish and install fiber optic cable outdoor plant 48- CT (SPV.0090)LF8,755$7.08$7.08$7.08$7.08$7.08$7.50
348Special 201. removing water main (SPV.0090)LF48$1.00$47.09$54.54$54.00$50.00$55.00
349Special 202. AWWA C900 DR-18 PVC water main 16-inch (SPV.0090)LF58$872.50$535.11$635.29$629.00$500.00$650.00
350Special 001. seedbed preparation (SPV.0165)SF1,755$1.00$0.95$0.30$0.95$0.95$1.00
351Special 002. seeding bioswale (SPV.0165)SF1,755$1.00$0.95$0.05$0.95$0.95$1.00
352Special 401. wall modular block mechanically stabilized earth R-67- 173 (SPV.0165)SF1,040$87.00$70.45$75.00$70.45$77.45$97.00
353Special 001. mulching bioswale (SPV.0180)SY195$0.55$5.00$0.81$5.00$5.00$5.00
354Special 005. excavation of phragmites contaminated soil (SPV.0180)SY195$75.00$41.97$92.50$93.62$50.00$36.00
WisDOT contract 20260915008: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of September 15, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy