Apron endwalls for culvert pipe reinforced concrete 15-inch, WisDOT 522.1015
Low bidders on WisDOT contracts carried a median of $1,337.54 per EACH for this item, over the 24 months to 10 NOV 2026, across 43 low bids. Half of all 201 bids fell between $1,180.76 and $1,541.39.
- Owner
- Wisconsin DOT
- Item
- 522.1015
- Unit
- EACH
- Data through
- 10 NOV 2026
WisDOT prints this item as “Apron Endwalls for Culvert Pipe Reinforced Concrete 15-Inch”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 18 | 18 | $1,000.00 | 69 | $1,000.00 |
| 2023 | 16 | 14 | $1,226.00 | 71 | $1,250.00 |
| 2024 | 20 | 18 | $1,262.66 | 95 | $1,272.00 |
| 2025 | 19 | 18 | $1,233.50 | 81 | $1,300.00 |
| 2026 | 18 | 18 | $1,432.65 | 81 | $1,374.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Outagamie | 10 | $1,242.00 | 45 | $1,250.00 |
| Waukesha | 5 | $1,635.35 | 44 | $1,550.00 |
| Dane | 4 | $1,199.43 | 26 | $1,237.12 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 10 | $1,221.43 |
| 1 to 2 | 11 | $1,500.00 |
| 2 to 6 | 11 | $1,361.63 |
| 6 to 75 | 11 | $1,250.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Vinton Construction Company | 27 | 13 (48%) |
| Zignego Company, Inc. | 37 | 12 (32%) |
| James Peterson Sons, Inc. | 37 | 11 (30%) |
| A.W. Oakes & Son, Inc. | 14 | 9 (64%) |
| Michels Road & Stone, Inc. | 29 | 7 (24%) |
| Zenith Tech., Inc. - Waukesha | 13 | 7 (54%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 10 NOV 2026 | 20261110003 | Green | 2 | $1,388.36 | $1,354.18 | 4 | Rock Road Companies, Inc. | WisDOT |
| 10 NOV 2026 | 20261110015 | Milwaukee | 1 | $1,590.00 | $1,379.23 | 5 | Payne and Dolan, Inc | WisDOT |
| 10 NOV 2026 | 20261110017 | Walworth | 3 | $1,098.33 | $1,098.33 | 5 | James Peterson Sons, Inc. | WisDOT |
| 10 NOV 2026 | 20261110018 | Kenosha | 1 | $1,250.00 | $1,174.16 | 6 | A.W. Oakes & Son, Inc. | WisDOT |
| 10 NOV 2026 | 20261110030 | Ashland | 1 | $1,549.00 | $1,549.00 | 1 | Northwoods Paving, A Div. of Mathy Construction610 | WisDOT |
| 13 OCT 2026 | 20261013010 | Outagamie | 75 | $1,219.76 | $1,177.38 | 5 | Zignego Company, Inc. | WisDOT |
| 15 SEP 2026 | 20260915008 | Waukesha | 1 | $1,500.00 | $1,671.00 | 9 | Zignego Company, Inc. | WisDOT |
| 15 SEP 2026 | 20260915018 | Lincoln | 4 | $1,413.30 | $1,413.30 | 5 | Musson Bros., Inc. | WisDOT |
| 15 SEP 2026 | 20260915023 | Wood | 6 | $2,130.00 | $1,500.00 | 3 | Norcon Corporation | WisDOT |
| 11 AUG 2026 | 20260811013 | Outagamie | 1 | $1,336.23 | $1,374.00 | 4 | Relyco Plus, LLC | WisDOT |
| 14 JUL 2026 | 20260714005 | Outagamie | 5 | $1,143.53 | $1,143.53 | 6 | Vinton Construction Company | WisDOT |
| 12 MAY 2026 | 20260512013 | Brown | 2 | $1,500.00 | $1,387.59 | 3 | Peters Concrete Company | WisDOT |
| 12 MAY 2026 | 20260512024 | Racine | 2 | $1,554.00 | $1,377.00 | 4 | Zignego Company, Inc. | WisDOT |
| 10 MAR 2026 | 20260310024 | Marinette | 7 | $1,452.00 | $1,522.54 | 3 | James Peterson Sons, Inc. | WisDOT |
| 10 FEB 2026 | 20260210018 | Kenosha | 3 | $1,520.00 | $1,595.78 | 2 | Musson Bros., Inc. | WisDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the WisDOT explorer.
How these prices were read
WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WisDOT's own: this item is compared with WisDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the WisDOT letting of 10 NOV 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.