WisDOT contract 20260915018 bid tabulation
1590-14-73. Let by Wisconsin DOT on September 15, 2026, Lincoln. 5 bids received; low bid $5,409,265 by Musson Bros., Inc..
- Owner
- Wisconsin DOT
- Letting
- 15 SEP 2026
- Pay items
- 186
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Musson Bros., Inc. | $5,409,265 | Low |
| 2 | James Peterson Sons, Inc. | $5,623,052 | +4.0% |
| 3 | S & N Incorporated | $5,772,721 | +7.0% |
| 4 | Hoffman Construction Company | $5,997,882 | +11% |
| 5 | A-1 Excavating LLC | $6,016,569 | +11% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Musson Bros., Inc. | 2. James Peterson Sons, Inc. | 3. S & N Incorporated | 4. Hoffman Construction Company | 5. A-1 Excavating LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 21 | $650.00 | $990.00 | $600.00 | $990.00 | $1,040.00 |
| 2 | Clearing (201.0120) | ID | 648 | $35.00 | $25.00 | $45.00 | $25.00 | $27.00 |
| 3 | Grubbing (201.0205) | STA | 21 | $275.00 | $325.00 | $600.00 | $325.00 | $375.00 |
| 4 | Grubbing (201.0220) | ID | 648 | $14.00 | $10.00 | $15.00 | $10.00 | $12.00 |
| 5 | Removing small pipe culverts (203.0100) | EACH | 7 | $627.09 | $750.00 | $1,600.00 | $2,400.00 | $1,000.00 |
| 6 | Removing concrete pavement (204.0100) | SY | 1,050 | $0.01 | $4.85 | $13.50 | $5.00 | $6.00 |
| 7 | Removing asphaltic surface (204.0110) | SY | 3,600 | $5.22 | $2.75 | $4.00 | $5.00 | $3.00 |
| 8 | Removing asphaltic surface butt joints (204.0115) | SY | 350 | $2.50 | $2.50 | $9.00 | $2.50 | $3.00 |
| 9 | Removing asphaltic surface milling (204.0120) | SY | 37,000 | $1.10 | $1.10 | $1.07 | $1.10 | $1.20 |
| 10 | Removing curb & gutter (204.0150) | LF | 836 | $8.11 | $4.00 | $4.75 | $5.00 | $5.00 |
| 11 | Removing delineators and markers (204.0180) | EACH | 23 | $25.00 | $25.00 | $25.00 | $25.00 | $30.00 |
| 12 | Removing concrete bases (204.0195) | EACH | 3 | $496.00 | $500.00 | $496.00 | $496.00 | $696.00 |
| 13 | Removing utility poles (204.0205) | EACH | 1 | $467.00 | $467.00 | $467.00 | $467.00 | $667.00 |
| 14 | Removing manholes (204.0210) | EACH | 1 | $627.15 | $750.00 | $600.00 | $350.00 | $600.00 |
| 15 | Removing inlets (204.0220) | EACH | 1 | $627.15 | $500.00 | $400.00 | $350.00 | $600.00 |
| 16 | Removing storm sewer (size) 01. 12-inch (204.0245) | LF | 20 | $10.45 | $26.75 | $18.00 | $13.50 | $20.00 |
| 17 | Removing storm sewer (size) 02. 18-inch (204.0245) | LF | 80 | $10.45 | $26.75 | $17.00 | $13.50 | $20.00 |
| 18 | Removing storm sewer (size) 03. 24-inch (204.0245) | LF | 33 | $10.45 | $26.75 | $30.00 | $13.50 | $30.00 |
| 19 | Removing storm sewer (size) 04. 30-inch (204.0245) | LF | 16 | $20.91 | $26.75 | $40.00 | $13.50 | $30.00 |
| 20 | Excavation common (205.0100) | CY | 35,151 | $8.80 | $14.05 | $11.20 | $20.00 | $10.00 |
| 21 | Borrow (208.0100) | CY | 27,073 | $0.01 | $11.85 | $14.16 | $1.00 | $24.00 |
| 22 | Prepare foundation for asphaltic paving (project) 01. 1590-14-73 (211.0101) | EACH | 1 | $500.00 | $1.00 | $1.00 | $1.00 | $36,650 |
| 23 | Prepare foundation for asphaltic shoulders (211.0400) | STA | 210 | $25.00 | $25.00 | $72.25 | $25.00 | $26.00 |
| 24 | Finishing roadway (project) 01. 1590-14-73 (213.0100) | EACH | 1 | $500.00 | $1,000.00 | $950.00 | $100.00 | $500.00 |
| 25 | Finishing roadway (project) 02. 1590-14-75 (213.0100) | EACH | 1 | $500.00 | $1,000.00 | $950.00 | $100.00 | $500.00 |
| 26 | Finishing roadway (project) 03. 1590-14-76 (213.0100) | EACH | 1 | $500.00 | $1,000.00 | $950.00 | $100.00 | $500.00 |
| 27 | Obliterating old road (214.0100) | STA | 4.90 | $382.29 | $1,500.00 | $500.00 | $350.00 | $700.00 |
| 28 | Base aggregate dense 3/4-inch (305.0110) | TON | 3,740 | $6.02 | $25.00 | $26.15 | $40.00 | $26.00 |
| 29 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 37,630 | $16.74 | $17.60 | $20.55 | $25.00 | $21.00 |
| 30 | Coloring concrete wisdot red (405.0100) | CY | 387 | $90.53 | $90.53 | $90.53 | $90.53 | $94.00 |
| 31 | Concrete truck apron 12-inch (415.2010) | SY | 1,158 | $105.88 | $105.88 | $105.88 | $105.88 | $109.00 |
| 32 | HMA cold weather paving (450.4000) | TON | 4,730 | $0.50 | $0.50 | $0.50 | $0.50 | $0.70 |
| 33 | Tack coat (455.0605) | GAL | 5,414 | $4.00 | $4.00 | $4.00 | $4.00 | $4.20 |
| 34 | Incentive density HMA pavement (460.2000) | DOL | 7,950 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 35 | HMA pavement 4 MT 58-28 S (460.6224) | TON | 5,253 | $85.00 | $85.00 | $85.00 | $85.00 | $86.00 |
| 36 | HMA pavement 3 HT 58-28 S (460.7223) | TON | 5,285 | $91.40 | $91.40 | $91.40 | $91.40 | $92.00 |
| 37 | HMA pavement 4 HT 58-34 H (460.7444) | TON | 2,375 | $98.00 | $98.00 | $98.00 | $98.00 | $99.00 |
| 38 | Asphaltic surface (465.0105) | TON | 610 | $85.00 | $85.00 | $85.00 | $85.00 | $88.00 |
| 39 | Asphaltic surface patching (465.0110) | TON | 110 | $120.00 | $120.00 | $120.00 | $120.00 | $160.00 |
| 40 | Asphaltic surface driveways and field entrances (465.0120) | TON | 40 | $120.00 | $120.00 | $120.00 | $120.00 | $160.25 |
| 41 | Asphaltic surface temporary (465.0125) | TON | 1,555 | $98.00 | $98.00 | $98.00 | $98.00 | $112.80 |
| 42 | Asphaltic flumes (465.0315) | SY | 122 | $25.00 | $25.00 | $25.00 | $25.00 | $36.00 |
| 43 | Asphaltic rumble strips, shoulder (465.0520) | LF | 22,647 | $0.22 | $0.25 | $0.56 | $0.36 | $0.50 |
| 44 | Asphaltic rumble strips, centerline (465.0560) | LF | 6,933 | $0.22 | $0.25 | $0.56 | $0.68 | $1.00 |
| 45 | Apron endwalls for culvert pipe 30- inch (520.1030) | EACH | 1 | $1,104.63 | $900.00 | $1,095.00 | $1,100.00 | $1,110.00 |
| 46 | Apron endwalls for culvert pipe 36- inch (520.1036) | EACH | 2 | $1,519.42 | $1,269.00 | $1,185.00 | $1,300.00 | $1,580.00 |
| 47 | Culvert pipe class III-A 18-inch (520.3318) | LF | 111 | $57.51 | $87.75 | $75.55 | $70.00 | $67.00 |
| 48 | Culvert pipe class III-A 30-inch (520.3330) | LF | 6 | $106.09 | $250.75 | $216.40 | $404.00 | $160.00 |
| 49 | Culvert pipe class III-B 36-inch (520.3536) | LF | 267 | $140.93 | $184.00 | $96.40 | $144.00 | $125.00 |
| 50 | Concrete collars for pipe (520.8000) | EACH | 2 | $1,173.84 | $750.00 | $975.00 | $1,250.00 | $1,500.00 |
| 51 | Apron endwalls for culvert pipe sloped side drains steel 18-inch 6 to 1 (521.1518) | EACH | 8 | $1,532.50 | $1,312.00 | $975.00 | $2,000.00 | $1,925.00 |
| 52 | Apron endwalls for culvert pipe sloped side drains steel 24-inch 6 to 1 (521.1524) | EACH | 2 | $2,306.58 | $1,960.00 | $2,250.00 | $2,700.00 | $2,475.00 |
| 53 | Culvert pipe reinforced concrete class III 30-inch (522.0130) | LF | 10 | $278.57 | $242.50 | $288.40 | $194.00 | $180.00 |
| 54 | Culvert pipe reinforced concrete class IV 15-inch (522.0415) | LF | 34 | $131.85 | $122.50 | $115.75 | $92.00 | $109.00 |
| 55 | Culvert pipe reinforced concrete class IV 24-inch (522.0424) | LF | 254 | $133.53 | $151.75 | $91.85 | $116.00 | $105.00 |
| 56 | Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012) | EACH | 9 | $1,334.22 | $858.00 | $1,280.00 | $1,822.00 | $1,870.00 |
| 57 | Apron endwalls for culvert pipe reinforced concrete 15-inch (522.1015) | EACH | 4 | $1,413.30 | $923.00 | $965.00 | $1,906.00 | $1,990.00 |
| 58 | Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024) | EACH | 3 | $1,753.00 | $1,305.00 | $1,615.00 | $2,260.00 | $2,370.00 |
| 59 | Apron endwalls for culvert pipe reinforced concrete 30-inch (522.1030) | EACH | 1 | $2,349.26 | $1,588.00 | $1,880.00 | $2,700.00 | $5,165.00 |
| 60 | Apron endwalls for culvert pipe salvaged 30-inch (524.0630) | EACH | 1 | $1,535.56 | $554.00 | $1,100.00 | $1,060.00 | $1,100.00 |
| 61 | Concrete gutter 24-inch (601.0205) | LF | 82 | $78.04 | $78.04 | $78.04 | $78.04 | $79.00 |
| 62 | Concrete curb & gutter 18-inch type A (601.0405) | LF | 478 | $41.03 | $41.03 | $41.03 | $41.03 | $42.00 |
| 63 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 3,374 | $25.96 | $25.96 | $25.96 | $25.96 | $26.50 |
| 64 | Concrete curb & gutter 4-inch sloped 36-inch type A (601.0551) | LF | 421 | $34.80 | $34.80 | $34.80 | $34.80 | $36.00 |
| 65 | Concrete curb & gutter 4-inch sloped 36-inch type D (601.0553) | LF | 2,858 | $27.92 | $27.92 | $27.92 | $27.92 | $28.50 |
| 66 | Concrete curb & gutter 4-inch sloped 30-inch type R (601.0581) | LF | 672 | $45.14 | $45.14 | $45.14 | $45.14 | $47.00 |
| 67 | Concrete curb pedestrian (601.0600) | LF | 310 | $40.72 | $40.72 | $40.72 | $40.72 | $42.00 |
| 68 | Concrete sidewalk 4-inch (602.0405) | SF | 32,960 | $7.66 | $7.66 | $7.66 | $7.66 | $8.00 |
| 69 | Concrete sidewalk 6-inch (602.0415) | SF | 220 | $17.70 | $17.70 | $17.70 | $17.70 | $19.00 |
| 70 | Curb ramp detectable warning field natural patina (602.0515) | SF | 496 | $60.38 | $60.38 | $60.38 | $60.38 | $61.50 |
| 71 | Riprap medium (606.0200) | CY | 160 | $160.94 | $102.00 | $160.00 | $150.00 | $140.00 |
| 72 | Storm sewer pipe reinforced concrete class IV 12-inch (608.0412) | LF | 558 | $134.74 | $113.32 | $77.35 | $75.00 | $86.00 |
| 73 | Storm sewer pipe reinforced concrete class IV 24-inch (608.0424) | LF | 29 | $171.01 | $130.00 | $111.35 | $150.00 | $138.00 |
| 74 | Inlet covers type H (611.0624) | EACH | 2 | $1,832.37 | $1,281.00 | $875.00 | $1,100.00 | $1,225.00 |
| 75 | Inlet covers type HM (611.0627) | EACH | 2 | $1,832.37 | $1,281.00 | $875.00 | $1,100.00 | $1,225.00 |
| 76 | Inlet covers type HM-S (611.0636) | EACH | 6 | $1,832.37 | $1,281.00 | $875.00 | $1,100.00 | $1,225.00 |
| 77 | Inlet covers type H-S (611.0639) | EACH | 6 | $1,832.37 | $1,281.00 | $875.00 | $1,100.00 | $1,225.00 |
| 78 | Inlet covers type T (611.0652) | EACH | 4 | $2,150.89 | $1,679.00 | $1,205.00 | $1,500.00 | $1,510.00 |
| 79 | Manholes 5-FT diameter (611.2005) | EACH | 1 | $4,579.53 | $4,222.00 | $4,300.00 | $5,500.00 | $6,020.00 |
| 80 | Inlets 4-FT diameter (611.3004) | EACH | 2 | $3,184.70 | $2,981.00 | $3,345.50 | $3,800.00 | $3,720.00 |
| 81 | Inlets 2X2.5-FT (611.3225) | EACH | 4 | $1,633.76 | $1,535.00 | $2,115.00 | $2,000.00 | $2,250.00 |
| 82 | Inlets 2X3-FT (611.3230) | EACH | 14 | $2,325.85 | $1,923.00 | $2,400.00 | $2,500.00 | $2,800.00 |
| 83 | Cover plates temporary (611.8120.S) | EACH | 1 | $430.56 | $250.00 | $950.00 | $300.00 | $200.00 |
| 84 | Pipe grates (size) 01. 30-inch (611.9850.S) | EACH | 2 | $2,604.46 | $3,010.00 | $2,600.00 | $3,200.00 | $2,300.00 |
| 85 | Pipe grates (size) 02. 36-inch (611.9850.S) | EACH | 2 | $3,455.59 | $4,138.00 | $2,750.00 | $4,400.00 | $3,000.00 |
| 86 | Maintenance and repair of haul roads (project) 01. 1590-14-73 (618.0100) | EACH | 1 | $1.00 | $500.00 | $100.00 | $100.00 | $500.00 |
| 87 | Mobilization (619.1000) | EACH | 1 | $860,000 | $287,000 | $415,000 | $486,250 | $204,047 |
| 88 | Concrete median sloped nose (620.0300) | SF | 952 | $14.27 | $14.27 | $14.27 | $14.27 | $15.00 |
| 89 | Water (624.0100) | MGAL | 772 | $1.00 | $50.00 | $1.00 | $0.01 | $1.00 |
| 90 | Topsoil (625.0100) | SY | 43,000 | $0.01 | $3.50 | $2.95 | $2.00 | $3.00 |
| 91 | Silt fence (628.1504) | LF | 9,400 | $1.70 | $1.70 | $1.70 | $1.70 | $1.75 |
| 92 | Silt fence maintenance (628.1520) | LF | 9,400 | $0.03 | $0.03 | $0.03 | $0.03 | $0.03 |
| 93 | Mobilizations erosion control (628.1905) | EACH | 20 | $193.00 | $193.00 | $193.00 | $193.00 | $213.00 |
| 94 | Mobilizations emergency erosion control (628.1910) | EACH | 14 | $293.00 | $293.00 | $293.00 | $293.00 | $313.00 |
| 95 | Erosion mat urban class I type B (628.2008) | SY | 43,000 | $1.70 | $1.70 | $1.70 | $1.70 | $1.75 |
| 96 | Inlet protection type A (628.7005) | EACH | 20 | $125.00 | $125.00 | $125.00 | $125.00 | $150.00 |
| 97 | Inlet protection type C (628.7015) | EACH | 20 | $75.00 | $75.00 | $75.00 | $75.00 | $100.00 |
| 98 | Temporary ditch checks (628.7504) | LF | 290 | $7.00 | $7.00 | $7.00 | $7.00 | $9.00 |
| 99 | Culvert pipe checks (628.7555) | EACH | 79 | $20.00 | $20.00 | $20.00 | $20.00 | $25.00 |
| 100 | Tracking pads (628.7560) | EACH | 11 | $1.00 | $500.00 | $450.00 | $500.00 | $1.00 |
| 101 | Rock bags (628.7570) | EACH | 220 | $5.00 | $5.00 | $5.00 | $5.00 | $9.00 |
| 102 | Fertilizer type B (629.0210) | CWT | 45 | $100.00 | $100.00 | $100.00 | $100.00 | $110.00 |
| 103 | Seeding mixture no. 30 (630.0130) | LB | 1,860 | $6.53 | $6.53 | $6.53 | $6.53 | $8.00 |
| 104 | Seeding temporary (630.0200) | LB | 546 | $4.33 | $4.33 | $4.33 | $4.33 | $5.00 |
| 105 | Seed water (630.0500) | MGAL | 2,885 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 106 | Markers culvert end (633.5200) | EACH | 16 | $75.00 | $75.00 | $75.00 | $75.00 | $85.00 |
| 107 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 33 | $100.00 | $100.00 | $100.00 | $100.00 | $110.00 |
| 108 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 25 | $125.00 | $125.00 | $125.00 | $125.00 | $135.00 |
| 109 | Posts tubular steel 2X2-inch X 12- FT (634.0812) | EACH | 7 | $275.00 | $275.00 | $275.00 | $275.00 | $285.00 |
| 110 | Posts tubular steel 2X2-inch X 14- FT (634.0814) | EACH | 19 | $275.00 | $275.00 | $275.00 | $275.00 | $285.00 |
| 111 | Signs type II reflective H (637.2210) | SF | 556.70 | $20.00 | $20.00 | $20.00 | $20.00 | $25.00 |
| 112 | Signs type II reflective F (637.2230) | SF | 88.75 | $30.00 | $30.00 | $30.00 | $30.00 | $33.00 |
| 113 | Moving signs type II (638.2102) | EACH | 31 | $100.00 | $100.00 | $100.00 | $100.00 | $110.00 |
| 114 | Removing signs type II (638.2602) | EACH | 25 | $25.00 | $25.00 | $25.00 | $25.00 | $35.00 |
| 115 | Removing small sign supports (638.3000) | EACH | 33 | $25.00 | $25.00 | $25.00 | $25.00 | $35.00 |
| 116 | Moving small sign supports (638.4000) | EACH | 28 | $100.00 | $100.00 | $100.00 | $100.00 | $110.00 |
| 117 | Field office type C (642.5201) | EACH | 1 | $25,000 | $15,000 | $17,500 | $25,000 | $12,000 |
| 118 | Traffic control drums (643.0300) | DAY | 9,000 | $0.50 | $0.50 | $0.50 | $0.50 | $0.60 |
| 119 | Traffic control barricades type III (643.0420) | DAY | 3,600 | $0.55 | $0.55 | $0.55 | $0.55 | $0.75 |
| 120 | Traffic control warning lights type A (643.0705) | DAY | 6,700 | $0.10 | $0.10 | $0.10 | $0.10 | $0.25 |
| 121 | Traffic control warning lights type C (643.0715) | DAY | 1,180 | $0.10 | $0.10 | $0.10 | $0.10 | $0.50 |
| 122 | Traffic control signs (643.0900) | DAY | 15,225 | $0.60 | $0.60 | $0.60 | $0.60 | $0.65 |
| 123 | Traffic control signs fixed message (643.1000) | SF | 72 | $10.20 | $10.20 | $10.20 | $10.20 | $13.20 |
| 124 | Traffic control signs PCMS (643.1050) | DAY | 60 | $45.00 | $45.00 | $45.00 | $45.00 | $50.00 |
| 125 | Temporary marking line paint 6- inch (643.3165) | LF | 52,750 | $0.39 | $0.77 | $0.77 | $0.77 | $0.80 |
| 126 | Temporary marking line removable tape 6-inch (643.3180) | LF | 13,155 | $1.90 | $1.90 | $1.90 | $1.90 | $1.95 |
| 127 | Traffic control (643.5000) | EACH | 1 | $5,182.00 | $5,182.00 | $5,182.00 | $5,182.00 | $20,182 |
| 128 | Temporary pedestrian barricade (644.1810) | LF | 350 | $5.00 | $5.00 | $5.00 | $5.00 | $6.00 |
| 129 | Geotextile type HR (645.0120) | SY | 385 | $8.21 | $3.50 | $7.50 | $10.00 | $5.00 |
| 130 | Marking line epoxy 6-inch (646.2020) | LF | 5,860 | $0.56 | $1.00 | $1.00 | $1.00 | $1.10 |
| 131 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 53,175 | $1.31 | $1.70 | $1.70 | $1.70 | $1.72 |
| 132 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 650 | $3.08 | $3.70 | $3.70 | $3.70 | $4.70 |
| 133 | Marking arrow epoxy (646.5020) | EACH | 2 | $239.53 | $350.00 | $350.00 | $350.00 | $400.00 |
| 134 | Marking stop line epoxy 18-inch (646.6120) | LF | 30 | $19.43 | $20.00 | $20.00 | $20.00 | $23.00 |
| 135 | Marking dotted extension epoxy 18-inch (646.6320) | LF | 126 | $19.43 | $20.00 | $20.00 | $20.00 | $23.00 |
| 136 | Cold weather marking epoxy 6-inch (646.6466) | LF | 39,850 | $0.56 | $0.32 | $0.32 | $0.32 | $0.35 |
| 137 | Cold weather marking epoxy 10- inch (646.6470) | LF | 125 | $5.00 | $0.49 | $0.49 | $0.49 | $5.00 |
| 138 | Marking diagonal epoxy 12-inch (646.7120) | LF | 465 | $15.96 | $9.00 | $9.00 | $9.00 | $11.00 |
| 139 | Marking curb epoxy (646.8120) | LF | 560 | $9.32 | $8.00 | $8.00 | $8.00 | $10.00 |
| 140 | Marking island nose epoxy (646.8220) | EACH | 9 | $348.10 | $330.00 | $330.00 | $330.00 | $380.00 |
| 141 | Marking removal line 4-inch (646.9000) | LF | 4,000 | $0.88 | $0.88 | $0.88 | $1.20 | $1.10 |
| 142 | Locating no-passing zones (648.0100) | MI | 1.95 | $623.81 | $2,000.00 | $2,000.00 | $2,000.00 | $2,200.00 |
| 143 | Construction staking storm sewer (650.4000) | EACH | 33 | $225.00 | $225.00 | $225.00 | $225.00 | $230.00 |
| 144 | Construction staking subgrade (650.4500) | LF | 7,325 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 145 | Construction staking base (650.5000) | LF | 7,325 | $1.12 | $1.12 | $1.12 | $1.12 | $1.25 |
| 146 | Construction staking pipe culverts (650.6000) | EACH | 9 | $275.00 | $275.00 | $275.00 | $275.00 | $325.00 |
| 147 | Construction staking resurfacing reference (650.8000) | LF | 10,333 | $0.15 | $0.15 | $0.15 | $0.15 | $0.25 |
| 148 | Construction staking electrical installations (project) 01. 1590-14- 75 (650.8501) | EACH | 1 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,200.00 |
| 149 | Construction staking electrical installations (project) 02. 1590-14- 76 (650.8501) | EACH | 1 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,200.00 |
| 150 | Construction staking curb ramps (650.9000) | EACH | 2 | $750.00 | $750.00 | $750.00 | $750.00 | $1,000.00 |
| 151 | Construction staking supplemental control (project) 01. 1590-14-73 (650.9911) | EACH | 1 | $10.00 | $10.00 | $10.00 | $10.00 | $210.00 |
| 152 | Construction staking supplemental control (project) 02. 1590-14-75 (650.9911) | EACH | 1 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,200.00 |
| 153 | Construction staking supplemental control (project) 03. 1590-14-76 (650.9911) | EACH | 1 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,200.00 |
| 154 | Construction staking slope stakes (650.9920) | LF | 7,325 | $1.12 | $1.12 | $1.12 | $1.12 | $1.25 |
| 155 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 4,281 | $10.94 | $10.94 | $10.94 | $10.94 | $11.25 |
| 156 | Conduit rigid nonmetallic schedule 40 3-inch (652.0235) | LF | 108 | $12.23 | $12.23 | $12.23 | $12.23 | $15.25 |
| 157 | Pull boxes non-conductive 24X42- inch (653.0164) | EACH | 37 | $2,542.00 | $2,542.00 | $2,542.00 | $2,542.00 | $2,562.00 |
| 158 | Concrete bases type 5 (654.0105) | EACH | 27 | $1,400.00 | $1,400.00 | $1,400.00 | $1,400.00 | $1,420.00 |
| 159 | Concrete control cabinet bases type L30 (654.0230) | EACH | 2 | $3,355.00 | $3,355.00 | $3,355.00 | $3,355.00 | $3,555.00 |
| 160 | Electrical wire lighting 12 AWG (655.0610) | LF | 3,645 | $1.37 | $1.37 | $1.37 | $1.37 | $1.60 |
| 161 | Electrical wire lighting 10 AWG (655.0615) | LF | 20,823 | $1.54 | $1.54 | $1.54 | $1.54 | $1.60 |
| 162 | Electrical service meter breaker pedestal (location) 01. sta. 11+93.85 'rab', 56.4' RT (656.0201) | EACH | 1 | $3,395.00 | $3,395.00 | $3,395.00 | $3,395.00 | $3,895.00 |
| 163 | Electrical service meter breaker pedestal (location) 02. sta. 50+17.65 'rab', 51.0' RT (656.0201) | EACH | 1 | $3,395.00 | $3,395.00 | $3,395.00 | $3,395.00 | $3,895.00 |
| 164 | Transformer bases breakaway 11 1/2-inch bolt circle (657.0255) | EACH | 27 | $792.00 | $792.00 | $792.00 | $792.00 | $892.00 |
| 165 | Poles type 5-aluminum (657.0322) | EACH | 27 | $2,657.00 | $2,657.00 | $2,657.00 | $2,657.00 | $3,157.00 |
| 166 | Luminaire arms truss type 4 1/2- inch clamp 12-FT (657.0710) | EACH | 27 | $901.00 | $901.00 | $901.00 | $901.00 | $1,001.00 |
| 167 | Luminaires utility LED A (659.1115) | EACH | 27 | $323.00 | $323.00 | $323.00 | $323.00 | $373.00 |
| 168 | Lighting control cabinets 120/240 30-inch (659.2130) | EACH | 2 | $11,152 | $11,152 | $11,152 | $11,152 | $12,152 |
| 169 | Public land survey monument verify and reset (680.0100) | EACH | 1 | $500.00 | $500.00 | $500.00 | $500.00 | $800.00 |
| 170 | Sawing asphalt (690.0150) | LF | 8,116 | $3.00 | $1.60 | $1.60 | $1.60 | $3.00 |
| 171 | Sawing concrete (690.0250) | LF | 60 | $10.00 | $2.35 | $2.35 | $2.35 | $6.00 |
| 172 | Incentive compressive strength concrete pavement (715.0720) | DOL | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 173 | Incentive iri ride (740.0440) | DOL | 7,828 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 174 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,400 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 175 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 1,980 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 176 | Special 01. removing flashing beacon assembly, ush 8 & CTH L intersection (SPV.0060) | EACH | 1 | $500.00 | $500.00 | $500.00 | $500.00 | $700.00 |
| 177 | Special 02. removing flashing beacon assembly, ush 8 & CTH A intersection (SPV.0060) | EACH | 1 | $500.00 | $500.00 | $500.00 | $500.00 | $700.00 |
| 178 | Special 03. construction staking roundabout CTH L intersection (SPV.0060) | EACH | 1 | $8,000.00 | $8,000.00 | $8,000.00 | $8,000.00 | $9,000.00 |
| 179 | Special 04. construction staking roundabout CTH A intersection (SPV.0060) | EACH | 1 | $8,000.00 | $8,000.00 | $8,000.00 | $8,000.00 | $9,000.00 |
| 180 | Special 05. temporary lighting CTH L intersection (SPV.0060) | EACH | 1 | $27,513 | $27,513 | $27,513 | $27,513 | $29,013 |
| 181 | Special 06. temporary lighting CTH A intersection (SPV.0060) | EACH | 1 | $29,031 | $29,031 | $29,031 | $29,031 | $30,531 |
| 182 | Special 07. research and locate existing land parcel monuments (SPV.0060) | EACH | 3 | $269.00 | $269.00 | $269.00 | $269.00 | $368.00 |
| 183 | Special 08. verify and replace existing land parcel monuments (SPV.0060) | EACH | 3 | $269.00 | $269.00 | $269.00 | $269.00 | $369.00 |
| 184 | Special 01. seeding low maintenance fescue (SPV.0085) | LB | 55 | $15.00 | $15.00 | $15.00 | $15.00 | $20.00 |
| 185 | Special 01. protective thermoplastic coating at snowmobile trail crossing (SPV.0180) | SY | 200 | $135.00 | $160.00 | $160.00 | $160.00 | $165.00 |
| 186 | Special 02. removing distressed asphaltic surface milling (SPV.0180) | SY | 930 | $4.00 | $4.00 | $7.00 | $4.00 | $5.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of September 15, 2026. Compiled by Mirage Metrics.