WisDOT contract 20261110003 bid tabulation

Monroe - Brodhead; E Jct STH 81 Intersection (STH 011, Green County Monroe - Brodhead). Let by Wisconsin DOT on November 10, 2026, Green. 4 bids received; low bid $2,821,533 by Rock Road Companies, Inc..

Owner
Wisconsin DOT
Letting
10 NOV 2026
Pay items
147
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Rock Road Companies, Inc.$2,821,533Low
2James Peterson Sons, Inc.$3,021,671+7.0%
3Parisi Construction, LLC$3,073,965+9.0%
4Zignego Company, Inc.$3,234,921+15%
WisDOT contract 20261110003: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Rock Road Companies, Inc.2. James Peterson Sons, Inc.3. Parisi Construction, LLC4. Zignego Company, Inc.
1Clearing (201.0105)STA4$1,250.00$1,250.00$1,300.00$350.00
2Grubbing (201.0205)STA4$600.00$850.00$630.00$350.00
3Removing small pipe culverts (203.0100)EACH3$377.69$675.00$710.00$450.00
4Removing structure (structure) 01. 72-inch culvert pipe (203.0220)EACH1$2,517.94$5,000.00$1,400.00$1,500.00
5Removing concrete pavement (204.0100)SY7,768$11.54$0.75$2.90$2.50
6Removing asphaltic surface (204.0110)SY74$7.55$20.00$22.00$10.00
7Removing curb & gutter (204.0150)LF379$7.48$2.75$14.25$8.00
8Removing fence (204.0170)LF14$35.00$50.00$26.00$10.00
9Removing inlets (204.0220)EACH1$377.69$650.00$730.00$500.00
10Removing storm sewer (size) 01. 18-inch (204.0245)LF63$16.79$25.00$22.50$25.00
11Excavation common (205.0100)CY23,548$10.74$12.50$17.50$9.05
12Borrow (208.0100)CY3,326$11.79$18.12$11.25$9.83
13Finishing roadway (project) 01. 1706-04-76 (213.0100)EACH1$5,360.01$2,500.00$500.00$750.00
14Base aggregate dense 3/4-inch (305.0110)TON1,125$32.97$31.40$25.50$21.50
15Base aggregate dense 1 1/4-inch (305.0120)TON13,360$16.36$20.23$17.00$19.50
16Base aggregate open-graded (310.0115)CY14$36.80$75.00$49.88$21.00
17Select crushed material (312.0110)TON14,500$15.54$15.45$17.75$19.00
18Coloring concrete wisdot red (405.0100)CY390$120.00$120.00$120.00$125.00
19Concrete pavement 9 1/2-inch (415.0095)SY4,845$92.00$92.00$92.00$120.49
20Concrete truck apron 12-inch (415.2010)SY1,160$105.00$105.00$105.00$164.31
21Concrete pavement joint filling (415.4100)SY6,730$2.10$2.10$2.20$2.75
22Rout and seal (415.6000.S)LF935$4.50$4.50$4.70$4.50
23HMA pavement 3 MT 58-28 S (450.6223)TON3,060$86.00$76.20$92.00$76.20
24HMA pavement 4 MT 58-28 H (450.6424)TON672$88.00$88.00$96.00$88.00
25Tack coat (455.0605)GAL505$3.00$3.00$0.10$3.00
26Asphaltic surface (465.0105)TON12$163.00$163.00$150.00$163.00
27Asphaltic surface driveways and field entrances (465.0120)TON23$150.00$150.00$120.00$150.00
28Asphaltic flumes (465.0315)SY83$57.00$57.00$31.50$57.00
29Apron endwalls for culvert pipe 12- inch (520.1012)EACH3$922.62$370.00$850.00$225.00
30Apron endwalls for culvert pipe 24- inch (520.1024)EACH4$1,216.79$920.00$1,100.00$480.00
31Culvert pipe temporary 12-inch (520.2012)LF46$68.49$88.00$49.75$40.00
32Culvert pipe temporary 24-inch (520.2024)LF192$84.37$109.50$83.00$105.00
33Culvert pipe class III-A non-metal 24-inch (520.3424)LF222$130.22$124.25$80.00$105.00
34Concrete collars for pipe (520.8000)EACH3$664.81$950.00$1,700.00$750.00
35Culvert pipe reinforced concrete class IV 15-inch (522.0415)LF48$93.64$110.00$73.00$87.00
36Culvert pipe reinforced concrete class IV 36-inch (522.0436)LF90$200.41$226.00$170.00$320.00
37Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012)EACH2$1,332.81$1,265.00$1,200.00$2,080.00
38Apron endwalls for culvert pipe reinforced concrete 15-inch (522.1015)EACH2$1,388.36$1,320.00$1,200.00$2,200.00
39Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036)EACH2$2,477.07$2,500.00$3,700.00$3,800.00
40Concrete curb & gutter 18-inch type A (601.0405)LF202$45.00$45.00$45.00$51.48
41Concrete curb & gutter 30-inch type A (601.0409)LF1,340$35.00$35.00$35.00$57.06
42Concrete curb & gutter 4-inch sloped 36-inch type A (601.0551)LF1,930$35.00$35.00$35.00$60.78
43Concrete curb & gutter 4-inch sloped 30-inch type R (601.0581)LF356$39.00$39.00$39.00$57.06
44Concrete curb pedestrian (601.0600)LF173$85.00$85.00$85.00$46.35
45Concrete sidewalk 4-inch (602.0405)SF10,950$6.50$6.50$6.50$13.91
46Curb ramp detectable warning field natural patina (602.0515)SF128$48.00$48.00$48.00$50.00
47Riprap medium (606.0200)CY32$101.74$150.00$160.00$85.00
48Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF73$100.74$107.50$82.00$75.00
49Storm sewer pipe class III-A 12- inch (608.3012)LF180$86.41$107.00$49.50$45.00
50Inlet covers type HM (611.0627)EACH4$1,209.89$920.00$1,100.00$1,100.00
51Inlet covers type HM-S (611.0636)EACH2$1,209.89$920.00$1,100.00$1,100.00
52Inlet covers type H-S (611.0639)EACH2$1,209.89$920.00$1,100.00$1,100.00
53Inlet covers type MS (611.0642)EACH2$846.17$620.00$850.00$1,100.00
54Inlet covers type T (611.0652)EACH2$1,497.02$1,300.00$1,400.00$1,500.00
55Inlets 2X2.5-FT (611.3225)EACH2$2,170.98$2,250.00$1,700.00$1,700.00
56Inlets 2X3-FT (611.3230)EACH8$2,352.38$2,410.00$2,400.00$1,950.00
57Inlets median 2 grate (611.3902)EACH1$3,279.82$3,400.00$2,000.00$3,650.00
58Pipe underdrain 6-inch (612.0106)LF355$24.94$10.60$11.75$9.00
59Maintenance and repair of haul roads (project) 01. 1706-04-76 (618.0100)EACH1$0.01$100.00$500.00$1.00
60Mobilization (619.1000)EACH1$100,000$281,905$175,000$154,000
61Concrete median sloped nose (620.0300)SF621$13.75$13.75$13.75$46.99
62Water (624.0100)MGAL235$0.01$5.00$36.25$0.05
63Topsoil (625.0100)SY33,500$2.75$1.18$3.70$2.50
64Mulching (627.0200)SY25,150$0.40$0.40$0.40$0.40
65Silt fence (628.1504)LF4,005$2.20$2.20$2.30$2.20
66Silt fence maintenance (628.1520)LF4,005$0.01$0.01$0.01$0.01
67Mobilizations erosion control (628.1905)EACH7$100.00$100.00$100.00$100.00
68Mobilizations emergency erosion control (628.1910)EACH5$100.00$100.00$100.00$100.00
69Erosion mat class I type B (628.2004)SY8,350$1.15$1.15$1.20$1.15
70Inlet protection type A (628.7005)EACH5$145.00$145.00$150.00$145.00
71Inlet protection type C (628.7015)EACH13$70.00$70.00$73.00$70.00
72Temporary ditch checks (628.7504)LF136$10.00$10.00$10.50$10.00
73Culvert pipe checks (628.7555)EACH37$20.00$20.00$21.00$20.00
74Tracking pads (628.7560)EACH6$500.00$2,000.00$1,200.00$1.00
75Fertilizer type B (629.0210)CWT35$90.00$90.00$94.00$90.00
76Seeding mixture no. 20 (630.0120)LB1,320$7.95$7.95$8.30$7.95
77Seeding mixture no. 40 (630.0140)LB20$20.00$20.00$21.00$20.00
78Seeding temporary (630.0200)LB1,025$4.50$4.50$4.70$4.50
79Seed water (630.0500)MGAL1,520$1.00$1.00$1.10$1.00
80Markers culvert end (633.5200)EACH8$75.00$75.00$79.00$75.00
81Posts wood 4X6-inch X 12-FT (634.0612)EACH8$80.00$80.00$84.00$80.00
82Posts wood 4X6-inch X 14-FT (634.0614)EACH17$85.00$85.00$89.00$85.00
83Posts wood 4X6-inch X 16-FT (634.0616)EACH12$90.00$90.00$94.00$90.00
84Posts wood 4X6-inch X 18-FT (634.0618)EACH12$100.00$100.00$100.00$100.00
85Posts tubular steel 2X2-inch X 14- FT (634.0814)EACH13$200.00$200.00$210.00$200.00
86Signs type II reflective H (637.2210)SF401.79$23.50$23.50$24.50$23.50
87Signs type II reflective F (637.2230)SF70$24.00$24.00$25.00$24.00
88Moving signs type II (638.2102)EACH37$175.00$175.00$180.00$175.00
89Removing signs type II (638.2602)EACH30$35.00$35.00$36.75$35.00
90Removing small sign supports (638.3000)EACH26$35.00$35.00$36.75$35.00
91Moving small sign supports (638.4000)EACH21$125.00$125.00$130.00$125.00
92Field office type C (642.5201)EACH1$6,750.00$15,000$6,500.00$25,000
93Traffic control drums (643.0300)DAY11,850$0.09$0.25$0.25$0.25
94Traffic control barricades type III (643.0420)DAY2,100$0.60$0.45$0.45$0.45
95Traffic control warning lights type A (643.0705)DAY3,500$0.06$0.10$0.10$0.10
96Traffic control warning lights type C (643.0715)DAY1,600$0.06$0.10$0.10$0.10
97Traffic control signs (643.0900)DAY19,050$0.34$0.60$0.65$0.60
98Traffic control covering signs type II (643.0920)EACH25$50.00$45.00$47.00$45.00
99Traffic control signs PCMS (643.1050)DAY95$35.00$35.00$36.75$35.00
100Temporary marking line removable tape 6-inch (643.3180)LF2,615$1.70$2.25$2.40$2.25
101Temporary marking stop line paint 18-inch (643.3805)LF40$3.00$1.50$1.60$1.50
102Traffic control (643.5000)EACH1$21,000$17,000$17,800$17,000
103Geotextile type DF schedule A (645.0111)SY200$3.81$6.00$2.20$5.00
104Geotextile type HR (645.0120)SY100$2.59$11.00$3.61$9.00
105Marking line epoxy 6-inch (646.2020)LF1,855$0.90$0.90$0.95$0.90
106Marking line grooved wet ref epoxy 6-inch (646.2040)LF13,510$1.40$1.40$1.50$1.40
107Marking line epoxy 10-inch (646.4020)LF295$2.35$2.35$2.50$2.35
108Marking dotted extension epoxy 18-inch (646.6320)LF72$9.00$9.00$9.40$9.00
109Marking diagonal epoxy 12-inch (646.7120)LF255$10.00$10.00$10.50$10.00
110Marking curb epoxy (646.8120)LF245$8.00$8.00$8.40$8.00
111Marking island nose epoxy (646.8220)EACH4$325.00$325.00$340.00$325.00
112Marking removal line 4-inch (646.9000)LF2,300$0.75$0.50$0.50$0.50
113Marking removal line 8-inch (646.9100)LF190$1.11$1.00$1.10$1.00
114Construction staking storm sewer (650.4000)EACH16$1.00$200.00$50.00$200.00
115Construction staking subgrade (650.4500)LF5,130$0.01$0.01$0.01$0.01
116Construction staking base (650.5000)LF5,130$0.01$2.00$0.01$2.00
117Construction staking pipe culverts (650.6000)EACH11$50.00$400.00$50.00$400.00
118Construction staking electrical installations (project) 01. 1706-04- 76 (650.8501)EACH1$5,000.00$4,000.00$500.00$4,000.00
119Construction staking supplemental control (project) 01. 1706-04-76 (650.9911)EACH1$5,000.00$3,500.00$500.00$3,500.00
120Construction staking slope stakes (650.9920)LF5,130$0.09$2.00$0.01$2.00
121Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF1,905$10.00$10.00$10.50$10.00
122Conduit rigid nonmetallic schedule 40 3-inch (652.0235)LF170$13.00$13.00$13.50$13.00
123Conduit rigid nonmetallic schedule 80 2-inch (652.0325)LF495$11.00$11.00$11.50$11.00
124Pull boxes non-conductive 24X42- inch (653.0164)EACH8$2,200.00$2,200.00$2,300.00$2,200.00
125Concrete bases type 5 (654.0105)EACH15$1,250.00$1,250.00$1,300.00$1,250.00
126Concrete control cabinet bases type L30 (654.0230)EACH1$2,000.00$2,000.00$2,100.00$2,000.00
127Electrical wire lighting 12 AWG (655.0610)LF2,442$1.25$1.25$1.30$1.25
128Electrical wire lighting 10 AWG (655.0615)LF10,635$1.50$1.50$1.60$1.50
129Electrical service meter breaker pedestal (location) 01. STH 11 & STH 81/CTH GG (656.0201)EACH1$2,000.00$2,000.00$2,100.00$2,000.00
130Transformer bases breakaway 11 1/2-inch bolt circle (657.0255)EACH15$600.00$600.00$630.00$600.00
131Poles type 5-aluminum (657.0322)EACH15$2,400.00$2,400.00$2,500.00$2,400.00
132Luminaire arms single member 4 1/2-inch clamp 8-FT (657.0615)EACH15$350.00$350.00$370.00$350.00
133Luminaires utility LED A (659.1115)EACH15$200.00$200.00$210.00$200.00
134Lighting control cabinets 120/240 30-inch (659.2130)EACH1$8,700.00$8,700.00$9,100.00$8,700.00
135Sawing asphalt (690.0150)LF1,195$1.89$1.89$3.30$1.95
136Sawing concrete (690.0250)LF270$2.78$2.78$2.50$2.95
137Incentive compressive strength concrete pavement (707.0020)DOL1,802$1.00$1.00$1.00$1.00
138On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,000$5.00$5.00$5.00$5.00
139On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS1,320$5.00$5.00$5.00$5.00
140Special 01. construction staking roundabout (SPV.0060)EACH1$7,700.00$22,000$1,500.00$22,000
141Special 02. remove and salvage overhead stop sign pole (SPV.0060)EACH2$700.00$700.00$2,600.00$700.00
142Special 03. remove and salvage flashing beacon (SPV.0060)EACH1$500.00$500.00$520.00$500.00
143Special 04. apron endwalls temporary 12-inch (SPV.0060)EACH1$528.24$500.00$850.00$200.00
144Special 05. apron endwalls temporary 24-inch (SPV.0060)EACH5$813.45$500.00$1,100.00$350.00
145Special 06. temporary pipe seal (SPV.0060)EACH2$1,159.79$1,500.00$360.00$20.00
146Special 07. temporary lighting (SPV.0060)EACH1$7,500.00$7,500.00$7,900.00$7,500.00
147Special 01. temporary marking wet reflective epoxy 6-inch (SPV.0090)LF7,890$0.70$1.55$1.60$1.55
WisDOT contract 20261110003: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of November 10, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way