WisDOT contract 20260811013 bid tabulation

Appleton - Black Creek; CTH S Intersection (STH 047, Outagamie County Appleton - Black Creek). Let by Wisconsin DOT on August 11, 2026, Outagamie. 4 bids received; low bid $2,504,777 by Relyco Plus, LLC.

Owner
Wisconsin DOT
Letting
11 AUG 2026
Pay items
132
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Relyco Plus, LLC$2,504,777Low
2Michels Road & Stone, Inc.$2,613,740+4.0%
3MCC, Inc.$2,714,985+8.0%
4Zignego Company, Inc.$3,034,117+21%
WisDOT contract 20260811013: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Relyco Plus, LLC2. Michels Road & Stone, Inc.3. MCC, Inc.4. Zignego Company, Inc.
1Clearing (201.0105)STA5$545.00$1,975.00$800.00$800.00
2Clearing (201.0120)ID8$50.00$85.00$40.00$40.00
3Grubbing (201.0205)STA5$545.00$550.00$400.00$400.00
4Grubbing (201.0220)ID8$50.00$85.00$30.00$30.00
5Removing small pipe culverts (203.0100)EACH7$584.60$650.00$135.00$1,000.00
6Removing concrete pavement (204.0100)SY920$2.00$8.00$10.00$9.65
7Removing curb & gutter (204.0150)LF440$5.00$8.00$5.55$5.50
8Removing fence (204.0170)LF75$5.00$5.00$3.00$3.00
9Removing concrete bases (204.0195)EACH2$200.00$200.00$200.00$225.00
10Removing (item description) 01. flashing stop sign assembly (204.9060.S)EACH2$550.00$550.00$550.00$550.00
11Excavation common (205.0100)CY17,916$13.49$11.30$12.00$12.35
12Select borrow (208.1100)CY5,952$27.00$23.70$22.55$21.85
13Finishing roadway (project) 01. 6240-32-71 (213.0100)EACH1$4,000.00$5,000.00$4,675.00$5,305.00
14Obliterating old road (214.0100)STA4$825.00$700.00$490.00$550.00
15Base aggregate dense 3/4-inch (305.0110)TON1,480$27.40$17.80$28.85$28.00
16Base aggregate dense 1 1/4-inch (305.0120)TON10,290$12.79$9.90$16.25$15.75
17Base aggregate open-graded (310.0110)TON3$89.99$25.00$25.00$200.00
18Select crushed material (312.0110)TON12,820$14.60$17.30$16.00$15.50
19Coloring concrete wisdot red (405.0100)CY889$80.00$80.00$80.00$100.00
20Concrete truck apron 12-inch (415.2010)SY2,220$90.00$90.00$90.00$122.00
21Tack coat (455.0605)GAL1,255$3.20$3.20$3.75$4.90
22Incentive density HMA pavement (460.2000)DOL4,190$1.00$1.00$1.00$1.00
23HMA pavement 3 HT 58-28 S (460.7223)TON5,215$75.10$75.10$89.25$74.45
24HMA pavement 4 HT 58-28 H (460.7424)TON1,265$99.95$99.95$96.20$92.25
25Asphaltic surface driveways and field entrances (465.0120)TON20$134.20$134.20$225.00$158.00
26Asphaltic flumes (465.0315)SY63$57.10$57.10$120.00$63.30
27Asphaltic rumble strips, shoulder (465.0520)LF2,931$0.55$0.55$1.25$1.33
28Apron endwalls for culvert pipe sloped cross drains steel 36-inch 4 to 1 (521.0336)EACH2$5,045.25$4,589.00$3,300.00$3,000.00
29Apron endwalls for culvert pipe sloped side drains steel 18-inch 6 to 1 (521.1518)EACH4$1,131.85$3,579.00$1,000.00$3,000.00
30Culvert pipe corrugated steel 18- inch (521.3118)LF100$84.08$87.00$80.00$200.00
31Culvert pipe reinforced concrete class IV 24-inch (522.0424)LF96$118.51$155.00$155.00$250.00
32Culvert pipe reinforced concrete class IV 36-inch (522.0436)LF72$210.59$259.00$259.00$250.00
33Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012)EACH5$1,272.93$1,270.00$1,270.00$2,000.00
34Apron endwalls for culvert pipe reinforced concrete 15-inch (522.1015)EACH1$1,336.23$1,374.00$1,374.00$2,000.00
35Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024)EACH2$2,080.37$1,654.00$1,654.00$2,000.00
36Culvert pipe reinforced concrete horizontal elliptical class HE-IV 29X45-inch (522.2429)LF104$274.44$353.00$353.00$250.00
37Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 19X30-inch (522.2619)EACH2$1,972.21$1,800.00$1,800.00$2,000.00
38Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 29X45-inch (522.2629)EACH2$3,455.19$2,900.00$2,900.00$4,000.00
39Concrete sidewalk 4-inch (602.0405)SF12,110$6.85$6.55$6.55$8.00
40Riprap medium (606.0200)CY47$100.00$200.00$80.00$87.50
41Storm sewer pipe reinforced concrete class III 15-inch (608.0315)LF39$80.97$94.00$94.00$300.00
42Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF233$80.36$89.00$89.00$180.00
43Storm sewer pipe reinforced concrete horizontal elliptical class HE-IV 19X30-inch (608.2419)LF97$181.03$195.00$195.00$200.00
44Inlet covers type HM (611.0627)EACH4$727.84$810.00$810.00$2,000.00
45Inlet covers type HM-S (611.0636)EACH6$727.84$810.00$810.00$2,000.00
46Inlet covers type H-S (611.0639)EACH2$730.48$810.00$810.00$2,000.00
47Inlet covers type T (611.0652)EACH2$999.50$1,101.00$1,101.00$2,000.00
48Manholes 5-FT diameter (611.2005)EACH3$5,845.83$5,600.00$5,600.00$7,900.00
49Inlets 2X3-FT (611.3230)EACH9$2,831.54$3,062.00$3,062.00$4,995.00
50Pipe underdrain 6-inch (612.0106)LF48$25.96$40.00$40.00$20.00
51Maintenance and repair of haul roads (project) 01. 6240-32-71 (618.0100)EACH1$0.01$1.00$95.00$1.00
52Mobilization (619.1000)EACH1$85,500$189,506$190,000$242,000
53Concrete median sloped nose (620.0300)SF400$15.00$15.00$15.00$20.00
54Water (624.0100)MGAL71$40.00$55.00$36.00$200.00
55Salvaged topsoil (625.0500)SY20,660$1.89$2.80$1.60$1.95
56Mulching (627.0200)SY6,510$0.30$0.30$0.38$0.38
57Silt fence (628.1504)LF815$2.00$2.00$2.05$2.05
58Silt fence maintenance (628.1520)LF815$0.01$0.01$0.01$0.01
59Mobilizations erosion control (628.1905)EACH4$1.00$1.00$275.00$275.00
60Mobilizations emergency erosion control (628.1910)EACH4$1.00$1.00$275.00$275.00
61Erosion mat class I type B (628.2004)SY7,510$0.98$0.98$1.05$1.05
62Erosion mat urban class I type A (628.2006)SY2,940$1.75$1.75$1.80$1.80
63Erosion mat class II type C (628.2027)SY3,100$3.75$3.75$3.75$3.75
64Inlet protection type C (628.7015)EACH14$70.00$70.00$65.00$65.00
65Temporary ditch checks (628.7504)LF430$9.00$9.00$5.95$5.95
66Culvert pipe checks (628.7555)EACH8$30.00$30.00$20.00$20.00
67Tracking pads (628.7560)EACH4$0.01$1,200.00$900.00$1,000.00
68Rock bags (628.7570)EACH25$30.00$30.00$12.00$12.00
69Fertilizer type B (629.0210)CWT13$75.00$75.00$85.00$85.00
70Seeding mixture no. 20 (630.0120)LB148$7.50$7.50$8.95$8.95
71Seeding mixture no. 30 (630.0130)LB735$7.50$7.50$8.50$8.50
72Seed water (630.0500)MGAL464$1.00$1.00$9.00$9.00
73Markers culvert end (633.5200)EACH18$65.00$65.00$70.00$70.00
74Posts wood 4X6-inch X 14-FT (634.0614)EACH29$75.00$75.00$100.00$100.00
75Posts wood 4X6-inch X 16-FT (634.0616)EACH7$80.00$80.00$105.00$105.00
76Posts wood 4X6-inch X 18-FT (634.0618)EACH14$95.00$95.00$135.00$135.00
77Posts tubular steel 2X2-inch X 12- FT (634.0812)EACH4$150.00$150.00$225.00$225.00
78Signs type II reflective H (637.2210)SF401.58$23.00$23.00$22.00$22.00
79Signs type II reflective F (637.2230)SF100.49$24.50$24.50$24.00$24.00
80Removing signs type II (638.2602)EACH15$25.00$25.00$30.00$30.00
81Removing small sign supports (638.3000)EACH16$25.00$25.00$30.00$30.00
82Field office type B (642.5001)EACH1$11,000$6,000.00$16,300$20,000
83Traffic control barricades type III (643.0420)DAY1,980$0.45$0.45$0.65$0.65
84Traffic control warning lights type A (643.0705)DAY2,760$0.01$0.20$0.15$0.15
85Traffic control signs (643.0900)DAY19,020$0.30$0.40$0.40$0.40
86Traffic control covering signs type II (643.0920)EACH20$27.00$85.00$75.00$75.00
87Traffic control signs fixed message (643.1000)SF52$14.00$18.00$24.00$24.00
88Traffic control signs PCMS (643.1050)DAY140$60.00$68.00$50.00$50.00
89Traffic control (643.5000)EACH1$15,500$2,500.00$3,500.00$3,500.00
90Geotextile type DF schedule A (645.0111)SY26$7.21$7.00$7.00$10.00
91Geotextile type HR (645.0120)SY96$5.00$5.00$7.00$10.00
92Marking line epoxy 6-inch (646.2020)LF3,225$1.00$0.88$0.56$1.00
93Marking line grooved wet ref epoxy 6-inch (646.2040)LF10,300$1.55$1.41$1.52$1.55
94Marking line grooved wet ref epoxy 10-inch (646.4040)LF348$3.00$4.00$3.15$3.00
95Marking dotted extension epoxy 18-inch (646.6320)LF152$20.00$15.00$20.00$20.00
96Marking diagonal epoxy 12-inch (646.7120)LF431$9.75$12.00$19.15$9.75
97Marking curb epoxy (646.8120)LF232$8.00$10.00$9.45$8.00
98Marking island nose epoxy (646.8220)EACH4$305.00$250.00$352.00$305.00
99Marking removal line 4-inch (646.9000)LF125$5.00$4.00$2.00$5.00
100Construction staking storm sewer (650.4000)EACH14$125.00$125.00$125.00$125.00
101Construction staking subgrade (650.4500)LF4,231$0.01$0.01$0.01$0.01
102Construction staking base (650.5000)LF4,231$0.75$0.75$0.75$0.75
103Construction staking curb gutter and curb & gutter (650.5500)LF4,779$0.90$0.90$0.90$0.90
104Construction staking pipe culverts (650.6000)EACH4$200.00$200.00$200.00$200.00
105Construction staking electrical installations (project) 01. 6240-32- 71 (650.8501)EACH1$2,500.00$2,500.00$2,500.00$2,500.00
106Construction staking sidewalk (project) 01. 6240-32-71 (650.9500)EACH1$100.00$100.00$100.00$100.00
107Construction staking supplemental control (project) 01. 6240-32-71 (650.9911)EACH1$10.00$10.00$10.00$10.00
108Construction staking slope stakes (650.9920)LF4,231$1.25$1.25$1.25$1.25
109Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF2,085$10.00$10.00$10.00$10.00
110Pull boxes non-conductive 24X42- inch (653.0164)EACH8$1,950.00$1,950.00$1,950.00$1,950.00
111Removing pull boxes (653.0905)EACH2$75.00$75.00$75.00$75.00
112Concrete bases type 5 (654.0105)EACH18$1,750.00$1,750.00$1,750.00$1,750.00
113Concrete control cabinet bases type 10 (654.0220)EACH1$2,200.00$2,200.00$2,200.00$2,200.00
114Electrical wire lighting 12 AWG (655.0610)LF2,700$1.10$1.10$1.10$1.10
115Electrical wire lighting 10 AWG (655.0615)LF8,519$1.25$1.25$1.25$1.25
116Electrical service meter breaker pedestal (location) 01. STH 47 roundabout (656.0201)EACH1$1,950.00$1,950.00$1,950.00$1,950.00
117Transformer bases breakaway 11 1/2-inch bolt circle (657.0255)EACH18$645.00$645.00$645.00$645.00
118Poles type 5-aluminum (657.0322)EACH18$1,995.00$1,995.00$1,995.00$1,995.00
119Luminaire arms truss type 4 1/2- inch clamp 12-FT (657.0710)EACH18$800.00$800.00$800.00$800.00
120Luminaires utility LED B (659.1120)EACH18$400.00$400.00$400.00$400.00
121Sawing asphalt (690.0150)LF136$2.50$2.50$6.15$2.25
122Sawing concrete (690.0250)LF3$7.00$7.00$25.00$3.25
123Incentive compressive strength concrete pavement (715.0720)DOL670$1.00$1.00$1.00$1.00
124On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,000$5.00$5.00$5.00$5.00
125On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS1,320$5.00$5.00$5.00$5.00
126Special 01. foundation backfill (SPV.0035)CY1,720$30.60$40.00$32.89$40.00
127Special 01. inlet 2 X 2.5-FT special (SPV.0060)EACH2$2,570.96$3,100.00$3,100.00$5,000.00
128Special 01. low maintenance seed mix (SPV.0085)LB12$15.00$15.00$125.00$125.00
129Special 01. concrete curb & gutter 18-inch type A modified (SPV.0090)LF170$24.00$24.00$24.00$60.00
130Special 02. concrete curb & gutter 30-inch type D modified (SPV.0090)LF972$24.00$24.00$24.00$60.00
131Special 03. concrete curb & gutter 4-inch sloped 36-inch type D modified (SPV.0090)LF3,252$24.00$24.00$24.00$43.18
132Special 04. concrete curb & gutter 4-inch sloped 30-inch type R modified (SPV.0090)LF385$24.00$24.00$24.00$60.00
WisDOT contract 20260811013: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of August 11, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy