WisDOT contract 20261013010 bid tabulation

1130-66-71. Let by Wisconsin DOT on October 13, 2026, Outagamie. 5 bids received; low bid $129,719,050 by Zignego Company, Inc..

Owner
Wisconsin DOT
Letting
13 OCT 2026
Pay items
519
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Zignego Company, Inc.$129,719,050Low
2James Peterson Sons, Inc.$131,774,432+2.0%
3Michels Road & Stone, Inc.$135,633,439+5.0%
4Hoffman Construction Company$137,429,253+6.0%
5Vinton Construction Company$156,105,904+20%
WisDOT contract 20261013010: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Zignego Company, Inc.2. James Peterson Sons, Inc.3. Michels Road & Stone, Inc.4. Hoffman Construction Company5. Vinton Construction Company
1Clearing (201.0105)STA158$400.00$690.00$690.00$689.96$690.00
2Grubbing (201.0205)STA158$300.00$255.00$255.00$254.99$255.00
3Removing small pipe culverts (203.0100)EACH34$1,333.00$1,333.00$738.00$1,607.13$1,607.21
4Removing structure (structure) 0001. B-44-40 (203.0220)EACH1$115,000$115,000$115,000$114,994$115,000
5Removing structure (structure) 0002. C-44-20 (203.0220)EACH1$58,165$58,165$28,000$13,869$13,870
6Removing structure (structure) 0003. B-44-41 (203.0220)EACH1$145,000$145,000$145,000$144,993$145,000
7Removing structure (structure) 0004. C-44-25 (203.0220)EACH1$39,500$39,500$28,000$15,739$15,740
8Removing structure (structure) 0005. B-44-43 (203.0220)EACH1$145,000$145,000$145,000$144,993$145,000
9Removing structure (structure) 0006. B-44-42 (203.0220)EACH1$115,000$115,000$115,000$114,994$115,000
10Removing structure (structure) 0007. R-44-24 (203.0220)EACH1$5,000.00$5,000.00$11,000$9,999.50$10,000
11Removing structure (structure) 0008. R-44-25 (203.0220)EACH1$5,000.00$5,000.00$11,000$9,999.50$10,000
12Removing structure (structure) 0009. C-44-26 (203.0220)EACH1$42,500$42,500$28,000$20,384$20,385
13Removing structure (structure) 0041. B-44-41 (203.0220)EACH1$100,000$100,000$100,000$99,995$100,000
14Removing structure (structure) 0043. B-44-43 (203.0220)EACH1$100,000$100,000$100,000$99,995$100,000
15Removing concrete pavement (204.0100)SY166,710$4.20$4.20$1.00$10.00$4.50
16Removing asphaltic surface milling (204.0120)SY24,611$3.80$3.80$3.80$3.80$3.80
17Removing curb & gutter (204.0150)LF1,225$3.02$3.02$10.00$10.00$6.00
18Removing concrete sidewalk (204.0155)SY2,100$4.15$4.15$15.00$20.00$9.00
19Removing guardrail (204.0165)LF16,330$2.00$2.00$2.00$2.00$2.00
20Removing cable barrier (204.0167)LF12,291$2.00$2.00$2.00$2.00$2.00
21Removing fence (204.0170)LF55,970$1.50$1.50$1.50$1.50$1.50
22Removing delineators and markers (204.0180)EACH137$35.00$35.00$35.00$35.00$35.00
23Removing surface drains (204.0190)EACH1$500.00$500.00$300.00$499.97$500.00
24Removing concrete bases (204.0195)EACH10$350.00$200.00$200.00$199.99$200.00
25Removing inlets (204.0220)EACH26$400.00$400.00$475.00$585.24$585.27
26Removing storm sewer (size) 0001. 18-inch or less (204.0245)LF1,843$17.23$17.23$8.00$17.66$17.66
27Removing storm sewer (size) 0002. 24-inch (204.0245)LF105$47.71$47.71$10.00$21.83$21.83
28Removing storm sewer (size) 0003. 30-inch (204.0245)LF300$13.34$13.34$15.00$22.82$22.82
29Removing storm sewer (size) 0004. 36-inch (204.0245)LF330$36.73$36.73$19.00$25.56$25.56
30Removing storm sewer (size) 0005. 42-inch (204.0245)LF160$14.47$14.47$22.00$27.96$27.96
31Removing ancillary structure (structure) 0001. S-44-144 (204.0246)EACH1$12,500$12,500$12,500$12,499$12,500
32Removing ancillary structure (structure) 0002. S-44-201 (204.0246)EACH1$12,500$12,500$12,500$12,499$12,500
33Removing ancillary structure (structure) 0003. S-44-202 (204.0246)EACH1$12,500$12,500$12,500$12,499$12,500
34Abandoning culvert pipes (204.0270)EACH1$5,000.00$5,000.00$1,426.00$6,067.70$6,068.00
35Sealing pipes (204.0280)EACH16$500.00$500.00$751.00$308.62$308.64
36Abandoning sewer (204.0291.S)CY44.10$400.00$400.00$352.00$145.50$145.51
37Removing (item description) 0002. business sign and base (204.9060.S)EACH1$4,000.00$4,000.00$4,000.00$3,999.80$4,000.00
38Removing (item description) 0003. inlet covers (204.9060.S)EACH1$400.00$400.00$250.00$584.97$226.72
39Removing (item description) 0501. street light assembly (204.9060.S)EACH9$1,000.00$1,000.00$1,000.00$999.95$1,000.00
40Removing (item description) 0502. lighting control (204.9060.S)EACH1$2,750.00$2,750.00$2,750.00$2,749.87$2,750.00
41Removing (item description) 0503. luminaires (204.9060.S)EACH10$200.00$200.00$200.00$199.99$200.00
42Removing (item description) 0504. temporary wood poles (204.9060.S)EACH4$350.00$350.00$350.00$349.98$350.00
43Removing (item description) 0701. communication vault (204.9060.S)EACH27$250.00$250.00$250.00$249.99$250.00
44Removing (item description) 0001. drain slotted vane (204.9090.S)LF2,361$10.00$10.00$22.00$17.00$17.00
45Removing (item description) 0501. electrical conductors from existing conduit (204.9090.S)LF2,053$2.00$2.00$2.00$2.00$2.00
46Removing (item description) 0502. or abandoning existing conduit (204.9090.S)LF540$2.00$2.00$2.00$2.00$2.00
47Excavation common (205.0100)CY609,182$13.44$13.44$15.40$25.00$19.98
48Excavation, hauling, and disposal of petroleum contaminated soil (205.0501.S)TON150$95.50$95.50$88.00$99.99$90.00
49Temporary emergency pullouts (205.3000.S)EACH1$5,000.00$35,250$11,250$4,999.75$50,000
50Excavation for structures bridges (structure) 0001. B-44-334 (206.1001)EACH1$27,540$35,300$64,000$7,499,627$20,000
51Excavation for structures bridges (structure) 0002. B-44-335 (206.1001)EACH1$23,000$32,292$70,000$74,996$20,000
52Excavation for structures bridges (structure) 0003. B-44-336 (206.1001)EACH1$28,700$55,970$67,000$7,499,627$35,000
53Excavation for structures bridges (structure) 0004. B-44-337 (206.1001)EACH1$43,455$60,800$73,000$74,996$35,000
54Excavation for structures culverts (structure) 0001. C-44-148 (206.2001)EACH1$92,004$92,004$80,000$59,221$59,224
55Excavation for structures culverts (structure) 0002. C-44-149 (206.2001)EACH1$88,024$88,024$80,000$69,286$69,289
56Excavation for structures culverts (structure) 0007. C-44-150 (206.2001)EACH1$53,671$53,671$82,000$78,766$78,770
57Backfill coarse aggregate (size) 0001. no. 1 (209.0300.S)CY700$63.65$63.65$47.00$73.01$73.01
58Backfill structure type A (210.1500)TON2,420$50.23$50.23$40.00$65.00$32.00
59Backfill structure type B (210.2500)TON6,937$39.49$39.49$25.00$25.00$25.00
60Prepare foundation for concrete pavement (project) 0001. 1130-66- 77 (211.0201)EACH1$1.00$0.01$30,000$0.01$5,000.00
61Prepare foundation for asphaltic shoulders (211.0400)STA24$50.00$250.00$350.00$249.99$700,000
62Finishing roadway (project) 0001. 1130-66-71 (213.0100)EACH1$1,000.00$1,500.00$5,000.00$0.01$10,000
63Finishing roadway (project) 0002. 1130-66-72 (213.0100)EACH1$1,000.00$1,500.00$5,000.00$0.01$10,000
64Finishing roadway (project) 0003. 1130-66-77 (213.0100)EACH1$1,000.00$1,500.00$2,500.00$0.01$10,000
65Finishing roadway (project) 0004. 1130-66-84 (213.0100)EACH1$1,000.00$1,500.00$1,000.00$0.01$10,000
66Base aggregate dense 3/4-inch (305.0110)TON11,854$30.36$30.36$27.20$50.00$35.90
67Base aggregate dense 1 1/4-inch (305.0120)TON274,693$16.15$15.66$14.65$0.01$14.59
68Base aggregate open-graded (310.0110)TON6$76.25$76.75$100.00$104.98$104.99
69Breaker run (311.0110)TON2,236$21.00$20.49$18.00$0.01$22.05
70Select crushed material (312.0110)TON1,012,653$21.00$20.49$14.65$0.04$19.90
71Concrete base 4-inch (320.0105)SY13,802$60.00$56.05$65.92$56.05$64.11
72Coloring concrete wisdot red (405.0100)CY378$200.00$100.11$175.00$100.10$90.00
73Concrete pavement 9-inch (415.0090)SY9,015$74.30$71.89$81.74$71.89$65.37
74Concrete pavement 9 1/2-inch (415.0095)SY2,800$75.00$103.21$132.07$103.21$96.49
75Concrete pavement approach slab (415.0410)SY1,152$236.00$218.78$249.78$218.77$247.00
76Concrete truck apron 12-inch (415.2010)SY805$140.00$142.98$109.00$142.97$116.28
77Concrete pavement joint filling (415.4100)SY4,783$3.00$2.50$2.50$2.50$2.50
78Drilled tie bars (416.0610)EACH10,309$12.00$10.39$12.29$10.39$11.00
79Drilled dowel bars (416.0620)EACH302$30.00$16.13$16.67$16.13$20.00
80HMA cold weather paving (450.4000)TON6,064$4.10$4.10$4.10$4.10$4.10
81Tack coat (455.0605)GAL11,108$4.40$4.40$4.40$4.40$4.40
82Incentive density HMA pavement (460.2000)DOL11,190$1.00$1.00$1.00$1.00$1.00
83HMA pavement 3 LT 58-28 S (460.5223)TON4,849$98.50$98.50$98.50$98.50$98.50
84HMA pavement 4 LT 58-28 S (460.5224)TON4,814$109.20$109.20$109.20$109.20$109.20
85HMA pavement 3 MT 58-28 S (460.6223)TON4,194$100.20$100.20$100.20$100.20$100.20
86HMA pavement 4 MT 58-28 S (460.6224)TON3,386$112.70$112.70$112.70$112.70$112.70
87Asphaltic surface temporary (465.0125)TON40,773$129.40$129.40$129.40$129.40$129.40
88Asphaltic flumes (465.0315)SY7$125.00$125.00$125.00$124.99$125.00
89Asphaltic rumble strips, shoulder divided roadway (465.0510)LF4,090$0.66$1.05$1.05$1.05$1.05
90Cold patch (495.1000.S)TON40$1.00$935.00$500.00$499.97$500.00
91Ice hot weather concreting (501.1000.S)LB18,949$0.01$0.01$0.01$0.01$0.01
92Concrete masonry bridges (502.0100)CY1,502.80$725.00$725.00$725.00$724.96$725.00
93Protective surface treatment (502.3200)SY5,895$2.50$2.50$2.50$2.50$2.50
94Pigmented surface sealer (502.3210)SY859$2.50$2.50$2.50$2.50$2.50
95Prestressed girder type I 36W-inch (503.0137)LF4,291$325.00$325.00$325.00$324.98$325.00
96Concrete masonry culverts (504.0100)CY851$1,130.12$1,130.12$1,046.49$947.95$948.00
97Bar steel reinforcement HS structures (505.0400)LB189,870$1.50$1.18$1.50$1.44$1.50
98Bar steel reinforcement HS coated structures (505.0600)LB643,740$1.55$1.55$1.55$1.55$1.55
99Bar steel reinforcement HS stainless structures (505.0800.S)LB9,500$5.00$5.00$5.00$5.00$5.00
100Bearing pads elastomeric non- laminated (506.2605)EACH140$100.00$100.00$100.00$99.99$100.00
101Steel diaphragms (structure) 0001. B-44-334 (506.4000)EACH24$950.00$950.00$950.00$949.95$950.00
102Steel diaphragms (structure) 0002. B-44-335 (506.4000)EACH24$950.00$950.00$950.00$949.95$950.00
103Steel diaphragms (structure) 0003. B-44-336 (506.4000)EACH18$950.00$950.00$950.00$949.95$950.00
104Steel diaphragms (structure) 0004. B-44-337 (506.4000)EACH18$950.00$950.00$950.00$949.95$950.00
105Polymer overlay (509.5100.S)SY12,143$43.08$39.00$43.08$43.08$43.08
106Temporary shoring (511.1100)SF34,776$0.01$0.01$0.01$0.01$0.01
107Temporary shoring (structure) 0001. B-44-336 (511.1200)SF1,260$0.01$0.01$0.01$0.01$0.01
108Temporary shoring (structure) 0002. B-44-337 (511.1200)SF1,260$0.01$0.01$0.01$0.01$0.01
109Temporary shoring (structure) 0003. C-44-148 (511.1200)SF1,080$0.01$0.01$75.00$56.00$56.00
110Temporary shoring (structure) 0004. C-44-149 (511.1200)SF1,200$0.01$0.01$75.00$56.00$56.00
111Temporary shoring (structure) 0005. B-44-334 (511.1200)SF1,260$0.01$0.01$0.01$0.01$0.01
112Temporary shoring (structure) 0006. B-44-335 (511.1200)SF1,260$0.01$0.01$0.01$0.01$0.01
113Temporary shoring (structure) 0007. C-44-150 (511.1200)SF750$0.01$0.01$75.00$134.99$135.00
114Rubberized membrane waterproofing (516.0500)SY240$20.00$30.42$20.00$33.33$20.00
115Concrete staining (structure) 0001. B-44-334 (517.1010.S)SF4,117$1.98$2.09$1.98$1.98$1.98
116Concrete staining (structure) 0002. B-44-335 (517.1010.S)SF4,117$1.98$2.09$1.98$1.98$1.98
117Concrete staining (structure) 0003. B-44-336 (517.1010.S)SF6,035$1.98$2.09$1.98$1.98$1.98
118Concrete staining (structure) 0004. B-44-337 (517.1010.S)SF5,990$1.98$2.09$1.98$1.98$1.98
119Apron endwalls for culvert pipe 12- inch (520.1012)EACH26$234.70$234.70$529.00$478.27$478.29
120Apron endwalls for culvert pipe 15- inch (520.1015)EACH4$265.67$265.67$567.00$511.72$511.75
121Apron endwalls for culvert pipe 30- inch (520.1030)EACH1$850.00$850.00$918.00$1,022.56$1,022.61
122Culvert pipe temporary 12-inch (520.2012)LF2,617$42.22$42.22$69.00$69.75$69.75
123Culvert pipe temporary 15-inch (520.2015)LF292$81.25$81.25$72.00$73.08$73.08
124Culvert pipe temporary 18-inch (520.2018)LF751$71.72$71.72$79.00$82.30$82.30
125Culvert pipe temporary 24-inch (520.2024)LF51$125.65$125.65$114.00$106.21$106.22
126Culvert pipe temporary 30-inch (520.2030)LF190$122.50$122.50$129.00$119.80$119.81
127Culvert pipe temporary 36-inch (520.2036)LF40$91.35$91.35$152.00$154.95$154.96
128Culvert pipe temporary 42-inch (520.2042)LF26$161.02$161.02$222.00$193.19$193.20
129Concrete collars for pipe (520.8000)EACH27$839.13$839.13$796.00$1,271.78$1,271.85
130Culvert pipe reinforced concrete class III 18-inch (522.0118)LF80$143.05$143.05$144.00$88.11$88.11
131Culvert pipe reinforced concrete class III 24-inch (522.0124)LF192$128.12$128.17$129.00$110.18$110.19
132Culvert pipe reinforced concrete class III 30-inch (522.0130)LF386$158.01$158.01$145.00$142.62$142.63
133Culvert pipe reinforced concrete class III 54-inch (522.0154)LF432$351.82$351.82$368.00$315.57$315.59
134Culvert pipe reinforced concrete class IV 18-inch (522.0418)LF104$98.86$98.86$94.00$88.11$88.11
135Culvert pipe reinforced concrete class IV 30-inch (522.0430)LF300$157.45$157.45$152.00$148.73$148.74
136Culvert pipe reinforced concrete class IV 36-inch (522.0436)LF250$413.02$413.02$222.00$177.20$177.21
137Apron endwalls for culvert pipe reinforced concrete 15-inch (522.1015)EACH75$1,219.76$1,219.76$1,145.00$1,177.32$1,177.38
138Apron endwalls for culvert pipe reinforced concrete 18-inch (522.1018)EACH23$1,340.91$1,340.91$1,263.00$1,376.71$1,376.78
139Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024)EACH15$1,528.61$1,528.61$1,443.00$1,706.08$1,706.17
140Apron endwalls for culvert pipe reinforced concrete 27-inch (522.1027)EACH1$1,636.57$1,636.57$1,584.00$2,045.28$2,045.39
141Apron endwalls for culvert pipe reinforced concrete 30-inch (522.1030)EACH13$1,721.82$1,721.82$1,693.00$2,121.82$2,121.93
142Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036)EACH9$2,279.62$2,279.62$2,257.00$2,682.06$2,682.19
143Apron endwalls for culvert pipe reinforced concrete 54-inch (522.1054)EACH4$4,122.26$4,122.26$3,417.00$3,913.81$3,914.00
144Culvert pipe reinforced concrete horizontal elliptical class HE-III 24X38-inch (522.2324)LF492$189.96$189.96$180.00$179.23$179.24
145Culvert pipe reinforced concrete horizontal elliptical class HE-III 29X45-inch (522.2329)LF542$256.16$256.16$259.00$225.62$225.63
146Culvert pipe reinforced concrete horizontal elliptical class HE-IV 14X23-inch (522.2414)LF293$157.25$157.25$170.00$151.55$151.56
147Culvert pipe reinforced concrete horizontal elliptical class HE-IV 24X38-inch (522.2424)LF336$232.18$232.18$195.00$194.06$194.07
148Culvert pipe reinforced concrete horizontal elliptical class HE-IV 29X45-inch (522.2429)LF180$282.48$282.48$237.00$258.47$258.48
149Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 19X30-inch (522.2619)EACH8$1,756.12$1,756.12$1,561.00$1,767.16$1,767.25
150Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 24X38-inch (522.2624)EACH8$2,097.29$2,097.29$1,966.00$2,311.46$2,311.58
151Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 29X45-inch (522.2629)EACH6$2,526.84$2,526.84$2,362.00$2,731.12$2,731.25
152Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 38X60-inch (522.2638)EACH2$4,096.98$4,096.98$3,231.00$3,903.42$3,903.61
153Apron endwalls for culvert pipe salvaged 12-inch (524.0612)EACH1$613.94$613.94$705.00$1,776.91$1,777.00
154Apron endwalls for culvert pipe salvaged 15-inch (524.0615)EACH4$614.12$614.12$754.00$1,538.92$1,539.00
155Apron endwalls for culvert pipe salvaged 18-inch (524.0618)EACH12$694.70$694.70$802.00$1,420.18$1,420.25
156Apron endwalls for culvert pipe salvaged 24-inch (524.0624)EACH2$845.53$845.53$850.00$2,026.89$2,027.00
157Apron endwalls for culvert pipe salvaged 30-inch (524.0630)EACH4$1,077.38$1,077.38$899.00$2,531.13$2,531.25
158Apron endwalls for culvert pipe salvaged 36-inch (524.0636)EACH1$1,669.94$1,669.94$947.00$2,644.48$2,644.61
159Apron endwalls for culvert pipe salvaged 42-inch (524.0642)EACH1$1,989.00$1,989.00$995.00$2,985.36$2,985.50
160Concrete masonry ancillary structures type NS (531.1100)CY26.40$800.00$800.00$800.00$799.96$800.00
161Steel reinforcement HS ancillary structures type NS (531.1140)LB3,960$4.00$4.00$4.00$4.00$4.00
162Drilling shaft 24-inch (531.2024)LF220$90.00$90.00$90.00$90.00$90.00
163Drilling shaft 30-inch (531.2030)LF120$250.00$250.00$250.00$249.99$250.00
164Drilling shaft 36-inch (531.2036)LF466$250.00$255.90$250.00$249.99$250.00
165Foundation camera pole 50-FT (531.4050)EACH2$2,500.00$2,500.00$2,500.00$2,499.88$2,500.00
166Foundation two-shaft butterfly type B-I (structure) 0001. S-44-336 (531.5030)EACH1$17,660$17,660$17,660$17,659$17,660
167Foundation two-shaft butterfly type B-I (structure) 0002. S-44-381 (531.5030)EACH1$17,660$17,660$17,660$17,659$17,660
168Foundation two-shaft butterfly type B-I (structure) 0003. S-44-386 (531.5030)EACH1$17,660$17,660$17,660$17,659$17,660
169Foundation two-shaft butterfly type B-I (structure) 0004. S-44-393 (531.5030)EACH1$17,660$17,660$17,660$17,659$17,660
170Foundation single-shaft type TF-II (structure) 0001. S-44-389 (531.5420)EACH2$9,500.00$9,500.00$9,500.00$9,499.53$9,500.00
171Foundation single-shaft type TF-II (structure) 0002. S-44-388 (531.5420)EACH2$9,500.00$9,500.00$9,500.00$9,499.53$9,500.00
172Foundation single-shaft type TF-II (structure) 0003. S-44-390 (531.5420)EACH2$9,500.00$9,500.00$9,500.00$9,499.53$9,500.00
173Foundation two-shaft type FC-I (structure) 0001. S-44-335 (531.6010)EACH1$23,600$23,600$23,600$23,599$23,600
174Foundation two-shaft type FC-I (structure) 0002. S-44-382 (531.6010)EACH1$23,600$23,600$23,600$23,599$23,600
175Foundation two-shaft type FC-I (structure) 0003. S-44-385 (531.6010)EACH1$23,600$23,600$23,600$23,599$23,600
176Foundation two-shaft type FC-I (structure) 0004. S-44-387 (531.6010)EACH1$23,600$23,600$23,600$23,599$23,600
177Foundation two-shaft type FC-II (structure) 0003. S-44-391 (531.6020)EACH1$23,600$23,600$23,600$23,599$23,600
178Foundation two-shaft type FC-II (structure) 0004. S-44-392 (531.6020)EACH1$23,600$23,600$23,600$23,599$23,600
179Foundation two-shaft type FC-II (structure) 0005. S-44-394 (531.6020)EACH1$23,600$23,600$23,600$23,599$23,600
180Foundation two-shaft type FC-II (structure) 0006. S-44-395 (531.6020)EACH1$23,600$23,600$23,600$23,599$23,600
181Foundation two-shaft type FF-II (structure) 0001. S-44-404 (531.6120)EACH2$37,600$37,600$37,600$37,598$37,600
182Butterfly 2-chord NS (structure) 0001. S-44-336 (532.5020)EACH1$45,244$45,244$45,244$45,242$45,244
183Butterfly 2-chord NS (structure) 0002. S-44-381 (532.5020)EACH1$46,311$46,311$46,311$46,309$46,311
184Butterfly 2-chord NS (structure) 0003. S-44-386 (532.5020)EACH1$45,948$45,948$45,948$45,946$45,948
185Butterfly 2-chord NS (structure) 0004. S-44-393 (532.5020)EACH1$45,651$45,651$45,651$45,649$45,651
186Truss full span 2-chord type II (structure) 0001. S-44-388 (532.5420)EACH1$65,550$65,550$65,550$65,547$65,550
187Truss full span 2-chord type II (structure) 0002. S-44-389 (532.5420)EACH1$65,550$65,550$65,550$65,547$65,550
188Truss full span 2-chord type II (structure) 0003. S-44-390 (532.5420)EACH1$54,000$54,000$54,000$53,997$54,000
189Truss cantilever 4-chord type I (structure) 0001. S-44-335 (532.6010)EACH1$56,751$56,751$56,751$56,748$56,751
190Truss cantilever 4-chord type I (structure) 0002. S-44-382 (532.6010)EACH1$58,181$58,181$58,181$58,178$58,181
191Truss cantilever 4-chord type I (structure) 0003. S-44-385 (532.6010)EACH1$56,762$56,762$56,762$56,759$56,762
192Truss cantilever 4-chord type I (structure) 0004. S-44-387 (532.6010)EACH1$57,026$57,026$57,026$57,023$57,026
193Truss cantilever 4-chord type II (structure) 0003. S-44-391 (532.6020)EACH1$61,756$61,756$61,756$61,753$61,756
194Truss cantilever 4-chord type II (structure) 0004. S-44-392 (532.6020)EACH1$61,162$61,162$61,162$61,159$61,162
195Truss cantilever 4-chord type II (structure) 0005. S-44-394 (532.6020)EACH1$61,184$61,184$61,184$61,181$61,184
196Truss cantilever 4-chord type II (structure) 0006. S-44-395 (532.6020)EACH1$62,251$62,251$62,251$62,248$62,251
197Truss full span 4-chord type II (structure) 0001. S-44-404 (532.6120)EACH1$128,592$128,592$128,592$128,586$128,592
198Noise barriers double-sided sound absorptive (structure) 0001. N-44- 18 (541.0300.S)SF73,639$88.00$88.00$88.70$88.50$88.00
199Piling steel HP 12-inch X 53 LB (550.1120)LF19,030$60.00$60.00$60.00$60.00$60.00
200Concrete curb & gutter 30-inch type A (601.0409)LF2,869$60.00$34.47$67.00$34.47$44.45
201Concrete curb & gutter 30-inch type D (601.0411)LF1,045$60.00$35.86$69.00$35.86$26.75
202Concrete curb & gutter 4-inch sloped 36-inch type A (601.0551)LF708$65.00$53.27$73.00$53.27$48.25
203Concrete curb & gutter 4-inch sloped 36-inch type TBT (601.0588)LF92$70.00$135.38$93.00$135.37$85.00
204Concrete curb & gutter 4-inch sloped 36-inch type TBTT (601.0590)LF63$70.00$127.24$93.00$127.23$85.00
205Concrete curb pedestrian (601.0600)LF130$70.00$115.99$93.00$115.98$55.00
206Concrete sidewalk 4-inch (602.0405)SF25,800$8.90$7.05$7.95$7.05$8.00
207Curb ramp detectable warning field yellow (602.0505)SF40$200.00$58.84$75.00$58.84$36.00
208Curb ramp detectable warning field natural patina (602.0515)SF120$300.00$56.10$75.00$56.10$35.00
209Concrete surface drains (602.3010)CY5$1,000.00$1,334.24$2,500.00$1,334.17$1,500.00
210Concrete rumble strips, shoulder divided roadway (602.3210)LF109,193$1.02$1.05$1.05$1.05$1.05
211Concrete barrier type S42A (603.1242)LF512$300.00$294.94$239.68$294.92$510.00
212Concrete barrier temporary precast delivered (603.8000)LF174,935$8.43$10.73$10.73$10.73$10.73
213Concrete barrier temporary precast installed (603.8125)LF302,985$4.00$4.38$4.38$4.38$4.38
214Anchoring concrete barrier temporary precast (603.8500)LF19,080$7.00$8.67$8.67$8.67$8.67
215Anchoring concrete barrier temporary precast on bridge decks (603.8505)LF238$20.00$19.84$19.84$19.84$19.84
216Slope paving concrete (604.0400)SY2,273$50.00$50.00$50.00$50.00$50.00
217Slope paving select crushed material (604.0600)SY335$40.00$40.00$40.00$40.00$40.00
218Riprap light (606.0100)CY3,312$125.00$125.00$89.00$134.99$102.00
219Riprap medium (606.0200)CY1,129$190.00$190.00$90.00$169.99$142.50
220Riprap heavy (606.0300)CY137$125.00$125.00$75.00$80.00$110.00
221Storm sewer pipe reinforced concrete class III 12-inch (608.0312)LF1,294$109.23$109.23$82.50$91.55$91.55
222Storm sewer pipe reinforced concrete class III 15-inch (608.0315)LF3,524$175.60$175.60$80.75$88.49$88.49
223Storm sewer pipe reinforced concrete class III 18-inch (608.0318)LF1,333$126.92$126.92$84.00$95.25$95.25
224Storm sewer pipe reinforced concrete class III 24-inch (608.0324)LF3,054$158.63$158.63$105.00$110.36$110.36
225Storm sewer pipe reinforced concrete class III 30-inch (608.0330)LF266$203.19$203.19$123.00$144.29$144.30
226Storm sewer pipe reinforced concrete class III 36-inch (608.0336)LF564$209.10$209.10$229.50$176.44$176.45
227Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF746$149.70$149.70$80.00$91.55$91.55
228Storm sewer pipe reinforced concrete class IV 15-inch (608.0415)LF3,320$100.38$100.38$81.00$88.49$88.49
229Storm sewer pipe reinforced concrete class IV 18-inch (608.0418)LF1,717$114.58$114.58$83.00$95.26$95.25
230Storm sewer pipe reinforced concrete class IV 24-inch (608.0424)LF2,918$134.86$134.86$103.00$119.06$119.07
231Storm sewer pipe reinforced concrete class IV 27-inch (608.0427)LF637$149.53$149.53$126.00$142.06$142.07
232Storm sewer pipe reinforced concrete class IV 30-inch (608.0430)LF68$207.89$207.89$140.00$166.59$166.60
233Storm sewer pipe reinforced concrete class V 12-inch (608.0512)LF116$125.95$125.95$76.00$91.55$91.55
234Storm sewer pipe reinforced concrete class V 15-inch (608.0515)LF11$177.23$177.23$82.00$115.74$115.75
235Storm sewer pipe reinforced concrete horizontal elliptical class HE-III 38X60-inch (608.2338)LF119$377.27$377.27$249.00$273.83$273.84
236Manhole covers type J (611.0530)EACH3$860.50$860.50$556.00$566.97$567.00
237Manhole covers type J-special (611.0535)EACH3$885.67$886.00$568.50$583.97$584.00
238Inlet covers type B (611.0606)EACH2$1,208.86$1,210.00$851.50$828.96$829.00
239Inlet covers type C (611.0612)EACH4$892.29$892.00$573.00$587.97$588.00
240Inlet covers type DW (611.0613)EACH4$1,287.98$1,288.00$823.00$803.96$804.00
241Inlet covers type H (611.0624)EACH3$1,273.40$1,273.00$807.00$789.96$790.00
242Inlet covers type H-S (611.0639)EACH4$1,273.40$1,273.00$807.00$789.96$790.00
243Inlet covers type MS (611.0642)EACH8$565.62$565.00$560.00$576.97$577.00
244Inlet covers type VV-B (611.0656)EACH295$2,402.99$2,403.00$1,783.50$1,585.92$1,586.00
245Manholes 3-FT diameter (611.2003)EACH3$1,955.20$1,955.00$2,632.00$3,642.82$3,643.00
246Manholes 5-FT diameter (611.2005)EACH288$4,214.48$4,214.48$4,675.00$5,768.62$5,768.91
247Manholes 6-FT diameter (611.2006)EACH4$5,957.05$5,957.00$6,096.00$6,889.90$6,890.25
248Manholes 8-FT diameter (611.2008)EACH1$15,197$15,197$14,177$15,309$15,310
249Inlets 3-FT diameter (611.3003)EACH32$1,662.06$1,662.06$2,427.00$3,367.59$3,367.75
250Inlets 4-FT diameter (611.3004)EACH3$2,621.14$2,621.14$3,087.00$4,277.29$4,277.50
251Inlets 2X2-FT (611.3220)EACH2$1,712.16$1,712.16$2,230.00$2,594.88$2,595.00
252Inlets 2X3-FT (611.3230)EACH9$1,544.22$1,544.22$2,220.00$2,868.17$2,868.31
253Inlets 2X3.5-FT (611.3260)EACH7$1,938.04$1,938.00$2,897.00$5,566.11$5,566.39
254Inlets median 1 grate (611.3901)EACH2$2,355.61$2,355.61$2,338.00$3,451.71$3,451.88
255Inlets median 2 grate (611.3902)EACH4$3,067.25$3,067.25$2,744.00$4,595.77$4,596.00
256Adjusting inlet covers (611.8115)EACH1$671.79$672.00$736.00$858.71$858.75
257Cover plates temporary (611.8120.S)EACH12$300.00$300.00$390.00$395.64$395.66
258Salvaged inlet covers (611.9710)EACH6$822.12$822.12$450.00$118.07$118.08
259Drain slotted vane (611.9900.S)EACH7$48,093$48,093$10,500$40,407$40,409
260Pipe underdrain 6-inch (612.0106)LF110$16.00$16.00$16.00$26.33$26.33
261Pipe underdrain unperforated 6- inch (612.0206)LF685$25.00$25.00$16.00$24.90$24.90
262Pipe underdrain wrapped 6-inch (612.0406)LF1,877$14.00$13.60$16.00$27.43$5.25
263Apron endwalls for underdrain reinforced concrete 6-inch (612.0806)EACH9$325.00$325.00$350.00$525.53$525.56
264Anchor assemblies for steel plate beam guard (614.0150)EACH8$250.00$250.00$250.00$249.99$250.00
265Guardrail mow strip emulsified asphalt (614.0397)SY5,088$17.00$17.00$17.00$17.00$17.00
266Crash cushions temporary (614.0905)EACH61$4,125.00$5,375.00$4,125.00$4,624.77$5,375.00
267MGS guardrail 3 (614.2300)LF10,596$28.00$28.00$28.00$28.00$28.00
268MGS guardrail 3 K (614.2330)LF100$50.00$50.00$50.00$50.00$50.00
269MGS guardrail 3 L (614.2340)LF902$38.00$38.00$38.00$38.00$38.00
270MGS thrie beam transition (614.2500)LF252.60$92.00$92.00$92.00$92.00$92.00
271MGS guardrail terminal eat (614.2610)EACH25$4,900.00$4,900.00$4,900.00$4,899.76$4,900.00
272MGS guardrail terminal type 2 (614.2620)EACH19$3,400.00$3,400.00$3,400.00$3,399.83$3,400.00
273Fence chain link 6-FT (616.0206)LF56,420$25.25$25.25$25.50$25.25$25.25
274Fence safety (616.0700.S)LF1,350$7.00$7.00$7.00$7.00$7.00
275Maintenance and repair of haul roads (project) 0001. 1130-66-71 (618.0100)EACH1$1.00$1,000.00$1.00$0.01$0.01
276Maintenance and repair of haul roads (project) 0002. 1130-66-72 (618.0100)EACH1$1.00$1,000.00$1.00$0.01$0.01
277Maintenance and repair of haul roads (project) 0003. 1130-66-77 (618.0100)EACH1$1.00$1,000.00$1.00$0.01$0.01
278Maintenance and repair of haul roads (project) 0004. 1130-66-84 (618.0100)EACH1$1.00$1,000.00$1.00$0.01$0.01
279Mobilization (619.1000)EACH1$8,164,000$6,911,615$18,829,003$11,393,923$15,100,000
280Concrete median blunt nose (620.0200)SF547$20.00$14.39$18.00$14.39$15.50
281Concrete median sloped nose (620.0300)SF235$20.00$14.24$17.00$14.24$15.50
282Water (624.0100)MGAL4,443$20.00$20.00$50.00$100.00$0.01
283Salvaged topsoil (625.0500)SY507,980$2.65$2.65$1.45$0.01$0.01
284Mulching (627.0200)SY110,500$0.01$0.01$0.01$0.01$0.01
285Silt fence (628.1504)LF13,180$3.00$3.00$3.00$3.00$3.00
286Silt fence maintenance (628.1520)LF51,990$0.01$0.01$0.01$0.01$0.01
287Silt fence heavy duty (628.1530.S)LF2,960$5.00$5.00$5.00$5.00$5.00
288Silt fence heavy duty maintenance (628.1535.S)LF2,960$0.01$0.01$0.01$0.01$0.01
289Mobilizations erosion control (628.1905)EACH34$1.00$1.00$1.00$1.00$1.00
290Mobilizations emergency erosion control (628.1910)EACH50$1.00$1.00$1.00$1.00$1.00
291Erosion mat class I type B (628.2004)SY459,200$1.12$1.12$1.12$1.12$1.12
292Erosion mat urban class I type A (628.2006)SY985$2.00$2.00$2.00$2.00$2.00
293Erosion mat urban class I type B (628.2008)SY3,660$2.00$2.00$2.00$2.00$2.00
294Erosion mat class II type B (628.2023)SY36,400$1.12$1.12$1.12$1.12$1.12
295Erosion mat class III type C (628.2037)SY170$25.00$25.00$25.00$25.00$25.00
296Erosion mat class III type D (628.2039)SY229$25.00$25.00$25.00$25.00$25.00
297Inlet protection type A (628.7005)EACH348$1.00$1.00$1.00$1.00$1.00
298Inlet protection type B (628.7010)EACH362$100.00$100.00$100.00$99.99$100.00
299Inlet protection type C (628.7015)EACH11$100.00$100.00$100.00$99.99$100.00
300Inlet protection type D (628.7020)EACH120$125.00$125.00$125.00$124.99$125.00
301Temporary ditch checks (628.7504)LF2,342$6.00$6.00$6.00$6.00$6.00
302Culvert pipe checks (628.7555)EACH295$15.00$15.00$15.00$15.00$15.00
303Tracking pads (628.7560)EACH31$1,650.00$1,650.00$1,300.00$0.01$0.01
304Rock bags (628.7570)EACH352$15.00$15.00$15.00$15.00$15.00
305Fertilizer type B (629.0210)CWT414.30$0.01$0.01$0.01$0.01$0.01
306Seeding mixture no. 30 (630.0130)LB25,003$7.00$7.00$7.00$7.00$7.00
307Seeding temporary (630.0200)LB220$7.00$7.00$7.00$7.00$7.00
308Seeding borrow pit (630.0300)LB63.90$7.00$7.00$7.00$7.00$7.00
309Seed water (630.0500)MGAL25,603.50$0.01$0.01$0.01$0.01$0.01
310Delineator posts steel (633.0100)EACH224$75.00$75.00$75.00$75.00$75.00
311Delineator reflectors (633.0500)EACH602$15.00$15.00$15.00$15.00$15.00
312Delineators barrier wall (633.1000)EACH769$80.00$80.00$80.00$80.00$80.00
313Markers culvert end (633.5200)EACH164$80.00$80.00$80.00$80.00$80.00
314Posts wood 4X6-inch X 14-FT (634.0614)EACH22$150.00$150.00$150.00$149.99$150.00
315Posts wood 4X6-inch X 16-FT (634.0616)EACH31$160.00$160.00$160.00$159.99$160.00
316Posts wood 4X6-inch X 18-FT (634.0618)EACH40$170.00$170.00$170.00$169.99$170.00
317Posts tubular steel 2X2-inch X 8-FT (634.0808)EACH31$500.00$500.00$500.00$499.97$500.00
318Sign supports structural steel HS (635.0200)LB16,400$6.75$6.75$6.75$6.75$6.75
319Signs type I reflective SH (637.1220)SF4,586.50$32.00$32.00$32.00$32.00$32.00
320Signs type II reflective H (637.2210)SF1,310.33$28.00$28.00$28.00$28.00$28.00
321Signs type II reflective F (637.2230)SF160$32.00$32.00$32.00$32.00$32.00
322Moving signs type I (638.2101)EACH3$2,500.00$2,500.00$2,500.00$2,499.88$2,500.00
323Moving signs type II (638.2102)EACH72$200.00$200.00$200.00$199.99$200.00
324Removing signs type I (638.2601)EACH17$475.00$475.00$475.00$474.98$475.00
325Removing signs type II (638.2602)EACH149$50.00$50.00$50.00$50.00$50.00
326Removing small sign supports (638.3000)EACH185$50.00$50.00$50.00$50.00$50.00
327Removing structural steel sign supports (638.3100)EACH24$600.00$600.00$600.00$599.97$600.00
328Pond liner clay (640.1303.S)CY7,510$27.00$27.00$27.70$10.00$39.42
329Traffic control drums (643.0300)DAY356,626$0.20$0.20$0.20$0.20$0.20
330Digital speed reduction system (DSRS) (643.0370.S)DAY2,042$75.00$75.00$75.00$75.00$75.00
331Traffic control barricades type III (643.0420)DAY33,873$0.65$0.65$0.65$0.65$0.65
332Traffic control flexible tubular marker posts (643.0500)EACH1,928$0.50$0.50$0.50$0.50$0.50
333Traffic control flexible tubular marker bases (643.0600)EACH1,928$0.50$0.50$0.50$0.50$0.50
334Traffic control warning lights type A (643.0705)DAY67,746$0.15$0.15$0.15$0.15$0.15
335Traffic control warning lights type C (643.0715)DAY47,915$0.20$0.20$0.20$0.20$0.20
336Traffic control connected arrow boards (643.0810)DAY2,337$19.50$19.50$19.50$19.50$19.50
337Traffic control signs (643.0900)DAY266,968$0.25$0.25$0.25$0.25$0.25
338Traffic control covering signs type I (643.0910)EACH71$300.00$300.00$300.00$299.98$300.00
339Traffic control covering signs type II (643.0920)EACH79$110.00$110.00$110.00$109.99$110.00
340Traffic control signs fixed message (643.1000)SF1,441.75$18.25$18.25$18.25$18.25$18.25
341Traffic control signs PCMS (643.1050)DAY105$20.00$20.00$20.00$20.00$20.00
342Traffic control signs PCMS with TMC communications (643.1051)DAY447$25.00$25.00$25.00$25.00$25.00
343Traffic control connected work zone start and end location markers (643.1220)DAY2,295$8.75$8.75$8.75$8.75$8.75
344Temporary marking line paint 6- inch (643.3165)LF375,688$0.25$0.25$0.25$0.25$0.25
345Temporary marking line epoxy 6- inch (643.3170)LF238,227$0.63$0.63$0.63$0.63$0.63
346Temporary marking line removable tape 6-inch (643.3180)LF14,560$2.00$2.00$2.00$2.00$2.00
347Temporary marking line paint 10- inch (643.3265)LF13,898$0.90$0.90$0.90$0.90$0.90
348Temporary marking line epoxy 10- inch (643.3270)LF11,730$1.80$1.80$1.80$1.80$1.80
349Temporary marking arrow epoxy (643.3520)EACH8$243.20$243.20$243.20$243.19$243.20
350Temporary marking word epoxy (643.3620)EACH3$329.00$329.00$329.00$328.98$329.00
351Temporary marking raised pavement marker type I (643.3760)EACH1,722$7.25$7.25$7.25$7.25$7.25
352Temporary marking diagonal epoxy 12-inch (643.3920)LF283$14.20$14.20$14.20$14.20$14.20
353Temporary marking diagonal removable tape 12-inch (643.3950)LF150$5.00$5.00$5.00$5.00$5.00
354Traffic control (643.5000)EACH1$1,700,000$1,700,000$1,700,000$1,699,915$1,700,000
355Temporary pedestrian surface asphalt (644.1410)SF1,960$129.40$9.01$15.00$2.00$12.00
356Temporary pedestrian barricade (644.1810)LF2,568$10.45$10.45$10.45$10.45$10.45
357Temporary audible message devices (644.1900.S)DAY1,832$12.15$12.15$12.15$12.15$12.15
358Geotextile type C (645.0105)SY1,560$2.87$2.87$5.00$4.75$4.75
359Geotextile type DF schedule A (645.0111)SY619$3.00$3.00$5.00$5.61$5.61
360Geotextile type HR (645.0120)SY3,957$2.00$2.00$8.00$5.95$3.50
361Geotextile type R (645.0130)SY2,802$1.50$1.50$7.00$3.00$3.50
362Geotextile type sas (645.0140)SY179,750$1.25$1.25$2.50$1.00$1.15
363Geogrid type SR-2 (645.0145.S)SY92,660$1.25$1.25$3.00$1.25$1.50
364Marking line epoxy 6-inch (646.2020)LF8,895$0.60$0.60$0.60$0.60$0.60
365Marking line grooved wet ref epoxy 6-inch (646.2040)LF153,026$1.43$1.43$1.43$1.43$1.43
366Marking line grooved permanent tape 6-inch (646.2050)LF71,210$7.94$7.94$7.94$7.94$7.94
367Marking line epoxy 10-inch (646.4020)LF1,217$1.30$1.30$1.30$1.30$1.30
368Marking line grooved wet ref epoxy 10-inch (646.4040)LF450$3.20$3.20$3.20$3.20$3.20
369Marking line grooved permanent tape 10-inch (646.4050)LF14,445$14.00$14.00$14.00$14.00$14.00
370Marking arrow epoxy (646.5020)EACH31$246.35$246.35$246.35$246.34$246.35
371Marking word epoxy (646.5120)EACH8$390.70$390.70$390.70$390.68$390.70
372Marking symbol epoxy (646.5220)EACH4$232.95$232.95$232.95$232.94$232.95
373Marking railroad crossing epoxy (646.5320)EACH2$2,377.50$2,377.50$1,000.00$2,377.38$2,377.50
374Marking aerial enforcement bar epoxy (646.5420)EACH26$474.55$474.55$470.55$474.53$474.55
375Marking stop line epoxy 12-inch (646.6020)LF57$15.25$15.25$15.25$15.25$15.25
376Marking stop line epoxy 18-inch (646.6120)LF82$17.00$17.00$17.00$17.00$17.00
377Marking dotted extension epoxy 18-inch (646.6320)LF112$20.00$20.00$20.00$20.00$20.00
378Marking chevron epoxy 24-inch (646.7220)LF623$32.85$32.85$32.85$32.85$32.85
379Marking crosswalk epoxy transverse line 6-inch (646.7420)LF398$13.75$13.75$13.75$13.75$13.75
380Marking parking stall epoxy (646.8320)LF2,650$4.50$4.50$4.50$4.50$4.50
381Marking removal line 6-inch (646.9002)LF85,220$0.25$0.25$0.25$0.25$0.25
382Marking removal line water blasting 4-inch (646.9010)LF945$0.55$0.55$0.55$0.55$0.55
383Marking removal line water blasting 6-inch (646.9012)LF21,480$0.65$0.65$0.65$0.65$0.65
384Marking removal line 10-inch (646.9102)LF6,110$0.55$0.55$0.55$0.55$0.55
385Marking removal line water blasting 8-inch (646.9110)LF570$1.25$1.25$1.25$1.25$1.25
386Marking removal special marking water blasting (646.9310)EACH5$495.00$495.00$495.00$494.97$495.00
387Conduit rigid metallic 2-inch (652.0125)LF72$475.00$475.00$475.00$474.98$475.00
388Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF45,878$12.00$12.00$12.00$12.00$12.00
389Conduit rigid nonmetallic schedule 40 3-inch (652.0235)LF4,086$16.00$16.00$16.00$16.00$16.00
390Conduit rigid nonmetallic schedule 80 2-inch (652.0325)LF80$16.00$16.00$16.00$16.00$16.00
391Conduit rigid nonmetallic schedule 80 3-inch (652.0335)LF1,299$20.00$20.00$20.00$20.00$20.00
392Conduit special 3-inch (652.0615)LF1,244$42.00$42.00$42.00$42.00$42.00
393Install conduit into existing item (652.0700.S)EACH21$375.00$375.00$375.00$374.98$375.00
394Pull boxes non-conductive 24X36- inch (653.0154)EACH4$3,500.00$3,500.00$3,500.00$3,499.83$3,500.00
395Pull boxes non-conductive 24X42- inch (653.0164)EACH72$3,575.00$3,575.00$3,575.00$3,574.82$3,575.00
396Junction boxes 18X12X6-inch (653.0222)EACH2$2,950.00$2,950.00$2,950.00$2,949.86$2,950.00
397Removing pull boxes (653.0905)EACH26$75.00$75.00$75.00$75.00$75.00
398Concrete bases type 1 (654.0101)EACH1$1,500.00$1,500.00$1,500.00$1,499.92$1,500.00
399Concrete bases type 5 (654.0105)EACH28$1,575.00$1,575.00$1,575.00$1,574.92$1,575.00
400Concrete bases type 7 (654.0107)EACH26$1,750.00$1,750.00$1,750.00$1,749.91$1,750.00
401Concrete control cabinet bases type L30 (654.0230)EACH1$2,400.00$2,400.00$2,400.00$2,399.89$2,400.00
402Electrical wire lighting 12 AWG (655.0610)LF80,863$1.50$1.50$1.50$1.50$1.50
403Electrical wire lighting 10 AWG (655.0615)LF16,609$1.40$1.40$1.40$1.40$1.40
404Electrical wire lighting 6 AWG (655.0625)LF1,828$3.00$3.00$3.00$3.00$3.00
405Electrical wire lighting 4 AWG (655.0630)LF63,410$3.50$3.50$3.50$3.50$3.50
406Electrical wire lighting 2 AWG (655.0635)LF132$5.00$5.00$5.00$5.00$5.00
407Electrical service meter breaker pedestal (location) 0001. MB7-2 (656.0201)EACH1$2,000.00$2,000.00$2,000.00$1,999.90$2,000.00
408Electrical service meter breaker pedestal (location) 0002. MD7-1 (656.0201)EACH1$2,000.00$2,000.00$2,000.00$1,999.90$2,000.00
409Electrical service breaker disconnect box (location) 0001. CB7-2 (656.0501)EACH1$900.00$900.00$900.00$899.95$900.00
410Electrical service breaker disconnect box (location) 0002. CB7-3 (656.0501)EACH1$900.00$900.00$900.00$899.95$900.00
411Electrical service breaker disconnect box (location) 0003. CB8-1 (656.0501)EACH1$900.00$900.00$900.00$899.95$900.00
412Pedestal bases (657.0100)EACH1$340.00$340.00$340.00$339.98$340.00
413Transformer bases breakaway 15- 17 inch bolt circle (657.0210)EACH32$796.00$796.00$796.00$795.96$796.00
414Transformer bases breakaway 11 1/2-inch bolt circle (657.0255)EACH35$695.00$695.00$695.00$694.96$695.00
415Poles type 5-aluminum (657.0322)EACH35$1,950.00$1,950.00$1,950.00$1,949.90$1,950.00
416Poles type 17-aluminum (657.0337)EACH32$7,374.00$7,374.00$7,374.00$7,373.64$7,374.00
417Luminaire arms single member 4 1/2-inch clamp 4-FT (657.0605)EACH3$360.00$360.00$360.00$359.98$360.00
418Luminaire arms single member 6- inch clamp 4-FT (657.0620)EACH32$385.00$385.00$385.00$384.98$385.00
419Luminaire arms single member 6- inch clamp 15-FT (657.0640)EACH4$880.00$880.00$880.00$879.95$880.00
420Luminaire arms truss type 4 1/2- inch clamp 12-FT (657.0710)EACH29$825.00$825.00$825.00$824.96$825.00
421Underdeck lighting (structure) 0001. B-44-334 (659.0601)EACH1$12,000$12,000$12,000$11,999$12,000
422Underdeck lighting (structure) 0002. B-44-335 (659.0601)EACH1$12,500$12,500$12,500$12,499$12,500
423Underdeck lighting (structure) 0003. B-44-336 (659.0601)EACH1$9,450.00$9,450.00$9,450.00$9,449.53$9,450.00
424Underdeck lighting (structure) 0004. B-44-337 (659.0601)EACH1$9,450.00$9,450.00$9,450.00$9,449.53$9,450.00
425Luminaires utility LED B (659.1120)EACH46$400.00$400.00$400.00$399.98$400.00
426Luminaires utility LED C (659.1125)EACH32$430.00$430.00$430.00$429.98$430.00
427Luminaires underdeck LED B (659.1210)EACH6$775.00$775.00$775.00$774.96$775.00
428Lamp, ballast, LED, switch disposal by contractor (659.5000.S)EACH27$75.00$75.00$75.00$75.00$75.00
429Field system integrator (670.0101)EACH1$50,075$50,075$50,075$50,073$50,075
430ITS documentation (670.0201)EACH1$8,000.00$8,000.00$8,000.00$7,999.61$8,000.00
431Conduit HDPE 3-duct 2-inch (671.0132)LF24,019$16.00$16.00$16.00$16.00$16.00
432Conduit HDPE directional bore 3- duct 2-inch (671.0232)LF4,449$38.00$38.00$38.00$38.00$38.00
433Fiber optic cable marker (671.0300)EACH104$75.00$75.00$75.00$75.00$75.00
434Communication vault type 1 (673.0105)EACH14$2,450.00$2,450.00$2,450.00$2,449.87$2,450.00
435Communication vault type round (673.0110)EACH5$4,275.00$4,275.00$4,275.00$4,274.79$4,275.00
436Tracer wire marker posts (673.0200)EACH38$150.00$150.00$150.00$149.99$150.00
437Install pole mounted cabinet (673.1225.S)EACH15$2,875.00$2,875.00$2,875.00$2,874.86$2,875.00
438Cable microwave detector (674.0200)LF14,901$4.20$4.20$4.20$4.20$4.20
439Remove cable (674.0300)LF29,404$2.00$2.00$2.00$2.00$2.00
440Install mounted controller microwave detector assembly (675.0300)EACH13$3,400.00$3,400.00$3,400.00$3,399.83$3,400.00
441Install camera pole 50-FT (677.0150)EACH2$4,325.00$4,325.00$4,325.00$4,324.79$4,325.00
442Install camera assembly (677.0200)EACH2$2,705.00$2,705.00$2,705.00$2,704.87$2,705.00
443Removing 50-FT camera pole (677.9051.S)EACH1$2,870.00$2,870.00$2,870.00$2,869.86$2,870.00
444Install fiber optic cable outdoor plant 12-CT (678.0012)LF5,335$2.00$2.00$2.00$2.00$2.00
445Install fiber optic cable outdoor plant 72-CT (678.0072)LF31,180$2.00$2.00$2.00$2.00$2.00
446Install overhead freeway DMS full matrix (678.0100.S)EACH1$124,750$124,750$124,750$124,744$124,750
447Fiber optic splice enclosure (678.0200)EACH8$1,500.00$1,500.00$1,500.00$1,499.92$1,500.00
448Fiber optic splice (678.0300)EACH384$100.00$100.00$100.00$99.99$100.00
449Fiber optic termination (678.0400)EACH28$300.00$300.00$300.00$299.98$300.00
450Communication system testing (678.0501)EACH2$4,200.00$4,200.00$4,200.00$4,199.79$4,200.00
451Install ethernet switches (678.0600)EACH5$1,000.00$1,000.00$1,000.00$999.95$1,000.00
452Install wireless antennas (678.0700)EACH3$3,100.00$3,100.00$3,100.00$3,099.85$3,100.00
453Sawing asphalt (690.0150)LF74,593$1.39$1.55$0.95$1.39$1.39
454Sawing concrete (690.0250)LF11,750$2.75$2.05$2.25$2.75$2.75
455Incentive strength concrete structures (715.0502)DOL29,298$1.00$1.00$1.00$1.00$1.00
456Incentive strength concrete barrier (715.0603)DOL35,101$1.00$1.00$1.00$1.00$1.00
457Incentive flexural strength concrete pavement (715.0715)DOL117,141$1.00$1.00$1.00$1.00$1.00
458On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,100$5.00$5.00$5.00$5.00$5.00
459On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS5,760$5.00$5.00$5.00$5.00$5.00
460Special 0100. roadway embankment (SPV.0035)CY174,626$0.01$0.01$0.01$25.00$0.01
461Special 0800. HPC masonry structures (SPV.0035)CY2,529$725.00$725.00$725.00$724.96$725.00
462Special 0100. incentive iri ride PCC surfaces (SPV.0055)DOL162,492$1.00$1.00$1.00$1.00$1.00
463Special 0041. temporary bridge widening B-44-41 (SPV.0060)EACH1$850,000$850,000$850,000$849,958$850,000
464Special 0043. temporary bridge widening B-44-43 (SPV.0060)EACH1$850,000$850,000$850,000$849,958$850,000
465Special 0100. construction staking survey project 1130-66-71 (SPV.0060)EACH1$275,000$269,057$269,100$269,044$295,120
466Special 0101. construction staking survey project 1130-66-72 (SPV.0060)EACH1$400,000$370,636$370,650$370,617$441,364
467Special 0102. construction staking survey project 1130-66-77 (SPV.0060)EACH1$15,000$19,742$19,750$19,741$19,742
468Special 0103. construction staking survey project 1130-66-84 (SPV.0060)EACH1$10,000$8,731.65$8,900.00$8,731.22$8,731.65
469Special 0105. baseline CPM progress schedule (SPV.0060)EACH4$1,000.00$5,000.00$2,500.00$0.01$5,000.00
470Special 0106. adjusting sanitary manhole covers (SPV.0060)EACH6$825.79$825.79$1,100.00$974.95$975.00
471Special 0110. CPM progress schedule and accepted revisions (SPV.0060)EACH132$1.00$1,000.00$250.00$0.01$100.00
472Special 0155. temporary water diversion C-44-148 (SPV.0060)EACH1$147,124$147,124$150,000$18,279$18,280
473Special 0201. STH 55 ramp A pond outlet storm sewer structure (SPV.0060)EACH1$8,847.21$8,847.00$9,032.00$11,025$11,026
474Special 0202. CTH J ramp D pond outlet storm sewer structure (SPV.0060)EACH1$10,352$10,352$9,032.00$10,749$10,750
475Special 0203. 66-1218-RT pond outlet storm sewer structure (SPV.0060)EACH1$15,427$15,427$11,580$14,561$14,562
476Special 0204. pond in-situ clay liner, STH 55 ramp A (SPV.0060)EACH1$59,475$59,475$25,000$4,999.75$0.01
477Special 0211. storm sewer tap (SPV.0060)EACH1$2,010.29$2,010.29$964.00$999.34$999.39
478Special 0230. median inlet cover type Y (SPV.0060)EACH32$982.37$982.37$652.00$657.00$657.03
479Special 0295. inlet marker (SPV.0060)EACH295$75.00$75.00$75.00$75.00$75.00
480Special 0296. installing inlet covers (SPV.0060)EACH14$836.32$836.32$650.00$740.50$740.54
481Special 0297. removing cover plates (SPV.0060)EACH14$258.00$258.00$250.00$404.84$404.86
482Special 0305. emergency response to traffic involving concrete barrier temporary (SPV.0060)EACH82$0.01$325.00$1,325.00$1,174.94$2,000.00
483Special 0310. emergency response to traffic involving crash cushion temporary (SPV.0060)EACH77$550.00$550.00$550.00$1,399.93$550.00
484Special 0320. temporary concrete barrier gate, 24-FT (SPV.0060)EACH1$12,225$12,225$12,500$12,224$12,225
485Special 0400. fixed message sign portable support (SPV.0060)EACH27$900.00$900.00$900.00$899.95$900.00
486Special 0501. concrete bases type 7 tall (SPV.0060)EACH114$3,475.00$3,475.00$3,475.00$3,474.83$3,475.00
487Special 0502. transport and install state furnished 277/480 lighting control cabinet (SPV.0060)EACH1$2,500.00$2,500.00$2,500.00$2,499.88$2,500.00
488Special 0503. anchor bolt cover shroud (SPV.0060)EACH108$525.00$525.00$525.00$524.97$525.00
489Special 0504. lighting control cabinets 277/480 30-inch 3-phase (SPV.0060)EACH1$17,500$17,500$17,500$17,499$17,500
490Special 0505. electrical service main lugs only meter pedestal 3- phase 600V (SPV.0060)EACH1$2,850.00$2,850.00$2,850.00$2,849.86$2,850.00
491Special 0506. concrete transformer pad (SPV.0060)EACH2$4,850.00$4,850.00$4,850.00$4,849.76$4,850.00
492Special 0507. temporary street lighting system (SPV.0060)EACH2$55,000$55,000$55,000$54,997$55,000
493Special 0508. temporary wood poles 40-foot (SPV.0060)EACH4$4,800.00$4,800.00$4,800.00$4,799.76$4,800.00
494Special 0509. concrete bases type 5 tall (SPV.0060)EACH4$2,475.00$2,475.00$2,475.00$2,474.88$2,475.00
495Special 0510. transport and install state furnished main lugs only meter pedestal (SPV.0060)EACH1$1,100.00$1,100.00$1,100.00$1,099.94$1,100.00
496Special 0511. concrete control cabinet bases type 10 NE region special (SPV.0060)EACH1$2,400.00$2,400.00$2,400.00$2,399.89$2,400.00
497Special 0512. electrical service meter breaker pedestal special (SPV.0060)EACH1$6,200.00$6,200.00$6,200.00$6,199.69$6,200.00
498Special 0701. removing ground mount dynamic message sign (SPV.0060)EACH1$4,750.00$4,750.00$4,750.00$4,749.76$4,750.00
499Special 0702. install ethernet extender (SPV.0060)EACH24$475.00$475.00$475.00$474.98$475.00
500Special 0703. remove poles wood (SPV.0060)EACH1$750.00$750.00$750.00$749.96$750.00
501Special 0704. remove and reinstall ITS equipment (SPV.0060)EACH1$13,750$13,750$13,750$13,749$13,750
502Special 0705. wood pole, 50-FT (SPV.0060)EACH1$5,500.00$5,500.00$5,500.00$5,499.72$5,500.00
503Special 0706. traffic signal standards aluminum 6-FT (SPV.0060)EACH1$550.00$550.00$550.00$549.97$550.00
504Special 0707. salvaging wireless antennas (SPV.0060)EACH4$2,220.00$2,220.00$2,220.00$2,219.88$2,220.00
505Special 0708. adjusting communication vaults (SPV.0060)EACH1$4,875.00$4,875.00$4,875.00$4,874.76$4,875.00
506Special 0100. street sweeping (SPV.0075)HRS2,194$0.01$133.00$25.00$299.98$0.01
507Special 0105. animal carcass removal (SPV.0075)HRS542$0.01$250.00$1.00$349.98$550.00
508Special 0106. roadway debris removal (SPV.0075)HRS542$0.01$250.00$1.00$349.98$550.00
509Special 0001. SSPRC horizontal elliptical class HE-IV 38X60-inch (SPV.0090)LF165$427.45$427.45$301.00$340.30$340.32
510Special 0002. pipe underdrain (6- inch) with geotextile fabric and aggregate (SPV.0090)LF5,865$14.50$14.50$17.00$25.00$25.00
511Special 0003. concrete curb and gutter 4-inch sloped 36-inch type R (SPV.0090)LF240$100.00$52.01$66.00$52.01$62.00
512Special 0100. HMA longitudinal joint repair (SPV.0090)LF56,580$3.00$3.00$3.00$3.00$3.00
513Special 0115. concrete barrier type S42 special (SPV.0090)LF7,856$79.00$92.14$107.49$92.14$80.78
514Special 0120. concrete barrier type S56 special (SPV.0090)LF63,430$90.00$101.52$111.89$101.52$82.64
515Special 0305. glare screens temporary (SPV.0090)LF6,855$7.50$7.50$7.50$7.50$7.50
516Special 0501. temporary overhead cable triplex 6 AWG (SPV.0090)LF576$7.50$7.50$7.50$7.50$7.50
517Special 0800. removing existing timber piling (SPV.0090)LF1,050$5.00$5.00$5.00$5.00$5.00
518Special 0800. longitudinal grooving bridge deck (SPV.0165)SF49,310$0.91$0.82$1.50$0.77$0.77
519Special 0100. concrete pavement 10 1/2-inch special (SPV.0180)SY378,741$62.31$68.17$63.23$68.17$66.36
WisDOT contract 20261013010: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of October 13, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy