Abandoning culvert pipes, WisDOT 204.0270

Low bidders on WisDOT contracts carried a median of $1,319.91 per EACH for this item, over the 24 months to 10 NOV 2026, across 14 low bids. Half of all 68 bids fell between $621.25 and $2,207.25.

Owner
Wisconsin DOT
Item
204.0270
Unit
EACH
Data through
10 NOV 2026

WisDOT prints this item as “Abandoning Culvert Pipes”.

$1,319.91Low bidder's median, per EACH
$1,229.51Median of all bids, per EACH
15Contracts in the window

By year of letting

Abandoning culvert pipes, WisDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202276$750.0022$750.00
20231111$900.0038$895.56
20241010$997.0038$1,000.00
202576$1,029.5123$935.00
202666$1,292.5030$1,385.00

Bid prices as published, not adjusted for inflation.

By quantity

Quantity (EACH)Low bidsLow-bid median
1 to 13$3,000.00
1 to 14$6,600.00
1 to 23$1,385.00
5 to 274$525.00
Abandoning culvert pipes, WisDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

Abandoning culvert pipes, WisDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
13 OCT 202620261013010Outagamie1$5,000.00$5,000.005Zignego Company, Inc.WisDOT
14 JUL 202620260714001Sauk1$692.66$846.332Gerke Excavating IncWisDOT
14 JUL 202620260714005Outagamie1$1,385.00$1,385.006Vinton Construction CompanyWisDOT
10 FEB 202620260210015Milwaukee8$550.00$550.004Wandel Contractors IncWisDOT
10 FEB 202620260210047Dane1$12,000$2,500.007Integrity Grading and Excavating, Inc.WisDOT
13 JAN 202620260113056Waukesha1$1,200.00$951.006Hoffman Construction CompanyWisDOT
11 NOV 202520251111010Milwaukee2$800.00$800.004Lalonde Contractors IncorporatedWisDOT
11 NOV 202520251111028Ashland1$24,436$6,949.133James Peterson Sons, Inc.WisDOT
14 OCT 202520251014010Marathon9$450.00$684.258James Peterson Sons, Inc.WisDOT
12 AUG 202520250812004Crawford1$1,259.02$1,259.021Iverson Construction, A Div. of Mathy CoWisDOT
11 MAR 202520250311040Barron5$500.00$500.002Zenith Tech., Inc. - WaukeshaWisDOT
11 FEB 202520250211004La Crosse1$3,000.00$3,000.002Pheifer Brothers Construction Co., Inc.WisDOT
11 FEB 202520250211033Forest1n/a$1,500.003Integrity Grading and Excavating, Inc.WisDOT
10 DEC 202420241210014Outagamie1$8,910.00$1,000.005Michels Road & Stone, Inc.WisDOT
12 NOV 202420241112019Waukesha27$1,380.81$1,345.2210Super Western, Inc.WisDOT
Latest WisDOT contracts carrying Abandoning culvert pipes

Filter this item by your own quantity, county and period, or check your price against it, in the WisDOT explorer.

How these prices were read

WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WisDOT's own: this item is compared with WisDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the WisDOT letting of 10 NOV 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way