WisDOT contract 20260113056 bid tabulation
IH 43 Rock Freeway; STH 83 to STH 164 (IH 043, Waukesha County IH 43 Rock Freeway). Let by Wisconsin DOT on January 13, 2026, Waukesha. 6 bids received; low bid $48,928,006 by Hoffman Construction Company.
- Owner
- Wisconsin DOT
- Letting
- 13 JAN 2026
- Pay items
- 472
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Hoffman Construction Company | $48,928,006 | Low |
| 2 | Musson Bros., Inc. | $52,940,966 | +8.0% |
| 3 | Zignego Company, Inc. | $55,869,517 | +14% |
| 4 | Michels Road & Stone, Inc. | $57,217,272 | +17% |
| 5 | James Peterson Sons, Inc. | $58,111,224 | +19% |
| 6 | Mashuda Contractors, Inc. | $59,453,934 | +22% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Hoffman Construction Company | 2. Musson Bros., Inc. | 3. Zignego Company, Inc. | 4. Michels Road & Stone, Inc. | 5. James Peterson Sons, Inc. | 6. Mashuda Contractors, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 130 | $263.75 | $263.75 | $263.75 | $263.75 | $263.75 | $263.75 |
| 2 | Grubbing (201.0205) | STA | 351 | $52.75 | $52.75 | $52.75 | $52.75 | $82.75 | $52.75 |
| 3 | Removing small pipe culverts (203.0100) | EACH | 21 | $1,600.00 | $2,280.00 | $2,280.00 | $2,280.00 | $1,900.00 | $2,161.00 |
| 4 | Abatement of asbestos containing material (structure) 001. B-67-122 (203.0211.S) | EACH | 1 | $7,500.00 | $10,000 | $10,000 | $10,000 | $10,000 | $10,000 |
| 5 | Debris containment over waterway (structure) 001. B-67-127 (203.0335) | EACH | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 6 | Debris containment over waterway (structure) 002. B-67-128 (203.0335) | EACH | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 7 | Removing concrete pavement (204.0100) | SY | 230,010 | $10.00 | $3.50 | $3.50 | $3.50 | $4.25 | $6.60 |
| 8 | Removing asphaltic surface (204.0110) | SY | 6,140 | $2.00 | $3.40 | $3.40 | $3.40 | $1.25 | $3.00 |
| 9 | Removing asphaltic surface butt joints (204.0115) | SY | 1,743 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 10 | Removing asphaltic surface milling (204.0120) | SY | 21,004 | $1.50 | $1.50 | $1.50 | $1.50 | $1.50 | $1.50 |
| 11 | Removing curb & gutter (204.0150) | LF | 2,317 | $2.50 | $4.50 | $4.50 | $4.50 | $2.75 | $3.00 |
| 12 | Removing concrete sidewalk (204.0155) | SY | 289 | $8.00 | $3.40 | $3.40 | $3.40 | $8.65 | $5.00 |
| 13 | Removing concrete barrier (204.0157) | LF | 9,126 | $10.00 | $15.00 | $15.00 | $15.00 | $12.52 | $12.00 |
| 14 | Removing guardrail (204.0165) | LF | 4,518 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 |
| 15 | Removing fence (204.0170) | LF | 3,850 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 |
| 16 | Removing surface drains (204.0190) | EACH | 7 | $300.00 | $90.00 | $90.00 | $90.00 | $275.00 | $400.00 |
| 17 | Removing concrete bases (204.0195) | EACH | 22 | $300.00 | $364.46 | $365.00 | $364.46 | $364.46 | $364.46 |
| 18 | Removing inlets (204.0220) | EACH | 26 | $425.00 | $499.00 | $499.00 | $499.00 | $750.00 | $799.00 |
| 19 | Removing storm sewer (size) 001. 12-inch (204.0245) | LF | 790 | $11.00 | $13.00 | $13.00 | $13.00 | $39.53 | $15.00 |
| 20 | Removing storm sewer (size) 002. 15-inch (204.0245) | LF | 63 | $11.00 | $15.00 | $15.00 | $15.00 | $47.57 | $15.00 |
| 21 | Removing storm sewer (size) 003. 18-inch (204.0245) | LF | 2,529 | $11.00 | $9.40 | $9.40 | $9.40 | $45.35 | $15.00 |
| 22 | Removing storm sewer (size) 004. 24-inch (204.0245) | LF | 179 | $11.00 | $14.50 | $14.50 | $14.50 | $48.64 | $15.00 |
| 23 | Removing storm sewer (size) 005. 30-inch (204.0245) | LF | 622 | $11.00 | $15.00 | $15.00 | $15.00 | $8.82 | $15.00 |
| 24 | Removing storm sewer (size) 006. 36-inch (204.0245) | LF | 97 | $21.00 | $21.50 | $21.50 | $21.50 | $11.78 | $15.00 |
| 25 | Removing storm sewer (size) 008. 48-inch (204.0245) | LF | 470 | $21.00 | $18.00 | $18.00 | $18.00 | $13.14 | $15.00 |
| 26 | Removing ancillary structure (structure) 001. S-67-230 (204.0246) | EACH | 1 | $6,500.00 | $6,500.00 | $6,500.00 | $6,500.00 | $6,500.00 | $6,500.00 |
| 27 | Abandoning wells (204.0265) | EACH | 2 | $1,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $1,000.00 | $3,500.00 |
| 28 | Abandoning culvert pipes (204.0270) | EACH | 1 | $1,200.00 | $702.00 | $702.00 | $702.00 | $3,000.00 | $2,122.00 |
| 29 | Sealing pipes (204.0280) | EACH | 2 | $1,200.00 | $453.00 | $453.00 | $453.00 | $1,000.00 | $615.00 |
| 30 | Removing (item description) 001. pavement terminal anchors (204.9060.S) | EACH | 18 | $850.00 | $2,000.00 | $2,000.00 | $2,000.00 | $1,228.50 | $2,500.00 |
| 31 | Removing (item description) 002. barricade rack and barricades (204.9060.S) | EACH | 2 | $250.00 | $250.00 | $250.00 | $250.00 | $250.00 | $250.00 |
| 32 | Removing (item description) 101. lighting units (204.9060.S) | EACH | 5 | $708.42 | $708.42 | $708.42 | $708.42 | $708.42 | $708.42 |
| 33 | Removing (item description) 102. removing distribution center (204.9060.S) | EACH | 1 | $1,650.98 | $1,650.98 | $1,650.98 | $1,650.98 | $1,650.98 | $1,650.98 |
| 34 | Removing (item description) 301. traffic signals STH 164 & CTH ES (204.9060.S) | EACH | 1 | $4,127.44 | $4,127.44 | $4,127.44 | $4,127.44 | $4,127.44 | $4,127.44 |
| 35 | Removing (item description) 302. traffic signals IH 43 ramps & STH 164 (204.9060.S) | EACH | 1 | $5,503.26 | $5,503.26 | $5,503.26 | $5,503.26 | $5,503.26 | $5,503.26 |
| 36 | Removing (item description) 303. loop detector lead-in cable STH 164 & CTH ES (204.9060.S) | EACH | 1 | $1,375.81 | $1,375.81 | $1,375.81 | $1,375.81 | $1,375.81 | $1,375.81 |
| 37 | Removing (item description) 304. loop detector lead-in cable IH 43 ramaps & STH 164 (204.9060.S) | EACH | 1 | $1,375.81 | $1,375.81 | $1,375.81 | $1,375.81 | $1,375.81 | $1,375.81 |
| 38 | Removing (item description) 801. apron endwalls for underdrain reinforced concrete (204.9060.S) | EACH | 424 | $30.00 | $0.01 | $0.01 | $0.01 | $35.00 | $75.00 |
| 39 | Removing (item description) 802. apron endwalls (204.9060.S) | EACH | 2 | $500.00 | $383.00 | $383.00 | $383.00 | $500.00 | $697.00 |
| 40 | Removing (item description) 801. underdrain (204.9090.S) | LF | 135,392 | $1.20 | $0.61 | $0.61 | $0.61 | $1.57 | $1.25 |
| 41 | Excavation common (205.0100) | CY | 418,723 | $20.00 | $11.50 | $11.50 | $11.50 | $19.62 | $12.90 |
| 42 | Temporary emergency pullouts (205.3000.S) | EACH | 4 | $6,229.09 | $4,100.00 | $4,650.00 | $4,650.00 | $6,807.00 | $7,500.00 |
| 43 | Excavation for structures retaining walls (structure) 001. R-67-172 (206.3001) | EACH | 1 | $210,000 | $149,578 | $120,000 | $49,000 | $320,000 | $120,000 |
| 44 | Borrow (208.0100) | CY | 236 | $0.01 | $15.46 | $15.46 | $15.46 | $25.00 | $50.00 |
| 45 | Backfill controlled low strength (209.0200.S) | CY | 2 | $1,000.00 | $600.00 | $600.00 | $600.00 | $600.00 | $600.00 |
| 46 | Backfill granular grade 1 (209.1100) | CY | 342 | $65.00 | $54.00 | $54.00 | $54.00 | $35.00 | $75.00 |
| 47 | Finishing roadway (project) 001. 1090-39-70 (213.0100) | EACH | 1 | $5,000.00 | $2,000.00 | $1,000.00 | $5,000.00 | $5,000.00 | $1,400.00 |
| 48 | Base aggregate dense 3/4-inch (305.0110) | TON | 16,495 | $0.01 | $21.00 | $21.00 | $25.00 | $21.52 | $33.35 |
| 49 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 312,175 | $0.01 | $11.70 | $11.70 | $13.10 | $13.68 | $17.31 |
| 50 | Base aggregate open-graded (310.0110) | TON | 246 | $37.26 | $25.00 | $25.00 | $25.00 | $30.75 | $50.00 |
| 51 | Breaker run (311.0110) | TON | 323,724 | $0.01 | $15.25 | $15.25 | $17.90 | $17.08 | $20.19 |
| 52 | Concrete pavement 8-inch (415.0080) | SY | 252 | $81.95 | $81.95 | $81.00 | $123.23 | $81.95 | $81.95 |
| 53 | Concrete pavement 9-inch (415.0090) | SY | 233 | $88.97 | $88.97 | $83.00 | $101.60 | $88.97 | $88.97 |
| 54 | Concrete pavement approach slab (415.0410) | SY | 1,844 | $188.27 | $188.27 | $181.00 | $202.14 | $188.27 | $188.27 |
| 55 | Rout and seal (415.6000.S) | LF | 162,600 | $0.60 | $0.60 | $0.60 | $0.60 | $0.60 | $0.60 |
| 56 | Drilled tie bars (416.0610) | EACH | 310 | $10.24 | $10.24 | $30.00 | $14.01 | $10.24 | $10.24 |
| 57 | Drilled dowel bars (416.0620) | EACH | 74 | $15.30 | $15.30 | $30.00 | $18.60 | $15.30 | $15.30 |
| 58 | Concrete pavement replacement (416.1720) | SY | 87 | $489.16 | $489.16 | $300.00 | $246.70 | $489.16 | $489.16 |
| 59 | HMA cold weather paving (450.4000) | TON | 7,750 | $1.75 | $1.75 | $1.75 | $1.75 | $1.75 | $1.75 |
| 60 | Tack coat (455.0605) | GAL | 7,605 | $2.25 | $2.25 | $2.25 | $2.25 | $2.25 | $2.25 |
| 61 | Incentive density HMA pavement (460.2000) | DOL | 32,740 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 62 | HMA pavement 3 LT 58-28 S (460.5223) | TON | 25,189 | $64.05 | $64.05 | $64.05 | $64.05 | $64.05 | $64.05 |
| 63 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 26,131 | $64.05 | $64.05 | $64.05 | $64.05 | $64.05 | $64.05 |
| 64 | Asphaltic surface (465.0105) | TON | 414 | $94.00 | $94.00 | $94.00 | $94.00 | $94.00 | $94.00 |
| 65 | Asphaltic surface patching (465.0110) | TON | 41 | $325.00 | $325.00 | $325.00 | $325.00 | $325.00 | $325.00 |
| 66 | Asphaltic surface driveways and field entrances (465.0120) | TON | 18 | $265.00 | $265.00 | $265.00 | $265.00 | $265.00 | $265.00 |
| 67 | Asphaltic surface temporary (465.0125) | TON | 10,494 | $74.75 | $74.75 | $74.75 | $74.75 | $74.75 | $74.75 |
| 68 | Asphaltic curb (465.0310) | LF | 94 | $20.00 | $20.00 | $20.00 | $20.00 | $20.10 | $20.00 |
| 69 | Asphaltic flumes (465.0315) | SY | 52 | $89.50 | $89.50 | $89.50 | $89.50 | $89.50 | $89.50 |
| 70 | Asphaltic rumble strips, shoulder divided roadway (465.0510) | LF | 73,593 | $0.28 | $0.28 | $0.28 | $0.15 | $0.28 | $0.30 |
| 71 | Cold patch (495.1000.S) | TON | 50 | $100.00 | $250.00 | $1.00 | $500.00 | $500.00 | $750.00 |
| 72 | Concrete masonry soldier pile footings (502.0110.S) | CY | 276 | $840.00 | $840.00 | $840.00 | $900.00 | $840.00 | $840.00 |
| 73 | Non-shrink grout (502.0120.S) | CF | 43 | $200.00 | $225.00 | $225.00 | $225.00 | $225.00 | $225.00 |
| 74 | Expansion device (502.3101) | LF | 60 | $430.00 | $340.00 | $340.00 | $340.00 | $340.00 | $340.00 |
| 75 | Protective surface treatment (502.3200) | SY | 2,539 | $4.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 76 | Pigmented surface sealer reseal (502.3205) | SY | 354 | $25.00 | $16.00 | $16.00 | $16.00 | $16.00 | $16.00 |
| 77 | Pigmented surface sealer (502.3210) | SY | 10 | $12.00 | $16.00 | $16.00 | $16.00 | $16.00 | $16.00 |
| 78 | Adhesive anchors no. 5 bar (502.4205) | EACH | 140 | $36.00 | $18.00 | $18.00 | $18.00 | $18.00 | $18.00 |
| 79 | Adhesive anchors no. 6 bar (502.4206) | EACH | 76 | $39.00 | $21.00 | $21.00 | $21.00 | $21.00 | $21.00 |
| 80 | Concrete masonry retaining walls (504.0500) | CY | 210 | $1,500.00 | $1,300.00 | $1,300.00 | $1,300.00 | $1,300.00 | $1,300.00 |
| 81 | Bar steel reinforcement HS coated structures (505.0600) | LB | 30,960 | $1.78 | $1.60 | $1.60 | $1.60 | $1.60 | $1.60 |
| 82 | Bar steel reinforcement HS stainless structures (505.0800.S) | LB | 4,180 | $4.67 | $4.50 | $4.50 | $4.50 | $4.50 | $4.50 |
| 83 | Structural steel HS (506.0605) | LB | 167,290 | $1.88 | $2.50 | $2.50 | $2.16 | $2.50 | $2.50 |
| 84 | Bearing pads elastomeric laminated (506.2610) | EACH | 8 | $2,500.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 |
| 85 | Welded stud shear connectors 7/8X5-inch (506.3010) | EACH | 532 | $12.00 | $12.00 | $12.00 | $12.00 | $12.00 | $12.00 |
| 86 | Removing bearings (structure) 001. B-67-0122 (506.7050.S) | EACH | 8 | $2,000.00 | $3,500.00 | $3,500.00 | $3,500.00 | $3,500.00 | $3,500.00 |
| 87 | Preparation decks type 1 (509.0301) | SY | 221 | $220.00 | $220.00 | $220.00 | $220.00 | $220.00 | $220.00 |
| 88 | Preparation decks type 2 (509.0302) | SY | 88 | $315.00 | $235.00 | $235.00 | $235.00 | $235.00 | $235.00 |
| 89 | Cleaning decks (509.0500) | SY | 1,646 | $27.00 | $24.50 | $24.50 | $24.50 | $24.50 | $24.50 |
| 90 | Cleaning decks to reapply concrete masonry overlay (509.0505.S) | SY | 883 | $15.00 | $8.00 | $8.00 | $8.00 | $8.00 | $8.00 |
| 91 | Joint repair (509.1000) | SY | 36 | $1,500.00 | $3,100.00 | $3,100.00 | $3,100.00 | $3,100.00 | $3,100.00 |
| 92 | Curb repair (509.1200) | LF | 10 | $160.00 | $150.00 | $150.00 | $150.00 | $150.00 | $150.00 |
| 93 | Concrete surface repair (509.1500) | SF | 295 | $240.00 | $180.00 | $180.00 | $180.00 | $180.00 | $180.00 |
| 94 | Full-depth deck repair (509.2000) | SY | 2 | $1,300.00 | $1,200.00 | $1,200.00 | $1,200.00 | $1,200.00 | $1,200.00 |
| 95 | Concrete masonry overlay decks (509.2500) | CY | 245 | $1,300.00 | $1,300.00 | $1,300.00 | $1,300.00 | $1,300.00 | $1,300.00 |
| 96 | Removing concrete masonry deck overlay (structure) 001. B-67-0122 (509.9005.S) | SY | 833 | $13.17 | $13.17 | $13.17 | $13.17 | $13.17 | $13.17 |
| 97 | Removing and resetting tubular railing (structure) 001. B-67-0122 (513.9006.S) | EACH | 1 | $9,500.00 | $15,000 | $15,000 | $15,000 | $15,000 | $15,000 |
| 98 | Rubberized membrane waterproofing (516.0500) | SY | 2 | $60.00 | $40.00 | $40.00 | $40.00 | $40.00 | $40.00 |
| 99 | Painting epoxy system (structure) 001. R-67-172 (517.0601) | EACH | 1 | $20,000 | $46,000 | $46,000 | $23,000 | $46,000 | $46,000 |
| 100 | Preparation and coating of top flanges (structure) 001. B-67-0122 (517.0901.S) | EACH | 1 | $8,500.00 | $5,300.00 | $5,300.00 | $5,300.00 | $5,300.00 | $5,300.00 |
| 101 | Concrete collars for pipe (520.8000) | EACH | 11 | $1,150.00 | $788.00 | $788.00 | $788.00 | $915.00 | $762.00 |
| 102 | Cleaning culvert pipes (520.8700) | EACH | 24 | $1,000.00 | $1,360.00 | $1,360.00 | $1,360.00 | $900.00 | $1,500.00 |
| 103 | Surface drain pipe corrugated metal slotted (inch) 001. 12-inch (521.2005.S) | LF | 995 | $160.00 | $154.00 | $154.00 | $154.00 | $155.95 | $145.00 |
| 104 | Surface drain pipe corrugated metal slotted (inch) 002. 18-inch (521.2005.S) | LF | 1,342 | $170.00 | $126.00 | $126.00 | $126.00 | $163.69 | $175.00 |
| 105 | Culvert pipe reinforced concrete class III 30-inch (522.0130) | LF | 114 | $120.00 | $160.00 | $160.00 | $160.00 | $193.96 | $190.00 |
| 106 | Culvert pipe reinforced concrete class III 42-inch (522.0142) | LF | 533 | $210.00 | $249.00 | $249.00 | $249.00 | $285.51 | $312.00 |
| 107 | Culvert pipe reinforced concrete class IV 24-inch (522.0424) | LF | 1,125 | $90.00 | $124.00 | $124.00 | $124.00 | $125.06 | $126.00 |
| 108 | Culvert pipe reinforced concrete class IV 42-inch (522.0442) | LF | 154 | $210.00 | $233.00 | $233.00 | $233.00 | $248.63 | $285.00 |
| 109 | Culvert pipe reinforced concrete class IV 48-inch (522.0448) | LF | 32 | $350.00 | $370.00 | $370.00 | $370.00 | $317.74 | $506.00 |
| 110 | Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012) | EACH | 4 | $1,600.00 | $1,040.00 | $1,040.00 | $1,040.00 | $853.35 | $1,505.00 |
| 111 | Apron endwalls for culvert pipe reinforced concrete 15-inch (522.1015) | EACH | 4 | $1,650.00 | $1,170.00 | $1,170.00 | $1,170.00 | $958.33 | $1,615.00 |
| 112 | Apron endwalls for culvert pipe reinforced concrete 18-inch (522.1018) | EACH | 9 | $1,750.00 | $1,220.00 | $1,220.00 | $1,220.00 | $1,045.00 | $1,537.00 |
| 113 | Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024) | EACH | 36 | $1,900.00 | $1,530.00 | $1,530.00 | $1,530.00 | $1,293.38 | $1,600.00 |
| 114 | Apron endwalls for culvert pipe reinforced concrete 30-inch (522.1030) | EACH | 7 | $2,100.00 | $2,090.00 | $2,090.00 | $2,090.00 | $1,757.48 | $1,892.00 |
| 115 | Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036) | EACH | 4 | $2,700.00 | $2,720.00 | $2,720.00 | $2,720.00 | $2,193.70 | $2,546.00 |
| 116 | Apron endwalls for culvert pipe reinforced concrete 42-inch (522.1042) | EACH | 8 | $3,300.00 | $3,780.00 | $3,780.00 | $3,780.00 | $2,562.86 | $2,784.00 |
| 117 | Apron endwalls for culvert pipe reinforced concrete 48-inch (522.1048) | EACH | 4 | $3,600.00 | $4,260.00 | $4,260.00 | $4,260.00 | $3,998.93 | $3,140.00 |
| 118 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 24X38-inch (522.2624) | EACH | 2 | $3,400.00 | $1,900.00 | $1,900.00 | $1,900.00 | $1,762.00 | $2,290.00 |
| 119 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 48X76-inch (522.2648) | EACH | 1 | $4,900.00 | $7,450.00 | $7,450.00 | $7,450.00 | $7,242.23 | $4,457.00 |
| 120 | Concrete masonry ancillary structures type NS (531.1100) | CY | 4 | $900.00 | $900.00 | $900.00 | $900.00 | $900.00 | $900.00 |
| 121 | Steel reinforcement HS ancillary structures type NS (531.1140) | LB | 520 | $4.00 | $4.00 | $4.00 | $4.00 | $4.00 | $4.00 |
| 122 | Drilling shaft 24-inch (531.2024) | LF | 22 | $75.00 | $75.00 | $75.00 | $75.00 | $75.00 | $75.00 |
| 123 | Drilling shaft 30-inch (531.2030) | LF | 68 | $150.00 | $150.00 | $150.00 | $150.00 | $150.00 | $150.00 |
| 124 | Drilling shaft 36-inch (531.2036) | LF | 154 | $225.00 | $225.00 | $225.00 | $225.00 | $225.00 | $225.00 |
| 125 | Drilling shaft 42-inch (531.2042) | LF | 118 | $250.00 | $250.00 | $250.00 | $250.00 | $250.00 | $250.00 |
| 126 | Drilling shaft 48-inch (531.2048) | LF | 28 | $275.00 | $275.00 | $275.00 | $275.00 | $275.00 | $275.00 |
| 127 | Foundation camera pole 50-FT (531.4050) | EACH | 1 | $8,100.00 | $8,100.00 | $8,100.00 | $8,100.00 | $8,100.00 | $8,100.00 |
| 128 | Foundation single-shaft type TC-IV (structure) 001. S-67-993 (531.5340) | EACH | 1 | $18,690 | $18,690 | $18,690 | $18,690 | $18,690 | $18,690 |
| 129 | Foundation single-shaft type TF-I (structure) 001. S-67-325 (531.5410) | EACH | 1 | $9,590.00 | $9,590.00 | $9,590.00 | $9,590.00 | $9,590.00 | $9,590.00 |
| 130 | Foundation single-shaft type TF-I (structure) 002. S-67-989 (531.5410) | EACH | 1 | $9,590.00 | $9,590.00 | $9,590.00 | $9,590.00 | $9,590.00 | $9,590.00 |
| 131 | Foundation single-shaft type TF-II (structure) 001. S-67-988 (531.5420) | EACH | 1 | $15,800 | $15,800 | $15,800 | $15,800 | $15,800 | $15,800 |
| 132 | Foundation single-shaft type TF-II (structure) 002. S-67-992 (531.5420) | EACH | 1 | $15,800 | $15,800 | $15,800 | $15,800 | $15,800 | $15,800 |
| 133 | Foundation single-shaft type TF-III (structure) 001. S-67-324 (531.5430) | EACH | 1 | $18,120 | $18,120 | $18,120 | $18,120 | $18,120 | $18,120 |
| 134 | Foundation single-shaft type TF-III (structure) 002. S-67-990 (531.5430) | EACH | 1 | $18,120 | $18,120 | $18,120 | $18,120 | $18,120 | $18,120 |
| 135 | Foundation single-shaft type TF-IV (structure) 001. S-67-991 (531.5440) | EACH | 1 | $23,940 | $23,940 | $23,940 | $23,940 | $23,940 | $23,940 |
| 136 | Foundation two-shaft type FC-I (structure) 001. S-67-322 (531.6010) | EACH | 1 | $24,115 | $24,115 | $24,115 | $24,115 | $24,115 | $24,115 |
| 137 | Foundation two-shaft type FC-I (structure) 002. S-67-323 (531.6010) | EACH | 1 | $24,115 | $24,115 | $24,115 | $24,115 | $24,115 | $24,115 |
| 138 | Truss cantilever 2-chord type IV (structure) 001. S-67-993 (532.5340) | EACH | 1 | $37,000 | $37,000 | $37,000 | $37,000 | $37,000 | $37,000 |
| 139 | Truss full span 2-chord type I (structure) 001. S-67-325 (532.5410) | EACH | 1 | $62,000 | $62,000 | $62,000 | $62,000 | $62,000 | $62,000 |
| 140 | Truss full span 2-chord type I (structure) 002. S-67-989 (532.5410) | EACH | 1 | $49,000 | $49,000 | $49,000 | $49,000 | $49,000 | $49,000 |
| 141 | Truss full span 2-chord type II (structure) 001. S-67-988 (532.5420) | EACH | 1 | $74,000 | $74,000 | $74,000 | $74,000 | $74,000 | $74,000 |
| 142 | Truss full span 2-chord type II (structure) 002. S-67-992 (532.5420) | EACH | 1 | $65,000 | $65,000 | $65,000 | $65,000 | $65,000 | $65,000 |
| 143 | Truss full span 2-chord type III (structure) 001. S-67-324 (532.5430) | EACH | 1 | $88,000 | $88,000 | $88,000 | $88,000 | $88,000 | $88,000 |
| 144 | Truss full span 2-chord type III (structure) 002. S-67-990 (532.5430) | EACH | 1 | $89,000 | $89,000 | $89,000 | $89,000 | $89,000 | $89,000 |
| 145 | Truss full span 2-chord type IV (structure) 001. S-67-991 (532.5440) | EACH | 1 | $85,000 | $85,000 | $85,000 | $85,000 | $85,000 | $85,000 |
| 146 | Truss cantilever 4-chord type I (structure) 001. S-67-322 (532.6010) | EACH | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 147 | Truss cantilever 4-chord type I (structure) 002. S-67-323 (532.6010) | EACH | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 148 | Concrete curb & gutter 30-inch type A (601.0409) | LF | 7,816 | $22.00 | $22.00 | $30.00 | $22.00 | $22.00 | $22.00 |
| 149 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 126 | $30.00 | $30.00 | $60.00 | $30.00 | $30.00 | $30.00 |
| 150 | Concrete curb & gutter 4-inch sloped 36-inch type A (601.0551) | LF | 455 | $26.00 | $26.00 | $60.00 | $26.00 | $26.00 | $26.00 |
| 151 | Concrete curb & gutter 6-inch sloped 36-inch type A (601.0555) | LF | 5,114 | $27.00 | $27.00 | $32.00 | $27.00 | $27.00 | $27.00 |
| 152 | Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557) | LF | 494 | $27.00 | $27.00 | $60.00 | $27.00 | $27.00 | $27.00 |
| 153 | Concrete curb & gutter 4-inch sloped 36-inch type TBT (601.0588) | LF | 1,400 | $30.00 | $30.00 | $32.00 | $30.00 | $30.00 | $30.00 |
| 154 | Concrete curb & gutter 4-inch sloped 36-inch type TBTT (601.0590) | LF | 375 | $30.00 | $30.00 | $60.00 | $30.00 | $30.00 | $30.00 |
| 155 | Concrete curb pedestrian (601.0600) | LF | 26 | $45.00 | $45.00 | $100.00 | $45.00 | $45.00 | $45.00 |
| 156 | Concrete sidewalk 5-inch (602.0410) | SF | 22,106 | $9.00 | $9.00 | $6.86 | $9.00 | $9.00 | $9.00 |
| 157 | Curb ramp detectable warning field yellow (602.0505) | SF | 216 | $45.00 | $45.00 | $50.00 | $45.00 | $45.00 | $45.00 |
| 158 | Concrete surface drains (602.3010) | CY | 54 | $1,100.00 | $1,100.00 | $1,000.00 | $1,100.00 | $1,100.00 | $1,100.00 |
| 159 | Concrete rumble strips, shoulder divided roadway (602.3210) | LF | 67,860 | $0.67 | $0.67 | $0.67 | $0.75 | $0.67 | $0.70 |
| 160 | Concrete barrier type S42 (603.1142) | LF | 8,452 | $103.00 | $103.00 | $97.00 | $96.68 | $103.00 | $103.00 |
| 161 | Concrete barrier transition type F32SF to S36 (603.3213) | EACH | 24 | $8,000.00 | $8,000.00 | $10,000 | $6,060.01 | $8,000.00 | $8,000.00 |
| 162 | Concrete barrier transition type F42SF to S42 (603.3255) | EACH | 4 | $8,000.00 | $8,000.00 | $10,000 | $9,316.17 | $8,000.00 | $8,000.00 |
| 163 | Concrete barrier transition type S36 to S42 (603.3535) | EACH | 24 | $8,000.00 | $8,000.00 | $10,000 | $4,945.71 | $8,000.00 | $8,000.00 |
| 164 | Concrete barrier temporary precast delivered (603.8000) | LF | 83,648 | $9.00 | $8.50 | $8.09 | $8.50 | $8.50 | $8.50 |
| 165 | Concrete barrier temporary precast installed (603.8125) | LF | 85,328 | $4.00 | $4.00 | $4.00 | $4.00 | $4.00 | $4.00 |
| 166 | Anchoring concrete barrier temporary precast (603.8500) | LF | 1,500 | $12.00 | $5.50 | $20.00 | $5.50 | $5.50 | $5.50 |
| 167 | Slope paving crushed aggregate (604.0500) | SY | 931 | $23.00 | $23.00 | $23.00 | $23.00 | $23.00 | $23.00 |
| 168 | Slope paving select crushed material (604.0600) | SY | 16 | $40.00 | $40.00 | $40.00 | $40.00 | $40.00 | $40.00 |
| 169 | Slope paving repair crushed aggregate (604.9010.S) | CY | 22 | $200.00 | $200.00 | $200.00 | $200.00 | $200.00 | $200.00 |
| 170 | Reseal crushed aggregate slope paving (604.9015.S) | SY | 6,259 | $18.00 | $18.00 | $18.00 | $16.50 | $16.50 | $16.50 |
| 171 | Riprap extra-light (606.0050) | CY | 59 | $210.00 | $85.50 | $85.50 | $85.50 | $147.00 | $196.00 |
| 172 | Riprap light (606.0100) | CY | 117 | $210.00 | $130.00 | $130.00 | $130.00 | $130.00 | $165.00 |
| 173 | Riprap medium (606.0200) | CY | 233 | $210.00 | $133.00 | $133.00 | $133.00 | $125.00 | $174.00 |
| 174 | Storm sewer pipe reinforced concrete class III 12-inch (608.0312) | LF | 1,004 | $64.00 | $99.00 | $99.00 | $99.00 | $78.97 | $90.00 |
| 175 | Storm sewer pipe reinforced concrete class III 15-inch (608.0315) | LF | 715 | $66.00 | $100.00 | $100.00 | $100.00 | $73.67 | $88.00 |
| 176 | Storm sewer pipe reinforced concrete class III 18-inch (608.0318) | LF | 698 | $68.00 | $113.00 | $113.00 | $113.00 | $83.27 | $101.00 |
| 177 | Storm sewer pipe reinforced concrete class III 24-inch (608.0324) | LF | 908 | $82.00 | $135.00 | $135.00 | $135.00 | $120.81 | $118.00 |
| 178 | Storm sewer pipe reinforced concrete class III 30-inch (608.0330) | LF | 85 | $150.00 | $150.00 | $150.00 | $150.00 | $118.28 | $139.00 |
| 179 | Storm sewer pipe reinforced concrete class III 36-inch (608.0336) | LF | 147 | $176.00 | $194.00 | $194.00 | $194.00 | $176.24 | $191.00 |
| 180 | Storm sewer pipe reinforced concrete class III 42-inch (608.0342) | LF | 390 | $218.00 | $312.00 | $312.00 | $312.00 | $334.30 | $336.00 |
| 181 | Storm sewer pipe reinforced concrete class IV 12-inch (608.0412) | LF | 753 | $64.00 | $88.00 | $88.00 | $88.00 | $75.90 | $80.00 |
| 182 | Storm sewer pipe reinforced concrete class IV 15-inch (608.0415) | LF | 317 | $66.00 | $98.00 | $98.00 | $98.00 | $80.68 | $84.00 |
| 183 | Storm sewer pipe reinforced concrete class IV 18-inch (608.0418) | LF | 576 | $68.00 | $97.00 | $97.00 | $97.00 | $89.07 | $87.00 |
| 184 | Storm sewer pipe reinforced concrete class IV 24-inch (608.0424) | LF | 801 | $90.00 | $125.00 | $125.00 | $125.00 | $107.21 | $112.00 |
| 185 | Storm sewer pipe reinforced concrete class IV 30-inch (608.0430) | LF | 564 | $122.00 | $161.00 | $161.00 | $161.00 | $121.55 | $165.00 |
| 186 | Storm sewer pipe reinforced concrete class IV 36-inch (608.0436) | LF | 424 | $186.00 | $386.00 | $386.00 | $386.00 | $438.62 | $335.00 |
| 187 | Storm sewer pipe reinforced concrete class IV 48-inch (608.0448) | LF | 425 | $300.00 | $525.00 | $525.00 | $525.00 | $514.72 | $404.00 |
| 188 | Storm sewer pipe reinforced concrete class V 12-inch (608.0512) | LF | 333 | $64.00 | $85.00 | $85.00 | $85.00 | $71.48 | $87.00 |
| 189 | Storm sewer pipe reinforced concrete class V 18-inch (608.0518) | LF | 217 | $72.00 | $98.00 | $98.00 | $98.00 | $90.41 | $112.00 |
| 190 | Storm sewer pipe reinforced concrete horizontal elliptical class HE-IV 24X38-inch (608.2424) | LF | 435 | $166.00 | $236.00 | $236.00 | $236.00 | $206.62 | $208.00 |
| 191 | Reconstructing inlets (611.0430) | EACH | 9 | $1,750.00 | $648.00 | $648.00 | $648.00 | $2,866.06 | $1,303.00 |
| 192 | Manhole covers type J (611.0530) | EACH | 10 | $730.00 | $744.00 | $744.00 | $744.00 | $1,205.39 | $818.00 |
| 193 | Manhole covers type L (611.0545) | EACH | 2 | $700.00 | $738.00 | $738.00 | $738.00 | $1,157.79 | $689.00 |
| 194 | Inlet covers type B (611.0606) | EACH | 11 | $900.00 | $900.00 | $900.00 | $900.00 | $1,373.39 | $1,109.00 |
| 195 | Inlet covers type C (611.0612) | EACH | 5 | $750.00 | $723.00 | $723.00 | $723.00 | $1,205.39 | $842.00 |
| 196 | Inlet covers type H (611.0624) | EACH | 23 | $1,000.00 | $993.00 | $993.00 | $993.00 | $1,610.12 | $1,066.00 |
| 197 | Inlet covers type HM (611.0627) | EACH | 39 | $1,000.00 | $993.00 | $993.00 | $993.00 | $1,610.12 | $1,066.00 |
| 198 | Inlet covers type MS (611.0642) | EACH | 30 | $780.00 | $543.00 | $543.00 | $543.00 | $588.00 | $628.00 |
| 199 | Inlet covers type S (611.0651) | EACH | 7 | $1,200.00 | $1,120.00 | $1,120.00 | $1,120.00 | $1,782.32 | $1,061.00 |
| 200 | Catch basins 5-FT diameter (611.1005) | EACH | 12 | $4,500.00 | $3,460.00 | $3,460.00 | $3,460.00 | $3,531.65 | $4,588.00 |
| 201 | Catch basins 6-FT diameter (611.1006) | EACH | 5 | $6,750.00 | $6,030.00 | $6,030.00 | $6,030.00 | $5,874.29 | $6,429.00 |
| 202 | Manholes 4-FT diameter (611.2004) | EACH | 2 | $2,600.00 | $2,020.00 | $2,020.00 | $2,020.00 | $2,125.95 | $2,763.00 |
| 203 | Manholes 5-FT diameter (611.2005) | EACH | 3 | $6,100.00 | $4,650.00 | $4,650.00 | $4,650.00 | $4,599.78 | $5,454.00 |
| 204 | Manholes 10-FT diameter (611.2010) | EACH | 4 | $25,000 | $20,500 | $20,500 | $20,500 | $17,995 | $20,042 |
| 205 | Inlets 3-FT diameter (611.3003) | EACH | 2 | $1,900.00 | $1,560.00 | $1,560.00 | $1,560.00 | $1,551.26 | $1,857.00 |
| 206 | Inlets 4-FT diameter (611.3004) | EACH | 38 | $2,500.00 | $2,050.00 | $2,050.00 | $2,050.00 | $2,098.08 | $2,238.00 |
| 207 | Inlets 2X2-FT (611.3220) | EACH | 4 | $1,600.00 | $1,410.00 | $1,410.00 | $1,410.00 | $1,592.49 | $1,520.00 |
| 208 | Inlets 2X3-FT (611.3230) | EACH | 21 | $1,900.00 | $1,570.00 | $1,570.00 | $1,570.00 | $1,761.53 | $1,649.00 |
| 209 | Inlets median 1 grate (611.3901) | EACH | 2 | $3,400.00 | $2,060.00 | $2,060.00 | $2,060.00 | $1,580.53 | $2,310.00 |
| 210 | Inlets median 2 grate (611.3902) | EACH | 14 | $5,200.00 | $4,190.00 | $4,190.00 | $4,190.00 | $3,698.74 | $3,832.00 |
| 211 | Adjusting manhole covers (611.8110) | EACH | 1 | $600.00 | $471.00 | $471.00 | $471.00 | $660.79 | $709.00 |
| 212 | Adjusting inlet covers (611.8115) | EACH | 65 | $600.00 | $361.00 | $361.00 | $361.00 | $774.32 | $709.00 |
| 213 | Cover plates temporary (611.8120.S) | EACH | 18 | $210.00 | $99.00 | $99.00 | $99.00 | $200.00 | $254.00 |
| 214 | Pipe underdrain 6-inch (612.0106) | LF | 3,290 | $10.00 | $9.80 | $9.80 | $9.80 | $10.88 | $18.00 |
| 215 | Pipe underdrain unperforated 6- inch (612.0206) | LF | 200 | $10.00 | $13.00 | $13.00 | $13.00 | $18.00 | $50.00 |
| 216 | Pipe underdrain unperforated 12- inch (612.0212) | LF | 526 | $15.00 | $27.50 | $27.50 | $27.50 | $32.31 | $35.00 |
| 217 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 15 | $22.00 | $20.00 | $20.00 | $20.00 | $66.00 | $75.00 |
| 218 | Drain tile exploration (612.0700) | LF | 40 | $16.00 | $20.00 | $20.00 | $20.00 | $100.00 | $50.00 |
| 219 | Apron endwalls for underdrain reinforced concrete 6-inch (612.0806) | EACH | 4 | $450.00 | $310.00 | $310.00 | $310.00 | $615.00 | $412.00 |
| 220 | Steel thrie beam bullnose terminal (614.0220) | EACH | 2 | $15,000 | $15,000 | $15,000 | $15,000 | $15,000 | $15,000 |
| 221 | Steel thrie beam (614.0230) | LF | 175 | $38.00 | $38.00 | $38.00 | $38.00 | $38.00 | $38.00 |
| 222 | Guardrail mow strip emulsified asphalt (614.0397) | SY | 3,309 | $18.00 | $18.00 | $18.00 | $11.75 | $11.75 | $11.75 |
| 223 | Crash cushions temporary (614.0905) | EACH | 8 | $4,500.00 | $4,500.00 | $4,500.00 | $4,750.00 | $4,500.00 | $7,000.00 |
| 224 | MGS guardrail temporary thrie beam transition (614.1100) | LF | 400 | $80.00 | $80.00 | $80.00 | $80.00 | $80.00 | $80.00 |
| 225 | MGS guardrail temporary terminal eat (614.1200) | EACH | 10 | $3,400.00 | $3,400.00 | $3,400.00 | $3,400.00 | $3,400.00 | $3,400.00 |
| 226 | MGS guardrail 3 (614.2300) | LF | 2,420 | $30.00 | $30.00 | $30.00 | $30.00 | $30.00 | $30.00 |
| 227 | MGS thrie beam transition (614.2500) | LF | 1,050 | $90.00 | $90.00 | $90.00 | $90.00 | $90.00 | $90.00 |
| 228 | MGS guardrail terminal eat (614.2610) | EACH | 29 | $4,000.00 | $4,000.00 | $4,000.00 | $4,000.00 | $4,000.00 | $4,000.00 |
| 229 | MGS guardrail terminal type 2 (614.2620) | EACH | 8 | $2,600.00 | $2,600.00 | $2,600.00 | $2,600.00 | $2,600.00 | $2,600.00 |
| 230 | Fence woven wire (height) 001. 4-FT (616.0100) | LF | 2,514 | $8.00 | $8.00 | $8.00 | $8.00 | $8.00 | $8.00 |
| 231 | Fence woven wire (height) 002. 5-FT (616.0100) | LF | 130 | $18.00 | $18.00 | $18.00 | $18.00 | $18.00 | $18.00 |
| 232 | Fence chain link 4-FT (616.0204) | LF | 541 | $38.00 | $38.00 | $38.00 | $38.00 | $38.00 | $38.00 |
| 233 | Maintenance and repair of haul roads (project) 001. 1090-39-70 (618.0100) | EACH | 1 | $100.00 | $1.00 | $1.00 | $1.00 | $1,500.00 | $100.00 |
| 234 | Mobilization (619.1000) | EACH | 1 | $2,697,628 | $2,328,968 | $3,505,000 | $4,003,621 | $2,084,800 | $3,962,179 |
| 235 | Concrete median sloped nose (620.0300) | SF | 971 | $16.00 | $16.00 | $20.00 | $16.00 | $16.00 | $16.00 |
| 236 | Water (624.0100) | MGAL | 225 | $120.00 | $100.00 | $100.00 | $100.00 | $65.00 | $100.00 |
| 237 | Salvaged topsoil (625.0500) | SY | 511,879 | $0.01 | $1.20 | $1.20 | $1.20 | $1.43 | $0.01 |
| 238 | Mulching (627.0200) | SY | 41,151 | $0.32 | $0.32 | $0.32 | $0.32 | $0.32 | $0.32 |
| 239 | Erosion bales (628.1104) | EACH | 3,087 | $11.00 | $11.00 | $11.00 | $11.00 | $11.00 | $11.00 |
| 240 | Silt fence (628.1504) | LF | 16,863 | $1.90 | $1.90 | $1.90 | $1.90 | $1.90 | $1.90 |
| 241 | Silt fence maintenance (628.1520) | LF | 16,863 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 242 | Mobilizations erosion control (628.1905) | EACH | 19 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 243 | Mobilizations emergency erosion control (628.1910) | EACH | 22 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 244 | Erosion mat class I type B (628.2004) | SY | 453,634 | $0.95 | $0.95 | $0.95 | $0.95 | $0.95 | $0.95 |
| 245 | Erosion mat urban class I type B (628.2008) | SY | 60,796 | $1.55 | $1.55 | $1.55 | $1.55 | $1.55 | $1.55 |
| 246 | Soil stabilizer type A (628.6505) | ACRE | 4.15 | $2,450.00 | $2,450.00 | $2,450.00 | $2,450.00 | $2,450.00 | $2,450.00 |
| 247 | Soil stabilizer type B (628.6510) | ACRE | 4.57 | $800.00 | $800.00 | $800.00 | $800.00 | $800.00 | $800.00 |
| 248 | Inlet protection type A (628.7005) | EACH | 94 | $70.00 | $70.00 | $70.00 | $70.00 | $70.00 | $70.00 |
| 249 | Inlet protection type B (628.7010) | EACH | 147 | $70.00 | $70.00 | $70.00 | $70.00 | $70.00 | $70.00 |
| 250 | Inlet protection type C (628.7015) | EACH | 59 | $70.00 | $70.00 | $70.00 | $70.00 | $70.00 | $70.00 |
| 251 | Inlet protection type D (628.7020) | EACH | 31 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 252 | Temporary ditch checks (628.7504) | LF | 3,863 | $7.75 | $7.75 | $7.75 | $7.75 | $7.75 | $7.75 |
| 253 | Culvert pipe checks (628.7555) | EACH | 379 | $18.00 | $18.00 | $18.00 | $18.00 | $18.00 | $18.00 |
| 254 | Tracking pads (628.7560) | EACH | 16 | $100.00 | $100.00 | $100.00 | $100.00 | $1,605.00 | $3,000.00 |
| 255 | Rock bags (628.7570) | EACH | 150 | $18.00 | $18.00 | $18.00 | $18.00 | $18.00 | $18.00 |
| 256 | Fertilizer type B (629.0210) | CWT | 301 | $80.00 | $80.00 | $80.00 | $80.00 | $80.00 | $80.00 |
| 257 | Seeding mixture no. 10 (630.0110) | LB | 1,384 | $8.00 | $8.00 | $8.00 | $8.00 | $8.00 | $8.00 |
| 258 | Seeding mixture no. 30 (630.0130) | LB | 20,412 | $7.75 | $7.75 | $7.75 | $7.75 | $7.75 | $7.75 |
| 259 | Seeding mixture no. 75 (630.0175) | LB | 78 | $55.00 | $55.00 | $55.00 | $55.00 | $55.00 | $55.00 |
| 260 | Seeding mixture no. 80 (630.0180) | LB | 114 | $55.00 | $55.00 | $55.00 | $55.00 | $55.00 | $55.00 |
| 261 | Seeding temporary (630.0200) | LB | 1,111 | $3.90 | $3.90 | $3.90 | $3.90 | $3.90 | $3.90 |
| 262 | Seed water (630.0500) | MGAL | 11,551 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 263 | Delineator posts steel (633.0100) | EACH | 276 | $34.00 | $34.00 | $34.00 | $34.00 | $34.00 | $34.00 |
| 264 | Delineator reflectors (633.0500) | EACH | 369 | $7.00 | $7.00 | $7.00 | $7.00 | $7.00 | $7.00 |
| 265 | Delineators temporary (633.1100) | EACH | 209 | $30.00 | $35.00 | $30.00 | $24.00 | $30.00 | $30.00 |
| 266 | Markers culvert end (633.5200) | EACH | 102 | $65.00 | $65.00 | $65.00 | $65.00 | $65.00 | $65.00 |
| 267 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 75 | $95.00 | $95.00 | $95.00 | $95.00 | $95.00 | $95.00 |
| 268 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 124 | $102.00 | $102.00 | $102.00 | $102.00 | $102.00 | $102.00 |
| 269 | Posts wood 4X6-inch X 22-FT (634.0622) | EACH | 182 | $115.00 | $115.00 | $115.00 | $115.00 | $115.00 | $115.00 |
| 270 | Posts tubular steel 2X2-inch X 9.5- FT (634.0809) | EACH | 2 | $175.00 | $175.00 | $175.00 | $175.00 | $175.00 | $175.00 |
| 271 | Sign supports structural steel HS (635.0200) | LB | 1,080 | $4.00 | $4.00 | $4.00 | $4.00 | $4.00 | $4.00 |
| 272 | Sign supports replacing base connection bolts (635.0300) | EACH | 14 | $250.00 | $250.00 | $250.00 | $250.00 | $250.00 | $250.00 |
| 273 | Foundation drilling (diameter) 001. 30-inch diameter (636.0050.S) | LF | 759 | $5.00 | $5.00 | $5.00 | $210.00 | $5.00 | $5.00 |
| 274 | Foundation drilling (diameter) 002. 36-inch diameter (636.0050.S) | LF | 1,086 | $5.00 | $5.00 | $5.00 | $177.00 | $5.00 | $5.00 |
| 275 | Signs type I reflective SH (637.1220) | SF | 2,915 | $27.00 | $27.00 | $27.00 | $27.00 | $27.00 | $27.00 |
| 276 | Signs type II reflective H (637.2210) | SF | 2,863 | $19.00 | $19.00 | $19.00 | $19.00 | $19.00 | $19.00 |
| 277 | Signs type II reflective H folding (637.2215) | SF | 159 | $26.00 | $26.00 | $26.00 | $26.00 | $26.00 | $26.00 |
| 278 | Signs type II reflective F (637.2230) | SF | 700 | $20.00 | $20.00 | $20.00 | $20.00 | $20.00 | $20.00 |
| 279 | Moving signs type II (638.2102) | EACH | 1 | $225.00 | $225.00 | $225.00 | $225.00 | $225.00 | $225.00 |
| 280 | Removing signs type I (638.2601) | EACH | 11 | $400.00 | $400.00 | $400.00 | $400.00 | $400.00 | $400.00 |
| 281 | Removing signs type II (638.2602) | EACH | 280 | $30.00 | $30.00 | $30.00 | $30.00 | $30.00 | $30.00 |
| 282 | Removing small sign supports (638.3000) | EACH | 275 | $30.00 | $30.00 | $30.00 | $30.00 | $30.00 | $30.00 |
| 283 | Removing structural steel sign supports (638.3100) | EACH | 10 | $400.00 | $400.00 | $400.00 | $400.00 | $400.00 | $400.00 |
| 284 | Moving small sign supports (638.4000) | EACH | 149 | $200.00 | $200.00 | $200.00 | $200.00 | $200.00 | $200.00 |
| 285 | Moving structural steel sign supports (638.4100) | EACH | 1 | $750.00 | $750.00 | $750.00 | $750.00 | $750.00 | $750.00 |
| 286 | Traffic control drums (643.0300) | DAY | 315,478 | $0.11 | $0.11 | $0.11 | $0.14 | $0.11 | $0.11 |
| 287 | Digital speed reduction system (DSRS) (643.0370.S) | DAY | 76 | $141.00 | $141.00 | $141.00 | $250.00 | $141.00 | $141.00 |
| 288 | Traffic control barricades type III (643.0420) | DAY | 33,009 | $0.40 | $0.40 | $0.40 | $0.55 | $0.40 | $0.40 |
| 289 | Traffic control flexible tubular marker posts (643.0500) | EACH | 502 | $36.00 | $36.00 | $36.00 | $34.50 | $36.00 | $36.00 |
| 290 | Traffic control flexible tubular marker bases (643.0600) | EACH | 502 | $5.00 | $5.00 | $5.00 | $12.50 | $5.00 | $5.00 |
| 291 | Traffic control warning lights type A (643.0705) | DAY | 65,886 | $0.04 | $0.04 | $0.04 | $0.10 | $0.04 | $0.04 |
| 292 | Traffic control warning lights type C (643.0715) | DAY | 42,532 | $0.04 | $0.04 | $0.04 | $0.10 | $0.04 | $0.04 |
| 293 | Traffic control connected arrow boards (643.0810) | DAY | 1,071 | $7.00 | $7.00 | $7.00 | $11.25 | $7.00 | $7.00 |
| 294 | Traffic control signs (643.0900) | DAY | 145,114 | $0.41 | $0.41 | $0.41 | $0.17 | $0.41 | $0.41 |
| 295 | Traffic control covering signs type II (643.0920) | EACH | 390 | $40.00 | $40.00 | $40.00 | $85.00 | $40.00 | $40.00 |
| 296 | Traffic control signs fixed message (643.1000) | SF | 760 | $40.00 | $40.00 | $40.00 | $29.75 | $40.00 | $40.00 |
| 297 | Traffic control signs PCMS (643.1050) | DAY | 539 | $30.00 | $30.00 | $30.00 | $24.25 | $30.00 | $30.00 |
| 298 | Dynamic late merge system (643.1100.S) | DAY | 416 | $108.00 | $108.00 | $108.00 | $145.00 | $108.00 | $108.00 |
| 299 | Basic traffic queue warning system (643.1205.S) | DAY | 216 | $60.00 | $60.00 | $60.00 | $95.00 | $60.00 | $60.00 |
| 300 | Traffic control connected work zone start and end location markers (643.1220) | DAY | 1,555 | $1.52 | $1.52 | $1.52 | $7.00 | $1.52 | $1.52 |
| 301 | Temporary marking line epoxy 6- inch (643.3170) | LF | 561,648 | $0.65 | $0.65 | $0.65 | $0.95 | $0.65 | $0.65 |
| 302 | Temporary marking line epoxy 10- inch (643.3270) | LF | 10,736 | $1.40 | $1.40 | $1.40 | $2.22 | $1.40 | $1.40 |
| 303 | Temporary marking raised pavement marker type I (643.3760) | EACH | 653 | $5.60 | $5.60 | $5.60 | $5.50 | $5.60 | $5.60 |
| 304 | Temporary marking stop line epoxy 18-inch (643.3820) | LF | 368 | $9.00 | $9.00 | $9.00 | $14.38 | $9.00 | $9.00 |
| 305 | Traffic control (643.5000) | EACH | 1 | $377,120 | $377,120 | $377,120 | $315,500 | $377,120 | $377,120 |
| 306 | Geotextile type DF schedule A (645.0111) | SY | 1,829 | $4.00 | $0.70 | $0.70 | $0.70 | $2.50 | $3.25 |
| 307 | Geotextile type HR (645.0120) | SY | 761 | $5.50 | $4.30 | $4.30 | $4.30 | $2.50 | $6.00 |
| 308 | Geotextile type R (645.0130) | SY | 847 | $4.50 | $3.80 | $3.80 | $3.80 | $2.50 | $5.50 |
| 309 | Geogrid type SR (645.0220) | SY | 482,411 | $1.50 | $0.94 | $0.94 | $1.40 | $0.80 | $1.00 |
| 310 | Marking line epoxy 4-inch (646.1020) | LF | 2,572 | $1.00 | $1.00 | $1.00 | $0.32 | $1.00 | $1.00 |
| 311 | Marking line epoxy 6-inch (646.2020) | LF | 5,947 | $1.50 | $1.50 | $1.50 | $0.44 | $1.50 | $1.50 |
| 312 | Marking line grooved black epoxy 6-inch (646.2025) | LF | 22,630 | $1.20 | $1.20 | $1.20 | $0.78 | $1.20 | $1.20 |
| 313 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 225,710 | $1.40 | $1.40 | $1.40 | $1.13 | $1.40 | $1.40 |
| 314 | Marking line epoxy 8-inch (646.3020) | LF | 86 | $1.95 | $1.95 | $1.95 | $0.85 | $1.95 | $1.95 |
| 315 | Marking line grooved black epoxy 10-inch (646.4025) | LF | 2,419 | $2.65 | $2.65 | $2.65 | $1.73 | $2.65 | $2.65 |
| 316 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 12,467 | $3.10 | $3.10 | $3.10 | $2.56 | $3.10 | $3.10 |
| 317 | Marking arrow epoxy (646.5020) | EACH | 65 | $230.00 | $230.00 | $230.00 | $232.23 | $230.00 | $230.00 |
| 318 | Marking word epoxy (646.5120) | EACH | 17 | $250.00 | $250.00 | $250.00 | $346.83 | $250.00 | $250.00 |
| 319 | Marking symbol epoxy (646.5220) | EACH | 3 | $300.00 | $300.00 | $300.00 | $332.30 | $300.00 | $300.00 |
| 320 | Marking aerial enforcement bar epoxy (646.5420) | EACH | 20 | $320.00 | $320.00 | $320.00 | $340.17 | $320.00 | $320.00 |
| 321 | Marking stop line epoxy 18-inch (646.6120) | LF | 521 | $12.00 | $12.00 | $12.00 | $14.38 | $12.00 | $12.00 |
| 322 | Marking yield line epoxy 18-inch (646.6220) | EACH | 18 | $45.00 | $45.00 | $45.00 | $34.32 | $45.00 | $45.00 |
| 323 | Marking diagonal epoxy 12-inch (646.7120) | LF | 8,377 | $11.00 | $11.00 | $11.00 | $11.79 | $11.00 | $11.00 |
| 324 | Marking chevron epoxy 24-inch (646.7220) | LF | 325 | $14.00 | $14.00 | $14.00 | $23.59 | $14.00 | $14.00 |
| 325 | Marking chevron epoxy 12-inch (646.7320) | LF | 367 | $13.00 | $13.00 | $13.00 | $22.81 | $13.00 | $13.00 |
| 326 | Marking curb epoxy (646.8120) | LF | 157 | $8.00 | $8.00 | $8.00 | $6.87 | $8.00 | $8.00 |
| 327 | Marking island nose epoxy (646.8220) | EACH | 13 | $300.00 | $300.00 | $300.00 | $258.87 | $300.00 | $300.00 |
| 328 | Marking parking stall epoxy (646.8320) | LF | 2,028 | $7.00 | $7.00 | $7.00 | $21.19 | $7.00 | $7.00 |
| 329 | Marking removal line 4-inch (646.9000) | LF | 45,116 | $0.45 | $0.45 | $0.45 | $0.29 | $0.45 | $0.45 |
| 330 | Marking removal line 8-inch (646.9100) | LF | 82 | $0.65 | $0.65 | $0.65 | $2.00 | $0.65 | $0.65 |
| 331 | Conduit rigid metallic 2-inch (652.0125) | LF | 15 | $164.93 | $164.93 | $164.93 | $164.93 | $164.93 | $164.93 |
| 332 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 10,317 | $6.86 | $6.86 | $6.86 | $6.86 | $6.86 | $6.86 |
| 333 | Conduit rigid nonmetallic schedule 40 3-inch (652.0235) | LF | 2,252 | $8.74 | $8.74 | $8.74 | $8.74 | $8.74 | $8.74 |
| 334 | Conduit special 2-inch (652.0605) | LF | 480 | $17.74 | $17.74 | $17.74 | $17.74 | $17.74 | $17.74 |
| 335 | Conduit special 3-inch (652.0615) | LF | 2,065 | $26.18 | $26.18 | $26.18 | $26.18 | $26.18 | $26.18 |
| 336 | Install conduit into existing item (652.0700.S) | EACH | 2 | $687.91 | $687.91 | $687.91 | $687.91 | $687.91 | $687.91 |
| 337 | Conduit loop detector (652.0800) | LF | 4,817 | $6.31 | $6.31 | $6.31 | $6.31 | $6.31 | $6.31 |
| 338 | Pull boxes steel 24X36-inch (653.0135) | EACH | 21 | $1,349.03 | $1,349.03 | $1,349.03 | $1,349.03 | $1,349.03 | $1,349.03 |
| 339 | Pull boxes steel 24X42-inch (653.0140) | EACH | 60 | $1,461.99 | $1,461.99 | $1,461.99 | $1,461.99 | $1,461.99 | $1,461.99 |
| 340 | Junction boxes 18X12X6-inch (653.0222) | EACH | 2 | $2,153.84 | $2,153.84 | $2,153.84 | $2,153.84 | $2,153.84 | $2,153.84 |
| 341 | Adjusting pull boxes (653.0900) | EACH | 2 | $1,175.86 | $1,175.86 | $1,175.86 | $1,175.86 | $1,175.86 | $1,175.86 |
| 342 | Removing pull boxes (653.0905) | EACH | 29 | $123.70 | $123.70 | $123.70 | $123.70 | $123.70 | $123.70 |
| 343 | Concrete bases type 1 (654.0101) | EACH | 25 | $981.65 | $981.65 | $981.65 | $981.65 | $981.65 | $981.65 |
| 344 | Concrete bases type 5 (654.0105) | EACH | 38 | $1,180.24 | $1,180.24 | $1,180.24 | $1,180.24 | $1,180.24 | $1,180.24 |
| 345 | Concrete bases type 10-special (654.0120) | EACH | 4 | $8,671.00 | $8,671.00 | $8,671.00 | $8,671.00 | $8,671.00 | $8,671.00 |
| 346 | Concrete control cabinet bases type 9 special (654.0217) | EACH | 1 | $2,783.90 | $2,783.90 | $2,783.90 | $2,783.90 | $2,783.90 | $2,783.90 |
| 347 | Concrete control cabinet bases type L30 (654.0230) | EACH | 1 | $2,162.07 | $2,162.07 | $2,162.07 | $2,162.07 | $2,162.07 | $2,162.07 |
| 348 | Cable traffic signal 5-14 AWG (655.0230) | LF | 8,237 | $1.66 | $1.66 | $1.66 | $1.66 | $1.66 | $1.66 |
| 349 | Cable traffic signal 7-14 AWG (655.0240) | LF | 3,314 | $2.12 | $2.12 | $2.12 | $2.12 | $2.12 | $2.12 |
| 350 | Cable traffic signal 12-14 AWG (655.0260) | LF | 2,429 | $3.39 | $3.39 | $3.39 | $3.39 | $3.39 | $3.39 |
| 351 | Cable traffic signal 15-12 AWG (655.0265) | LF | 800 | $4.48 | $4.48 | $4.48 | $4.48 | $4.48 | $4.48 |
| 352 | Cable type UF 2-12 AWG grounded (655.0305) | LF | 1,618 | $1.44 | $1.44 | $1.44 | $1.44 | $1.44 | $1.44 |
| 353 | Electrical wire traffic signals 10 AWG (655.0515) | LF | 43,479 | $1.19 | $1.19 | $1.19 | $1.19 | $1.19 | $1.19 |
| 354 | Electrical wire traffic signals 6 AWG (655.0525) | LF | 435 | $2.23 | $2.23 | $2.23 | $2.23 | $2.23 | $2.23 |
| 355 | Electrical wire lighting 12 AWG (655.0610) | LF | 7,258 | $0.99 | $0.99 | $0.99 | $0.99 | $0.99 | $0.99 |
| 356 | Electrical wire lighting 8 AWG (655.0620) | LF | 13,790 | $1.67 | $1.67 | $1.67 | $1.67 | $1.67 | $1.67 |
| 357 | Electrical wire lighting 4 AWG (655.0630) | LF | 11,680 | $2.84 | $2.84 | $2.84 | $2.84 | $2.84 | $2.84 |
| 358 | Electrical wire lighting 1 AWG (655.0640) | LF | 18 | $3.31 | $3.31 | $3.31 | $3.31 | $3.31 | $3.31 |
| 359 | Loop detector lead in cable (655.0700) | LF | 17,116 | $1.48 | $1.48 | $1.48 | $1.48 | $1.48 | $1.48 |
| 360 | Loop detector wire (655.0800) | LF | 16,337 | $1.30 | $1.30 | $1.30 | $1.30 | $1.30 | $1.30 |
| 361 | Traffic signal evp detector cable (655.0900) | LF | 3,186 | $1.48 | $1.48 | $1.48 | $1.48 | $1.48 | $1.48 |
| 362 | Electrical service meter breaker pedestal (location) 301. IH 43 ramps & STH 164 (656.0201) | EACH | 1 | $1,887.07 | $1,887.07 | $1,887.07 | $1,887.07 | $1,887.07 | $1,887.07 |
| 363 | Electrical service main lugs only meter pedestal (location) 101. HL- 67-BG (656.0401) | EACH | 1 | $1,365.00 | $1,365.00 | $1,365.00 | $1,365.00 | $1,365.00 | $1,365.00 |
| 364 | Electrical service breaker disconnect box (location) 001. CCTV670250 (656.0501) | EACH | 1 | $2,189.42 | $2,189.42 | $2,189.42 | $2,189.42 | $2,189.42 | $2,189.42 |
| 365 | Pedestal bases (657.0100) | EACH | 25 | $363.72 | $363.72 | $363.72 | $363.72 | $363.72 | $363.72 |
| 366 | Transformer bases breakaway 11 1/2-inch bolt circle (657.0255) | EACH | 39 | $847.00 | $847.00 | $847.00 | $847.00 | $847.00 | $847.00 |
| 367 | Poles type 5-aluminum (657.0322) | EACH | 36 | $2,458.48 | $2,458.48 | $2,458.48 | $2,458.48 | $2,458.48 | $2,458.48 |
| 368 | Traffic signal standards aluminum 3.5-FT (657.0405) | EACH | 5 | $402.58 | $402.58 | $402.58 | $402.58 | $402.58 | $402.58 |
| 369 | Traffic signal standards aluminum 13-FT (657.0420) | EACH | 20 | $1,032.17 | $1,032.17 | $1,032.17 | $1,032.17 | $1,032.17 | $1,032.17 |
| 370 | Luminaire arms single member 4- inch clamp 6-FT (657.0609) | EACH | 1 | $450.44 | $450.44 | $450.44 | $450.44 | $450.44 | $450.44 |
| 371 | Luminaire arms single member 4 1/2-inch clamp 6-FT (657.0610) | EACH | 38 | $440.87 | $440.87 | $440.87 | $440.87 | $440.87 | $440.87 |
| 372 | Traffic signal face 3S 12-inch (658.0173) | EACH | 31 | $951.92 | $951.92 | $951.92 | $951.92 | $951.92 | $951.92 |
| 373 | Pedestrian signal face 16-inch (658.0416) | EACH | 12 | $628.77 | $628.77 | $628.77 | $628.77 | $628.77 | $628.77 |
| 374 | Signal mounting hardware (location) 001. IH 43 ramps and STH 164 (658.5070) | EACH | 1 | $10,901 | $10,901 | $10,901 | $10,901 | $10,901 | $10,901 |
| 375 | Luminaires utility LED C (659.1125) | EACH | 43 | $412.01 | $412.01 | $412.01 | $412.01 | $412.01 | $412.01 |
| 376 | Luminaires underdeck LED C (659.1215) | EACH | 8 | $701.79 | $701.79 | $701.79 | $701.79 | $701.79 | $701.79 |
| 377 | Lighting control cabinets 240/480 30-inch (659.2230) | EACH | 1 | $11,984 | $11,984 | $11,984 | $11,984 | $11,984 | $11,984 |
| 378 | Lamp, ballast, LED, switch disposal by contractor (659.5000.S) | EACH | 79 | $13.76 | $13.76 | $13.76 | $13.76 | $13.76 | $13.76 |
| 379 | Temporary traffic signals for intersections (location) 001. IH 43 ramps and STH 164 (661.0201) | EACH | 1 | $113,954 | $113,954 | $113,954 | $113,954 | $113,954 | $113,954 |
| 380 | Temporary traffic signals for intersections (location) 002. STH 164 & CTH ES (661.0201) | EACH | 1 | $44,328 | $44,328 | $44,328 | $44,328 | $44,328 | $44,328 |
| 381 | Ramp closure gates 24-FT (662.1024.S) | EACH | 1 | $33,518 | $33,518 | $33,518 | $33,518 | $33,518 | $33,518 |
| 382 | Ramp closure gates 26-FT (662.1026.S) | EACH | 1 | $33,758 | $33,758 | $33,758 | $33,758 | $33,758 | $33,758 |
| 383 | Ramp closure gates 28-FT (662.1028.S) | EACH | 1 | $33,997 | $33,997 | $33,997 | $33,997 | $33,997 | $33,997 |
| 384 | Ramp closure gates 40-FT (662.1040.S) | EACH | 1 | $36,766 | $36,766 | $36,766 | $36,766 | $36,766 | $36,766 |
| 385 | Field system integrator (670.0101) | EACH | 2 | $30,627 | $30,627 | $30,627 | $30,627 | $30,627 | $30,627 |
| 386 | ITS documentation (670.0201) | EACH | 2 | $10,885 | $10,885 | $10,885 | $10,885 | $10,885 | $10,885 |
| 387 | Conduit HDPE 3-duct 2-inch (671.0132) | LF | 29,030 | $9.59 | $9.59 | $9.59 | $9.59 | $9.59 | $9.59 |
| 388 | Conduit HDPE directional bore 3- duct 2-inch (671.0232) | LF | 5,941 | $28.67 | $28.67 | $28.67 | $28.67 | $28.67 | $28.67 |
| 389 | Communication vault type 1 (673.0105) | EACH | 32 | $3,285.63 | $3,285.63 | $3,285.63 | $3,285.63 | $3,285.63 | $3,285.63 |
| 390 | Install pole mounted cabinet (673.1225.S) | EACH | 1 | $3,982.29 | $3,982.29 | $3,982.29 | $3,982.29 | $3,982.29 | $3,982.29 |
| 391 | Install mounted controller microwave detector assembly (675.0300) | EACH | 1 | $3,119.47 | $3,119.47 | $3,119.47 | $3,119.47 | $3,119.47 | $3,119.47 |
| 392 | Install camera pole 50-FT (677.0150) | EACH | 1 | $2,346.67 | $2,346.67 | $2,346.67 | $2,346.67 | $2,346.67 | $2,346.67 |
| 393 | Install camera assembly (677.0200) | EACH | 1 | $3,119.47 | $3,119.47 | $3,119.47 | $3,119.47 | $3,119.47 | $3,119.47 |
| 394 | Install fiber optic cable outdoor plant 6-CT (678.0006) | LF | 835 | $1.34 | $1.34 | $1.34 | $1.34 | $1.34 | $1.34 |
| 395 | Install fiber optic cable outdoor plant 12-CT (678.0012) | LF | 2,670 | $1.60 | $1.60 | $1.60 | $1.60 | $1.60 | $1.60 |
| 396 | Install fiber optic cable outdoor plant 72-CT (678.0072) | LF | 37,470 | $0.81 | $0.81 | $0.81 | $0.81 | $0.81 | $0.81 |
| 397 | Fiber optic splice enclosure (678.0200) | EACH | 13 | $1,449.04 | $1,449.04 | $1,449.04 | $1,449.04 | $1,449.04 | $1,449.04 |
| 398 | Fiber optic splice (678.0300) | EACH | 148 | $81.63 | $81.63 | $81.63 | $81.63 | $81.63 | $81.63 |
| 399 | Fiber optic termination (678.0400) | EACH | 4 | $320.93 | $320.93 | $320.93 | $320.93 | $320.93 | $320.93 |
| 400 | Communication system testing (678.0501) | EACH | 2 | $11,196 | $11,196 | $11,196 | $11,196 | $11,196 | $11,196 |
| 401 | Install ethernet switches (678.0600) | EACH | 3 | $1,363.27 | $1,363.27 | $1,363.27 | $1,363.27 | $1,363.27 | $1,363.27 |
| 402 | Sawing asphalt (690.0150) | LF | 6,669 | $1.30 | $2.00 | $1.50 | $1.30 | $1.50 | $1.30 |
| 403 | Sawing concrete (690.0250) | LF | 905 | $2.95 | $2.50 | $2.00 | $2.95 | $2.00 | $2.95 |
| 404 | Incentive strength concrete structures (715.0502) | DOL | 4,266 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 405 | Incentive strength concrete barrier (715.0603) | DOL | 4,225 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 406 | Incentive flexural strength concrete pavement (715.0715) | DOL | 80,984 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 407 | Incentive iri ride (740.0440) | DOL | 65,338 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 408 | Installing and maintaining bird deterrent system (station) 001. 368+44 (999.2000.S) | EACH | 1 | $1.00 | $0.01 | $0.01 | $0.01 | $1.00 | $0.01 |
| 409 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 7,000 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 410 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 27,000 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 411 | Special 001. baseline CPM progress schedule (SPV.0060) | EACH | 1 | $1,000.00 | $30,000 | $5,000.00 | $5,000.00 | $29,000 | $1,000.00 |
| 412 | Special 002. monthly CPM progress schedule updates (SPV.0060) | EACH | 21 | $100.00 | $500.00 | $100.00 | $500.00 | $500.00 | $500.00 |
| 413 | Special 003. removing bus shelter (SPV.0060) | EACH | 1 | $2,800.00 | $792.00 | $792.00 | $792.00 | $5,000.00 | $4,000.00 |
| 414 | Special 004. survey project 1090- 39-70 (SPV.0060) | EACH | 1 | $348,750 | $411,750 | $348,750 | $348,750 | $348,750 | $229,451 |
| 415 | Special 005. exposing existing infrastructure paved area (SPV.0060) | EACH | 10 | $4,200.00 | $1,000.00 | $1,000.00 | $2,000.00 | $2,000.00 | $2,107.00 |
| 416 | Special 006. exposing existing infrastructure unpaved area (SPV.0060) | EACH | 10 | $3,000.00 | $500.00 | $1,000.00 | $800.00 | $1,000.00 | $2,107.00 |
| 417 | Special 007. traffic control close- open freeway entrance ramp (SPV.0060) | EACH | 2 | $500.00 | $500.00 | $5,400.00 | $950.00 | $500.00 | $500.00 |
| 418 | Special 008. traffic control full freeway closure (SPV.0060) | EACH | 2 | $4,500.00 | $4,500.00 | $9,500.00 | $3,500.00 | $4,500.00 | $4,500.00 |
| 419 | Special 009. traffic control local road lane closures (SPV.0060) | EACH | 2 | $700.00 | $700.00 | $5,650.00 | $950.00 | $700.00 | $700.00 |
| 420 | Special 010. emergency response to traffic incident involving concrete barrier temporary (SPV.0060) | EACH | 4 | $4,500.00 | $4,000.00 | $6,000.00 | $2,650.00 | $4,500.00 | $6,000.00 |
| 421 | Special 011. emergency response to traffic incident involving crash cushion (SPV.0060) | EACH | 2 | $8,500.00 | $8,500.00 | $2,500.00 | $2,500.00 | $8,500.00 | $20,000 |
| 422 | Special 012. mobilizations emergency pavement repair (SPV.0060) | EACH | 4 | $5,800.00 | $1,500.00 | $6,000.00 | $1,850.00 | $4,000.00 | $10,000 |
| 423 | Special 013. temporary concrete barrier gate, 24-FT (SPV.0060) | EACH | 10 | $6,000.00 | $6,000.00 | $7,500.00 | $5,450.00 | $6,000.00 | $6,000.00 |
| 424 | Special 014. crash cushions temporary left in place (SPV.0060) | EACH | 1 | $30,000 | $30,000 | $28,850 | $28,850 | $30,000 | $30,000 |
| 425 | Special 015. connect to existing inlet (SPV.0060) | EACH | 2 | $1,200.00 | $856.00 | $856.00 | $856.00 | $1,743.00 | $1,743.00 |
| 426 | Special 016. drilled high performance dowel bars (SPV.0060) | EACH | 390 | $16.06 | $16.06 | $35.00 | $21.53 | $16.06 | $16.06 |
| 427 | Special 101. concrete bases type 5 special (SPV.0060) | EACH | 2 | $1,180.24 | $1,180.24 | $1,180.24 | $1,180.24 | $1,180.24 | $1,180.24 |
| 428 | Special 102. lighting system survey (1090-39-70) (SPV.0060) | EACH | 1 | $4,500.00 | $4,500.00 | $4,500.00 | $4,500.00 | $4,500.00 | $6,875.00 |
| 429 | Special 200. ground rod (SPV.0060) | EACH | 2 | $329.86 | $329.86 | $329.86 | $329.86 | $329.86 | $329.86 |
| 430 | Special 301. install poles type 10 (SPV.0060) | EACH | 4 | $1,120.85 | $1,120.85 | $1,120.85 | $1,120.85 | $1,120.85 | $1,120.85 |
| 431 | Special 302. install monotube arms 35-FT type 9/10 pole (SPV.0060) | EACH | 3 | $1,731.34 | $1,731.34 | $1,731.34 | $1,731.34 | $1,731.34 | $1,731.34 |
| 432 | Special 303. install monotube arms 45-FT type 9/10 pole (SPV.0060) | EACH | 1 | $2,036.58 | $2,036.58 | $2,036.58 | $2,036.58 | $2,036.58 | $2,036.58 |
| 433 | Special 304. install luminaire arms steel 15-FT (SPV.0060) | EACH | 4 | $781.42 | $781.42 | $781.42 | $781.42 | $781.42 | $781.42 |
| 434 | Special 305. transport & install state furnished traffic signal cabinet (SPV.0060) | EACH | 1 | $3,439.54 | $3,439.54 | $3,439.54 | $3,439.54 | $3,439.54 | $3,439.54 |
| 435 | Special 306. transport traffic signal & internal lighting materials (SPV.0060) | EACH | 1 | $2,751.63 | $2,751.63 | $2,751.63 | $2,751.63 | $2,751.63 | $2,751.63 |
| 436 | Special 307. transport & install state furnished evp heads (STH 164 & CTH ES) (SPV.0060) | EACH | 1 | $2,751.63 | $2,751.63 | $2,751.63 | $2,751.63 | $2,751.63 | $2,751.63 |
| 437 | Special 308. transport & install state furnished evp heads (IH 43 ramps & STH 164) (SPV.0060) | EACH | 1 | $2,751.63 | $2,751.63 | $2,751.63 | $2,751.63 | $2,751.63 | $2,751.63 |
| 438 | Special 309. transport & install state furnished FO cable pigtail 6- CT (SPV.0060) | EACH | 2 | $687.91 | $687.91 | $687.91 | $687.91 | $687.91 | $687.91 |
| 439 | Special 310. concrete control cabinet bases type 9 special super P (SPV.0060) | EACH | 1 | $2,783.19 | $2,783.19 | $2,783.19 | $2,783.19 | $2,783.19 | $2,783.19 |
| 440 | Special 401. tighten bearing anchor bolt nuts (SPV.0060) | EACH | 2 | $300.00 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 441 | Special 402. cleaning and sealing concrete girder (SPV.0060) | EACH | 12 | $3,500.00 | $450.00 | $450.00 | $450.00 | $450.00 | $450.00 |
| 442 | Special 403. tieback anchors (SPV.0060) | EACH | 32 | $7,160.00 | $7,160.00 | $7,160.00 | $6,750.00 | $7,160.00 | $7,160.00 |
| 443 | Special 404. tieback anchors performance tests (SPV.0060) | EACH | 3 | $2,500.00 | $2,500.00 | $2,500.00 | $755.00 | $2,500.00 | $2,500.00 |
| 444 | Special 801. outlet control manhole 4X4-FT (SPV.0060) | EACH | 2 | $8,600.00 | $17,400 | $17,400 | $17,400 | $550.00 | $8,080.00 |
| 445 | Special 802. outlet control manhole 5X5-FT (SPV.0060) | EACH | 4 | $11,300 | $23,400 | $23,400 | $23,400 | $14,231 | $10,290 |
| 446 | Special 001. pavement cleanup project 1090-39-70 (SPV.0075) | HRS | 300 | $250.00 | $180.00 | $300.00 | $210.00 | $150.00 | $250.00 |
| 447 | Special 002. animal carcass removal (SPV.0075) | HRS | 10 | $1,050.00 | $223.00 | $200.00 | $500.00 | $465.00 | $750.00 |
| 448 | Special 001. sealing cracks and joints with hot-applied sealant (SPV.0085) | LB | 561 | $18.50 | $33.07 | $33.07 | $33.07 | $33.07 | $33.07 |
| 449 | Special 001. marking epoxy 6-inch black non grooved (SPV.0090) | LF | 673 | $1.25 | $1.25 | $1.25 | $0.36 | $1.25 | $1.25 |
| 450 | Special 002. glare screens temporary (SPV.0090) | LF | 81,149 | $6.50 | $6.50 | $6.50 | $4.55 | $6.50 | $6.50 |
| 451 | Special 003. concrete curb and gutter 30-inch special (SPV.0090) | LF | 821 | $28.00 | $28.00 | $60.00 | $28.00 | $28.00 | $28.00 |
| 452 | Special 004. concrete curb and gutter 60-inch special (SPV.0090) | LF | 93 | $49.00 | $49.00 | $200.00 | $49.00 | $49.00 | $49.00 |
| 453 | Special 005. concrete barrier temporary precast left in place (SPV.0090) | LF | 427 | $15.00 | $60.00 | $60.00 | $60.00 | $60.00 | $60.00 |
| 454 | Special 200. outdoor rated network cable (SPV.0090) | LF | 95 | $21.32 | $21.32 | $21.32 | $21.32 | $21.32 | $21.32 |
| 455 | Special 301. fiber optic warning tape (SPV.0090) | LF | 2,108 | $0.48 | $0.48 | $0.48 | $0.48 | $0.48 | $0.48 |
| 456 | Special 401. saw cutting and chipping concrete (SPV.0090) | LF | 2,944 | $18.00 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 |
| 457 | Special 402. pipe underdrain 6-inch special (SPV.0090) | LF | 631 | $18.00 | $17.50 | $17.50 | $17.50 | $25.50 | $60.00 |
| 458 | Special 801. cleaning storm sewer (SPV.0090) | LF | 3,759 | $4.00 | $12.50 | $12.50 | $12.50 | $3.00 | $10.00 |
| 459 | Special 802.storm sewer pipe reinforced concrete horizontal elliptical class HE-IV 38X60 (SPV.0090) | LF | 572 | $330.00 | $413.00 | $413.00 | $413.00 | $331.47 | $361.00 |
| 460 | Special 803. storm sewer pipe reinforced concrete horizontal elliptical class HE-IV 48X6 (SPV.0090) | LF | 60 | $500.00 | $816.00 | $816.00 | $816.00 | $696.87 | $557.00 |
| 461 | Special 804. reinforced concrete drainage channel (SPV.0090) | LF | 541 | $215.00 | $120.00 | $145.00 | $120.00 | $131.09 | $120.00 |
| 462 | Special 401. timber lagging (SPV.0110) | MBM | 19 | $6,500.00 | $6,500.00 | $6,500.00 | $7,475.00 | $6,500.00 | $6,500.00 |
| 463 | Special 001. field facilities office space (SPV.0135) | MON | 29 | $3,500.00 | $4,700.00 | $6,000.00 | $2,000.00 | $5,000.00 | $6,000.00 |
| 464 | Special 401. removing loose concrete overhead (SPV.0165) | SF | 82 | $45.00 | $145.00 | $145.00 | $145.00 | $145.00 | $145.00 |
| 465 | Special 402. geocomposite drain board (SPV.0165) | SF | 6,085 | $4.50 | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 |
| 466 | Special 001. excavation of phragmites contaminated soil (SPV.0180) | SY | 11,466 | $40.00 | $15.00 | $15.00 | $15.00 | $43.90 | $56.00 |
| 467 | Special 002. herbicide application (SPV.0180) | SY | 11,466 | $0.50 | $0.50 | $0.50 | $0.50 | $0.50 | $0.50 |
| 468 | Special 003. HPC pavement 10 1/2- inch (SPV.0180) | SY | 224,754 | $42.58 | $42.58 | $48.05 | $46.77 | $42.58 | $42.58 |
| 469 | Special 004. HPC pavement 8 1/2- inch (SPV.0180) | SY | 42,865 | $62.89 | $62.89 | $71.29 | $69.47 | $62.89 | $62.89 |
| 470 | Special 005. compost (SPV.0180) | SY | 2,528 | $12.00 | $11.75 | $11.75 | $11.75 | $11.75 | $11.75 |
| 471 | Special 401. abutment seat cleaning and sealing (SPV.0180) | SY | 28 | $150.00 | $150.00 | $150.00 | $150.00 | $150.00 | $150.00 |
| 472 | Special 001. HMA longitudinal joint repair (SPV.0195) | TON | 447 | $225.00 | $225.00 | $225.00 | $225.00 | $225.00 | $225.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of January 13, 2026. Compiled by Mirage Metrics.