Steel thrie beam, WisDOT 614.0230

Low bidders on WisDOT contracts carried a median of $38.00 per LF for this item, over the 24 months to 10 NOV 2026, across 36 low bids. Half of all 119 bids fell between $35.00 and $40.00.

Owner
Wisconsin DOT
Item
614.0230
Unit
LF
Data through
10 NOV 2026

WisDOT prints this item as “Steel Thrie Beam”.

$38.00Low bidder's median, per LF
$38.00Median of all bids, per LF
37Contracts in the window

By year of letting

Steel thrie beam, WisDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202286$45.7513$43.00
2023109$38.5032$38.25
20241414$38.5041$39.00
20251615$36.8056$39.00
20261717$38.0050$38.00

Bid prices as published, not adjusted for inflation.

By county

CountyLow bidsLow-bid medianAll bidsMedian, all bids
Waukesha3$36.0015$38.00
Outagamie4$38.5013$39.00
Steel thrie beam, WisDOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Quantity (LF)Low bidsLow-bid median
69 to 1509$40.00
175 to 2309$35.50
250 to 4009$39.00
450 to 1,7759$38.00
Steel thrie beam, WisDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

Steel thrie beam, WisDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
10 NOV 202620261110019Sheboygan175$35.00$35.003Michels Road & Stone, Inc.WisDOT
13 OCT 202620261013002Crawford69$75.00$75.001Iverson Construction, A Div. of Mathy CoWisDOT
13 OCT 202620261013009Fond Du Lac1,300$32.50$32.503Vinton Construction CompanyWisDOT
13 OCT 202620261013014Winnebago1,425$38.00$38.003Vinton Construction CompanyWisDOT
13 OCT 202620261013022Dunn450$51.35$51.352Lunda Construction CompanyWisDOT
13 OCT 202620261013023Dunn125$50.00$50.003Sheet Piling Services LLCWisDOT
15 SEP 202620260915007Milwaukee325$35.90$38.003Payne and Dolan, IncWisDOT
15 SEP 202620260915029Jackson125$52.25$52.252Zenith Tech., Inc. - WaukeshaWisDOT
11 AUG 202620260811009Walworth450$38.00$38.006Musson Bros., Inc.WisDOT
11 AUG 202620260811011Brown250$40.00$37.002Northeast Asphalt, IncWisDOT
14 JUL 202620260714008Marquette225$40.00$40.001D L Gasser ConstructionWisDOT
10 MAR 202620260310002Columbia72$38.00$35.005Parisi Construction, LLCWisDOT
10 FEB 202620260210011Washington525$38.00$38.001Zenith Tech., Inc. - WaukeshaWisDOT
10 FEB 202620260210024Calumet150$33.00$33.004Northeast Asphalt, IncWisDOT
10 FEB 202620260210031Shawano725$34.00$34.003Vinton Construction CompanyWisDOT
Latest WisDOT contracts carrying Steel thrie beam

Filter this item by your own quantity, county and period, or check your price against it, in the WisDOT explorer.

How these prices were read

WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WisDOT's own: this item is compared with WisDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the WisDOT letting of 10 NOV 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.