WisDOT contract 20260811011 bid tabulation
Manitowoc - Green Bay; STH 172 - Atkinson Drive (IH 043, Brown County Manitowoc - Green Bay). Let by Wisconsin DOT on August 11, 2026, Brown. 2 bids received; low bid $25,867,882 by Northeast Asphalt, Inc.
- Owner
- Wisconsin DOT
- Letting
- 11 AUG 2026
- Pay items
- 199
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Northeast Asphalt, Inc | $25,867,882 | Low |
| 2 | Zignego Company, Inc. | $30,105,005 | +16% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Northeast Asphalt, Inc | 2. Zignego Company, Inc. |
|---|---|---|---|---|---|
| 1 | Roadside clearing (202.0110) | SY | 44 | $100.00 | $100.00 |
| 2 | Removing small pipe culverts (203.0100) | EACH | 7 | $1,186.43 | $2,000.00 |
| 3 | Removing concrete pavement (204.0100) | SY | 2,398 | $17.70 | $35.00 |
| 4 | Removing concrete pavement butt joints (204.0105) | SY | 2,553 | $12.60 | $12.60 |
| 5 | Removing asphaltic surface butt joints (204.0115) | SY | 20,071 | $12.60 | $12.60 |
| 6 | Removing asphaltic surface milling (204.0120) | SY | 411,211 | $2.10 | $2.10 |
| 7 | Removing asphaltic longitudinal notched wedge joint milling (204.0126.S) | LF | 89,918 | $0.50 | $0.50 |
| 8 | Removing curb & gutter (204.0150) | LF | 925 | $15.00 | $30.00 |
| 9 | Removing concrete sidewalk (204.0155) | SY | 90 | $27.00 | $30.00 |
| 10 | Removing concrete barrier (204.0157) | LF | 7,322 | $20.05 | $10.00 |
| 11 | Removing guardrail (204.0165) | LF | 41,429 | $3.00 | $2.75 |
| 12 | Removing fence (204.0170) | LF | 30 | $25.00 | $10.00 |
| 13 | Removing surface drains (204.0190) | EACH | 2 | $350.00 | $1,000.00 |
| 14 | Removing concrete bases (204.0195) | EACH | 3 | $200.00 | $1,000.00 |
| 15 | Removing inlets (204.0220) | EACH | 39 | $1,000.00 | $800.00 |
| 16 | Removing ancillary structure (structure) 01. S-5-32 (204.0246) | EACH | 1 | $10,500 | $3,000.00 |
| 17 | Abandoning sewer (204.0291.S) | CY | 17 | $600.00 | $500.00 |
| 18 | Excavation common (205.0100) | CY | 2,202 | $25.15 | $75.00 |
| 19 | Prepare foundation for asphaltic paving (project) 01. 1227-08-73 (211.0101) | EACH | 1 | $43,780 | $43,780 |
| 20 | Finishing roadway (project) 01. 1227-08-73 (213.0100) | EACH | 1 | $1,500.00 | $1,000.00 |
| 21 | Base aggregate dense 3/4-inch (305.0110) | TON | 17,786 | $23.40 | $45.00 |
| 22 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 762 | $19.38 | $50.00 |
| 23 | Select crushed material (312.0110) | TON | 1,773 | $19.38 | $50.00 |
| 24 | Removing pavement for base patching (390.0100) | CY | 2,167 | $131.20 | $100.00 |
| 25 | Base patching concrete shes (390.0405) | CY | 1,995 | $575.00 | $472.00 |
| 26 | Concrete pavement approach slab hes (415.1410) | SY | 252 | $275.00 | $298.00 |
| 27 | Drilled tie bars (416.0610) | EACH | 5,700 | $10.00 | $15.00 |
| 28 | Drilled dowel bars (416.0620) | EACH | 4,874 | $19.50 | $20.00 |
| 29 | Tack coat (455.0605) | GAL | 61,437 | $3.00 | $3.00 |
| 30 | HMA percent within limits (PWL) test strip volumetrics (460.0105.S) | EACH | 1 | $3,215.00 | $3,215.00 |
| 31 | HMA percent within limits (PWL) test strip density (460.0110.S) | EACH | 1 | $4,720.00 | $4,720.00 |
| 32 | HMA pavement test strip volumetrics (460.0115.S) | EACH | 1 | $3,215.00 | $3,215.00 |
| 33 | HMA test strip density (460.0120.S) | EACH | 1 | $4,645.00 | $4,645.00 |
| 34 | Incentive density HMA pavement (460.2000) | DOL | 36,270 | $1.00 | $1.00 |
| 35 | Incentive density PWL HMA pavement (460.2005) | DOL | 8,825 | $1.00 | $1.00 |
| 36 | Incentive density HMA pavement longitudinal joints (460.2007) | DOL | 7,500 | $1.00 | $1.00 |
| 37 | Incentive air voids HMA pavement (460.2010) | DOL | 50,150 | $1.00 | $1.00 |
| 38 | HMA pavement 3 LT 58-28 S (460.5223) | TON | 9,979 | $79.20 | $79.20 |
| 39 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 10,788 | $88.70 | $88.70 |
| 40 | HMA pavement 3 HT 58-28 H (460.7423) | TON | 44,178 | $90.25 | $90.25 |
| 41 | HMA pavement 4 HT 58-28 H (460.7424) | TON | 17,527 | $115.75 | $115.75 |
| 42 | HMA pavement 4 SMA 58-28 V (460.8624) | TON | 34,878 | $120.85 | $120.85 |
| 43 | Material transfer vehicle (460.9000.S) | EACH | 1 | $91,775 | $91,775 |
| 44 | Asphaltic surface (465.0105) | TON | 460 | $129.50 | $129.50 |
| 45 | Asphaltic rumble strips, shoulder divided roadway (465.0510) | LF | 148,700 | $0.30 | $0.30 |
| 46 | Removing asphaltic concrete deck overlay (structure) 01. B-05-0158 (509.9010.S) | SY | 17,100 | $7.80 | $7.80 |
| 47 | Apron endwalls for culvert pipe 24- inch (520.1024) | EACH | 2 | $631.78 | $2,500.00 |
| 48 | Culvert pipe class III-A 24-inch (520.3324) | LF | 70 | $147.00 | $200.00 |
| 49 | Concrete collars for pipe (520.8000) | EACH | 4 | $2,500.00 | $2,000.00 |
| 50 | Cleaning culvert pipes (520.8700) | EACH | 37 | $1,000.00 | $1,475.00 |
| 51 | Apron endwalls for culvert pipe steel 12-inch (521.1012) | EACH | 3 | $401.43 | $3,000.00 |
| 52 | Apron endwalls for culvert pipe steel 18-inch (521.1018) | EACH | 3 | $457.70 | $3,000.00 |
| 53 | Culvert pipe corrugated steel 12- inch (521.3112) | LF | 18 | $112.79 | $200.00 |
| 54 | Culvert pipe corrugated steel 18- inch (521.3118) | LF | 20 | $133.53 | $200.00 |
| 55 | Culvert pipe reinforced concrete class III 18-inch (522.0118) | LF | 8 | $177.12 | $200.00 |
| 56 | Culvert pipe reinforced concrete class III 42-inch (522.0142) | LF | 16 | $403.32 | $400.00 |
| 57 | Culvert pipe reinforced concrete class III 48-inch (522.0148) | LF | 16 | $466.62 | $500.00 |
| 58 | Apron endwalls for culvert pipe reinforced concrete 18-inch (522.1018) | EACH | 1 | $1,834.55 | $3,000.00 |
| 59 | Apron endwalls for culvert pipe reinforced concrete 42-inch (522.1042) | EACH | 1 | $4,142.55 | $5,000.00 |
| 60 | Apron endwalls for culvert pipe reinforced concrete 48-inch (522.1048) | EACH | 1 | $6,521.65 | $5,000.00 |
| 61 | Drilling shaft 30-inch (531.2030) | LF | 30 | $350.00 | $200.00 |
| 62 | Foundation two-shaft butterfly type B-I (structure) 01. S-5-447 (531.5030) | EACH | 1 | $18,850 | $19,000 |
| 63 | Butterfly 2-chord type I (structure) 01. S-5-447 (532.5030) | EACH | 1 | $39,500 | $30,500 |
| 64 | Concrete curb & gutter 30-inch type A (601.0409) | LF | 532 | $85.00 | $82.00 |
| 65 | Concrete curb & gutter 4-inch sloped 30-inch type TBTT (601.0586) | LF | 666 | $85.00 | $82.00 |
| 66 | Concrete sidewalk 5-inch (602.0410) | SF | 307 | $18.00 | $15.00 |
| 67 | Concrete surface drains (602.3010) | CY | 22 | $2,500.00 | $1,000.00 |
| 68 | Concrete barrier type S42 (603.1142) | LF | 4,700 | $145.25 | $102.00 |
| 69 | Concrete barrier transition type NJ32SF to S36 (603.3113) | EACH | 2 | $6,975.00 | $12,000 |
| 70 | Concrete barrier transition type NJ32DF to S36 (603.3313) | EACH | 4 | $7,750.00 | $12,000 |
| 71 | Concrete barrier transition type S36 to S42 (603.3535) | EACH | 6 | $6,800.00 | $12,000 |
| 72 | Concrete barrier temporary precast delivered (603.8000) | LF | 10,914 | $10.00 | $19.00 |
| 73 | Concrete barrier temporary precast installed (603.8125) | LF | 10,914 | $6.75 | $5.00 |
| 74 | Riprap medium (606.0200) | CY | 54 | $265.78 | $500.00 |
| 75 | Storm sewer pipe reinforced concrete class III 12-inch (608.0312) | LF | 133 | $192.10 | $250.00 |
| 76 | Manhole covers type K (611.0540) | EACH | 2 | $2,400.00 | $1,400.00 |
| 77 | Inlet covers type A (611.0600) | EACH | 5 | $965.00 | $1,400.00 |
| 78 | Inlet covers type BW (611.0610) | EACH | 16 | $795.00 | $1,400.00 |
| 79 | Inlet covers type H (611.0624) | EACH | 8 | $1,268.00 | $1,400.00 |
| 80 | Inlets 3-FT diameter (611.3003) | EACH | 6 | $4,250.00 | $5,995.00 |
| 81 | Inlets 2X2.5-FT (611.3225) | EACH | 16 | $3,500.00 | $6,995.00 |
| 82 | Inlets 2X3-FT (611.3230) | EACH | 2 | $4,000.00 | $4,995.00 |
| 83 | Adjusting manhole covers (611.8110) | EACH | 2 | $550.00 | $2,500.00 |
| 84 | Adjusting inlet covers (611.8115) | EACH | 24 | $535.00 | $1,700.00 |
| 85 | Pipe underdrain 6-inch (612.0106) | LF | 30 | $49.27 | $200.00 |
| 86 | Pipe underdrain unperforated 12- inch (612.0212) | LF | 45 | $129.84 | $250.00 |
| 87 | Apron endwalls for underdrain reinforced concrete 6-inch (612.0806) | EACH | 2 | $494.63 | $1,000.00 |
| 88 | Cable barrier type 1 (613.1100.S) | LF | 10,931 | $41.00 | $40.00 |
| 89 | Cable barrier end terminal type 1 (613.1200.S) | EACH | 14 | $8,250.00 | $7,500.00 |
| 90 | Barrier system grading shaping finishing (614.0010) | EACH | 49 | $3,000.00 | $1,400.00 |
| 91 | Anchorages for steel plate beam guard type 2 (614.0115) | EACH | 2 | $4,000.00 | $2,500.00 |
| 92 | Steel thrie beam bullnose terminal (614.0220) | EACH | 4 | $15,750 | $13,800 |
| 93 | Steel thrie beam (614.0230) | LF | 250 | $40.00 | $34.00 |
| 94 | Steel plate beam guard class A (614.0305) | LF | 40 | $26.00 | $28.00 |
| 95 | Adjusting steel plate beam guard (614.0400) | LF | 2,262 | $14.00 | $10.00 |
| 96 | Crash cushions temporary (614.0905) | EACH | 2 | $4,250.00 | $3,550.00 |
| 97 | MGS guardrail 3 (614.2300) | LF | 38,073 | $27.00 | $28.00 |
| 98 | MGS guardrail 3 HS (614.2310) | LF | 25 | $36.00 | $35.00 |
| 99 | MGS guardrail 3 QS (614.2320) | LF | 38 | $40.00 | $45.00 |
| 100 | MGS guardrail 3 K (614.2330) | LF | 763 | $36.00 | $42.75 |
| 101 | MGS guardrail short radius (614.2350) | LF | 123 | $40.00 | $38.00 |
| 102 | MGS thrie beam transition (614.2500) | LF | 1,830 | $90.00 | $92.00 |
| 103 | MGS guardrail terminal eat (614.2610) | EACH | 51 | $4,300.00 | $3,400.00 |
| 104 | MGS guardrail terminal type 2 (614.2620) | EACH | 37 | $3,800.00 | $2,850.00 |
| 105 | Fence chain link 5-FT (616.0205) | LF | 30 | $95.00 | $150.00 |
| 106 | Maintenance and repair of haul roads (project) 01. 1227-08-73 (618.0100) | EACH | 1 | $1.00 | $1.00 |
| 107 | Mobilization (619.1000) | EACH | 1 | $1,701,400 | $5,519,000 |
| 108 | Concrete median sloped nose (620.0300) | SF | 141 | $17.00 | $30.00 |
| 109 | Water (624.0100) | MGAL | 278 | $50.00 | $50.00 |
| 110 | Silt fence (628.1504) | LF | 5,915 | $2.50 | $2.00 |
| 111 | Silt fence maintenance (628.1520) | LF | 5,915 | $0.01 | $0.01 |
| 112 | Mobilizations erosion control (628.1905) | EACH | 17 | $1.00 | $75.00 |
| 113 | Mobilizations emergency erosion control (628.1910) | EACH | 13 | $1.00 | $50.00 |
| 114 | Erosion mat urban class I type B (628.2008) | SY | 80,406 | $1.90 | $1.65 |
| 115 | Inlet protection type A (628.7005) | EACH | 18 | $150.00 | $5.00 |
| 116 | Temporary ditch checks (628.7504) | LF | 788 | $8.00 | $6.75 |
| 117 | Culvert pipe checks (628.7555) | EACH | 31 | $20.00 | $14.50 |
| 118 | Fertilizer type B (629.0210) | CWT | 50 | $150.00 | $100.00 |
| 119 | Seeding mixture no. 20 (630.0120) | LB | 2,170 | $8.00 | $7.15 |
| 120 | Seed water (630.0500) | MGAL | 1,506 | $0.01 | $2.00 |
| 121 | Delineators barrier wall (633.1000) | EACH | 47 | $110.00 | $58.00 |
| 122 | Posts wood 4X6-inch X 22-FT (634.0622) | EACH | 2 | $300.00 | $150.00 |
| 123 | Signs type I reflective SH (637.1220) | SF | 135 | $40.00 | $38.45 |
| 124 | Moving signs type II (638.2102) | EACH | 1 | $300.00 | $75.00 |
| 125 | Removing signs type I (638.2601) | EACH | 1 | $1,000.00 | $1,000.00 |
| 126 | Removing small sign supports (638.3000) | EACH | 2 | $100.00 | $50.00 |
| 127 | Field office type C (642.5201) | EACH | 1 | $10,200 | $20,000 |
| 128 | Traffic control drums (643.0300) | DAY | 282,760 | $0.25 | $0.25 |
| 129 | Temporary tape rumble strip orange (643.0320.S) | LF | 10,368 | $8.50 | $20.00 |
| 130 | Digital speed reduction system (DSRS) (643.0370.S) | DAY | 605 | $155.00 | $71.00 |
| 131 | Traffic control barricades type III (643.0420) | DAY | 2,160 | $2.50 | $0.75 |
| 132 | Traffic control warning lights type A (643.0705) | DAY | 4,304 | $0.50 | $0.11 |
| 133 | Traffic control warning lights type C (643.0715) | DAY | 47,086 | $0.20 | $0.13 |
| 134 | Traffic control connected arrow boards (643.0810) | DAY | 620 | $19.25 | $18.50 |
| 135 | Traffic control signs (643.0900) | DAY | 34,452 | $0.30 | $0.55 |
| 136 | Traffic control covering signs type II (643.0920) | EACH | 556 | $70.00 | $40.00 |
| 137 | Traffic control signs fixed message (643.1000) | SF | 69.50 | $43.50 | $18.00 |
| 138 | Traffic control signs PCMS (643.1050) | DAY | 646 | $16.25 | $50.00 |
| 139 | Dynamic late merge system (643.1100.S) | DAY | 545 | $165.00 | $115.00 |
| 140 | Basic traffic queue warning system (643.1205.S) | DAY | 144 | $150.00 | $82.38 |
| 141 | Traffic control connected work zone start and end location markers (643.1220) | DAY | 609 | $10.50 | $10.00 |
| 142 | Temporary marking line paint 6- inch (643.3165) | LF | 431,278 | $0.28 | $0.16 |
| 143 | Temporary marking line paint 10- inch (643.3265) | LF | 50,122 | $0.44 | $0.30 |
| 144 | Traffic control (643.5000) | EACH | 1 | $950,000 | $250,000 |
| 145 | Geotextile type HR (645.0120) | SY | 112 | $10.00 | $10.00 |
| 146 | Marking line epoxy 6-inch (646.2020) | LF | 67,132 | $0.48 | $0.85 |
| 147 | Marking line grooved black epoxy 6-inch (646.2025) | LF | 20,694 | $0.71 | $1.25 |
| 148 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 248,635 | $1.13 | $1.61 |
| 149 | Marking line epoxy 10-inch (646.4020) | LF | 2,289 | $1.08 | $1.80 |
| 150 | Marking line grooved black epoxy 10-inch (646.4025) | LF | 872 | $1.95 | $2.70 |
| 151 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 25,161 | $2.64 | $3.00 |
| 152 | Marking arrow epoxy (646.5020) | EACH | 33 | $205.30 | $260.00 |
| 153 | Marking word epoxy (646.5120) | EACH | 5 | $274.17 | $340.00 |
| 154 | Marking stop line epoxy 18-inch (646.6120) | LF | 97 | $13.10 | $16.00 |
| 155 | Marking chevron epoxy 24-inch (646.7220) | LF | 892 | $18.78 | $13.00 |
| 156 | Marking curb epoxy (646.8120) | LF | 57 | $7.99 | $13.00 |
| 157 | Marking island nose epoxy (646.8220) | EACH | 5 | $298.36 | $340.00 |
| 158 | Marking removal line grooved contrast permanent tape 4-inch (646.9055) | LF | 700 | $2.70 | $0.22 |
| 159 | Marking removal line grooved permanent tape 8-inch (646.9150) | LF | 3,400 | $3.50 | $0.44 |
| 160 | Marking removal line grooved permanent tape 10-inch (646.9152) | LF | 200 | $4.20 | $0.44 |
| 161 | Marking removal line grooved contrast permanent tape 8-inch (646.9155) | LF | 365 | $5.00 | $0.44 |
| 162 | Construction staking storm sewer (650.4000) | EACH | 18 | $50.00 | $50.00 |
| 163 | Construction staking base (650.5000) | LF | 300 | $1.00 | $1.00 |
| 164 | Construction staking pipe culverts (650.6000) | EACH | 13 | $50.00 | $50.00 |
| 165 | Construction staking structure layout (structure) 01. S-05-447 (650.6501) | EACH | 1 | $500.00 | $500.00 |
| 166 | Construction staking concrete barrier (650.7500) | LF | 5,014 | $1.25 | $1.25 |
| 167 | Construction staking resurfacing reference (650.8000) | LF | 142,128 | $0.08 | $0.08 |
| 168 | Construction staking supplemental control (project) 01. 1227-08-73 (650.9911) | EACH | 1 | $10.00 | $10.00 |
| 169 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 110 | $10.00 | $10.00 |
| 170 | Conduit rigid nonmetallic schedule 40 3-inch (652.0235) | LF | 30 | $14.00 | $14.00 |
| 171 | Conduit special 3-inch (652.0615) | LF | 160 | $30.00 | $30.00 |
| 172 | Pull boxes non-conductive 24X42- inch (653.0164) | EACH | 2 | $3,400.00 | $3,400.00 |
| 173 | Removing pull boxes (653.0905) | EACH | 2 | $75.00 | $75.00 |
| 174 | Electrical service meter breaker pedestal (location) 01. S-05-0575 (IH 43 SB & CTH V/E mason) (656.0201) | EACH | 1 | $1,950.00 | $1,950.00 |
| 175 | Temporary traffic signals for intersections (location) 01. US 141 and wis 29 (661.0201) | EACH | 2 | $7,850.00 | $20,000 |
| 176 | Temporary traffic signals for intersections (location) 02. US 141 and elm view RD (661.0201) | EACH | 2 | $10,500 | $20,000 |
| 177 | Temporary traffic signals for intersections (location) 03. IH 43 SB and elm view RD (661.0201) | EACH | 2 | $7,850.00 | $20,000 |
| 178 | Temporary traffic signals for intersections (location) 04. mason ST and huron ST (661.0201) | EACH | 3 | $8,250.00 | $20,000 |
| 179 | Temporary traffic signals for intersections (location) 05. wis 54/57 and bay settlement RD (661.0201) | EACH | 2 | $10,500 | $20,000 |
| 180 | Sawing concrete (690.0250) | LF | 36,861 | $2.50 | $2.55 |
| 181 | Incentive strength concrete barrier (715.0603) | DOL | 2,430 | $1.00 | $1.00 |
| 182 | Incentive iri ride (740.0440) | DOL | 29,000 | $1.00 | $1.00 |
| 183 | Installing and maintaining climbing turtle exclusion fence (999.2100.S) | LF | 11,522 | $2.25 | $3.50 |
| 184 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,100 | $5.00 | $5.00 |
| 185 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 5,760 | $5.00 | $5.00 |
| 186 | Special 01. base patching concrete hes (SPV.0035) | CY | 172 | $395.00 | $472.00 |
| 187 | Special 02. continuously reinforced concrete repair hes (SPV.0035) | CY | 664 | $625.00 | $707.00 |
| 188 | Special 03. continuously reinforced concrete repair shes (SPV.0035) | CY | 168 | $860.00 | $807.00 |
| 189 | Special 01. grading, shaping and finishing culvert pipes and apron endwalls (SPV.0060) | EACH | 12 | $1,933.33 | $4,000.00 |
| 190 | Special 02. concrete barrier transition type S42SF to S42DF (SPV.0060) | EACH | 2 | $17,950 | $12,000 |
| 191 | Special 03. inlet extension ring (SPV.0060) | EACH | 67 | $367.50 | $1,000.00 |
| 192 | Special 04. resetting pipe end (SPV.0060) | EACH | 1 | $5,558.20 | $5,000.00 |
| 193 | Special 05. removing sand barrel arrays with restoration (SPV.0060) | EACH | 3 | $3,250.00 | $5,300.00 |
| 194 | Special 06. removing raised pavement markers (SPV.0060) | EACH | 161 | $38.50 | $50.00 |
| 195 | Special 07. concrete control cabinet bases type 9 NE region special (SPV.0060) | EACH | 1 | $4,800.00 | $4,800.00 |
| 196 | Special 01. grading, shaping and finishing ditch (SPV.0090) | LF | 1,629 | $22.28 | $100.00 |
| 197 | Special 02. concrete joint and crack cleaning and repair (SPV.0090) | LF | 5,670 | $7.30 | $7.30 |
| 198 | Special 05. cured in place pipe liner for steel plate pipe arch (app dim 74" X 51") (SPV.0090) | LF | 275 | $1,385.00 | $1,385.00 |
| 199 | Special 01. cable guard median grading and shaping (SPV.0170) | STA | 122 | $800.00 | $4,200.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of August 11, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.