Removing concrete barrier, WisDOT 204.0157

Low bidders on WisDOT contracts carried a median of $20.18 per LF for this item, over the 24 months to 10 NOV 2026, across 22 low bids. Half of all 83 bids fell between $15.00 and $30.00.

Owner
Wisconsin DOT
Item
204.0157
Unit
LF
Data through
10 NOV 2026

WisDOT prints this item as “Removing Concrete Barrier”.

$20.18Low bidder's median, per LF
$20.00Median of all bids, per LF
24Contracts in the window

By year of letting

Removing concrete barrier, WisDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
2022109$25.0025$25.00
2023109$25.0033$25.00
20241111$21.0042$20.00
20251211$21.0040$27.50
202698$20.1829$20.00

Bid prices as published, not adjusted for inflation.

By county

CountyLow bidsLow-bid medianAll bidsMedian, all bids
Outagamie5$15.0025$20.00
Milwaukee4$20.0014$18.04
Removing concrete barrier, WisDOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Quantity (LF)Low bidsLow-bid median
9 to 1565$21.00
192 to 8046$26.00
1,257 to 3,3505$15.00
3,480 to 9,1266$15.15
Removing concrete barrier, WisDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

Removing concrete barrier, WisDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
13 OCT 202620261013009Fond Du Lac314$34.06$75.003Vinton Construction CompanyWisDOT
13 OCT 202620261013022Dunn192$20.30$20.302Lunda Construction CompanyWisDOT
13 OCT 202620261013023Dunn130$17.90$17.903Sheet Piling Services LLCWisDOT
11 AUG 202620260811010Brown3,480$30.00$28.503Zignego Company, Inc.WisDOT
11 AUG 202620260811011Brown7,322$20.05$15.032Northeast Asphalt, IncWisDOT
14 JUL 202620260714005Outagamie3,592$10.30$20.006Vinton Construction CompanyWisDOT
12 MAY 202620260512003Rock9$140.00$157.422Parisi Construction, LLCWisDOT
10 FEB 202620260210022Outagamie2,130n/a$19.322Michels Road & Stone, Inc.WisDOT
13 JAN 202620260113056Waukesha9,126$10.00$13.766Hoffman Construction CompanyWisDOT
14 OCT 202520251014008Outagamie110$21.00$25.005Vinton Construction CompanyWisDOT
09 SEP 202520250909006Milwaukee15,273n/a$18.502WisDOT
09 SEP 202520250909007Milwaukee2,170$9.00$9.003Zenith Tech., Inc. - WaukeshaWisDOT
08 JUL 202520250708002Milwaukee804$22.00$56.103Rock Road Companies, Inc.WisDOT
08 JUL 202520250708003Milwaukee6,391$20.00$13.044Zignego Company, Inc.WisDOT
10 JUN 202520250610001Grant1,257$15.00$15.003Michels Road & Stone, Inc.WisDOT
Latest WisDOT contracts carrying Removing concrete barrier

Filter this item by your own quantity, county and period, or check your price against it, in the WisDOT explorer.

How these prices were read

WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WisDOT's own: this item is compared with WisDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the WisDOT letting of 10 NOV 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.