WisDOT contract 20250708003 bid tabulation
1100-20-77. Let by Wisconsin DOT on July 8, 2025, Milwaukee. 4 bids received; low bid $29,064,699 by Zignego Company, Inc..
- Owner
- Wisconsin DOT
- Letting
- 08 JUL 2025
- Pay items
- 426
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Zignego Company, Inc. | $29,064,699 | Low |
| 2 | Michels Road & Stone, Inc. | $32,541,439 | +12% |
| 3 | Zenith Tech., Inc. - Waukesha | $34,322,084 | +18% |
| 4 | Lalonde Contractors Incorporated | $41,734,439 | +44% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Zignego Company, Inc. | 2. Michels Road & Stone, Inc. | 3. Zenith Tech., Inc. - Waukesha | 4. Lalonde Contractors Incorporated |
|---|---|---|---|---|---|---|---|
| 1 | CPM progress schedule (108.4400) | EACH | 1 | $1,000.00 | $5,000.00 | $0.01 | $24,440 |
| 2 | Removing structure (structure) 001. B-40-349 (203.0220) | EACH | 1 | $400,000 | $400,000 | $300,000 | $168,000 |
| 3 | Removing structure (structure) 002. B-40-348 (203.0220) | EACH | 1 | $400,000 | $400,000 | $300,000 | $168,000 |
| 4 | Removing structure (structure) 009. B-40-346 (203.0220) | EACH | 1 | $45,000 | $45,000 | $100,000 | $35,000 |
| 5 | Removing structure (structure) 010. B-40-347 (203.0220) | EACH | 1 | $45,000 | $45,000 | $100,000 | $35,000 |
| 6 | Removing structure (structure) 013. B-40-365 (203.0220) | EACH | 1 | $80,000 | $80,000 | $50,000 | $25,000 |
| 7 | Removing structure (structure) 014. removing structure B-40-366 (203.0220) | EACH | 1 | $80,000 | $80,000 | $50,000 | $25,000 |
| 8 | Debris containment (structure) 013. B-40-365 (203.0330) | EACH | 1 | $1,000.00 | $1,000.00 | $15,000 | $11,000 |
| 9 | Debris containment (structure) 014. debris containment B-40-366 (203.0330) | EACH | 1 | $1,000.00 | $1,000.00 | $15,000 | $11,000 |
| 10 | Removing concrete pavement (204.0100) | SY | 11,045 | $20.00 | $5.00 | $5.00 | $11.07 |
| 11 | Removing concrete surface partial depth (204.0109.S) | SF | 58,375 | $0.40 | $0.40 | $0.40 | $0.40 |
| 12 | Removing asphaltic surface butt joints (204.0115) | SY | 317 | $10.75 | $10.75 | $25.00 | $10.75 |
| 13 | Removing asphaltic surface milling (204.0120) | SY | 107,864 | $2.25 | $2.25 | $4.80 | $2.25 |
| 14 | Removing curb & gutter (204.0150) | LF | 2,291 | $20.00 | $4.00 | $4.00 | $12.01 |
| 15 | Removing concrete sidewalk (204.0155) | SY | 140 | $20.00 | $4.00 | $4.00 | $20.69 |
| 16 | Removing concrete barrier (204.0157) | LF | 6,391 | $20.00 | $10.00 | $10.00 | $16.08 |
| 17 | Removing guardrail (204.0165) | LF | 3,871 | $3.00 | $3.00 | $2.50 | $3.00 |
| 18 | Removing fence (204.0170) | LF | 1,581 | $3.00 | $3.00 | $4.50 | $3.00 |
| 19 | Removing concrete slope paving (204.0175) | SY | 309 | $20.00 | $52.00 | $52.00 | $18.32 |
| 20 | Removing concrete bases (204.0195) | EACH | 17 | $1,000.00 | $250.00 | $250.00 | $1,500.00 |
| 21 | Removing inlets (204.0220) | EACH | 11 | $500.00 | $500.00 | $500.00 | $1,200.00 |
| 22 | Removing storm sewer (size) 001. 12-inch (204.0245) | LF | 362 | $35.00 | $32.00 | $32.00 | $152.00 |
| 23 | Removing ancillary structure (structure) 001. S-40-240 (204.0246) | EACH | 1 | $9,500.00 | $9,500.00 | $13,000 | $9,500.00 |
| 24 | Removing (item description) 001. apron endwall (204.9060.S) | EACH | 4 | $500.00 | $208.00 | $208.00 | $3,700.00 |
| 25 | Removing (item description) 301. remove traffic signals IH 41 SB off ramp/N115TH ST & CTH PP (204.9060.S) | EACH | 1 | $5,610.00 | $5,610.00 | $5,610.00 | $5,610.00 |
| 26 | Removing (item description) 302. remove loop detector wire & lead-in cable IH 41 SB off/N 115TH ST & CTH PP (204.9060.S) | EACH | 1 | $1,122.00 | $1,122.00 | $1,122.00 | $1,122.00 |
| 27 | Excavation common (205.0100) | CY | 9,500 | $24.00 | $24.00 | $24.00 | $38.22 |
| 28 | Excavation for structures bridges (structure) 009. B-40-346 (206.1001) | EACH | 1 | $10,000 | $3,219.00 | $3,219.00 | $11,000 |
| 29 | Excavation for structures bridges (structure) 010. B-40-347 (206.1001) | EACH | 1 | $10,000 | $2,840.00 | $2,840.00 | $11,000 |
| 30 | Excavation for structures bridges (structure) 013. excavation for structures bridges B-40-365 (206.1001) | EACH | 1 | $10,000 | $2,035.00 | $2,035.00 | $11,000 |
| 31 | Excavation for structures bridges (structure) 014. B-40-366 (206.1001) | EACH | 1 | $10,000 | $2,083.00 | $2,083.00 | $11,000 |
| 32 | Excavation for structures retaining walls (structure) 001. R-40-714 (206.3001) | EACH | 1 | $1.00 | $172,000 | $172,000 | $176,237 |
| 33 | Excavation for structures retaining walls (structure) 004. R-40-715 (206.3001) | EACH | 1 | $1.00 | $178,000 | $178,000 | $179,728 |
| 34 | Borrow (208.0100) | CY | 7,813 | $0.01 | $0.01 | $0.01 | $18.81 |
| 35 | Backfill granular grade 1 (209.1100) | CY | 1,794 | $47.00 | $88.00 | $88.00 | $68.76 |
| 36 | Backfill structure type A (210.1100) | CY | 66 | $100.00 | $50.00 | $50.00 | $92.92 |
| 37 | Backfill structure type A (210.1500) | TON | 1,628 | $50.00 | $28.00 | $28.00 | $29.99 |
| 38 | Prepare foundation for asphaltic paving (project) 001. 1100-21-70 (211.0101) | EACH | 1 | $1.00 | $0.01 | $7,005.00 | $12,500 |
| 39 | Prepare foundation for asphaltic paving (project) 002. 1100-21-71 (211.0101) | EACH | 1 | $1.00 | $0.01 | $12,132 | $12,500 |
| 40 | Finishing roadway (project) 001. 1100-20-77 (213.0100) | EACH | 1 | $1,000.00 | $3,000.00 | $3,500.00 | $3,680.00 |
| 41 | Finishing roadway (project) 002. 1100-21-70 (213.0100) | EACH | 1 | $1,000.00 | $3,000.00 | $3,500.00 | $3,680.00 |
| 42 | Finishing roadway (project) 003. 1100-21-71 (213.0100) | EACH | 1 | $1,000.00 | $3,000.00 | $3,500.00 | $3,680.00 |
| 43 | Base aggregate dense 3/4-inch (305.0110) | TON | 594 | $50.00 | $39.00 | $39.00 | $39.37 |
| 44 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 9,261 | $19.50 | $22.00 | $22.00 | $25.03 |
| 45 | Base aggregate open-graded (310.0110) | TON | 86 | $100.00 | $34.00 | $34.00 | $58.92 |
| 46 | Select crushed material (312.0110) | TON | 12,118 | $18.00 | $25.00 | $25.00 | $29.64 |
| 47 | Removing pavement for base patching (390.0100) | CY | 8,818 | $40.00 | $110.00 | $207.59 | $100.54 |
| 48 | Base patching concrete shes (390.0405) | CY | 8,818 | $110.00 | $365.00 | $407.73 | $528.64 |
| 49 | Concrete pavement 6-inch (415.0060) | SY | 34 | $300.00 | $150.00 | $135.20 | $90.28 |
| 50 | Concrete pavement 8-inch (415.0080) | SY | 76 | $300.00 | $145.00 | $110.51 | $117.39 |
| 51 | Concrete pavement 9-inch (415.0090) | SY | 9,679 | $67.00 | $85.00 | $64.69 | $77.15 |
| 52 | Concrete pavement approach slab (415.0410) | SY | 472 | $0.01 | $275.00 | $169.99 | $197.64 |
| 53 | Concrete pavement hes 8-inch (415.1080) | SY | 418 | $68.00 | $155.00 | $74.72 | $125.01 |
| 54 | Concrete pavement approach slab hes (415.1410) | SY | 1,006 | $0.01 | $375.00 | $168.87 | $201.98 |
| 55 | Drilled tie bars (416.0610) | EACH | 4,629 | $0.01 | $10.00 | $8.48 | $15.76 |
| 56 | Drilled dowel bars (416.0620) | EACH | 10,061 | $0.01 | $5.00 | $26.98 | $19.05 |
| 57 | Concrete pavement repair shes (416.1715) | SY | 414 | $200.00 | $180.00 | $219.58 | $304.71 |
| 58 | Concrete pavement replacement shes (416.1725) | SY | 4,540 | $193.00 | $184.00 | $223.87 | $257.51 |
| 59 | Continuous diamond grinding concrete pavement (420.1000) | SY | 29,802 | $4.74 | $4.74 | $12.62 | $4.97 |
| 60 | HMA cold weather paving (450.4000) | TON | 183 | $5.00 | $5.00 | $1.50 | $5.00 |
| 61 | Tack coat (455.0605) | GAL | 14,555 | $3.60 | $3.60 | $2.25 | $3.60 |
| 62 | HMA pavement test strip volumetrics (460.0115.S) | EACH | 1 | $5,000.00 | $5,000.00 | $1,185.00 | $5,000.00 |
| 63 | HMA pavement test strip density (460.0120.S) | EACH | 1 | $5,000.00 | $5,000.00 | $4,800.00 | $5,000.00 |
| 64 | Incentive density HMA pavement (460.2000) | DOL | 10,221 | $1.00 | $1.00 | $1.00 | $1.00 |
| 65 | Incentive density HMA pavement longitudinal joints (460.2007) | DOL | 8,863 | $1.00 | $1.00 | $1.00 | $1.00 |
| 66 | HMA pavement 3 HT 58-28 H (460.7423) | TON | 15,787 | $96.05 | $96.05 | $102.80 | $96.05 |
| 67 | HMA pavement 5 SMA 58-28 V (460.8625) | TON | 10,696 | $136.05 | $136.05 | $119.50 | $136.05 |
| 68 | Material transfer vehicle (460.9000.S) | EACH | 1 | $0.01 | $0.01 | $32,000 | $0.01 |
| 69 | Asphaltic surface (465.0105) | TON | 440 | $102.00 | $102.00 | $90.35 | $102.00 |
| 70 | Asphaltic surface temporary (465.0125) | TON | 2,199 | $95.00 | $95.00 | $99.25 | $95.00 |
| 71 | Cold patch (495.1000.S) | TON | 5 | $750.00 | $750.00 | $250.00 | $876.00 |
| 72 | Ice hot weather concreting (501.1000.S) | LB | 9,440 | $0.01 | $0.01 | $0.90 | $1.00 |
| 73 | Concrete masonry bridges (502.0100) | CY | 573 | $825.00 | $825.00 | $1,600.00 | $1,050.00 |
| 74 | Expansion device (502.3101) | LF | 433 | $255.00 | $255.00 | $500.00 | $385.00 |
| 75 | Protective surface treatment (502.3200) | SY | 2,413 | $5.00 | $5.00 | $5.00 | $4.00 |
| 76 | Pigmented surface sealer reseal (502.3205) | SY | 1,272 | $15.00 | $15.00 | $25.00 | $20.00 |
| 77 | Pigmented surface sealer (502.3210) | SY | 340 | $11.00 | $11.00 | $15.00 | $13.00 |
| 78 | Adhesive anchors no. 5 bar (502.4205) | EACH | 761 | $18.00 | $18.00 | $30.00 | $25.00 |
| 79 | Prestressed girder type I 54W-inch (503.0155) | LF | 1,442 | $275.00 | $275.00 | $275.00 | $240.00 |
| 80 | Bar steel reinforcement HS structures (505.0400) | LB | 19,590 | $1.25 | $1.25 | $2.00 | $1.80 |
| 81 | Bar steel reinforcement HS coated structures (505.0600) | LB | 208,210 | $1.40 | $1.40 | $1.65 | $1.55 |
| 82 | Bar steel reinforcement HS stainless structures (505.0800.S) | LB | 4,480 | $3.80 | $3.80 | $4.00 | $3.85 |
| 83 | Bar couplers no. 4 (505.0904) | EACH | 8 | $55.00 | $55.00 | $160.00 | $140.00 |
| 84 | Bar couplers no. 5 (505.0905) | EACH | 54 | $35.00 | $35.00 | $61.00 | $55.00 |
| 85 | Bar couplers no. 6 (505.0906) | EACH | 38 | $52.00 | $52.00 | $89.00 | $75.00 |
| 86 | Structural steel carbon (506.0105) | LB | 80 | $150.00 | $150.00 | $300.00 | $300.00 |
| 87 | Structural steel HS (506.0605) | LB | 890 | $37.50 | $37.50 | $35.00 | $25.00 |
| 88 | Bearing pads elastomeric non- laminated (506.2605) | EACH | 28 | $100.00 | $100.00 | $155.00 | $155.00 |
| 89 | Bearing pads elastomeric laminated (506.2610) | EACH | 19 | $2,500.00 | $2,500.00 | $2,000.00 | $2,000.00 |
| 90 | Steel diaphragms (structure) 001. B-40-1022 (506.4000) | EACH | 12 | $1,800.00 | $1,800.00 | $2,500.00 | $2,500.00 |
| 91 | Steel diaphragms (structure) 002. B-40-1023 (506.4000) | EACH | 12 | $1,800.00 | $1,800.00 | $2,500.00 | $2,500.00 |
| 92 | Removing bearings (structure) 011. B-40-350 (506.7050.S) | EACH | 9 | $1,100.00 | $1,100.00 | $2,700.00 | $1,800.00 |
| 93 | Removing bearings (structure) 012. B-40-351 (506.7050.S) | EACH | 10 | $1,100.00 | $1,100.00 | $2,700.00 | $1,800.00 |
| 94 | Preparation decks type 1 (509.0301) | SY | 11 | $285.00 | $285.00 | $300.00 | $300.00 |
| 95 | Preparation decks type 2 (509.0302) | SY | 9 | $285.00 | $285.00 | $550.00 | $550.00 |
| 96 | Sawing pavement deck preparation areas (509.0310.S) | LF | 122 | $10.00 | $10.00 | $15.00 | $15.00 |
| 97 | Cleaning decks (509.0500) | SY | 7,697 | $12.61 | $12.61 | $13.00 | $13.00 |
| 98 | Joint repair (509.1000) | SY | 277 | $850.00 | $850.00 | $2,000.00 | $1,900.00 |
| 99 | Concrete surface repair (509.1500) | SF | 371 | $210.00 | $210.00 | $350.00 | $350.00 |
| 100 | Full-depth deck repair (509.2000) | SY | 2 | $500.00 | $500.00 | $1,650.00 | $1,650.00 |
| 101 | Concrete masonry deck repair (509.2100.S) | CY | 30 | $600.00 | $600.00 | $2,500.00 | $2,500.00 |
| 102 | Epoxy crack sealing (509.9020.S) | LF | 114 | $25.00 | $25.00 | $100.00 | $100.00 |
| 103 | Temporary shoring (511.1100) | SF | 499 | $78.00 | $0.01 | $0.01 | $0.10 |
| 104 | Temporary shoring (structure) 001. B-40-1022 (511.1200) | SF | 2,070 | $78.00 | $78.00 | $150.00 | $150.00 |
| 105 | Temporary shoring (structure) 013. B-40-365 (511.1200) | SF | 60 | $55.00 | $55.00 | $300.00 | $210.00 |
| 106 | Temporary shoring (structure) 014. temporary shoring B-40-366 (511.1200) | SF | 60 | $55.00 | $55.00 | $300.00 | $210.00 |
| 107 | Railing pipe (513.2001) | LF | 554 | $200.00 | $200.00 | $250.00 | $225.00 |
| 108 | Rubberized membrane waterproofing (516.0500) | SY | 121 | $35.00 | $35.00 | $75.00 | $70.00 |
| 109 | Painting epoxy system (structure) 015.painting epoxy system B-40- 369 (517.0601) | EACH | 1 | $25,000 | $7,500.00 | $25,000 | $25,220 |
| 110 | Preparation and coating of top flanges (structure) 009. B-40-346 (517.0901.S) | EACH | 1 | $20,000 | $9,500.00 | $20,000 | $20,176 |
| 111 | Preparation and coating of top flanges (structure) 010. B-40-347 (517.0901.S) | EACH | 1 | $20,000 | $9,500.00 | $20,000 | $20,176 |
| 112 | Preparation and coating of top flanges (structure) 013. B-40-365 (517.0901.S) | EACH | 1 | $20,000 | $9,500.00 | $20,000 | $20,176 |
| 113 | Preparation and coating of top flanges (structure) 014. B-40-366 (517.0901.S) | EACH | 1 | $20,000 | $9,500.00 | $20,000 | $20,176 |
| 114 | Structure repainting recycled abrasive (structure) 007. B-40-248 (517.1801.S) | EACH | 1 | $200,000 | $224,420 | $200,000 | $201,763 |
| 115 | Structure repainting recycled abrasive (structure) 008. B-40-249 (517.1801.S) | EACH | 1 | $200,000 | $224,420 | $200,000 | $201,763 |
| 116 | Structure repainting recycled abrasive (structure) 009. B-40-346 (517.1801.S) | EACH | 1 | $160,000 | $192,780 | $160,000 | $161,410 |
| 117 | Structure repainting recycled abrasive (structure) 010. B-40-347 (517.1801.S) | EACH | 1 | $138,000 | $192,780 | $138,000 | $139,217 |
| 118 | Structure repainting recycled abrasive (structure) 013. B-40-365 (517.1801.S) | EACH | 1 | $120,000 | $140,400 | $120,000 | $121,058 |
| 119 | Structure repainting recycled abrasive (structure) 014. B-40-366 (517.1801.S) | EACH | 1 | $115,000 | $140,400 | $115,000 | $116,014 |
| 120 | Structure repainting recycled abrasive (structure) 015. B-40-369 (517.1801.S) | EACH | 1 | $150,000 | $179,010 | $150,000 | $151,322 |
| 121 | Structure overcoating cleaning and priming (structure) 013. B-40-365 (517.3001.S) | EACH | 1 | $75,000 | $82,500 | $75,000 | $75,661 |
| 122 | Structure overcoating cleaning and priming (structure) 014. B-40-366 (517.3001.S) | EACH | 1 | $80,000 | $82,500 | $80,000 | $80,705 |
| 123 | Structure overcoating cleaning and priming (structure) 015. B-40-369 (517.3001.S) | EACH | 1 | $2,500.00 | $3,000.00 | $2,500.00 | $2,522.04 |
| 124 | Containment and collection of waste materials (structure) 013. B- 40-365 (517.4001.S) | EACH | 1 | $40,000 | $27,500 | $40,000 | $40,353 |
| 125 | Containment and collection of waste materials (structure) 014. B- 40-366 (517.4001.S) | EACH | 1 | $45,000 | $27,500 | $45,000 | $45,397 |
| 126 | Containment and collection of waste materials (structure) 015. B- 40-369 (517.4001.S) | EACH | 1 | $2,500.00 | $3,000.00 | $2,500.00 | $2,522.04 |
| 127 | Negative pressure containment and collection of waste materials (structure) 007. B-40-248 (517.4501.S) | EACH | 1 | $110,000 | $128,240 | $110,000 | $110,970 |
| 128 | Negative pressure containment and collection of waste materials (structure) 008. B-40-249 (517.4501.S) | EACH | 1 | $110,000 | $128,240 | $110,000 | $110,970 |
| 129 | Negative pressure containment and collection of waste materials (structure) 009. B-40-346 (517.4501.S) | EACH | 1 | $105,000 | $123,930 | $105,000 | $105,926 |
| 130 | Negative pressure containment and collection of waste materials (structure) 010. B-40-347 (517.4501.S) | EACH | 1 | $92,000 | $123,930 | $92,000 | $92,811 |
| 131 | Negative pressure containment and collection of waste materials (structure) 013. B-40-365 (517.4501.S) | EACH | 1 | $80,000 | $93,600 | $80,000 | $80,705 |
| 132 | Negative pressure containment and collection of waste materials (structure) 014. B-40-366 (517.4501.S) | EACH | 1 | $75,000 | $93,600 | $75,000 | $75,661 |
| 133 | Negative pressure containment and collection of waste materials (structure) 015. B-40-369 (517.4501.S) | EACH | 1 | $110,000 | $119,340 | $110,000 | $110,970 |
| 134 | Portable decontamination facility (517.6001.S) | EACH | 7 | $2,000.00 | $500.00 | $2,000.00 | $2,017.63 |
| 135 | Apron endwalls for culvert pipe reinforced concrete 18-inch (522.1018) | EACH | 4 | $1,500.00 | $1,756.00 | $1,756.00 | $5,051.00 |
| 136 | Concrete masonry ancillary structures type NS (531.1100) | CY | 34 | $1,100.00 | $1,100.00 | $1,050.00 | $1,100.00 |
| 137 | Steel reinforcement HS ancillary structures type NS (531.1140) | LB | 3,988 | $4.25 | $4.25 | $5.00 | $4.25 |
| 138 | Steel reinforcement HS coated ancillary structures type NS (531.1160) | LB | 890 | $4.50 | $4.50 | $5.50 | $4.50 |
| 139 | Drilling shaft 24-inch (531.2024) | LF | 141 | $79.00 | $79.00 | $30.00 | $79.00 |
| 140 | Drilling shaft 30-inch (531.2030) | LF | 30 | $225.00 | $225.00 | $150.00 | $225.00 |
| 141 | Drilling shaft 36-inch (531.2036) | LF | 20 | $298.00 | $298.00 | $298.00 | $298.00 |
| 142 | Foundation camera pole 50-FT (531.4050) | EACH | 2 | $4,180.00 | $4,180.00 | $4,180.00 | $4,180.00 |
| 143 | Butterfly 2-chord NS (structure) 001. S-40-3063 (532.5020) | EACH | 1 | $31,500 | $31,500 | $41,000 | $31,500 |
| 144 | Pile points (550.0500) | EACH | 48 | $150.00 | $150.00 | $145.00 | $145.00 |
| 145 | Piling steel HP 14-inch X 73 LB (550.1140) | LF | 3,360 | $51.00 | $51.00 | $110.00 | $100.00 |
| 146 | Concrete curb & gutter 31-inch (601.0331) | LF | 297 | $30.00 | $30.00 | $38.13 | $30.00 |
| 147 | Concrete curb & gutter 30-inch type A (601.0409) | LF | 310 | $30.00 | $30.00 | $51.95 | $30.00 |
| 148 | Concrete curb & gutter 4-inch sloped 36-inch type A (601.0551) | LF | 431 | $30.00 | $30.00 | $46.29 | $30.00 |
| 149 | Concrete curb & gutter 4-inch sloped 36-inch type TBTT (601.0590) | LF | 2,089 | $28.00 | $28.00 | $24.32 | $28.00 |
| 150 | Concrete curb pedestrian (601.0600) | LF | 36 | $45.00 | $45.00 | $74.30 | $45.00 |
| 151 | Concrete sidewalk 5-inch (602.0410) | SF | 2,742 | $12.00 | $12.00 | $7.71 | $12.00 |
| 152 | Curb ramp detectable warning field yellow (602.0505) | SF | 183 | $48.00 | $48.00 | $51.80 | $48.00 |
| 153 | Concrete driveway 7-inch (602.0815) | SY | 58 | $75.00 | $75.00 | $93.75 | $75.00 |
| 154 | Concrete barrier single-faced 32- inch (603.0105) | LF | 1,115 | $200.00 | $200.00 | $122.49 | $200.00 |
| 155 | Concrete barrier type S42 (603.1142) | LF | 5,132 | $125.00 | $125.00 | $94.36 | $125.00 |
| 156 | Concrete barrier type S56C (603.1456) | LF | 281 | $265.00 | $265.00 | $202.81 | $265.00 |
| 157 | Concrete barrier transition type NJ32SF to S36 (603.3113) | EACH | 1 | $7,500.00 | $7,500.00 | $4,786.41 | $7,500.00 |
| 158 | Concrete barrier transition type F32SF to S32 (603.3211) | EACH | 4 | $7,500.00 | $7,500.00 | $4,683.26 | $7,500.00 |
| 159 | Concrete barrier transition type S36 to S42 (603.3535) | EACH | 5 | $7,500.00 | $7,500.00 | $4,487.62 | $7,500.00 |
| 160 | Concrete barrier temporary precast delivered (603.8000) | LF | 29,580 | $7.00 | $7.00 | $0.01 | $0.01 |
| 161 | Concrete barrier temporary precast installed (603.8125) | LF | 29,580 | $3.50 | $3.50 | $19.50 | $19.50 |
| 162 | Anchoring concrete barrier temporary precast (603.8500) | LF | 12,215 | $3.00 | $3.00 | $4.00 | $4.00 |
| 163 | Slope paving concrete (604.0400) | SY | 426 | $150.00 | $125.00 | $390.00 | $194.69 |
| 164 | Slope paving crushed aggregate (604.0500) | SY | 304 | $55.00 | $55.00 | $34.00 | $56.72 |
| 165 | Slope paving repair crushed aggregate (604.9010.S) | CY | 24 | $175.00 | $175.00 | $100.00 | $1,018.75 |
| 166 | Reseal crushed aggregate slope paving (604.9015.S) | SY | 1,731 | $15.61 | $24.00 | $24.00 | $30.44 |
| 167 | Riprap medium (606.0200) | CY | 39 | $300.00 | $141.00 | $141.00 | $204.30 |
| 168 | Storm sewer pipe reinforced concrete class III 12-inch (608.0312) | LF | 16 | $164.00 | $197.00 | $197.00 | $416.00 |
| 169 | Storm sewer pipe reinforced concrete class III 18-inch (608.0318) | LF | 747 | $167.00 | $119.00 | $119.00 | $344.00 |
| 170 | Storm sewer pipe reinforced concrete class IV 12-inch (608.0412) | LF | 10 | $300.00 | $236.00 | $236.00 | $416.00 |
| 171 | Manhole covers type J-special (611.0535) | EACH | 9 | $886.00 | $1,083.00 | $1,083.00 | $1,093.00 |
| 172 | Inlet covers type BW (611.0610) | EACH | 56 | $1,110.00 | $1,509.00 | $1,509.00 | $1,425.00 |
| 173 | Inlet covers type H (611.0624) | EACH | 2 | $1,093.00 | $1,486.00 | $1,486.00 | $1,195.00 |
| 174 | Inlet covers type MS (611.0642) | EACH | 1 | $878.00 | $616.00 | $616.00 | $786.00 |
| 175 | Inlet covers type V (611.0654) | EACH | 14 | $1,041.00 | $1,421.00 | $1,421.00 | $1,144.00 |
| 176 | Manholes 4-FT diameter (611.2004) | EACH | 9 | $4,000.00 | $6,387.00 | $6,387.00 | $12,450 |
| 177 | Inlets 4-FT diameter (611.3004) | EACH | 56 | $5,000.00 | $5,753.00 | $5,753.00 | $14,906 |
| 178 | Inlets 2X2.5-FT (611.3225) | EACH | 14 | $5,000.00 | $2,543.00 | $2,543.00 | $7,661.00 |
| 179 | Inlets 2X3-FT (611.3230) | EACH | 2 | $6,000.00 | $5,190.00 | $5,190.00 | $6,941.00 |
| 180 | Inlets median 1 grate (611.3901) | EACH | 1 | $7,500.00 | $4,609.00 | $4,609.00 | $6,829.00 |
| 181 | Adjusting inlet covers (611.8115) | EACH | 4 | $1,000.00 | $1,401.00 | $1,401.00 | $4,166.00 |
| 182 | Cover plates temporary (611.8120.S) | EACH | 7 | $300.00 | $100.00 | $100.00 | $1,500.00 |
| 183 | Pipe underdrain 6-inch (612.0106) | LF | 2,823 | $15.00 | $8.00 | $8.00 | $37.53 |
| 184 | Pipe underdrain unperforated 6- inch (612.0206) | LF | 185 | $50.00 | $17.00 | $17.00 | $44.64 |
| 185 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 1,044 | $15.00 | $4.00 | $4.00 | $39.48 |
| 186 | Guardrail mow strip emulsified asphalt (614.0397) | SY | 294 | $18.50 | $18.50 | $22.00 | $37.98 |
| 187 | Crash cushions temporary (614.0905) | EACH | 23 | $3,215.11 | $3,215.11 | $3,000.00 | $3,215.11 |
| 188 | MGS guardrail 3 (614.2300) | LF | 2,381 | $33.00 | $33.00 | $28.50 | $33.00 |
| 189 | MGS guardrail 3 QS (614.2320) | LF | 94 | $47.00 | $47.00 | $48.00 | $47.00 |
| 190 | MGS guardrail 3 K (614.2330) | LF | 1,289 | $39.00 | $39.00 | $38.50 | $39.00 |
| 191 | MGS thrie beam transition (614.2500) | LF | 512.40 | $92.00 | $92.00 | $94.00 | $92.00 |
| 192 | MGS guardrail terminal eat (614.2610) | EACH | 12 | $4,300.00 | $4,300.00 | $3,800.00 | $4,300.00 |
| 193 | MGS guardrail terminal type 2 (614.2620) | EACH | 3 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 |
| 194 | Fence chain link 6-FT (616.0206) | LF | 1,589 | $44.50 | $44.50 | $45.50 | $44.50 |
| 195 | Gates chain link (width) 001. 12-FT (616.0329) | EACH | 1 | $3,521.00 | $3,521.00 | $3,400.00 | $3,521.00 |
| 196 | Fence track clearance (616.0800.S) | LF | 540 | $5.00 | $5.00 | $10.50 | $5.00 |
| 197 | Maintenance and repair of haul roads (project) 001. 1100-20-77 (618.0100) | EACH | 1 | $1.00 | $100.00 | $4,000.00 | $1.00 |
| 198 | Maintenance and repair of haul roads (project) 002. 1100-21-70 (618.0100) | EACH | 1 | $1.00 | $100.00 | $4,000.00 | $1.00 |
| 199 | Maintenance and repair of haul roads (project) 003. 1100-21-71 (618.0100) | EACH | 1 | $1.00 | $100.00 | $4,000.00 | $1.00 |
| 200 | Mobilization (619.1000) | EACH | 1 | $4,474,000 | $3,607,302 | $1,650,000 | $5,785,704 |
| 201 | Dust control surface treatment (623.0200) | SY | 8,774 | $0.01 | $0.01 | $0.01 | $0.01 |
| 202 | Water (624.0100) | MGAL | 61 | $100.00 | $151.00 | $151.00 | $42.20 |
| 203 | Topsoil (625.0100) | SY | 9,317 | $0.01 | $2.00 | $2.00 | $8.00 |
| 204 | Salvaged topsoil (625.0500) | SY | 5,053 | $6.00 | $3.00 | $3.00 | $4.68 |
| 205 | Mulching (627.0200) | SY | 3,286 | $0.65 | $0.65 | $0.32 | $0.65 |
| 206 | Silt fence (628.1504) | LF | 8,061 | $2.50 | $2.50 | $2.25 | $2.50 |
| 207 | Silt fence maintenance (628.1520) | LF | 8,061 | $0.01 | $0.01 | $0.05 | $0.01 |
| 208 | Mobilizations erosion control (628.1905) | EACH | 46 | $100.00 | $100.00 | $250.00 | $100.00 |
| 209 | Mobilizations emergency erosion control (628.1910) | EACH | 27 | $100.00 | $100.00 | $300.00 | $100.00 |
| 210 | Erosion mat class I type A (628.2002) | SY | 11,097 | $1.25 | $1.25 | $0.93 | $1.25 |
| 211 | Erosion mat class I type B (628.2004) | SY | 210 | $1.25 | $1.25 | $0.98 | $1.25 |
| 212 | Erosion mat class II type B (628.2023) | SY | 12 | $2.50 | $2.50 | $1.75 | $2.50 |
| 213 | Inlet protection type A (628.7005) | EACH | 15 | $150.00 | $150.00 | $160.00 | $150.00 |
| 214 | Inlet protection type C (628.7015) | EACH | 16 | $75.00 | $75.00 | $60.00 | $75.00 |
| 215 | Inlet protection type D (628.7020) | EACH | 210 | $110.00 | $110.00 | $215.00 | $110.00 |
| 216 | Temporary ditch checks (628.7504) | LF | 360 | $9.00 | $9.00 | $9.50 | $9.00 |
| 217 | Tracking pads (628.7560) | EACH | 9 | $1.00 | $2,330.00 | $2,330.00 | $1,694.50 |
| 218 | Fertilizer type B (629.0210) | CWT | 5.30 | $125.00 | $125.00 | $75.00 | $125.00 |
| 219 | Seeding mixture no. 40 (630.0140) | LB | 10 | $25.00 | $25.00 | $50.00 | $25.00 |
| 220 | Seeding mixture no. 70 (630.0170) | LB | 52 | $155.00 | $155.00 | $100.00 | $155.00 |
| 221 | Seeding temporary (630.0200) | LB | 6 | $10.00 | $10.00 | $50.00 | $10.00 |
| 222 | Seed water (630.0500) | MGAL | 273.50 | $20.00 | $20.00 | $80.00 | $20.00 |
| 223 | Sod lawn (631.1000) | SY | 114 | $25.00 | $25.00 | $20.00 | $25.00 |
| 224 | Delineators barrier wall (633.1000) | EACH | 6 | $65.00 | $65.00 | $50.00 | $65.00 |
| 225 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 48 | $110.00 | $110.00 | $125.00 | $110.00 |
| 226 | Posts wood 4X6-inch X 22-FT (634.0622) | EACH | 55 | $125.00 | $125.00 | $175.00 | $125.00 |
| 227 | Posts tubular steel 2X2-inch X 14- FT (634.0814) | EACH | 3 | $200.00 | $200.00 | $250.00 | $200.00 |
| 228 | Sign supports structural steel HS (635.0200) | LB | 13,000 | $4.50 | $4.50 | $6.50 | $4.50 |
| 229 | Sign supports replacing base connection bolts (635.0300) | EACH | 4 | $275.00 | $275.00 | $250.00 | $275.00 |
| 230 | Signs type I reflective SH (637.1220) | SF | 4,152 | $26.00 | $26.00 | $29.50 | $26.00 |
| 231 | Signs type II reflective H (637.2210) | SF | 1,236.63 | $20.00 | $20.00 | $24.50 | $20.00 |
| 232 | Signs type II reflective H folding (637.2215) | SF | 92.22 | $26.00 | $26.00 | $30.00 | $26.00 |
| 233 | Signs type II reflective F (637.2230) | SF | 486.50 | $22.00 | $22.00 | $24.50 | $22.00 |
| 234 | Moving signs type I (638.2101) | EACH | 2 | $1,000.00 | $1,000.00 | $850.00 | $1,000.00 |
| 235 | Moving signs type II (638.2102) | EACH | 15 | $225.00 | $225.00 | $75.00 | $225.00 |
| 236 | Removing signs type I (638.2601) | EACH | 29 | $700.00 | $700.00 | $350.00 | $700.00 |
| 237 | Removing signs type II (638.2602) | EACH | 129 | $40.00 | $40.00 | $35.00 | $40.00 |
| 238 | Removing small sign supports (638.3000) | EACH | 97 | $40.00 | $40.00 | $35.00 | $40.00 |
| 239 | Removing structural steel sign supports (638.3100) | EACH | 22 | $500.00 | $500.00 | $400.00 | $500.00 |
| 240 | Traffic control drums (643.0300) | DAY | 200,663 | $0.16 | $0.16 | $0.12 | $0.16 |
| 241 | Traffic control barricades type III (643.0420) | DAY | 5,793 | $0.92 | $0.92 | $0.55 | $0.92 |
| 242 | Traffic control warning lights type A (643.0705) | DAY | 11,586 | $0.32 | $0.32 | $0.10 | $0.32 |
| 243 | Traffic control warning lights type C (643.0715) | DAY | 41,228 | $0.13 | $0.13 | $0.10 | $0.13 |
| 244 | Traffic control arrow boards (643.0800) | DAY | 1,583 | $12.25 | $12.25 | $6.50 | $12.25 |
| 245 | Traffic control signs (643.0900) | DAY | 52,484 | $0.29 | $0.29 | $0.25 | $0.29 |
| 246 | Traffic control covering signs type I (643.0910) | EACH | 30 | $200.00 | $200.00 | $150.00 | $200.00 |
| 247 | Traffic control covering signs type II (643.0920) | EACH | 12 | $50.00 | $50.00 | $20.00 | $50.00 |
| 248 | Traffic control signs fixed message (643.1000) | SF | 1,429 | $21.16 | $21.16 | $12.50 | $21.16 |
| 249 | Traffic control signs PCMS (643.1050) | DAY | 170 | $50.00 | $50.00 | $22.00 | $50.00 |
| 250 | Dynamic late merge system (643.1100.S) | DAY | 498 | $169.02 | $169.02 | $225.00 | $169.02 |
| 251 | Portable automated real-time traffic queue warning system (643.1200.S) | DAY | 153 | $223.53 | $223.53 | $135.00 | $223.53 |
| 252 | Temporary marking line paint 4- inch (643.3105) | LF | 6,994 | $0.28 | $0.28 | $0.40 | $0.28 |
| 253 | Temporary marking line removable tape 4-inch (643.3150) | LF | 250 | $3.89 | $3.89 | $2.00 | $3.89 |
| 254 | Temporary marking line paint 6- inch (643.3165) | LF | 287,106 | $0.30 | $0.30 | $0.30 | $0.30 |
| 255 | Temporary marking line paint 8- inch (643.3205) | LF | 830 | $0.60 | $0.60 | $1.00 | $0.60 |
| 256 | Temporary marking line paint 10- inch (643.3265) | LF | 6,499 | $0.65 | $0.65 | $1.00 | $0.65 |
| 257 | Temporary marking raised pavement marker type I (643.3760) | EACH | 237 | $6.74 | $6.74 | $5.00 | $6.74 |
| 258 | Temporary marking stop line removable tape 18-inch (643.3850) | LF | 182 | $8.57 | $8.57 | $5.00 | $8.57 |
| 259 | Traffic control interim lane closure (643.4100) | EACH | 30 | $1,950.00 | $950.00 | $600.00 | $950.00 |
| 260 | Traffic control (643.5000) | EACH | 1 | $100,000 | $100,000 | $302,239 | $100,000 |
| 261 | Temporary pedestrian barricade (644.1810) | LF | 664 | $7.26 | $7.26 | $4.50 | $7.26 |
| 262 | Temporary audible message devices (644.1900.S) | DAY | 248 | $8.21 | $8.21 | $3.50 | $8.21 |
| 263 | Geotextile type DF schedule A (645.0111) | SY | 1,181 | $1.00 | $2.00 | $2.00 | $4.00 |
| 264 | Geotextile type HR (645.0120) | SY | 6 | $100.00 | $204.00 | $204.00 | $20.00 |
| 265 | Marking line epoxy 4-inch (646.1020) | LF | 8,016 | $0.80 | $0.80 | $0.32 | $0.80 |
| 266 | Marking line grooved wet ref epoxy 4-inch (646.1040) | LF | 2,184 | $1.25 | $1.25 | $1.06 | $1.25 |
| 267 | Marking line grooved black epoxy 6-inch (646.2025) | LF | 12,643 | $1.10 | $1.10 | $0.81 | $1.10 |
| 268 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 75,001 | $1.65 | $1.65 | $1.33 | $1.65 |
| 269 | Marking line grooved permanent tape 6-inch (646.2050) | LF | 12,643 | $9.20 | $9.20 | $6.97 | $9.20 |
| 270 | Marking line epoxy 8-inch (646.3020) | LF | 980 | $1.60 | $1.60 | $0.87 | $1.60 |
| 271 | Marking line grooved wet ref epoxy 8-inch (646.3040) | LF | 480 | $2.70 | $2.70 | $1.73 | $2.70 |
| 272 | Marking line grooved black epoxy 10-inch (646.4025) | LF | 2,202 | $2.25 | $2.25 | $1.78 | $2.25 |
| 273 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 15,926 | $3.00 | $3.00 | $2.65 | $3.00 |
| 274 | Marking line grooved permanent tape 10-inch (646.4050) | LF | 18,845 | $12.00 | $12.00 | $11.55 | $12.00 |
| 275 | Marking arrow epoxy (646.5020) | EACH | 37 | $300.00 | $300.00 | $233.23 | $300.00 |
| 276 | Marking word epoxy (646.5120) | EACH | 13 | $400.00 | $400.00 | $352.02 | $400.00 |
| 277 | Marking symbol epoxy (646.5220) | EACH | 25 | $405.00 | $405.00 | $225.15 | $405.00 |
| 278 | Marking stop line epoxy 18-inch (646.6120) | LF | 700 | $22.00 | $22.00 | $14.60 | $22.00 |
| 279 | Marking yield line epoxy 18-inch (646.6220) | EACH | 52 | $90.00 | $90.00 | $34.83 | $90.00 |
| 280 | Cold weather marking epoxy 4-inch (646.6464) | LF | 6,421 | $0.60 | $0.60 | $0.32 | $0.60 |
| 281 | Cold weather marking epoxy 6-inch (646.6466) | LF | 87,590 | $0.70 | $0.70 | $0.45 | $0.70 |
| 282 | Cold weather marking epoxy 10- inch (646.6470) | LF | 15,926 | $1.20 | $1.20 | $1.00 | $1.20 |
| 283 | Marking diagonal epoxy 12-inch (646.7120) | LF | 4,926 | $11.00 | $11.00 | $11.11 | $11.00 |
| 284 | Marking chevron epoxy 24-inch (646.7220) | LF | 1,253 | $14.00 | $14.00 | $23.94 | $14.00 |
| 285 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 823 | $13.00 | $13.00 | $10.72 | $13.00 |
| 286 | Marking island nose epoxy (646.8220) | EACH | 6 | $350.00 | $350.00 | $263.06 | $350.00 |
| 287 | Marking removal line 4-inch (646.9000) | LF | 150 | $1.15 | $1.15 | $2.00 | $1.15 |
| 288 | Marking removal line grooved contrast permanent tape 4-inch (646.9055) | LF | 45 | $1.50 | $1.50 | $5.00 | $1.50 |
| 289 | Marking removal line grooved contrast permanent tape 8-inch (646.9155) | LF | 1,239 | $1.75 | $1.75 | $3.00 | $1.75 |
| 290 | Conduit rigid metallic 2-inch (652.0125) | LF | 18 | $149.50 | $149.50 | $149.50 | $149.50 |
| 291 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 1,530 | $9.48 | $9.48 | $9.48 | $9.48 |
| 292 | Conduit rigid nonmetallic schedule 40 3-inch (652.0235) | LF | 588 | $11.90 | $11.90 | $11.90 | $11.90 |
| 293 | Conduit special 3-inch (652.0615) | LF | 788 | $31.70 | $31.70 | $31.70 | $31.70 |
| 294 | Install conduit into existing item (652.0700.S) | EACH | 10 | $220.00 | $220.00 | $220.00 | $220.00 |
| 295 | Conduit loop detector (652.0800) | LF | 1,618 | $8.05 | $8.05 | $8.05 | $8.05 |
| 296 | Pull boxes steel 24X36-inch (653.0135) | EACH | 8 | $1,312.00 | $1,312.00 | $1,312.00 | $1,312.00 |
| 297 | Pull boxes steel 24X42-inch (653.0140) | EACH | 15 | $1,409.00 | $1,409.00 | $1,409.00 | $1,409.00 |
| 298 | Removing pull boxes (653.0905) | EACH | 16 | $108.00 | $108.00 | $108.00 | $108.00 |
| 299 | Concrete bases type 1 (654.0101) | EACH | 6 | $1,054.00 | $1,054.00 | $1,054.00 | $1,054.00 |
| 300 | Concrete bases type 10 (654.0110) | EACH | 2 | $6,875.00 | $6,875.00 | $6,875.00 | $6,875.00 |
| 301 | Concrete bases type 10-special (654.0120) | EACH | 1 | $9,857.00 | $9,857.00 | $9,857.00 | $9,857.00 |
| 302 | Concrete control cabinet bases type 9 special (654.0217) | EACH | 1 | $2,989.00 | $2,989.00 | $2,989.00 | $2,989.00 |
| 303 | Cable in duct 4-4 AWG (655.0144) | LF | 3,936 | $14.34 | $14.34 | $14.34 | $14.34 |
| 304 | Cable in duct 4-6 AWG (655.0146) | LF | 4,243 | $12.94 | $12.94 | $12.94 | $12.94 |
| 305 | Cable in duct 4-8 AWG (655.0148) | LF | 1,254 | $11.34 | $11.34 | $11.34 | $11.34 |
| 306 | Cable traffic signal 5-14 AWG (655.0230) | LF | 511 | $1.92 | $1.92 | $1.92 | $1.92 |
| 307 | Cable traffic signal 7-14 AWG (655.0240) | LF | 153 | $2.27 | $2.27 | $2.27 | $2.27 |
| 308 | Cable traffic signal 12-14 AWG (655.0260) | LF | 1,705 | $3.32 | $3.32 | $3.32 | $3.32 |
| 309 | Electrical wire traffic signals 12 AWG (655.0510) | LF | 427 | $0.98 | $0.98 | $0.98 | $0.98 |
| 310 | Electrical wire traffic signals 10 AWG (655.0515) | LF | 1,664 | $1.52 | $1.52 | $1.52 | $1.52 |
| 311 | Electrical wire lighting 12 AWG (655.0610) | LF | 2,784 | $0.98 | $0.98 | $0.98 | $0.98 |
| 312 | Electrical wire lighting 6 AWG (655.0625) | LF | 124 | $2.12 | $2.12 | $2.12 | $2.12 |
| 313 | Loop detector lead in cable (655.0700) | LF | 5,559 | $2.17 | $2.17 | $2.17 | $2.17 |
| 314 | Loop detector wire (655.0800) | LF | 6,478 | $1.29 | $1.29 | $1.29 | $1.29 |
| 315 | Electrical service meter breaker pedestal (location) 301.IH 41 SB off ramp/N 115TH ST & CTH PP (656.0201) | EACH | 1 | $1,780.00 | $1,780.00 | $1,780.00 | $1,780.00 |
| 316 | Pedestal bases (657.0100) | EACH | 6 | $247.00 | $247.00 | $247.00 | $247.00 |
| 317 | Poles type A (657.0375) | EACH | 8 | $4,651.40 | $4,651.40 | $4,651.40 | $4,651.40 |
| 318 | Traffic signal standards aluminum 13-FT (657.0420) | EACH | 3 | $555.00 | $555.00 | $555.00 | $555.00 |
| 319 | Traffic signal standards aluminum 15-FT (657.0425) | EACH | 3 | $593.00 | $593.00 | $593.00 | $593.00 |
| 320 | Luminaire arms single member 6- inch clamp 4-FT (657.0620) | EACH | 16 | $284.00 | $284.00 | $284.00 | $284.00 |
| 321 | Luminaire arms single member 6- inch clamp 15-FT (657.0640) | EACH | 22 | $714.00 | $714.00 | $714.00 | $714.00 |
| 322 | Traffic signal face 3S 12-inch (658.0173) | EACH | 12 | $886.60 | $886.60 | $886.60 | $886.60 |
| 323 | Traffic signal face 4S 12-inch (658.0174) | EACH | 3 | $1,196.80 | $1,196.80 | $1,196.80 | $1,196.80 |
| 324 | Pedestrian signal face 16-inch (658.0416) | EACH | 4 | $697.80 | $697.80 | $697.80 | $697.80 |
| 325 | Pedestrian push buttons (658.0500) | EACH | 5 | $401.00 | $401.00 | $401.00 | $401.00 |
| 326 | Signal mounting hardware (location) 301. IH 41 SB off ramp/N115TH ST & CTH PP (658.5070) | EACH | 1 | $5,888.00 | $5,888.00 | $5,888.00 | $5,888.00 |
| 327 | Luminaires utility LED D (659.1130) | EACH | 38 | $375.20 | $375.20 | $375.20 | $375.20 |
| 328 | Lamp, ballast, LED, switch disposal by contractor (659.5000.S) | EACH | 30 | $8.60 | $8.60 | $8.60 | $8.60 |
| 329 | Temporary traffic signals for intersections (location) 301. IH 41 SB off ramp/N115TH ST & CTH PP (661.0201) | EACH | 1 | $45,109 | $45,109 | $45,109 | $45,109 |
| 330 | Generators (661.0300) | DAY | 2 | $290.00 | $290.00 | $290.00 | $290.00 |
| 331 | Field system integrator (670.0101) | EACH | 1 | $19,122 | $19,122 | $19,122 | $19,122 |
| 332 | ITS documentation (670.0201) | EACH | 1 | $6,912.00 | $6,912.00 | $6,912.00 | $6,912.00 |
| 333 | Remove cable (674.0300) | LF | 385 | $1.46 | $1.46 | $1.46 | $1.46 |
| 334 | Install camera pole 50-FT (677.0150) | EACH | 2 | $3,630.00 | $3,630.00 | $3,630.00 | $3,630.00 |
| 335 | Install camera assembly (677.0200) | EACH | 3 | $4,510.00 | $4,510.00 | $4,510.00 | $4,510.00 |
| 336 | Removing 50-FT camera pole (677.9051.S) | EACH | 2 | $2,805.00 | $2,805.00 | $2,805.00 | $2,805.00 |
| 337 | Removing CCTV camera (677.9200.S) | EACH | 2 | $830.00 | $830.00 | $830.00 | $830.00 |
| 338 | Fiber optic splice enclosure (678.0200) | EACH | 1 | $1,376.00 | $1,376.00 | $1,376.00 | $1,376.00 |
| 339 | Fiber optic splice (678.0300) | EACH | 4 | $301.40 | $301.40 | $301.40 | $301.40 |
| 340 | Communication system testing (678.0501) | EACH | 1 | $6,912.00 | $6,912.00 | $6,912.00 | $6,912.00 |
| 341 | Install ethernet switches (678.0600) | EACH | 1 | $1,211.00 | $1,211.00 | $1,211.00 | $1,211.00 |
| 342 | Sawing asphalt (690.0150) | LF | 102 | $2.55 | $2.55 | $2.55 | $2.55 |
| 343 | Sawing concrete (690.0250) | LF | 61,680 | $2.55 | $2.55 | $2.55 | $2.55 |
| 344 | Incentive strength concrete structures (715.0502) | DOL | 9,566 | $1.00 | $1.00 | $1.00 | $1.00 |
| 345 | Incentive strength concrete barrier (715.0603) | DOL | 3,264 | $1.00 | $1.00 | $1.00 | $1.00 |
| 346 | Incentive compressive strength concrete pavement (715.0720) | DOL | 3,269 | $1.00 | $1.00 | $1.00 | $1.00 |
| 347 | Incentive iri ride (740.0440) | DOL | 23,723 | $1.00 | $1.00 | $1.00 | $1.00 |
| 348 | Railroad flagging reimbursement (801.0117) | DOL | 17,250 | $1.00 | $1.00 | $1.00 | $1.00 |
| 349 | Installing and maintaining bird deterrent system (station) 001. sta 398+50 SB (999.2000.S) | EACH | 1 | $0.01 | $0.01 | $5,000.00 | $10,000 |
| 350 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,800 | $5.00 | $5.00 | $5.00 | $5.00 |
| 351 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 17,280 | $5.00 | $5.00 | $5.00 | $5.00 |
| 352 | Special 001. backfill slurry (SPV.0035) | CY | 100 | $100.00 | $113.00 | $113.00 | $190.60 |
| 353 | Special 200. HPC masonry structures (SPV.0035) | CY | 932 | $1,200.00 | $1,200.00 | $1,250.00 | $950.00 |
| 354 | Special 001. incentive density HMA pavement (SPV.0055) | DOL | 14,169 | $1.00 | $1.00 | $1.00 | $1.00 |
| 355 | Special 002. incentive air voids HMA pavement (SPV.0055) | DOL | 14,851 | $1.00 | $1.00 | $1.00 | $1.00 |
| 356 | Special 001. concrete barrier type S42 end anchor (SPV.0060) | EACH | 4 | $6,000.00 | $6,000.00 | $4,564.27 | $6,000.00 |
| 357 | Special 002. concrete barrier transition type M1 (SPV.0060) | EACH | 4 | $18,000 | $18,000 | $8,031.33 | $18,000 |
| 358 | Special 003. concrete barrier transition type M2 (SPV.0060) | EACH | 2 | $19,000 | $19,000 | $11,400 | $19,000 |
| 359 | Special 004. concrete barrier transition type M3 (SPV.0060) | EACH | 2 | $20,000 | $20,000 | $7,986.72 | $20,000 |
| 360 | Special 005. mobilizations emergency pavement repair (SPV.0060) | EACH | 8 | $500.00 | $4,450.00 | $4,150.00 | $10,000 |
| 361 | Special 006. storm sewer pipe reinforced concrete special tee fitting (SPV.0060) | EACH | 1 | $3,000.00 | $43,872 | $43,872 | $15,016 |
| 362 | Special 007. beehive grate on 12- inch pipe bell (SPV.0060) | EACH | 1 | $1,000.00 | $991.00 | $991.00 | $3,495.00 |
| 363 | Special 009. utility line opening (SPV.0060) | EACH | 21 | $1.00 | $1,985.00 | $1,309.52 | $1,985.00 |
| 364 | Special 010. field facilities office space (SPV.0060) | EACH | 1 | $54,000 | $45,325 | $240,000 | $45,510 |
| 365 | Special 011. traffic control close- open freeway ramp (SPV.0060) | EACH | 7 | $1,250.00 | $250.00 | $450.00 | $250.00 |
| 366 | Special 012. traffic control local road lane closures (SPV.0060) | EACH | 3 | $150.00 | $150.00 | $450.00 | $150.00 |
| 367 | Special 013. traffic control full freeway closure (SPV.0060) | EACH | 3 | $1,597.53 | $1,597.53 | $1,200.00 | $1,597.53 |
| 368 | Special 016. reconnect storm sewer (SPV.0060) | EACH | 67 | $1,750.00 | $2,733.00 | $2,733.00 | $7,172.00 |
| 369 | Special 018. emergency inlet repair (SPV.0060) | EACH | 5 | $6,000.00 | $9,641.00 | $9,641.00 | $15,000 |
| 370 | Special 019. emergency response to traffic involving concrete barrier temporary (SPV.0060) | EACH | 5 | $6,000.00 | $958.52 | $2,800.00 | $958.52 |
| 371 | Special 020. emergency response to traffic involving crash cushion (SPV.0060) | EACH | 5 | $958.52 | $958.52 | $650.00 | $958.52 |
| 372 | Special 021. survey project 1100- 21-70 (SPV.0060) | EACH | 1 | $52,941 | $52,941 | $52,941 | $52,941 |
| 373 | Special 022. survey project 1100- 21-71 (SPV.0060) | EACH | 1 | $77,941 | $77,941 | $77,941 | $77,941 |
| 374 | Special 025. marking median inlet epoxy 6-inch (SPV.0060) | EACH | 95 | $150.00 | $150.00 | $34.83 | $90.00 |
| 375 | Special 027. concrete barrier type S56 end anchor (SPV.0060) | EACH | 4 | $7,000.00 | $7,000.00 | $5,504.42 | $7,000.00 |
| 376 | Special 050. ground rod (SPV.0060) | EACH | 2 | $145.00 | $145.00 | $145.00 | $145.00 |
| 377 | Special 051. loop detector splice (SPV.0060) | EACH | 6 | $132.00 | $132.00 | $132.00 | $132.00 |
| 378 | Special 100. removing light poles (SPV.0060) | EACH | 8 | $561.00 | $561.00 | $561.00 | $561.00 |
| 379 | Special 101. removing luminaire arms (SPV.0060) | EACH | 16 | $68.00 | $68.00 | $68.00 | $68.00 |
| 380 | Special 102. temporary wood pole 60-FT (SPV.0060) | EACH | 38 | $3,653.00 | $3,653.00 | $3,653.00 | $3,653.00 |
| 381 | Special 103. concrete bases type B (SPV.0060) | EACH | 14 | $3,430.00 | $3,430.00 | $3,430.00 | $3,430.00 |
| 382 | Special 104. lighting system integrator 1100-21-70 (SPV.0060) | EACH | 1 | $2,018.00 | $2,018.00 | $2,018.00 | $2,018.00 |
| 383 | Special 105. lighting system integrator 1100-21-71 (SPV.0060) | EACH | 1 | $2,018.00 | $2,018.00 | $2,018.00 | $2,018.00 |
| 384 | Special 106. lighting system survey 1100-21-70 (SPV.0060) | EACH | 1 | $2,040.00 | $2,040.00 | $2,040.00 | $2,040.00 |
| 385 | Special 107. lighting system survey 1100-21-71 (SPV.0060) | EACH | 1 | $2,040.00 | $2,040.00 | $2,040.00 | $2,040.00 |
| 386 | Special 108. maintenance of lighting systems 1100-21-70 (SPV.0060) | EACH | 1 | $7,504.00 | $7,504.00 | $7,504.00 | $7,504.00 |
| 387 | Special 109. maintenance of lighting system 1100-21-71 (SPV.0060) | EACH | 1 | $7,504.00 | $7,504.00 | $7,504.00 | $7,504.00 |
| 388 | Special 200. embedded galvanic anodes (SPV.0060) | EACH | 341 | $60.00 | $60.00 | $60.00 | $60.00 |
| 389 | Special 201. cleaning and sealing concrete girder ends (SPV.0060) | EACH | 19 | $450.00 | $450.00 | $3,500.00 | $2,400.00 |
| 390 | Special 202. vegetation removal B- 40-365 (SPV.0060) | EACH | 1 | $1,500.00 | $1,500.00 | $3,500.00 | $1,500.00 |
| 391 | Special 203. vegetation removal B- 40-366 (SPV.0060) | EACH | 1 | $1,500.00 | $1,500.00 | $3,500.00 | $1,500.00 |
| 392 | Special 250. heat straightening of damaged girders (SPV.0060) | EACH | 1 | $70,000 | $70,000 | $67,000 | $67,000 |
| 393 | Special 260. RE-epoxy bearing anchor bolt (SPV.0060) | EACH | 50 | $650.00 | $650.00 | $700.00 | $700.00 |
| 394 | Special 261. bearing anchor bolt nut adjustment (SPV.0060) | EACH | 3 | $1,600.00 | $1,600.00 | $265.00 | $265.00 |
| 395 | Special 301. install poles type 9 (SPV.0060) | EACH | 2 | $1,646.00 | $1,646.00 | $1,646.00 | $1,646.00 |
| 396 | Special 302. install poles type 9- special (SPV.0060) | EACH | 1 | $1,646.00 | $1,646.00 | $1,646.00 | $1,646.00 |
| 397 | Special 303. install monotube arms 20-FT (SPV.0060) | EACH | 1 | $2,640.00 | $2,640.00 | $2,640.00 | $2,640.00 |
| 398 | Special 304. install monotube arms 30-FT (SPV.0060) | EACH | 1 | $2,895.00 | $2,895.00 | $2,895.00 | $2,895.00 |
| 399 | Special 305. install monotube arms 35-FT-special (SPV.0060) | EACH | 1 | $2,980.00 | $2,980.00 | $2,980.00 | $2,980.00 |
| 400 | Special 306. TRSNPT & inst state furn traff signal cab IH 41SB off /N 115TH ST & CTH PP (SPV.0060) | EACH | 1 | $5,810.00 | $5,810.00 | $5,810.00 | $5,810.00 |
| 401 | Special 307. TRSNPT traffic signal materials IH 41SB off /N 115TH ST & CTH PP (SPV.0060) | EACH | 1 | $680.00 | $680.00 | $680.00 | $680.00 |
| 402 | Special 308. temporary non- intrusive vehicle detection system for intersections (SPV.0060) | EACH | 1 | $6,647.00 | $6,647.00 | $6,647.00 | $6,647.00 |
| 403 | Special 309. TRSNPT & inst S-F FO cable pigtail IH 41SB off /N 115TH ST & CTH PP (SPV.0060) | EACH | 1 | $1,172.00 | $1,172.00 | $1,172.00 | $1,172.00 |
| 404 | Special 450. tension anchor rod (SPV.0060) | EACH | 40 | $500.00 | $500.00 | $800.00 | $500.00 |
| 405 | Special 451. remove debris (SPV.0060) | EACH | 2 | $1,500.00 | $1,500.00 | $1,000.00 | $1,500.00 |
| 406 | Special 452. remove catwalk (SPV.0060) | EACH | 4 | $7,500.00 | $7,500.00 | $5,000.00 | $7,500.00 |
| 407 | Special 453. tension structural bolt (SPV.0060) | EACH | 8 | $250.00 | $250.00 | $400.00 | $250.00 |
| 408 | Special 454. vertical sign support (SPV.0060) | EACH | 2 | $800.00 | $800.00 | $1,000.00 | $800.00 |
| 409 | Special 455. replace junction box cover (SPV.0060) | EACH | 1 | $350.00 | $1,234.40 | $250.00 | $1,234.40 |
| 410 | Special 456. conduit plug (SPV.0060) | EACH | 1 | $150.00 | $254.00 | $200.00 | $254.00 |
| 411 | Special 001. pavement cleanup project 1100-21-71 (SPV.0075) | HRS | 100 | $300.00 | $150.00 | $211.90 | $244.00 |
| 412 | Special 001. seeding mixture no. 90A (SPV.0085) | LB | 64 | $120.00 | $120.00 | $125.00 | $120.00 |
| 413 | Special 001. glare screen temporary (SPV.0090) | LF | 12,154 | $7.12 | $7.12 | $6.00 | $7.12 |
| 414 | Special 024. temporary precast trench drain (SPV.0090) | LF | 1,157 | $250.00 | $231.00 | $231.00 | $2,181.00 |
| 415 | Special 110. temporary overhead cable quadruplex 2 AWG (SPV.0090) | LF | 12,503 | $6.49 | $6.49 | $6.49 | $6.49 |
| 416 | Special 200. longitudinal grooving bridge deck (SPV.0165) | SF | 18,054 | $0.50 | $0.50 | $1.08 | $1.06 |
| 417 | Special 201. wall concrete panel mechanically stabilized earth R-40- 714 (SPV.0165) | SF | 6,470 | $123.00 | $137.00 | $160.00 | $171.47 |
| 418 | Special 202. wall concrete panel mechanically stabilized earth R-40- 715 (SPV.0165) | SF | 6,550 | $123.00 | $137.00 | $160.00 | $172.03 |
| 419 | Special 203. temporary wire faced mechanically stabilized earth (SPV.0165) | SF | 1,815 | $100.00 | $124.00 | $124.00 | $200.00 |
| 420 | Special 204. removing loose concrete (SPV.0165) | SF | 75 | $75.00 | $75.00 | $100.00 | $65.00 |
| 421 | Special 450. repair galvanized coating (SPV.0165) | SF | 3 | $150.00 | $150.00 | $250.00 | $150.00 |
| 422 | Special 001. resin binder high friction surface treatment (SPV.0180) | SY | 3,806 | $24.90 | $25.50 | $24.90 | $24.90 |
| 423 | Special 002. removing concrete rumble strips (SPV.0180) | SY | 642 | $35.00 | $35.00 | $49.50 | $35.00 |
| 424 | Special 200. polyester polymer concrete overlay (SPV.0180) | SY | 7,697 | $118.00 | $118.00 | $143.00 | $144.26 |
| 425 | Special 201. abutment seat cleaning and sealing (SPV.0180) | SY | 115 | $120.00 | $120.00 | $130.00 | $90.00 |
| 426 | Special 001. asphaltic repair (SPV.0195) | TON | 40 | $337.00 | $337.00 | $350.00 | $337.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of July 8, 2025. Compiled by Mirage Metrics.