Loop detector wire, WisDOT 655.0800

Low bidders on WisDOT contracts carried a median of $1.14 per LF for this item, over the 24 months to 10 NOV 2026, across 66 low bids. Half of all 255 bids fell between $1.00 and $1.30.

Owner
Wisconsin DOT
Item
655.0800
Unit
LF
Data through
10 NOV 2026

WisDOT prints this item as “Loop Detector Wire”.

$1.14Low bidder's median, per LF
$1.20Median of all bids, per LF
67Contracts in the window

By year of letting

Loop detector wire, WisDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20222827$1.1076$1.10
20233734$1.23133$1.25
20243331$1.01133$1.01
20253433$1.12123$1.12
20262323$1.2093$1.25

Bid prices as published, not adjusted for inflation.

By county

CountyLow bidsLow-bid medianAll bidsMedian, all bids
Milwaukee15$1.2564$1.15
Dane8$1.0038$1.00
Outagamie6$0.9522$0.90
Waukesha5$1.0319$1.30
Walworth4$1.2111$1.30
Winnebago3$0.9011$0.90
Loop detector wire, WisDOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Quantity (LF)Low bidsLow-bid median
270 to 2,39516$1.25
2,630 to 4,84417$1.00
5,242 to 9,00016$1.19
9,525 to 81,15117$1.12
Loop detector wire, WisDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

Loop detector wire, WisDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
10 NOV 202620261110011Dane3,400$1.25$1.274Rock Road Companies, Inc.WisDOT
10 NOV 202620261110013Dane3,606$0.99$0.992Rock Road Companies, Inc.WisDOT
13 OCT 202620261013006Milwaukee4,292$2.42$2.422Zenith Tech., Inc. - WaukeshaWisDOT
15 SEP 202620260915007Milwaukee59,859$1.52$1.523Payne and Dolan, IncWisDOT
11 AUG 202620260811009Walworth19,378$1.13$1.296Musson Bros., Inc.WisDOT
11 AUG 202620260811015Portage1,990$1.43$1.437Hoffman Construction CompanyWisDOT
14 JUL 202620260714002Dane5,454$1.25$1.255R.G. Huston Company, Inc.WisDOT
14 JUL 202620260714004Milwaukee18,708$1.34$1.346Lalonde Contractors IncorporatedWisDOT
14 JUL 202620260714005Outagamie424$1.20$1.206Vinton Construction CompanyWisDOT
09 JUN 202620260609001Waukesha24,388$1.03$1.032Payne and Dolan, IncWisDOT
12 MAY 202620260512007Sauk3,094$1.80$1.803Zignego Company, Inc.WisDOT
14 APR 202620260414017Ozaukee2,208$1.47$1.474Stark Pavement CorporationWisDOT
10 MAR 202620260310016Milwaukee14,364$0.88$0.885Hoffman Construction CompanyWisDOT
10 FEB 202620260210009Milwaukee5,660$0.88$0.884Lalonde Contractors IncorporatedWisDOT
10 FEB 202620260210011Washington3,402$1.00$1.001Zenith Tech., Inc. - WaukeshaWisDOT
Latest WisDOT contracts carrying Loop detector wire

Filter this item by your own quantity, county and period, or check your price against it, in the WisDOT explorer.

How these prices were read

WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WisDOT's own: this item is compared with WisDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the WisDOT letting of 10 NOV 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy