WisDOT contract 20260414017 bid tabulation
4030-03-70. Let by Wisconsin DOT on April 14, 2026, Ozaukee. 4 bids received; low bid $3,939,352 by Stark Pavement Corporation.
- Owner
- Wisconsin DOT
- Letting
- 14 APR 2026
- Pay items
- 133
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Stark Pavement Corporation | $3,939,352 | Low |
| 2 | Lalonde Contractors Incorporated | $4,150,196 | +5.0% |
| 3 | Zignego Company, Inc. | $4,150,574 | +5.0% |
| 4 | Payne and Dolan, Inc | $4,283,709 | +9.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Stark Pavement Corporation | 2. Lalonde Contractors Incorporated | 3. Zignego Company, Inc. | 4. Payne and Dolan, Inc |
|---|---|---|---|---|---|---|---|
| 1 | Grubbing (201.0220) | ID | 54 | $45.00 | $40.00 | $40.00 | $40.00 |
| 2 | Removing concrete pavement (204.0100) | SY | 45 | $50.00 | $16.00 | $70.00 | $20.00 |
| 3 | Removing asphaltic surface (204.0110) | SY | 4,221 | $5.00 | $13.33 | $11.00 | $9.00 |
| 4 | Removing asphaltic surface butt joints (204.0115) | SY | 217 | $6.80 | $33.50 | $33.50 | $8.00 |
| 5 | Removing asphaltic surface milling (204.0120) | SY | 88,000 | $4.90 | $3.15 | $3.15 | $3.90 |
| 6 | Removing curb & gutter (204.0150) | LF | 5,045 | $9.50 | $9.10 | $9.50 | $9.00 |
| 7 | Removing concrete sidewalk (204.0155) | SY | 2,340 | $8.00 | $11.14 | $13.00 | $6.50 |
| 8 | Removing inlets (204.0220) | EACH | 1 | $550.00 | $550.00 | $850.00 | $550.00 |
| 9 | Removing storm sewer (size) 01. 12-inch (204.0245) | LF | 38 | $12.00 | $12.00 | $50.00 | $12.00 |
| 10 | Removing storm sewer (size) 02. 36-inch (204.0245) | LF | 35 | $30.00 | $30.00 | $50.00 | $30.00 |
| 11 | Removing (item description) 01. traffic signals (STH 33 & foster drive) (204.9060.S) | EACH | 1 | $3,227.00 | $3,227.00 | $3,227.00 | $3,227.00 |
| 12 | Excavation common (205.0100) | CY | 731 | $29.90 | $42.14 | $60.00 | $34.60 |
| 13 | Finishing roadway (project) 01. 4030-03-70 (213.0100) | EACH | 1 | $5,500.00 | $2,910.00 | $1,000.00 | $2,400.00 |
| 14 | Finishing roadway (project) 02. 4030-03-71 (213.0100) | EACH | 1 | $5,500.00 | $2,910.00 | $1,000.00 | $2,400.00 |
| 15 | Base aggregate dense 3/4-inch (305.0115) | CY | 61 | $114.20 | $61.82 | $100.00 | $220.00 |
| 16 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 35 | $55.85 | $34.60 | $50.00 | $110.00 |
| 17 | Base aggregate dense 1 1/4-inch (305.0125) | CY | 98 | $94.50 | $61.81 | $100.00 | $74.00 |
| 18 | Drilled tie bars (416.0610) | EACH | 540 | $18.00 | $20.37 | $20.00 | $10.00 |
| 19 | Tack coat (455.0605) | GAL | 6,229 | $3.00 | $2.30 | $2.30 | $2.30 |
| 20 | HMA percent within limits (PWL) test strip volumetrics (460.0105.S) | EACH | 1 | $8,000.00 | $1,225.00 | $1,225.00 | $1,450.00 |
| 21 | HMA percent within limits (PWL) test strip density (460.0110.S) | EACH | 1 | $4,000.00 | $7,975.00 | $7,975.00 | $8,800.00 |
| 22 | Incentive density PWL HMA pavement (460.2005) | DOL | 9,515 | $1.00 | $1.00 | $1.00 | $1.00 |
| 23 | Incentive density HMA pavement longitudinal joints (460.2007) | DOL | 4,920 | $1.00 | $1.00 | $1.00 | $1.00 |
| 24 | Incentive air voids HMA pavement (460.2010) | DOL | 11,615 | $1.00 | $1.00 | $1.00 | $1.00 |
| 25 | HMA pavement 3 MT 58-28 S (460.6223) | TON | 270 | $180.10 | $159.50 | $159.50 | $176.75 |
| 26 | HMA pavement 4 MT 58-28 H (460.6424) | TON | 11,720 | $99.85 | $91.10 | $91.10 | $97.25 |
| 27 | Asphaltic surface (465.0105) | TON | 453 | $187.10 | $285.00 | $285.00 | $365.00 |
| 28 | Asphaltic surface temporary (465.0125) | TON | 16 | $265.00 | $225.00 | $225.00 | $225.00 |
| 29 | Cold patch (495.1000.S) | TON | 100 | $265.00 | $225.00 | $1.00 | $225.00 |
| 30 | Concrete collars for pipe (520.8000) | EACH | 3 | $550.00 | $550.00 | $1,500.00 | $550.00 |
| 31 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 4,969 | $26.00 | $52.81 | $50.00 | $54.95 |
| 32 | Concrete curb pedestrian (601.0600) | LF | 1,292 | $55.00 | $54.59 | $60.00 | $26.20 |
| 33 | Concrete sidewalk 5-inch (602.0410) | SF | 24,082 | $9.20 | $10.45 | $13.50 | $10.30 |
| 34 | Curb ramp detectable warning field yellow (602.0505) | SF | 1,853 | $52.00 | $45.98 | $60.00 | $45.00 |
| 35 | Curb ramp detectable warning field radial yellow (602.0605) | SF | 358 | $65.00 | $66.41 | $100.00 | $58.00 |
| 36 | Concrete driveway 6-inch (602.0810) | SY | 29 | $85.00 | $87.99 | $100.00 | $100.00 |
| 37 | Concrete driveway 8-inch (602.0820) | SY | 45 | $95.00 | $102.85 | $100.00 | $115.00 |
| 38 | Storm sewer pipe reinforced concrete class III 12-inch (608.0312) | LF | 43 | $88.00 | $88.00 | $200.00 | $88.00 |
| 39 | Storm sewer pipe reinforced concrete class III 36-inch (608.0336) | LF | 44 | $196.00 | $196.00 | $300.00 | $196.00 |
| 40 | Storm sewer pipe class III-A 12- inch (608.3012) | LF | 65 | $88.00 | $88.00 | $150.00 | $88.00 |
| 41 | Reconstructing manholes (611.0420) | EACH | 3 | $1,443.00 | $1,443.00 | $1,850.00 | $1,443.00 |
| 42 | Reconstructing inlets (611.0430) | EACH | 7 | $1,443.00 | $1,443.00 | $1,650.00 | $1,443.00 |
| 43 | Manhole covers type J-special (611.0535) | EACH | 1 | $810.00 | $810.00 | $1,250.00 | $810.00 |
| 44 | Manhole covers type K (611.0540) | EACH | 1 | $1,764.00 | $1,764.00 | $1,350.00 | $1,764.00 |
| 45 | Inlet covers type A (611.0600) | EACH | 4 | $1,012.00 | $1,012.00 | $1,350.00 | $1,012.00 |
| 46 | Catch basins 6-FT diameter (611.1006) | EACH | 2 | $5,428.00 | $5,428.00 | $8,000.00 | $5,428.00 |
| 47 | Manholes 6-FT diameter (611.2006) | EACH | 1 | $5,873.00 | $5,873.00 | $9,000.00 | $5,873.00 |
| 48 | Inlets 3-FT diameter (611.3003) | EACH | 2 | $2,108.00 | $2,108.00 | $3,000.00 | $2,108.00 |
| 49 | Adjusting manhole covers (611.8110) | EACH | 1 | $1,050.00 | $1,050.00 | $950.00 | $1,050.00 |
| 50 | Adjusting inlet covers (611.8115) | EACH | 36 | $1,050.00 | $1,050.00 | $1,000.00 | $1,050.00 |
| 51 | Maintenance and repair of haul roads (project) 01. 4030-03-70 (618.0100) | EACH | 1 | $5,000.00 | $1.00 | $1.00 | $1.00 |
| 52 | Maintenance and repair of haul roads (project) 02. 4030-03-71 (618.0100) | EACH | 1 | $5,000.00 | $1.00 | $1.00 | $1.00 |
| 53 | Mobilization (619.1000) | EACH | 1 | $210,500 | $530,397 | $365,000 | $430,000 |
| 54 | Water (624.0100) | MGAL | 27 | $50.00 | $56.20 | $1.00 | $50.00 |
| 55 | Mulching (627.0200) | SY | 2,000 | $0.33 | $0.33 | $0.33 | $0.33 |
| 56 | Mobilizations erosion control (628.1905) | EACH | 4 | $85.00 | $85.00 | $85.00 | $85.00 |
| 57 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $50.00 | $50.00 | $50.00 | $50.00 |
| 58 | Inlet protection type B (628.7010) | EACH | 2 | $45.00 | $45.00 | $45.00 | $45.00 |
| 59 | Inlet protection type C (628.7015) | EACH | 66 | $33.00 | $33.00 | $33.00 | $33.00 |
| 60 | Inlet protection type D (628.7020) | EACH | 174 | $62.50 | $62.50 | $62.50 | $62.50 |
| 61 | Seeding temporary (630.0200) | LB | 6 | $12.00 | $12.00 | $12.00 | $12.00 |
| 62 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 316 | $76.50 | $76.50 | $76.50 | $76.50 |
| 63 | Signs type I reflective SH (637.1220) | SF | 28 | $43.00 | $43.00 | $43.00 | $43.00 |
| 64 | Signs type II reflective H (637.2210) | SF | 2,357 | $19.99 | $19.99 | $19.99 | $19.99 |
| 65 | Signs type II reflective H folding (637.2215) | SF | 153 | $27.90 | $27.90 | $27.90 | $27.90 |
| 66 | Signs type II reflective SH (637.2220) | SF | 7 | $28.00 | $28.00 | $28.00 | $28.00 |
| 67 | Signs type II reflective F (637.2230) | SF | 881 | $19.25 | $19.25 | $19.25 | $19.25 |
| 68 | Moving signs type II (638.2102) | EACH | 11 | $85.00 | $85.00 | $85.00 | $85.00 |
| 69 | Removing signs type II (638.2602) | EACH | 510 | $12.00 | $12.00 | $12.00 | $12.00 |
| 70 | Removing small sign supports (638.3000) | EACH | 295 | $12.50 | $12.50 | $12.50 | $12.50 |
| 71 | Field office type C (642.5201) | EACH | 1 | $10,150 | $13,664 | $20,000 | $17,000 |
| 72 | Traffic control drums (643.0300) | DAY | 9,044 | $0.25 | $0.50 | $0.50 | $0.15 |
| 73 | Traffic control barricades type III (643.0420) | DAY | 3,072 | $0.60 | $1.00 | $1.00 | $0.45 |
| 74 | Traffic control warning lights type A (643.0705) | DAY | 6,144 | $0.10 | $0.20 | $0.20 | $0.12 |
| 75 | Traffic control warning lights type C (643.0715) | DAY | 648 | $0.10 | $0.20 | $0.20 | $0.12 |
| 76 | Traffic control connected arrow boards (643.0810) | DAY | 108 | $18.00 | $40.00 | $40.00 | $12.00 |
| 77 | Traffic control signs (643.0900) | DAY | 22,700 | $0.35 | $0.45 | $0.45 | $0.20 |
| 78 | Traffic control covering signs type II (643.0920) | EACH | 100 | $35.00 | $50.00 | $50.00 | $48.50 |
| 79 | Traffic control signs fixed message (643.1000) | SF | 300 | $18.00 | $24.00 | $24.00 | $19.00 |
| 80 | Traffic control signs PCMS (643.1050) | DAY | 86 | $35.00 | $75.00 | $75.00 | $12.50 |
| 81 | Traffic control cones 42-inch (643.1070) | DAY | 113,184 | $0.20 | $0.50 | $0.50 | $0.13 |
| 82 | Traffic control connected work zone start and end location markers (643.1220) | DAY | 432 | $10.00 | $5.00 | $5.00 | $3.60 |
| 83 | Temporary marking line paint 4- inch (643.3105) | LF | 62,632 | $0.35 | $0.45 | $0.45 | $0.18 |
| 84 | Temporary marking line epoxy 6- inch (643.3170) | LF | 3,952 | $2.05 | $4.00 | $4.00 | $0.44 |
| 85 | Temporary marking line paint 8- inch (643.3205) | LF | 13,004 | $0.60 | $0.85 | $0.85 | $0.40 |
| 86 | Temporary marking line epoxy 10- inch (643.3270) | LF | 1,177 | $3.40 | $6.75 | $6.75 | $1.49 |
| 87 | Temporary marking arrow paint (643.3505) | EACH | 94 | $115.00 | $75.00 | $75.00 | $183.00 |
| 88 | Temporary marking word paint (643.3605) | EACH | 37 | $130.00 | $75.00 | $75.00 | $283.00 |
| 89 | Temporary marking stop line paint 18-inch (643.3805) | LF | 1,139 | $4.00 | $1.91 | $1.91 | $12.25 |
| 90 | Traffic control (643.5000) | EACH | 1 | $161,000 | $30,000 | $30,000 | $152,000 |
| 91 | Temporary pedestrian barricade (644.1810) | LF | 6,750 | $4.50 | $5.00 | $5.00 | $4.30 |
| 92 | Temporary audible message devices (644.1900.S) | DAY | 4,368 | $5.00 | $5.00 | $5.00 | $3.50 |
| 93 | Marking line grooved black epoxy 6-inch (646.2025) | LF | 14,864 | $1.10 | $1.10 | $1.10 | $0.87 |
| 94 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 59,993 | $1.45 | $1.45 | $1.45 | $1.42 |
| 95 | Marking line grooved black epoxy 10-inch (646.4025) | LF | 4,267 | $2.25 | $2.25 | $2.25 | $1.93 |
| 96 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 13,004 | $3.10 | $3.10 | $3.10 | $2.85 |
| 97 | Marking arrow epoxy (646.5020) | EACH | 94 | $225.00 | $225.00 | $225.00 | $383.42 |
| 98 | Marking word epoxy (646.5120) | EACH | 37 | $245.00 | $245.00 | $245.00 | $388.12 |
| 99 | Marking stop line epoxy 18-inch (646.6120) | LF | 1,139 | $13.00 | $13.00 | $13.00 | $16.09 |
| 100 | Marking diagonal epoxy 12-inch (646.7120) | LF | 76 | $9.75 | $9.75 | $9.75 | $15.67 |
| 101 | Marking chevron epoxy 24-inch (646.7220) | LF | 131 | $13.75 | $13.75 | $13.75 | $26.39 |
| 102 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 2,639 | $10.50 | $10.50 | $10.50 | $15.25 |
| 103 | Marking crosswalk epoxy block style 24-inch (646.7520) | LF | 1,042 | $17.50 | $17.50 | $17.50 | $26.39 |
| 104 | Marking curb epoxy (646.8120) | LF | 1,033 | $8.00 | $8.00 | $8.00 | $7.69 |
| 105 | Marking island nose epoxy (646.8220) | EACH | 32 | $275.00 | $275.00 | $275.00 | $289.41 |
| 106 | Construction staking storm sewer (650.4000) | EACH | 6 | $180.00 | $180.00 | $180.00 | $180.00 |
| 107 | Construction staking subgrade (650.4500) | LF | 761 | $0.01 | $0.01 | $0.01 | $0.01 |
| 108 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 4,969 | $1.50 | $1.50 | $1.50 | $1.50 |
| 109 | Construction staking resurfacing reference (650.8000) | LF | 11,181 | $0.25 | $0.25 | $0.25 | $0.25 |
| 110 | Construction staking electrical installations (project) 01. 4030-03- 70 (650.8501) | EACH | 1 | $800.00 | $800.00 | $800.00 | $800.00 |
| 111 | Construction staking curb ramps (650.9000) | EACH | 144 | $200.00 | $200.00 | $200.00 | $200.00 |
| 112 | Construction staking sidewalk (project) 01. 4030-03-70 (650.9500) | EACH | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 113 | Construction staking sidewalk (project) 02. 4030-03-71 (650.9500) | EACH | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 114 | Construction staking supplemental control (project) 01. 4030-03-70 (650.9911) | EACH | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 115 | Construction staking supplemental control (project) 02. 4030-03-71 (650.9911) | EACH | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 116 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 42 | $41.71 | $41.71 | $41.71 | $41.71 |
| 117 | Conduit loop detector (652.0800) | LF | 736 | $8.67 | $8.67 | $8.67 | $8.67 |
| 118 | Pull boxes steel 24X36-inch (653.0135) | EACH | 1 | $1,490.00 | $1,483.00 | $1,483.00 | $1,483.00 |
| 119 | Loop detector lead in cable (655.0700) | LF | 1,944 | $2.17 | $2.17 | $2.17 | $2.17 |
| 120 | Loop detector wire (655.0800) | LF | 2,208 | $1.47 | $1.47 | $1.47 | $1.47 |
| 121 | Sawing asphalt (690.0150) | LF | 6,189 | $1.25 | $1.20 | $1.39 | $1.20 |
| 122 | Sawing concrete (690.0250) | LF | 1,110 | $2.30 | $2.25 | $1.95 | $2.10 |
| 123 | Incentive iri ride (740.0440) | DOL | 4,250 | $1.00 | $1.00 | $1.00 | $1.00 |
| 124 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 1,100 | $5.00 | $5.00 | $5.00 | $5.00 |
| 125 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 2,400 | $5.00 | $5.00 | $5.00 | $5.00 |
| 126 | Special 01. RRFB system STH 33 WB right at sweetwater BLVD (SPV.0060) | EACH | 1 | $8,500.00 | $6,031.00 | $6,031.00 | $6,031.00 |
| 127 | Special 02. RRFB system STH 33 median back to back at sweetwater BLVD (SPV.0060) | EACH | 1 | $8,500.00 | $6,414.00 | $6,414.00 | $6,414.00 |
| 128 | Special 03. RRFB system STH 33 EB right at sweetwater BLVD (SPV.0060) | EACH | 1 | $8,500.00 | $6,031.00 | $6,031.00 | $6,031.00 |
| 129 | Special 04. curb ramp grading, shaping, and finishing (SPV.0060) | EACH | 104 | $210.00 | $408.58 | $1,210.00 | $660.00 |
| 130 | Special 01. cleaning storm sewers (SPV.0090) | LF | 3,825 | $35.00 | $25.00 | $12.50 | $25.00 |
| 131 | Special 02. marking line grooved wet ref epoxy 18-inch (SPV.0090) | LF | 450 | $13.50 | $13.50 | $13.50 | $23.20 |
| 132 | Special 01. exposed aggregate concrete sidewalk 5-inch (SPV.0165) | SF | 695 | $18.00 | $19.72 | $15.00 | $18.00 |
| 133 | Special 01. asphaltic repair (SPV.0195) | TON | 264 | $268.10 | $355.00 | $355.00 | $420.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of April 14, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.