WisDOT contract 20261110011 bid tabulation
C Madison, Mineral Point Road; USH 12 to High Point Road (LOC STR, Dane County C Madison, Mineral Point Road). Let by Wisconsin DOT on November 10, 2026, Dane. 4 bids received; low bid $3,526,335 by Rock Road Companies, Inc..
- Owner
- Wisconsin DOT
- Letting
- 10 NOV 2026
- Pay items
- 195
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rock Road Companies, Inc. | $3,526,335 | Low |
| 2 | Parisi Construction, LLC | $3,945,695 | +12% |
| 3 | Integrity Grading and Excavating, Inc. | $4,307,421 | +22% |
| 4 | Zignego Company, Inc. | $4,391,469 | +25% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rock Road Companies, Inc. | 2. Parisi Construction, LLC | 3. Integrity Grading and Excavating, Inc. | 4. Zignego Company, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Removing concrete pavement (204.0100) | SY | 7,740 | $6.35 | $5.00 | $9.02 | $17.00 |
| 2 | Removing asphaltic surface (204.0110) | SY | 3,250 | $3.64 | $12.00 | $2.29 | $10.23 |
| 3 | Removing asphaltic surface milling (204.0120) | SY | 850 | $11.75 | $12.00 | $2.29 | $12.00 |
| 4 | Removing curb & gutter (204.0150) | LF | 2,435 | $8.68 | $12.50 | $9.10 | $12.98 |
| 5 | Removing concrete sidewalk (204.0155) | SY | 305 | $18.66 | $31.50 | $12.31 | $12.97 |
| 6 | Removing concrete bases (204.0195) | EACH | 10 | $695.81 | $730.00 | $492.37 | $500.00 |
| 7 | Removing manholes (204.0210) | EACH | 5 | $695.81 | $1,300.00 | $899.34 | $500.00 |
| 8 | Removing inlets (204.0220) | EACH | 11 | $695.81 | $1,300.00 | $895.11 | $500.00 |
| 9 | Removing storm sewer (size) 01. 12-inch (204.0245) | LF | 46 | $29.16 | $62.00 | $61.91 | $35.00 |
| 10 | Removing storm sewer (size) 02. 15-inch (204.0245) | LF | 7 | $29.16 | $100.00 | $276.89 | $35.00 |
| 11 | Removing storm sewer (size) 03. 18-inch (204.0245) | LF | 242 | $29.16 | $59.00 | $38.92 | $35.00 |
| 12 | Removing storm sewer (size) 04. 21-inch (204.0245) | LF | 276 | $29.16 | $68.00 | $39.17 | $25.00 |
| 13 | Removing storm sewer (size) 05. 24-inch (204.0245) | LF | 32 | $29.16 | $90.00 | $92.55 | $35.00 |
| 14 | Removing (item description) 01. light pole (204.9060.S) | EACH | 6 | $800.00 | $840.00 | $800.00 | $1,000.00 |
| 15 | Removing (item description) 01. water main (204.9090.S) | LF | 52 | $25.41 | $83.00 | $53.34 | $1.00 |
| 16 | Excavation common (205.0100) | CY | 7,358 | $30.23 | $35.25 | $30.34 | $22.00 |
| 17 | Prepare foundation for concrete pavement (project) 01. 5992-10-20 (211.0201) | EACH | 1 | $0.01 | $500.00 | $0.01 | $0.01 |
| 18 | Finishing roadway (project) 01. 5992-10-20 (213.0100) | EACH | 1 | $5,789.49 | $500.00 | $500.00 | $1,000.00 |
| 19 | Base aggregate dense 3/4-inch (305.0110) | TON | 159 | $44.07 | $45.75 | $63.51 | $49.88 |
| 20 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 3,865 | $19.17 | $22.50 | $30.12 | $29.16 |
| 21 | Base aggregate dense 3-inch (305.0130) | TON | 4,042 | $19.93 | $20.25 | $25.07 | $27.00 |
| 22 | Coloring concrete wisdot red (405.0100) | CY | 251 | $98.92 | $135.00 | $98.92 | $130.00 |
| 23 | Coloring concrete custom (405.0200) | CY | 13 | $122.23 | $174.00 | $120.00 | $115.00 |
| 24 | Stamping colored concrete (405.1000) | CY | 13 | $566.70 | $650.00 | $330.00 | $100.00 |
| 25 | Concrete pavement 9 1/2-inch (415.0095) | SY | 8,308 | $82.50 | $125.00 | $100.00 | $103.56 |
| 26 | Concrete pavement gaps (415.0210) | EACH | 3 | $856.40 | $2,100.00 | $900.00 | $1,000.00 |
| 27 | Concrete pavement hes 9 1/2-inch (415.1095) | SY | 289 | $83.52 | $140.00 | $85.00 | $106.65 |
| 28 | Concrete pavement joint filling (415.4100) | SY | 9,563 | $3.10 | $4.10 | $3.87 | $2.75 |
| 29 | Drilled tie bars (416.0610) | EACH | 902 | $10.24 | $18.00 | $10.24 | $15.00 |
| 30 | Drilled dowel bars (416.0620) | EACH | 70 | $15.25 | $24.00 | $15.25 | $30.00 |
| 31 | Tack coat (455.0605) | GAL | 606 | $3.25 | $0.01 | $0.01 | $0.01 |
| 32 | Incentive density HMA pavement (460.2000) | DOL | 230 | $1.00 | $1.00 | $1.00 | $1.00 |
| 33 | HMA pavement 3 MT 58-28 S (460.6223) | TON | 432 | $107.50 | $110.00 | $105.00 | $105.00 |
| 34 | HMA pavement 4 MT 58-28 H (460.6424) | TON | 248 | $145.00 | $130.00 | $120.00 | $120.00 |
| 35 | Asphaltic surface temporary (465.0125) | TON | 593 | $95.00 | $84.00 | $80.00 | $80.00 |
| 36 | Concrete collars for pipe (520.8000) | EACH | 6 | $950.27 | $1,700.00 | $1,705.62 | $1,000.00 |
| 37 | Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036) | EACH | 1 | $2,511.53 | $3,300.00 | $5,349.52 | $2,000.00 |
| 38 | Apron endwalls for culvert pipe reinforced concrete 48-inch (522.1048) | EACH | 2 | $3,394.35 | $4,700.00 | $6,494.50 | $3,200.00 |
| 39 | Concrete curb pedestrian (601.0600) | LF | 150 | $116.27 | $85.00 | $57.00 | $86.04 |
| 40 | Concrete sidewalk 5-inch (602.0410) | SF | 2,443 | $9.12 | $11.00 | $9.50 | $15.95 |
| 41 | Concrete sidewalk 7-inch (602.0420) | SF | 1,575 | $17.42 | $20.50 | $10.50 | $20.03 |
| 42 | Curb ramp detectable warning field natural patina (602.0515) | SF | 119 | $50.48 | $55.00 | $45.00 | $50.00 |
| 43 | Curb ramp detectable warning field radial natural patina (602.0615) | SF | 28 | $70.96 | $100.00 | $65.00 | $100.00 |
| 44 | Concrete driveway 7-inch (602.0815) | SY | 89 | $83.28 | $110.00 | $94.50 | $89.30 |
| 45 | Riprap heavy (606.0300) | CY | 100 | $119.60 | $140.00 | $175.01 | $150.00 |
| 46 | Storm sewer pipe reinforced concrete class III 15-inch (608.0315) | LF | 109 | $194.61 | $150.00 | $181.25 | $309.45 |
| 47 | Storm sewer pipe reinforced concrete class III 18-inch (608.0318) | LF | 29 | $195.36 | $180.00 | $189.45 | $357.95 |
| 48 | Storm sewer pipe reinforced concrete class III 24-inch (608.0324) | LF | 199 | $171.14 | $190.00 | $205.53 | $285.90 |
| 49 | Storm sewer pipe reinforced concrete class III 30-inch (608.0330) | LF | 248 | $197.52 | $210.00 | $219.18 | $202.05 |
| 50 | Storm sewer pipe reinforced concrete class III 36-inch (608.0336) | LF | 140 | $231.37 | $270.00 | $277.13 | $317.71 |
| 51 | Storm sewer pipe reinforced concrete class III 48-inch (608.0348) | LF | 183 | $345.55 | $390.00 | $322.22 | $355.21 |
| 52 | Storm sewer pipe reinforced concrete horizontal elliptical class HE-III 24X38-inch (608.2324) | LF | 74 | $249.07 | $320.00 | $321.90 | $259.01 |
| 53 | Storm sewer pipe reinforced concrete horizontal elliptical class HE-III 29X45-inch (608.2329) | LF | 290 | $328.64 | $430.00 | $356.73 | $517.45 |
| 54 | Catch basins 6-FT diameter (611.1006) | EACH | 1 | $10,845 | $6,300.00 | $33,471 | $28,199 |
| 55 | Manholes 4-FT diameter (611.2004) | EACH | 1 | $3,465.47 | $4,200.00 | $31,666 | $4,319.31 |
| 56 | Manholes 5-FT diameter (611.2005) | EACH | 6 | $4,900.41 | $3,600.00 | $31,766 | $6,026.58 |
| 57 | Manholes 6-FT diameter (611.2006) | EACH | 3 | $5,813.98 | $4,900.00 | $33,471 | $11,184 |
| 58 | Inlets 2X3-FT (611.3230) | EACH | 8 | $3,279.15 | $2,600.00 | $31,666 | $6,062.22 |
| 59 | Adjusting manhole covers (611.8110) | EACH | 7 | $1,097.99 | $560.00 | $774.49 | $850.00 |
| 60 | Adjusting inlet covers (611.8115) | EACH | 2 | $1,144.87 | $680.00 | $774.49 | $1,000.00 |
| 61 | Mobilization (619.1000) | EACH | 1 | $460,000 | $250,000 | $398,560 | $199,000 |
| 62 | Concrete median sloped nose (620.0300) | SF | 273 | $13.60 | $15.00 | $15.00 | $20.00 |
| 63 | Water (624.0100) | MGAL | 158.40 | $0.01 | $34.50 | $65.49 | $1.00 |
| 64 | Topsoil (625.0100) | SY | 2,940 | $12.94 | $12.25 | $24.67 | $7.15 |
| 65 | Silt fence (628.1504) | LF | 84 | $5.00 | $5.30 | $5.00 | $2.05 |
| 66 | Silt fence maintenance (628.1520) | LF | 84 | $0.01 | $0.01 | $0.01 | $0.01 |
| 67 | Mobilizations erosion control (628.1905) | EACH | 4 | $100.00 | $110.00 | $100.00 | $300.00 |
| 68 | Mobilizations emergency erosion control (628.1910) | EACH | 12 | $100.00 | $110.00 | $100.00 | $300.00 |
| 69 | Erosion mat urban class I type B (628.2008) | SY | 718 | $3.00 | $3.20 | $3.00 | $1.75 |
| 70 | Inlet protection type A (628.7005) | EACH | 12 | $150.00 | $160.00 | $150.00 | $100.00 |
| 71 | Inlet protection type C (628.7015) | EACH | 51 | $70.00 | $74.00 | $70.00 | $60.00 |
| 72 | Tracking pads (628.7560) | EACH | 6 | $100.00 | $800.00 | $500.00 | $0.01 |
| 73 | Fertilizer type B (629.0210) | CWT | 1.50 | $300.00 | $320.00 | $300.00 | $90.00 |
| 74 | Seeding mixture no. 40 (630.0140) | LB | 33 | $25.00 | $26.25 | $25.00 | $12.95 |
| 75 | Seeding temporary (630.0200) | LB | 21 | $15.00 | $15.75 | $15.00 | $8.00 |
| 76 | Seed water (630.0500) | MGAL | 17 | $10.00 | $10.50 | $10.00 | $10.00 |
| 77 | Sod water (631.0300) | MGAL | 62 | $150.00 | $160.00 | $150.00 | $55.00 |
| 78 | Sod lawn (631.1000) | SY | 2,419 | $10.00 | $10.50 | $10.00 | $7.95 |
| 79 | Signs type II reflective H (637.2210) | SF | 87.50 | $30.00 | $31.50 | $30.00 | $25.00 |
| 80 | Moving signs type I (638.2101) | EACH | 4 | $400.00 | $420.00 | $400.00 | $950.00 |
| 81 | Moving signs type II (638.2102) | EACH | 18 | $200.00 | $210.00 | $200.00 | $110.00 |
| 82 | Removing signs type II (638.2602) | EACH | 3 | $45.00 | $47.25 | $45.00 | $25.00 |
| 83 | Removing small sign supports (638.3000) | EACH | 2 | $45.00 | $47.25 | $45.00 | $25.00 |
| 84 | Moving small sign supports (638.4000) | EACH | 5 | $200.00 | $210.00 | $200.00 | $110.00 |
| 85 | Field office type C (642.5201) | EACH | 1 | $8,100.00 | $27,100 | $20,000 | $30,000 |
| 86 | Traffic control drums (643.0300) | DAY | 38,951 | $0.10 | $0.20 | $0.10 | $0.20 |
| 87 | Traffic control barricades type III (643.0420) | DAY | 3,939 | $0.40 | $0.55 | $0.40 | $0.50 |
| 88 | Traffic control flexible tubular marker posts (643.0500) | EACH | 20 | $37.00 | $26.25 | $37.00 | $25.00 |
| 89 | Traffic control flexible tubular marker bases (643.0600) | EACH | 20 | $2.00 | $5.30 | $2.00 | $5.00 |
| 90 | Traffic control warning lights type A (643.0705) | DAY | 7,878 | $0.06 | $0.10 | $0.06 | $0.10 |
| 91 | Traffic control warning lights type C (643.0715) | DAY | 9,255 | $0.06 | $0.10 | $0.06 | $0.10 |
| 92 | Traffic control connected arrow boards (643.0810) | DAY | 206 | $7.00 | $24.25 | $7.00 | $23.00 |
| 93 | Traffic control signs (643.0900) | DAY | 10,605 | $0.30 | $0.35 | $0.30 | $0.35 |
| 94 | Traffic control signs PCMS (643.1050) | DAY | 110 | $32.00 | $36.75 | $32.00 | $35.00 |
| 95 | Traffic control connected work zone end location marker (643.1222) | DAY | 1,242 | $2.26 | $6.30 | $2.26 | $6.00 |
| 96 | Temporary marking line paint 6- inch (643.3165) | LF | 6,054 | $0.35 | $0.45 | $0.35 | $0.45 |
| 97 | Temporary marking line removable tape 6-inch (643.3180) | LF | 11,484 | $1.60 | $2.20 | $1.60 | $2.05 |
| 98 | Temporary marking arrow removable tape (643.3550) | EACH | 19 | $75.00 | $150.00 | $75.00 | $140.00 |
| 99 | Temporary marking removable mask out tape 6-inch (643.3960) | LF | 1,812 | $1.70 | $2.60 | $1.70 | $2.50 |
| 100 | Traffic control (643.5000) | EACH | 1 | $36,900 | $50,400 | $36,900 | $48,000 |
| 101 | Temporary pedestrian barricade (644.1810) | LF | 718 | $5.00 | $6.30 | $5.00 | $6.00 |
| 102 | Temporary audible message devices (644.1900.S) | DAY | 1,908 | $3.00 | $5.30 | $3.00 | $5.00 |
| 103 | Geotextile type HR (645.0120) | SY | 140 | $2.88 | $6.40 | $3.50 | $10.00 |
| 104 | Marking line epoxy 4-inch (646.1020) | LF | 2,926 | $0.70 | $0.40 | $0.70 | $0.37 |
| 105 | Marking line epoxy 6-inch (646.2020) | LF | 1,697 | $1.05 | $0.55 | $1.05 | $0.51 |
| 106 | Marking line epoxy 8-inch (646.3020) | LF | 2,474 | $1.40 | $3.20 | $1.40 | $3.00 |
| 107 | Marking line epoxy 10-inch (646.4020) | LF | 172 | $1.65 | $1.20 | $1.65 | $1.15 |
| 108 | Marking arrow epoxy (646.5020) | EACH | 14 | $230.00 | $460.00 | $230.00 | $435.41 |
| 109 | Marking word epoxy (646.5120) | EACH | 21 | $250.00 | $460.00 | $250.00 | $440.25 |
| 110 | Marking symbol epoxy (646.5220) | EACH | 3 | $300.00 | $440.00 | $300.00 | $423.64 |
| 111 | Marking stop line epoxy 18-inch (646.6120) | LF | 204 | $12.00 | $19.00 | $12.00 | $18.19 |
| 112 | Marking diagonal epoxy 12-inch (646.7120) | LF | 34 | $9.50 | $18.75 | $9.50 | $17.76 |
| 113 | Marking crosswalk epoxy block style 24-inch (646.7520) | LF | 966 | $18.00 | $31.50 | $18.00 | $29.88 |
| 114 | Marking curb epoxy (646.8120) | LF | 235 | $8.50 | $9.20 | $8.50 | $8.73 |
| 115 | Marking island nose epoxy (646.8220) | EACH | 11 | $305.00 | $340.00 | $305.00 | $325.09 |
| 116 | Marking removal line 6-inch (646.9002) | LF | 755 | $1.00 | $1.10 | $1.00 | $1.00 |
| 117 | Marking removal special marking water blasting (646.9310) | EACH | 9 | $250.00 | $210.00 | $250.00 | $200.00 |
| 118 | Construction staking storm sewer (650.4000) | EACH | 31 | $10.00 | $150.00 | $100.00 | $100.00 |
| 119 | Construction staking subgrade (650.4500) | LF | 2,532 | $0.01 | $0.01 | $1.25 | $0.01 |
| 120 | Construction staking base (650.5000) | LF | 633 | $0.01 | $1.00 | $1.29 | $1.29 |
| 121 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 3,000 | $1.00 | $0.01 | $1.95 | $1.95 |
| 122 | Construction staking concrete pavement (650.7000) | LF | 1,899 | $1.00 | $0.01 | $2.35 | $2.35 |
| 123 | Construction staking resurfacing reference (650.8000) | LF | 198 | $0.01 | $0.50 | $3.00 | $3.00 |
| 124 | Construction staking electrical installations (project) 01. 5992-10- 20 (650.8501) | EACH | 1 | $5,000.00 | $2,500.00 | $5,595.00 | $5,595.00 |
| 125 | Construction staking curb ramps (650.9000) | EACH | 6 | $15.00 | $250.00 | $250.00 | $250.00 |
| 126 | Construction staking sidewalk (project) 01. 5992-10-20 (650.9500) | EACH | 1 | $5,000.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 127 | Construction staking supplemental control (project) 01. 5992-10-20 (650.9911) | EACH | 1 | $5,000.00 | $5,000.00 | $4,850.00 | $4,850.00 |
| 128 | Construction staking slope stakes (650.9920) | LF | 2,532 | $0.01 | $0.01 | $1.56 | $1.56 |
| 129 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 1,802 | $10.00 | $10.50 | $10.00 | $20.00 |
| 130 | Conduit rigid nonmetallic schedule 40 3-inch (652.0235) | LF | 1,530 | $12.00 | $12.50 | $12.00 | $24.00 |
| 131 | Conduit rigid nonmetallic schedule 80 2-inch (652.0325) | LF | 300 | $11.00 | $11.50 | $11.00 | $24.00 |
| 132 | Conduit rigid nonmetallic schedule 80 3-inch (652.0335) | LF | 364 | $14.00 | $14.75 | $14.00 | $26.00 |
| 133 | Install conduit into existing item (652.0700.S) | EACH | 2 | $300.00 | $320.00 | $300.00 | $500.00 |
| 134 | Conduit loop detector (652.0800) | LF | 837 | $8.00 | $8.40 | $8.00 | $10.00 |
| 135 | Pull boxes steel 24X36-inch (653.0135) | EACH | 2 | $1,100.00 | $1,200.00 | $1,100.00 | $1,500.00 |
| 136 | Removing pull boxes (653.0905) | EACH | 3 | $250.00 | $260.00 | $250.00 | $500.00 |
| 137 | Concrete bases type 1 (654.0101) | EACH | 1 | $1,100.00 | $1,200.00 | $1,100.00 | $1,200.00 |
| 138 | Concrete bases type 2 (654.0102) | EACH | 1 | $1,500.00 | $1,600.00 | $1,500.00 | $2,500.00 |
| 139 | Concrete bases type 5 (654.0105) | EACH | 6 | $1,250.00 | $1,300.00 | $1,250.00 | $2,100.00 |
| 140 | Electrical wire lighting 12 AWG (655.0610) | LF | 1,530 | $1.25 | $1.30 | $1.25 | $2.00 |
| 141 | Loop detector lead in cable (655.0700) | LF | 3,840 | $1.75 | $1.80 | $1.75 | $2.50 |
| 142 | Loop detector wire (655.0800) | LF | 3,400 | $1.25 | $1.30 | $1.25 | $2.00 |
| 143 | Transformer bases breakaway 11 1/2-inch bolt circle (657.0255) | EACH | 7 | $625.00 | $660.00 | $625.00 | $825.00 |
| 144 | Poles type 5-aluminum (657.0322) | EACH | 7 | $2,615.00 | $2,700.00 | $2,615.00 | $2,400.00 |
| 145 | Traffic signal standards aluminum 15-FT (657.0425) | EACH | 2 | $1,413.00 | $1,500.00 | $1,413.00 | $850.00 |
| 146 | Luminaire arms truss type 4 1/2- inch clamp 15-FT (657.0715) | EACH | 14 | $875.00 | $920.00 | $875.00 | $1,200.00 |
| 147 | Signal mounting hardware (location) 01. mineral point road & S. high point road (658.5070) | EACH | 1 | $1,800.00 | $1,900.00 | $1,800.00 | $7,000.00 |
| 148 | Luminaires utility LED B (659.1120) | EACH | 14 | $250.00 | $260.00 | $250.00 | $300.00 |
| 149 | Fiber optic splice enclosure (678.0200) | EACH | 1 | $2,000.00 | $2,100.00 | $2,000.00 | $1,200.00 |
| 150 | Sawing asphalt (690.0150) | LF | 579 | $1.25 | $1.50 | $1.39 | $1.25 |
| 151 | Sawing concrete (690.0250) | LF | 8,690 | $2.10 | $1.90 | $1.85 | $2.10 |
| 152 | Incentive compressive strength concrete pavement (715.0720) | DOL | 2,565 | $1.00 | $1.00 | $1.00 | $1.00 |
| 153 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,400 | $5.00 | $5.00 | $5.00 | $5.00 |
| 154 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 2,160 | $5.00 | $5.00 | $5.00 | $5.00 |
| 155 | Special 04. precast sign post base (SPV.0060) | EACH | 14 | $250.00 | $260.00 | $250.00 | $250.00 |
| 156 | Special 05. sign post base for concrete installation (SPV.0060) | EACH | 5 | $250.00 | $260.00 | $250.00 | $250.00 |
| 157 | Special 07. construction staking water main (SPV.0060) | EACH | 1 | $500.00 | $500.00 | $850.00 | $850.00 |
| 158 | Special 09. furnish and install 16- inch water valve (SPV.0060) | EACH | 1 | $9,233.99 | $14,400 | $8,131.89 | $10,000 |
| 159 | Special 11. cut-in or connect-to existing water system (SPV.0060) | EACH | 2 | $5,036.00 | $5,700.00 | $10,469 | $7,000.00 |
| 160 | Special 12. adjust water valve box section (SPV.0060) | EACH | 6 | $382.55 | $530.00 | $1,546.28 | $850.00 |
| 161 | Special 30. inlet cover type H special (SPV.0060) | EACH | 12 | $1,982.28 | $1,400.00 | $1,238.40 | $1,000.00 |
| 162 | Special 32. manhole cover type J special (SPV.0060) | EACH | 7 | $1,591.19 | $1,100.00 | $1,020.01 | $1,000.00 |
| 163 | Special 39. precast concrete culvert bend (SPV.0060) | EACH | 2 | $12,899 | $4,000.00 | $6,666.06 | $3,000.00 |
| 164 | Special 50. temporary traffic signals (mineral point road & W. beltline highway) (SPV.0060) | EACH | 1 | $125,000 | $131,300 | $125,000 | $250,000 |
| 165 | Special 51. temporary traffic signals (mineral point road & S. high point road) (SPV.0060) | EACH | 1 | $60,000 | $63,000 | $60,000 | $250,000 |
| 166 | Special 52. removing, salvaging & reinstalling signal (mineral point RD/W beltline hwy) (SPV.0060) | EACH | 1 | $4,500.00 | $4,700.00 | $4,500.00 | $50,000 |
| 167 | Special 53. removing, salvaging & reinstalling signal (mineral point RD/S high point RD) (SPV.0060) | EACH | 1 | $4,500.00 | $4,700.00 | $4,500.00 | $50,000 |
| 168 | Special 54. removing & salvaging signal (mineral point RD & S high point RD) (SPV.0060) | EACH | 1 | $4,500.00 | $4,700.00 | $4,500.00 | $20,000 |
| 169 | Special 55. electrical pull box, type III (SPV.0060) | EACH | 1 | $600.00 | $630.00 | $600.00 | $800.00 |
| 170 | Special 56. electrical pull box, type V (SPV.0060) | EACH | 4 | $1,200.00 | $1,300.00 | $1,200.00 | $1,800.00 |
| 171 | Special 57. electrical pull box, type VII (SPV.0060) | EACH | 1 | $1,850.00 | $1,900.00 | $1,850.00 | $3,000.00 |
| 172 | Special 58. concrete base type LB- 8R (SPV.0060) | EACH | 1 | $1,500.00 | $1,600.00 | $1,500.00 | $3,000.00 |
| 173 | Special 59. traffic signal heads 12- inch 4-section (SPV.0060) | EACH | 4 | $1,050.00 | $1,100.00 | $1,050.00 | $1,350.00 |
| 174 | Special 60. backplates signal face, 4-section 12-inch (SPV.0060) | EACH | 4 | $175.00 | $180.00 | $175.00 | $175.00 |
| 175 | Special 61. removing, salvaging & reinstalling cable/wire (mineral PT RD/W beltline hwy) (SPV.0060) | EACH | 1 | $6,500.00 | $6,800.00 | $6,500.00 | $50,000 |
| 176 | Special 62. removing, salvaging & reinstalling cable/wire (mineral PT RD/S high PT RD) (SPV.0060) | EACH | 1 | $8,000.00 | $8,400.00 | $8,000.00 | $30,000 |
| 177 | Special 63. fiber optic fusion splice (SPV.0060) | EACH | 444 | $100.00 | $110.00 | $100.00 | $30.00 |
| 178 | Special 67. inlet covers flat, temporary (SPV.0060) | EACH | 9 | $1,655.38 | $180.00 | $1,356.56 | $500.00 |
| 179 | Special 68. temporary bus stop (SPV.0060) | EACH | 3 | $2,100.00 | $3,000.00 | $2,500.00 | $1,000.00 |
| 180 | Special 71. utility line opening (ulo) (SPV.0060) | EACH | 5 | $200.00 | $650.00 | $1,733.86 | $500.00 |
| 181 | Special 72. termination panel (SPV.0060) | EACH | 1 | $1,500.00 | $1,600.00 | $1,500.00 | $1,500.00 |
| 182 | Special 73. temporary lighting system mineral point road (SPV.0060) | EACH | 1 | $27,000 | $28,400 | $27,000 | $100,000 |
| 183 | Special 01. furnish and install watermain pipe & fittings, 16-inch (SPV.0090) | LF | 52 | $360.32 | $460.00 | $854.64 | $739.32 |
| 184 | Special 04. concrete curb & gutter 30-inch type D special (SPV.0090) | LF | 143 | $74.70 | $65.00 | $58.60 | $62.18 |
| 185 | Special 05. concrete curb & gutter 24-inch type A special (SPV.0090) | LF | 2,439 | $35.83 | $46.00 | $32.00 | $45.95 |
| 186 | Special 06. concrete curb & gutter 30-inch type A special (SPV.0090) | LF | 373 | $89.21 | $65.00 | $58.60 | $64.18 |
| 187 | Special 08. reflective sign post (SPV.0090) | LF | 246 | $18.00 | $19.00 | $18.00 | $45.00 |
| 188 | Special 09. staking temporary pavement (SPV.0090) | LF | 1,200 | $0.01 | $0.10 | $1.25 | $1.25 |
| 189 | Special 10. select fill for water main (SPV.0090) | LF | 52 | $275.24 | $1.00 | $0.01 | $125.00 |
| 190 | Special 11. fiber optic cable 12- count (SPV.0090) | LF | 210 | $5.00 | $5.30 | $5.00 | $5.00 |
| 191 | Special 12. fiber optic cable 144- count (SPV.0090) | LF | 3,060 | $7.00 | $7.40 | $7.00 | $7.00 |
| 192 | Special 01. high friction colored surface, green (SPV.0165) | SF | 520 | $14.54 | $15.25 | $14.54 | $9.80 |
| 193 | Special 02. methyl methacrylate marking red (SPV.0165) | SF | 3,000 | $13.04 | $6.60 | $6.30 | $6.30 |
| 194 | Special 03. marking removal water blasting area (SPV.0165) | SF | 4,288 | $1.15 | $2.10 | $1.15 | $2.00 |
| 195 | Special 01. pavement cleanup (SPV.0170) | STA | 43 | $100.00 | $180.00 | $1,090.52 | $300.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of November 10, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.