WisDOT contract 20260310016 bid tabulation

2410-15-70. Let by Wisconsin DOT on March 10, 2026, Milwaukee. 5 bids received; low bid $22,328,024 by Hoffman Construction Company.

Owner
Wisconsin DOT
Letting
10 MAR 2026
Pay items
353
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Hoffman Construction Company$22,328,024Low
2Vinton Construction Company$23,000,387+3.0%
3Super Western, Inc.$23,197,394+4.0%
4Lalonde Contractors Incorporated$23,766,563+6.0%
5Zignego Company, Inc.$24,890,943+11%
WisDOT contract 20260310016: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Hoffman Construction Company2. Vinton Construction Company3. Super Western, Inc.4. Lalonde Contractors Incorporated5. Zignego Company, Inc.
1Grubbing (201.0205)STA19$265.00$267.65$275.00$265.00$250.00
2Grubbing (201.0220)ID126$10.00$10.10$10.00$10.00$15.00
3Removing concrete pavement (204.0100)SY51,495$30.00$1.50$1.90$6.34$8.00
4Removing curb (204.0130)LF95$10.00$10.00$6.27$6.18$10.00
5Removing curb & gutter (204.0150)LF495$10.00$10.00$4.71$6.33$10.00
6Removing concrete sidewalk (204.0155)SY6,255$10.00$9.54$6.25$9.97$8.00
7Removing fence (204.0170)LF260$5.00$2.00$6.00$2.00$2.00
8Removing concrete slope paving (204.0175)SY280$22.00$25.00$16.37$18.70$50.00
9Removing concrete bases (204.0195)EACH93$400.00$200.00$300.00$200.00$300.00
10Removing manholes (204.0210)EACH38$350.00$797.93$840.00$1,000.00$1,847.00
11Removing catch basins (204.0215)EACH60$350.00$556.50$335.00$1,000.00$929.00
12Removing storm sewer (size) 001. 10-inch (204.0245)LF85$12.50$29.36$20.00$25.00$35.00
13Removing storm sewer (size) 002. 12-inch (204.0245)LF2,540$12.50$35.65$40.00$25.00$27.00
14Removing storm sewer (size) 003. 15-inch (204.0245)LF735$12.50$22.60$46.00$25.00$26.00
15Removing storm sewer (size) 004. 18-inch (204.0245)LF1,330$12.50$54.29$55.00$25.00$37.00
16Removing storm sewer (size) 005. 21-inch (204.0245)LF675$12.50$66.61$60.00$25.00$41.00
17Removing storm sewer (size) 006. 24-inch (204.0245)LF375$12.50$27.65$80.00$25.00$28.00
18Removing storm sewer (size) 007. 27-inch (204.0245)LF35$12.50$15.61$80.00$25.00$35.00
19Removing storm sewer (size) 008. 36-inch (204.0245)LF305$25.00$67.99$100.00$35.00$73.00
20Removing storm sewer (size) 009. 48-inch (204.0245)LF1,795$25.00$246.42$260.00$35.00$71.00
21Removing storm sewer (size) 010. 60-inch (204.0245)LF595$25.00$25.08$135.00$35.00$78.00
22Removing storm sewer (size) 011. 84-inch (204.0245)LF945$75.00$46.69$222.00$35.00$53.00
23Removing (item description) 001. landscaping bed (204.9060.S)EACH1$3,500.00$1,000.00$5,181.70$1,490.00$1,800.00
24Removing (item description) 101. traffic signals national ave & cleveland ave (204.9060.S)EACH1$7,198.00$7,198.00$5,996.09$7,198.00$7,198.00
25Removing (item description) 102. traffic signals national ave & 102ND ST (204.9060.S)EACH1$7,198.00$7,198.00$6,178.09$7,198.00$7,198.00
26Removing (item description) 103. loop detector wire & lead-in cable STH 100 & national ave (204.9060.S)EACH1$1,448.00$1,448.00$2,753.75$1,448.00$1,448.00
27Removing (item description) 001. pipe railing partial (204.9090.S)LF15$80.00$15.00$103.83$1.00$100.00
28Removing (item description) 201. removing electrical conductors from existing conduit (204.9090.S)LF990$2.06$2.06$2.02$2.06$2.06
29Removing (item description) 202. removing or abandoning conduit (204.9090.S)LF990$3.00$3.00$3.84$3.00$3.00
30Excavation common (205.0100)CY55,441$30.00$29.16$23.71$18.98$25.00
31Finishing roadway (project) 001. 2410-15-70 (213.0100)EACH1$500.00$10,000$6,067.26$4,150.00$1,000.00
32Base aggregate dense 3/4-inch (305.0110)TON10$146.67$100.00$47.52$44.20$100.00
33Base aggregate dense 1 1/4-inch (305.0120)TON24,410$0.01$18.20$19.90$19.57$25.00
34Base aggregate open-graded (310.0110)TON325$29.74$50.18$34.08$40.00$50.00
35Breaker run (311.0110)TON38,169$0.01$17.60$19.73$19.42$0.01
36Concrete base 9-inch (320.0155)SY2,030$83.31$70.18$83.31$73.28$95.00
37Coloring concrete custom (405.0200)CY655$127.99$97.02$127.99$125.45$100.00
38Concrete pavement 8-inch (415.0080)SY34,695$58.24$72.50$58.24$57.41$75.22
39Concrete pavement gaps (415.0210)EACH4$854.89$2,000.00$854.89$1,325.33$1,000.00
40Concrete pavement hes 8-inch (415.1080)SY285$78.97$95.61$78.97$84.11$92.00
41Concrete pavement joint filling (415.4100)SY38,905$1.70$2.00$1.70$1.61$1.25
42Drilled tie bars (416.0610)EACH2,095$9.64$6.00$9.64$14.40$15.00
43Drilled dowel bars (416.0620)EACH705$14.00$11.00$14.00$18.56$20.00
44Tack coat (455.0605)GAL255$2.25$2.25$2.25$2.25$2.25
45HMA pavement 3 MT 58-28 S (460.6223)TON85$119.00$119.00$119.00$119.00$119.00
46HMA pavement 4 MT 58-28 H (460.6424)TON420$119.00$119.00$119.00$119.00$119.00
47Asphaltic surface driveways and field entrances (465.0120)TON215$245.00$245.00$245.00$245.00$245.00
48Asphaltic surface temporary (465.0125)TON1,280$103.25$103.25$103.25$103.25$103.25
49Cold patch (495.1000.S)TON50$550.00$249.00$131.86$396.80$0.01
50Concrete collars for pipe (520.8000)EACH11$750.00$975.00$425.00$2,500.00$951.00
51Drilling shaft 48-inch (531.2048)LF28$500.00$18.00$450.00$330.00$500.00
52Foundation single-shaft type TC-IV (structure) 001. S-40-673 (531.5340)EACH1$19,950$23,066$22,500$22,970$19,950
53Truss cantilever 2-chord type IV (structure) 001. S-40-673 (532.5340)EACH1$69,900$68,600$73,000$65,000$69,900
54Concrete curb type D (601.0110)LF100$86.13$42.74$86.13$53.47$42.75
55Concrete curb integral type D (601.0150)LF1,525$4.60$40.58$4.60$15.97$40.00
56Concrete curb & gutter 19-inch (601.0319)LF1,030$29.76$28.29$29.76$19.71$28.36
57Concrete curb & gutter 31-inch (601.0331)LF18,315$25.15$27.12$25.15$31.88$27.08
58Concrete curb pedestrian (601.0600)LF1,730$82.54$35.69$82.54$45.66$35.68
59Concrete sidewalk 5-inch (602.0410)SF95,845$6.46$7.36$6.46$8.34$6.81
60Concrete sidewalk 7-inch (602.0420)SF5,440$15.69$13.81$15.69$8.60$15.35
61Curb ramp detectable warning field yellow (602.0505)SF1,475$54.15$32.16$54.15$45.88$32.76
62Curb ramp detectable warning field radial yellow (602.0605)SF445$75.66$44.03$75.66$61.45$44.86
63Concrete driveway 7-inch (602.0815)SY1,685$74.24$85.97$74.24$73.38$71.07
64Concrete safety islands (602.2400)SF6,300$11.81$14.95$11.81$15.33$14.98
65Slope paving concrete (604.0400)SY300$53.51$85.57$53.51$137.28$200.00
66Storm sewer pipe reinforced concrete class III 12-inch (608.0312)LF2,310$64.00$117.02$135.00$190.00$82.00
67Storm sewer pipe reinforced concrete class III 15-inch (608.0315)LF407$66.00$141.47$150.00$200.00$90.00
68Storm sewer pipe reinforced concrete class III 18-inch (608.0318)LF40$86.00$203.09$250.00$225.00$112.00
69Storm sewer pipe reinforced concrete class III 21-inch (608.0321)LF189$78.00$175.90$188.00$230.00$98.00
70Storm sewer pipe reinforced concrete class III 24-inch (608.0324)LF1,114$90.00$202.77$230.00$235.00$116.00
71Storm sewer pipe reinforced concrete class III 30-inch (608.0330)LF140$132.00$251.22$323.00$260.00$173.00
72Storm sewer pipe reinforced concrete class III 36-inch (608.0336)LF418$156.00$251.99$350.00$320.00$186.00
73Storm sewer pipe reinforced concrete class III 42-inch (608.0342)LF200$182.00$295.55$470.00$385.00$228.00
74Storm sewer pipe reinforced concrete class III 48-inch (608.0348)LF39$256.00$342.32$695.00$500.00$275.00
75Storm sewer pipe reinforced concrete class III 60-inch (608.0360)LF406$388.00$506.72$565.00$700.00$458.00
76Storm sewer pipe reinforced concrete class III 66-inch (608.0366)LF183$424.00$625.57$690.00$750.00$604.00
77Storm sewer pipe reinforced concrete class III 108-inch (608.0398)LF923$1,900.00$2,066.22$1,995.00$2,700.00$2,310.00
78Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF1,011$64.00$95.70$130.00$190.00$79.00
79Storm sewer pipe reinforced concrete class IV 15-inch (608.0415)LF241$66.00$107.11$143.00$200.00$84.00
80Storm sewer pipe reinforced concrete class IV 30-inch (608.0430)LF293$128.00$199.49$240.00$275.00$144.00
81Storm sewer pipe reinforced concrete class IV 66-inch (608.0466)LF1,022$456.00$532.00$385.00$800.00$578.00
82Reconstructing manholes (611.0420)EACH3$1,800.00$3,455.00$4,370.00$4,500.00$1,800.00
83Manhole covers type J (611.0530)EACH40$850.00$540.99$500.00$465.00$1,800.00
84Inlet covers type C (611.0612)EACH2$900.00$563.15$525.00$527.00$1,800.00
85Inlet covers type H (611.0624)EACH1$1,200.00$776.26$768.00$562.00$1,800.00
86Inlet covers type MS (611.0642)EACH6$900.00$550.49$512.00$515.00$1,000.00
87Inlet covers type R (611.0648)EACH124$1,700.00$1,211.97$1,250.00$1,275.00$1,650.00
88Inlet covers type Z (611.0666)EACH9$1,200.00$789.97$785.00$790.00$1,200.00
89Catch basins 3-FT diameter (611.1003)EACH6$1,600.00$4,716.78$1,610.00$2,800.00$2,138.00
90Catch basins 4-FT diameter (611.1004)EACH1$2,100.00$5,641.05$1,765.00$3,300.00$2,813.00
91Catch basins 6-FT diameter (611.1006)EACH1$4,300.00$8,794.35$3,200.00$5,400.00$5,092.00
92Manholes 4-FT diameter (611.2004)EACH6$2,100.00$5,849.56$2,020.00$4,300.00$3,170.00
93Manholes 5-FT diameter (611.2005)EACH11$3,500.00$7,632.80$3,050.00$6,500.00$5,797.00
94Manholes 6-FT diameter (611.2006)EACH4$5,500.00$10,089$4,750.00$11,000$8,145.00
95Manholes 7-FT diameter (611.2007)EACH3$9,800.00$19,039$10,910$12,800$11,411
96Manholes 8-FT diameter (611.2008)EACH1$15,300$27,546$17,130$22,500$22,879
97Manholes 9-FT diameter (611.2009)EACH1$14,500$30,423$22,000$25,000$21,905
98Manholes 10-FT diameter (611.2010)EACH1$27,200$37,974$32,500$35,000$27,940
99Manholes variable tee 4-FT diameter (611.2504)EACH13$3,400.00$36,193$11,150$40,000$42,530
100Inlets 3-FT diameter (611.3003)EACH1$1,400.00$4,640.13$1,650.00$2,700.00$1,565.00
101Inlets 2X3-FT (611.3230)EACH1$1,750.00$4,862.43$1,950.00$3,800.00$3,450.00
102Inlets median 1 grate (611.3901)EACH6$2,600.00$3,818.45$4,300.00$3,600.00$2,615.00
103Adjusting inlet covers (611.8115)EACH2$2,450.00$540.00$940.00$2,900.00$800.00
104Cover plates temporary (611.8120.S)EACH10$200.00$209.95$500.00$150.00$650.00
105Pipe underdrain 6-inch (612.0106)LF2,845$14.83$37.71$22.22$50.00$15.00
106Pipe underdrain unperforated 6- inch (612.0206)LF295$36.00$41.33$20.00$50.00$12.00
107Pipe underdrain unperforated 8- inch (612.0208)LF305$24.00$47.30$38.07$60.00$45.00
108Pipe underdrain unperforated 10- inch (612.0210)LF65$38.00$54.05$57.87$70.00$50.00
109Insulation board polystyrene (inch) 001. 2-inch (612.0902.S)SY15$150.00$45.54$5.00$50.00$48.00
110Fence chain link 6-FT (616.0206)LF175$75.00$55.00$75.00$75.00$40.00
111Gates chain link (width) 001. 12-FT (616.0329)EACH1$2,500.00$5,000.00$2,500.00$2,500.00$3,500.00
112Mobilization (619.1000)EACH1$2,214,219$706,000$1,095,510$785,909$3,539,000
113Concrete median sloped nose (620.0300)SF605$12.10$24.52$12.10$17.77$24.53
114Dust control surface treatment (623.0200)SY22,500$0.01$0.01$0.01$0.01$0.01
115Water (624.0100)MGAL600$110.00$0.01$20.88$0.01$50.00
116Topsoil (625.0100)SY27,225$9.00$6.80$10.62$4.60$8.00
117Mulching (627.0200)SY10,380$0.05$0.29$0.30$0.01$0.05
118Erosion bales (628.1104)EACH100$1.00$10.00$20.00$0.01$1.00
119Silt fence (628.1504)LF3,030$2.00$2.00$3.00$2.10$2.00
120Silt fence maintenance (628.1520)LF1,517$0.05$0.01$0.01$0.01$0.05
121Mobilizations erosion control (628.1905)EACH21$100.00$25.00$250.00$50.00$100.00
122Mobilizations emergency erosion control (628.1910)EACH15$150.00$50.00$150.00$10.00$150.00
123Erosion mat class I type B (628.2004)SY2,000$1.10$1.00$1.00$0.01$1.10
124Soil stabilizer type B (628.6510)ACRE1.70$500.00$200.00$1,000.00$500.00$500.00
125Inlet protection type A (628.7005)EACH137$115.00$50.00$125.00$0.01$115.00
126Inlet protection type B (628.7010)EACH17$45.00$50.00$85.00$60.00$45.00
127Inlet protection type D (628.7020)EACH375$115.00$95.00$125.00$110.00$115.00
128Temporary ditch checks (628.7504)LF171$4.50$7.00$12.00$0.01$4.50
129Tracking pads (628.7560)EACH24$100.00$0.01$100.00$0.01$0.01
130Rock bags (628.7570)EACH250$10.00$5.00$15.00$0.01$10.00
131Fertilizer type B (629.0210)CWT17.30$75.00$80.00$150.00$80.00$75.00
132Seeding mixture no. 40 (630.0140)LB360$8.00$10.00$8.00$0.01$8.00
133Seeding temporary (630.0200)LB215$2.90$1.00$3.00$0.01$2.90
134Seeding borrow pit (630.0300)LB200$7.00$9.00$8.00$0.01$7.00
135Seed water (630.0500)MGAL190$1.00$1.00$1.00$0.01$1.00
136Sod water (631.0300)MGAL519$1.00$28.90$1.00$30.00$1.00
137Sod lawn (631.1000)SY19,823$8.50$6.70$12.00$7.10$8.50
138Landscape planting surveillance and care cycles (632.9101)EACH10$700.00$100.00$1,250.00$100.00$700.00
139Posts wood 4X6-inch X 18-FT (634.0618)EACH63$95.00$115.00$150.00$120.00$95.00
140Posts wood 4X6-inch X 20-FT (634.0620)EACH3$110.00$115.00$160.00$140.00$110.00
141Posts wood 4X6-inch X 22-FT (634.0622)EACH4$125.00$115.00$200.00$180.00$125.00
142Posts tubular steel 2X2-inch X 14- FT (634.0814)EACH14$175.00$210.00$300.00$200.00$175.00
143Signs type I reflective SH (637.1220)SF148.50$29.75$30.90$32.00$29.10$29.75
144Signs type II reflective H (637.2210)SF1,363.78$24.50$21.90$28.00$20.10$24.50
145Signs type II reflective H folding (637.2215)SF223.96$32.00$29.90$40.00$24.10$32.00
146Signs type II reflective F (637.2230)SF387.50$24.50$23.90$28.00$22.10$24.50
147Removing signs type II (638.2602)EACH157$25.00$10.00$50.00$10.00$25.00
148Removing small sign supports (638.3000)EACH63$25.00$20.00$50.00$10.00$25.00
149Field office type D (642.5401)EACH1$25,000$35,000$63,754$59,080$50,000
150Traffic control drums (643.0300)DAY97,675$0.20$0.20$0.20$0.20$0.20
151Traffic control barricades type III (643.0420)DAY41,975$0.25$0.25$0.25$0.25$0.25
152Traffic control warning lights type A (643.0705)DAY83,950$0.10$0.10$0.10$0.10$0.10
153Traffic control warning lights type C (643.0715)DAY13,300$0.10$0.10$0.10$0.10$0.10
154Traffic control connected arrow boards (643.0810)DAY565$25.00$25.00$25.00$25.00$25.00
155Traffic control signs (643.0900)DAY201,215$0.25$0.25$0.25$0.25$0.25
156Traffic control covering signs type I (643.0910)EACH6$500.00$500.00$500.00$500.00$500.00
157Traffic control covering signs type II (643.0920)EACH22$25.00$25.00$25.00$25.00$25.00
158Traffic control signs fixed message (643.1000)SF196$20.00$20.00$20.00$20.00$20.00
159Traffic control signs PCMS (643.1050)DAY227$50.00$50.00$50.00$50.00$50.00
160Traffic control connected work zone start and end location markers (643.1220)DAY930$10.00$10.00$10.00$10.00$10.00
161Temporary marking line paint 6- inch (643.3165)LF12,200$1.45$1.45$1.45$1.45$1.45
162Temporary marking line epoxy 6- inch (643.3170)LF935$0.42$0.42$3.35$3.35$3.35
163Temporary marking line removable tape 6-inch (643.3180)LF11,355$1.50$1.50$1.50$1.50$1.50
164Temporary marking line paint 10- inch (643.3265)LF800$2.55$2.55$2.55$2.55$2.55
165Temporary marking line epoxy 10- inch (643.3270)LF945$1.42$1.42$5.55$5.55$5.55
166Temporary marking line removable tape 10-inch (643.3280)LF1,755$2.50$2.50$2.50$2.50$2.50
167Temporary marking crosswalk removable tape 6-inch (643.3350)LF605$1.50$1.50$1.50$1.50$1.50
168Temporary marking arrow epoxy (643.3520)EACH2$355.90$355.90$115.00$115.00$115.00
169Temporary marking word epoxy (643.3620)EACH1$363.10$363.10$130.00$130.00$130.00
170Traffic control (643.5000)EACH1$68,000$68,000$80,000$68,000$68,000
171Temporary pedestrian surface matting (644.1440)SF2,565$6.00$6.00$6.00$6.00$6.00
172Temporary pedestrian curb ramp (644.1601)DAY1,374$7.00$7.00$7.00$7.00$7.00
173Temporary pedestrian detectable warning field (644.1605)SF530$5.00$5.00$5.00$5.00$5.00
174Temporary pedestrian barricade (644.1810)LF20,425$3.50$3.50$3.50$3.50$3.50
175Temporary audible message devices (644.1900.S)DAY4,666$2.50$2.50$2.50$2.50$2.50
176Geotextile type DF schedule A (645.0111)SY1,560$3.00$6.57$4.01$3.00$4.00
177Geotextile type DF schedule B (645.0112)SY2,260$3.00$2.62$4.00$3.00$4.00
178Geogrid type SR (645.0220)SY46,855$1.50$1.65$2.50$1.73$2.50
179Marking line grooved wet ref epoxy 6-inch (646.2040)LF8,445$1.37$1.37$3.10$2.10$1.36
180Marking line grooved wet ref epoxy 10-inch (646.4040)LF4,625$2.72$2.72$5.50$3.40$2.72
181Marking arrow epoxy (646.5020)EACH34$358.50$358.50$330.00$250.00$358.33
182Marking arrow mma (646.5060.S)EACH8$1,000.00$1,000.00$450.00$325.00$1,000.00
183Marking word epoxy (646.5120)EACH9$363.10$363.10$350.00$275.00$362.91
184Marking symbol epoxy (646.5220)EACH32$347.40$347.40$315.00$350.00$347.22
185Marking symbol mma (646.5260.S)EACH8$900.00$900.00$440.00$325.00$900.00
186Marking stop line epoxy 18-inch (646.6120)LF550$15.07$15.07$21.00$13.25$15.06
187Cold weather marking epoxy 6-inch (646.6466)LF4,240$0.47$0.47$0.40$1.40$0.47
188Cold weather marking epoxy 10- inch (646.6470)LF2,325$1.05$1.05$0.60$2.35$1.04
189Marking diagonal epoxy 12-inch (646.7120)LF530$14.66$14.66$9.00$10.00$14.65
190Marking crosswalk epoxy transverse line 6-inch (646.7420)LF3,125$14.25$14.25$15.50$11.00$14.24
191Marking crosswalk epoxy block style 24-inch (646.7520)LF2,305$24.71$24.71$28.50$18.50$24.69
192Marking bike lane mma (646.7760.S)SF4,345$8.80$8.80$17.50$14.50$8.80
193Marking curb epoxy (646.8120)LF285$7.19$7.19$15.00$8.50$7.19
194Marking island nose epoxy (646.8220)EACH17$271.91$271.91$330.00$300.00$271.78
195Marking removal line 6-inch (646.9002)LF6,835$1.00$1.00$1.00$1.00$1.00
196Marking removal line water blasting 6-inch (646.9012)LF275$2.00$2.00$2.00$2.00$2.00
197Marking removal line 10-inch (646.9102)LF2,675$2.00$2.00$2.00$2.00$2.00
198Marking removal line water blasting 10-inch (646.9112)LF510$2.00$2.00$2.00$2.00$2.00
199Marking removal line wide (646.9200)LF335$3.00$3.00$3.00$3.00$3.00
200Marking removal special marking (646.9300)EACH16$50.00$50.00$50.00$50.00$50.00
201Marking removal special marking water blasting (646.9310)EACH2$50.00$50.00$50.00$50.00$50.00
202Construction staking storm sewer (650.4000)EACH182$120.00$120.00$120.00$120.00$120.00
203Construction staking subgrade (650.4500)LF9,250$0.01$0.01$0.01$0.01$0.01
204Construction staking base (650.5000)LF85$2.00$2.00$2.00$2.00$2.00
205Construction staking curb gutter and curb & gutter (650.5500)LF170$2.50$2.50$2.50$2.50$2.50
206Construction staking structure layout (structure) 001. S-40-673 (650.6501)EACH1$550.00$550.00$550.00$550.00$550.00
207Construction staking concrete pavement (650.7000)LF9,170$0.01$0.01$0.01$0.01$0.01
208Construction staking electrical installations (project) 001. 2410-15- 70 (650.8501)EACH1$7,000.00$7,000.00$7,000.00$7,000.00$7,000.00
209Construction staking curb ramps (650.9000)EACH74$130.00$130.00$130.00$130.00$130.00
210Construction staking sidewalk (project) 001. 2410-15-70 (650.9500)EACH1$14,000$14,000$14,000$14,000$14,000
211Construction staking supplemental control (project) 001. 2410-15-70 (650.9911)EACH1$23,000$23,000$23,000$23,000$23,000
212Construction staking slope stakes (650.9920)LF10,700$0.75$0.75$0.75$0.75$0.75
213Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF12,149$10.02$10.02$9.00$10.02$10.02
214Conduit rigid nonmetallic schedule 40 3-inch (652.0235)LF958$11.34$11.34$11.42$11.34$11.34
215Conduit rigid nonmetallic schedule 80 2-inch (652.0325)LF1,485$11.12$11.12$12.85$11.12$11.12
216Conduit special 2-inch (652.0605)LF1,315$21.00$21.00$20.46$21.00$21.00
217Conduit special 3-inch (652.0615)LF1,953$27.00$27.00$23.20$27.00$27.00
218Install conduit into existing item (652.0700.S)EACH8$422.00$422.00$364.01$422.00$422.00
219Conduit loop detector (652.0800)LF3,686$7.00$7.00$10.16$7.00$7.00
220Pull boxes steel 24X36-inch (653.0135)EACH9$1,135.00$1,135.00$1,303.42$1,135.00$1,135.00
221Pull boxes steel 24X42-inch (653.0140)EACH37$1,180.00$1,180.00$1,409.62$1,180.00$1,180.00
222Pull boxes non-conductive 24X42- inch (653.0164)EACH56$2,148.00$2,148.00$2,426.86$2,148.00$2,148.00
223Adjusting pull boxes (653.0900)EACH1$498.00$498.00$1,078.71$498.00$498.00
224Removing pull boxes (653.0905)EACH26$87.00$87.00$103.14$87.00$87.00
225Concrete bases type 1 (654.0101)EACH11$1,138.00$1,138.00$965.26$1,138.00$1,138.00
226Concrete bases type 2 (654.0102)EACH8$1,434.00$1,434.00$1,259.94$1,434.00$1,434.00
227Concrete bases type 5 (654.0105)EACH35$1,298.00$1,298.00$1,121.11$1,298.00$1,298.00
228Concrete bases type 10 (654.0110)EACH4$8,976.00$8,976.00$6,346.18$8,976.00$8,976.00
229Concrete bases type 10-special (654.0120)EACH4$9,908.00$9,908.00$8,595.58$9,908.00$9,908.00
230Concrete control cabinet bases type 9 special (654.0217)EACH2$2,100.00$2,100.00$2,563.19$2,100.00$2,100.00
231Cable traffic signal 5-14 AWG (655.0230)LF1,490$1.42$1.42$1.87$1.42$1.42
232Cable traffic signal 7-14 AWG (655.0240)LF2,021$1.99$1.99$2.59$1.99$1.99
233Cable traffic signal 12-14 AWG (655.0260)LF2,395$3.24$3.24$3.91$3.24$3.24
234Cable traffic signal 15-14 AWG (655.0270)LF3,033$3.97$3.97$4.61$3.97$3.97
235Cable type UF 2-12 AWG grounded (655.0305)LF2,281$1.54$1.54$1.74$1.54$1.54
236Electrical wire traffic signals 10 AWG (655.0515)LF4,694$0.98$0.98$1.93$0.98$0.98
237Electrical wire lighting 12 AWG (655.0610)LF15,136$0.85$0.85$0.90$0.85$0.85
238Electrical wire lighting 6 AWG (655.0625)LF25,215$1.68$1.68$1.82$1.68$1.68
239Loop detector lead in cable (655.0700)LF14,091$1.16$1.16$1.20$1.16$1.16
240Loop detector wire (655.0800)LF14,364$0.88$0.88$0.91$0.88$0.88
241Traffic signal evp detector cable (655.0900)LF1,968$2.75$2.75$0.99$2.75$2.75
242Electrical service meter breaker pedestal (location) 101. national ave & cleveland ave (656.0201)EACH1$1,336.00$1,336.00$1,427.77$1,336.00$1,336.00
243Electrical service meter breaker pedestal (location) 102. national ave & 102ND ST (656.0201)EACH1$1,336.00$1,336.00$1,427.77$1,336.00$1,336.00
244Pedestal bases (657.0100)EACH11$315.00$315.00$387.74$315.00$315.00
245Transformer bases breakaway 11 1/2-inch bolt circle (657.0255)EACH8$672.00$672.00$703.03$672.00$672.00
246Poles type 3 (657.0310)EACH8$3,456.00$3,456.00$3,527.94$3,456.00$3,456.00
247Poles type 9 (657.0345)EACH1$8,378.00$8,378.00$8,615.30$8,378.00$8,378.00
248Poles type 9-special (657.0347)EACH3$11,264$11,264$11,957$11,264$11,264
249Poles type 10 (657.0350)EACH3$9,724.00$9,724.00$10,603$9,724.00$9,724.00
250Poles type 10-special (657.0352)EACH1$12,516$12,516$13,951$12,516$12,516
251Traffic signal standards aluminum 15-FT (657.0425)EACH9$784.00$784.00$980.04$784.00$784.00
252Traffic signal standards aluminum 10-FT (657.0430)EACH2$718.00$718.00$856.14$718.00$718.00
253Monotube arms 30-FT (657.0530)EACH4$6,156.00$6,156.00$5,781.43$6,156.00$6,156.00
254Monotube arms 40-FT-special (657.0541)EACH2$6,935.00$6,935.00$6,308.40$6,935.00$6,935.00
255Monotube arms 45-FT-special (657.0546)EACH2$7,283.00$7,283.00$6,418.27$7,283.00$7,283.00
256Luminaire arms single member 4- inch clamp 6-FT (657.0609)EACH10$292.00$292.00$357.52$292.00$292.00
257Luminaire arms steel 6-FT (657.0806)EACH6$962.00$962.00$760.31$962.00$962.00
258Traffic signal face 3S 12-inch (658.0173)EACH25$740.00$740.00$847.12$740.00$740.00
259Traffic signal face 4S 12-inch (658.0174)EACH20$900.00$900.00$1,045.84$900.00$900.00
260Traffic signal face 5S 12-inch (658.0175)EACH2$1,090.00$1,090.00$1,268.61$1,090.00$1,090.00
261Pedestrian signal face 16-inch (658.0416)EACH24$580.00$580.00$544.38$580.00$580.00
262Signal mounting hardware (location) 101. national ave & cleveland ave (658.5070)EACH1$7,496.00$7,496.00$7,740.05$7,496.00$7,496.00
263Signal mounting hardware (location) 102. national ave & 102ND ST (658.5070)EACH1$6,278.00$6,278.00$6,337.32$6,278.00$6,278.00
264Underdeck lighting (structure) 001. B-40-123 (659.0601)EACH1$9,652.00$9,652.00$17,953$9,652.00$9,652.00
265Underdeck lighting (structure) 002. B-40-124 (659.0601)EACH1$9,652.00$9,652.00$17,953$9,652.00$9,652.00
266Luminaires utility LED B (659.1120)EACH16$248.00$248.00$562.91$248.00$248.00
267Luminaires underdeck LED B (659.1210)EACH4$585.00$585.00$842.84$585.00$585.00
268Temporary traffic signals for intersections (location) 101. national ave & cleveland ave (661.0201)EACH1$51,539$51,539$98,641$51,539$51,539
269Temporary traffic signals for intersections (location) 102. national ave & 102ND ST (661.0201)EACH1$51,539$51,539$80,302$51,539$51,539
270Generators (661.0300)DAY2$206.00$206.00$384.25$206.00$206.00
271Sawing asphalt (690.0150)LF1,905$1.39$1.50$1.39$1.15$1.15
272Sawing concrete (690.0250)LF5,705$2.50$2.50$2.50$2.25$2.25
273Incentive compressive strength concrete pavement (715.0720)DOL10,410$1.00$1.00$1.00$1.00$1.00
274Incentive iri ride (740.0440)DOL1,565$1.00$1.00$1.00$1.00$1.00
275On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS10,500$5.00$5.00$5.00$5.00$5.00
276On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS36,000$5.00$5.00$5.00$5.00$5.00
277Special 001. backfill slurry (SPV.0035)CY150$140.00$125.33$110.00$150.00$106.00
278Special 002. engineered soil bioswales (SPV.0035)CY1,515$115.00$60.50$85.00$60.00$60.50
279Special 003. bedding layer bioswales (SPV.0035)CY200$125.00$60.50$80.00$60.00$60.50
280Special 004. storage layer bioswales (SPV.0035)CY2,260$62.00$60.50$70.00$53.00$60.50
281Special 005. cobblestones (SPV.0035)CY1,540$0.01$60.00$175.00$5.00$80.00
282Special 001. manholes 6X11-FT (SPV.0060)EACH1$102,000$58,823$111,000$50,000$41,055
283Special 002. storm sewer chamber (SPV.0060)EACH1$90,000$136,098$470,000$225,000$259,748
284Special 003. bioswale drains (SPV.0060)EACH32$2,700.00$2,850.00$700.00$1,200.00$5,000.00
285Special 004. bus stop bench (SPV.0060)EACH7$4,500.00$3,600.00$6,000.00$3,000.00$4,500.00
286Special 005. trash receptacle (SPV.0060)EACH7$3,500.00$3,600.00$4,000.00$2,400.00$3,500.00
287Special 006. tree root sawing (SPV.0060)EACH74$125.00$150.00$111.37$219.78$50.00
288Special 007. utility line opening (ulo) (SPV.0060)EACH25$350.00$1,153.30$1,782.66$1,453.03$0.01
289Special 008. catmint nepeta 'blue wonder' 1 gallon (SPV.0060)EACH205$33.00$25.00$5.00$20.00$33.00
290Special 009. daylilies 'stella D'oro' 1 gallon (SPV.0060)EACH295$35.00$25.00$5.00$20.00$35.00
291Special 010. false indigo 'midnight prairie blue eyes' 1 gallon (SPV.0060)EACH143$34.00$25.00$5.00$20.00$34.00
292Special 011. gro low sumac 2 gallon (SPV.0060)EACH95$80.00$50.00$5.00$30.00$80.00
293Special 012. karl foerster grass 1 gallon (SPV.0060)EACH67$46.00$20.00$5.00$20.00$46.00
294Special 013. panicum grass 'apache rose' 1 gallon (SPV.0060)EACH176$46.00$40.00$5.00$20.00$46.00
295Special 014. purple coneflower 'magnus' 1 gallon (SPV.0060)EACH250$34.00$20.00$5.00$20.00$34.00
296Special 015. red twigged dogwood 3 gallon (SPV.0060)EACH59$65.00$60.00$5.00$30.00$65.00
297Special 016. connection to existing storm sewer (SPV.0060)EACH1$1,700.00$5,688.50$5,600.00$2,800.00$9,663.00
298Special 017. inlets 3.5-FT diameter (SPV.0060)EACH6$2,000.00$3,703.50$2,100.00$2,700.00$1,801.00
299Special 018. dewatering for storm sewer construction (SPV.0060)EACH1$500.00$56,000$110,000$50,000$65,083
300Special 029. concrete saddle (SPV.0060)EACH8$4,000.00$3,087.50$1,400.00$1,200.00$697.00
301Special 030. catch basins 3.5-FT diameter (SPV.0060)EACH86$2,300.00$4,820.26$2,310.00$3,800.00$2,839.00
302Special 031. round steel sign post system (SPV.0060)EACH150$200.00$275.00$390.00$287.00$200.00
303Special 100. furnish & install signal cabinet & controller national ave & cleveland ave (SPV.0060)EACH1$30,765$30,765$37,183$30,765$30,765
304Special 101. furnish & install signal cabinet & controller national ave & 102ND ST (SPV.0060)EACH1$30,478$30,478$36,385$30,478$30,478
305Special 102. furnish & install evp system national ave & cleveland ave (SPV.0060)EACH1$8,012.00$8,012.00$9,698.10$8,012.00$8,012.00
306Special 103. furnish & install evp system national ave & 102ND ST (SPV.0060)EACH1$8,012.00$8,012.00$10,608$8,012.00$8,012.00
307Special 104. furnish & install accessible ped signals national ave & cleveland ave (SPV.0060)EACH1$11,274$11,274$13,979$11,274$11,274
308Special 105. furnish & install accessible ped signals national ave & 102ND ST (SPV.0060)EACH1$11,274$11,274$13,979$11,274$11,274
309Special 106. removing concrete monotube traffic signals (SPV.0060)EACH8$1,668.00$1,668.00$2,047.57$1,668.00$1,668.00
310Special 107. temporary infrared evp system national ave & cleveland ave (SPV.0060)EACH1$3,693.40$3,693.40$3,526.90$3,693.40$3,693.40
311Special 108. temporary infrared evp system national ave & 102ND ST (SPV.0060)EACH1$3,693.40$3,693.40$3,526.90$3,693.40$3,693.40
312Special 200. transformer bases breakaway 11 1/2-inch bolt circle bronze (SPV.0060)EACH2$745.00$745.00$760.81$745.00$745.00
313Special 201. poles type 5- aluminum bronze (SPV.0060)EACH35$2,980.00$2,980.00$2,895.15$2,980.00$2,980.00
314Special 202. luminaire arms single member 4 1/2-inch clamp 6-FT bronze (SPV.0060)EACH60$412.00$412.00$479.09$412.00$412.00
315Special 203. luminaires utility LED B bronze (SPV.0060)EACH60$264.00$264.00$520.92$264.00$264.00
316Special 204. remove and salvage lighting unit (SPV.0060)EACH73$639.50$639.50$444.90$639.50$639.50
317Special 300. internal sanitary manhole seal (SPV.0060)EACH20$595.00$595.00$1,200.00$1,000.00$800.00
318Special 301. adjust sanitary manhole frame (SPV.0060)EACH20$597.50$597.50$1,100.00$2,900.00$1,400.00
319Special 302. sanitary manhole frame with solid gasketed lid (SPV.0060)EACH20$1,127.06$1,127.06$1,300.00$850.00$1,400.00
320Special 303. sanitary manhole abandonment (SPV.0060)EACH9$2,846.64$2,846.64$2,600.00$2,100.00$2,448.00
321Special 304. construction staking sanitary sewer (SPV.0060)EACH19$150.00$150.00$150.00$150.00$150.00
322Special 305. reconstructing MMSD manhole (SPV.0060)EACH4$3,268.44$3,268.44$1,260.00$4,700.00$4,127.00
323Special 400. water main connection 6-inch (SPV.0060)EACH5$5,642.64$5,642.64$8,000.00$9,500.00$7,018.00
324Special 401. water main connection 8-inch (SPV.0060)EACH4$7,463.76$7,463.76$7,500.00$12,000$7,461.00
325Special 402. water main connection 12-inch (SPV.0060)EACH5$8,400.29$8,400.29$9,500.00$13,500$8,615.00
326Special 403. water main valve 6- inch (SPV.0060)EACH5$2,504.51$2,504.51$2,400.00$2,800.00$3,012.00
327Special 404. water main valve 8- inch (SPV.0060)EACH3$3,575.91$3,575.91$3,300.00$3,800.00$4,109.00
328Special 405. water main valve 12- inch (SPV.0060)EACH12$6,123.90$6,123.90$6,000.00$6,700.00$7,028.00
329Special 406. short side hydrant (SPV.0060)EACH14$14,050$14,050$14,600$17,000$20,159
330Special 407. long side hydrant (SPV.0060)EACH7$21,510$21,510$20,700$25,000$24,778
331Special 408. air release assembly 1.5-inch (SPV.0060)EACH3$8,409.77$8,409.77$5,900.00$8,000.00$5,144.00
332Special 409. adjust water valve box (SPV.0060)EACH41$439.36$439.36$240.00$800.00$850.00
333Special 410. water service reconnect 4-inch (SPV.0060)EACH1$9,879.49$9,879.49$8,050.00$12,000$10,663
334Special 411. water service reconnect 6-inch (SPV.0060)EACH1$8,953.20$8,953.20$6,800.00$13,500$7,321.00
335Special 412. temporary water main connection (SPV.0060)EACH4$5,997.08$5,997.08$8,700.00$15,000$8,615.00
336Special 001. pipe railing black (SPV.0090)LF30$535.00$50.00$40.00$722.00$40.00
337Special 002. concrete curb & gutter 19-inch type D 9-inch gutter (SPV.0090)LF20$90.33$55.38$90.33$87.10$55.46
338Special 003. construction staking fence (SPV.0090)LF100$3.00$3.00$3.00$3.00$3.00
339Special 004. marking crosswalk epoxy block style 12-inch (SPV.0090)LF295$15.00$15.00$28.00$16.00$16.00
340Special 300. sanitary sewer relay SDR 35 PVC SP 8-inch (SPV.0090)LF2,836$288.22$288.22$290.00$290.00$200.00
341Special 301. sanitary sewer relay SDR 35 PVC SP 10-inch (SPV.0090)LF700$296.29$296.29$320.00$350.00$229.00
342Special 302. building sanitary sewer 6-inch (SPV.0090)LF1,025$299.89$299.89$283.00$330.00$201.00
343Special 400. water main relay 6- inch (SPV.0090)LF377$236.08$236.08$248.00$245.00$271.00
344Special 401. water main relay 8- inch (SPV.0090)LF490$257.50$257.50$242.00$250.00$188.00
345Special 402. water main relay 12- inch (SPV.0090)LF5,880$253.47$253.47$223.00$280.00$220.00
346Special 403. water service 1-inch (SPV.0090)LF864$242.89$242.89$205.00$260.00$225.00
347Special 404. water service 1.5-inch (SPV.0090)LF105$248.49$248.49$202.00$270.00$210.00
348Special 405. water service 2-inch (SPV.0090)LF216$232.50$232.52$210.00$275.00$165.00
349Special 406. construction staking water main (SPV.0090)LF6,750$1.50$1.50$1.50$1.50$1.50
350Special 001. detectable edge tiles (SPV.0165)SF840$54.12$48.54$54.12$49.83$49.19
351Special 001. mulch bioswales (SPV.0180)SY2,260$6.00$2.49$13.00$2.10$6.00
352Special 300. sanitary sewer 48-inch diameter (SPV.0200)VF214$726.97$726.97$326.00$650.00$752.00
353Special 301. sanitary riser 6-inch (SPV.0200)VF4$325.33$325.33$650.00$275.00$982.00
WisDOT contract 20260310016: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of March 10, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way