WisDOT contract 20260811015 bid tabulation
Plover - Waupaca; Maple Drive to I-39 (STH 054, Portage County Plover - Waupaca). Let by Wisconsin DOT on August 11, 2026, Portage. 7 bids received; low bid $2,095,063 by Hoffman Construction Company.
- Owner
- Wisconsin DOT
- Letting
- 11 AUG 2026
- Pay items
- 113
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Hoffman Construction Company | $2,095,063 | Low |
| 2 | James Peterson Sons, Inc. | $2,197,435 | +5.0% |
| 3 | Gerke Excavating Inc | $2,198,184 | +5.0% |
| 4 | Musson Bros., Inc. | $2,405,647 | +15% |
| 5 | Haas Sons, Inc. | $2,497,285 | +19% |
| 6 | Vinton Construction Company | $2,519,116 | +20% |
| 7 | A-1 Excavating LLC | $2,742,666 | +31% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Hoffman Construction Company | 2. James Peterson Sons, Inc. | 3. Gerke Excavating Inc | 4. Musson Bros., Inc. | 5. Haas Sons, Inc. | 6. Vinton Construction Company |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing small pipe culverts (203.0100) | EACH | 10 | $1,000.00 | $1,200.00 | $617.45 | $494.12 | $1,400.00 | $861.10 |
| 2 | Removing concrete pavement (204.0100) | SY | 26,880 | $5.00 | $5.48 | $4.00 | $3.59 | $4.55 | $1.50 |
| 3 | Removing asphaltic surface (204.0110) | SY | 420 | $10.00 | $4.85 | $4.56 | $5.44 | $4.00 | $10.00 |
| 4 | Removing curb & gutter (204.0150) | LF | 28 | $25.00 | $25.30 | $11.49 | $65.88 | $7.00 | $12.91 |
| 5 | Removing concrete sidewalk (204.0155) | SY | 8 | $100.00 | $50.00 | $36.31 | $82.36 | $100.00 | $27.29 |
| 6 | Removing guardrail (204.0165) | LF | 460 | $2.50 | $2.50 | $2.63 | $2.50 | $2.50 | $2.50 |
| 7 | Excavation common (205.0100) | CY | 14,148 | $10.00 | $4.50 | $5.20 | $7.50 | $14.00 | $16.74 |
| 8 | Backfill granular grade 1 (209.1500) | TON | 30 | $30.00 | $16.22 | $42.15 | $27.11 | $29.00 | $55.68 |
| 9 | Prepare foundation for asphaltic paving (project) 01. 6414-01-74 (211.0101) | EACH | 1 | $100.00 | $13,580 | $30,830 | $100.00 | $31,980 | $31,980 |
| 10 | Finishing roadway (project) 01. 6414-01-74 (213.0100) | EACH | 1 | $100.00 | $2,000.00 | $4,286.54 | $100.00 | $1.00 | $5,000.00 |
| 11 | Base aggregate dense 3/4-inch (305.0110) | TON | 3,060 | $0.01 | $16.45 | $25.07 | $24.27 | $23.00 | $22.50 |
| 12 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 10,570 | $0.01 | $10.95 | $9.87 | $20.99 | $16.00 | $17.70 |
| 13 | Drilled tie bars (416.0610) | EACH | 206 | $12.13 | $12.13 | $12.74 | $12.13 | $12.13 | $10.00 |
| 14 | Drilled dowel bars (416.0620) | EACH | 256 | $16.59 | $16.59 | $17.42 | $16.59 | $16.59 | $18.50 |
| 15 | Concrete pavement replacement (416.1720) | SY | 505 | $135.10 | $135.10 | $141.86 | $135.10 | $135.10 | $135.00 |
| 16 | Tack coat (455.0605) | GAL | 2,598 | $4.68 | $4.68 | $4.91 | $4.68 | $4.68 | $4.68 |
| 17 | Incentive density HMA pavement (460.2000) | DOL | 6,090 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 18 | HMA pavement 3 MT 58-28 S (460.6223) | TON | 6,520 | $88.38 | $88.38 | $92.80 | $88.38 | $88.38 | $88.38 |
| 19 | HMA pavement 4 MT 58-28 H (460.6424) | TON | 2,990 | $102.74 | $102.74 | $107.88 | $102.74 | $102.74 | $102.74 |
| 20 | Asphaltic surface driveways and field entrances (465.0120) | TON | 70 | $220.86 | $220.86 | $231.90 | $220.86 | $220.86 | $220.86 |
| 21 | Asphaltic surface safety islands (465.0305) | TON | 1 | $550.00 | $550.00 | $577.50 | $550.00 | $550.00 | $550.00 |
| 22 | Asphaltic rumble strips, shoulder (465.0520) | LF | 2,390 | $1.91 | $0.75 | $2.24 | $1.92 | $1.00 | $0.75 |
| 23 | Asphaltic rumble strips, centerline (465.0560) | LF | 5,570 | $0.78 | $0.75 | $0.97 | $0.78 | $1.00 | $0.75 |
| 24 | Sheet membrane waterproofing for buried structures (516.0610.S) | SY | 103 | $70.00 | $58.00 | $65.10 | $62.00 | $145.00 | $137.69 |
| 25 | Culvert pipe reinforced concrete class IV 18-inch (522.0418) | LF | 64 | $75.00 | $92.94 | $98.55 | $105.34 | $90.00 | $133.84 |
| 26 | Culvert pipe reinforced concrete class IV 24-inch (522.0424) | LF | 400 | $95.00 | $110.48 | $110.13 | $144.10 | $133.00 | $169.29 |
| 27 | Culvert pipe reinforced concrete class IV 48-inch (522.0448) | LF | 128 | $215.00 | $219.98 | $236.53 | $406.41 | $450.00 | $419.24 |
| 28 | Culvert pipe reinforced concrete class IV 54-inch (522.0454) | LF | 112 | $325.00 | $291.58 | $309.98 | $499.26 | $565.00 | $535.27 |
| 29 | Apron endwalls for culvert pipe reinforced concrete 18-inch (522.1018) | EACH | 2 | $1,200.00 | $840.28 | $1,192.33 | $1,274.35 | $1,700.00 | $1,513.35 |
| 30 | Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024) | EACH | 8 | $1,500.00 | $1,145.90 | $2,012.16 | $1,453.80 | $1,905.00 | $1,628.13 |
| 31 | Apron endwalls for culvert pipe reinforced concrete 48-inch (522.1048) | EACH | 4 | $4,500.00 | $4,267.30 | $4,646.23 | $3,466.08 | $4,750.00 | $4,086.25 |
| 32 | Apron endwalls for culvert pipe reinforced concrete 54-inch (522.1054) | EACH | 4 | $5,500.00 | $5,250.23 | $5,437.40 | $4,266.81 | $5,500.00 | $4,850.00 |
| 33 | Culvert pipe reinforced concrete horizontal elliptical class HE-IV 24X38-inch (522.2424) | LF | 128 | $215.00 | $189.40 | $199.24 | $232.45 | $232.00 | $275.90 |
| 34 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 24X38-inch (522.2624) | EACH | 4 | $1,400.00 | $1,372.95 | $2,024.38 | $2,037.27 | $2,950.00 | $2,715.00 |
| 35 | Anchor assemblies poles on structures (531.8990) | EACH | 1 | $1.00 | $1,500.00 | $1.00 | $1.00 | $1.00 | $2,500.00 |
| 36 | Concrete curb & gutter 18-inch type A (601.0405) | LF | 7 | $113.76 | $113.76 | $119.45 | $113.76 | $113.76 | $85.00 |
| 37 | Concrete curb & gutter 30-inch type A (601.0409) | LF | 20 | $116.16 | $116.16 | $121.97 | $116.16 | $116.16 | $85.00 |
| 38 | Concrete sidewalk 6-inch (602.0415) | SF | 65 | $54.92 | $54.92 | $57.67 | $54.92 | $54.92 | $15.00 |
| 39 | Riprap light (606.0100) | CY | 15 | $160.00 | $100.00 | $138.53 | $407.99 | $160.00 | $150.00 |
| 40 | Riprap medium (606.0200) | CY | 150 | $130.00 | $125.00 | $109.62 | $186.93 | $98.00 | $150.00 |
| 41 | Insulation board polystyrene (inch) 01. 2-inch (612.0902.S) | SY | 4 | $50.00 | $25.00 | $285.85 | $81.04 | $57.00 | $42.13 |
| 42 | Guardrail mow strip asphalt (614.0396) | SY | 104 | $49.80 | $59.80 | $52.29 | $49.80 | $49.80 | $49.80 |
| 43 | MGS guardrail 3 (614.2300) | LF | 214 | $29.85 | $29.85 | $31.34 | $29.85 | $29.85 | $29.85 |
| 44 | MGS guardrail 3 L (614.2340) | LF | 226 | $35.00 | $35.00 | $36.75 | $35.00 | $35.00 | $35.00 |
| 45 | MGS guardrail terminal eat (614.2610) | EACH | 4 | $3,425.00 | $3,425.00 | $3,596.25 | $3,425.00 | $3,425.00 | $3,425.00 |
| 46 | Maintenance and repair of haul roads (project) 01. 6414-01-74 (618.0100) | EACH | 1 | $100.00 | $0.01 | $4.12 | $1.00 | $1.00 | $0.01 |
| 47 | Mobilization (619.1000) | EACH | 1 | $257,319 | $218,163 | $207,334 | $207,050 | $218,000 | $269,000 |
| 48 | Water (624.0100) | MGAL | 270 | $100.00 | $50.00 | $40.30 | $100.69 | $40.00 | $40.00 |
| 49 | Topsoil (625.0100) | SY | 2,755 | $5.00 | $5.28 | $4.72 | $3.92 | $8.65 | $7.50 |
| 50 | Silt fence (628.1504) | LF | 3,160 | $1.95 | $1.95 | $2.05 | $1.95 | $1.95 | $1.95 |
| 51 | Silt fence maintenance (628.1520) | LF | 3,160 | $0.03 | $0.03 | $0.03 | $0.03 | $0.03 | $0.03 |
| 52 | Mobilizations erosion control (628.1905) | EACH | 3 | $285.00 | $285.00 | $299.25 | $285.00 | $285.00 | $285.00 |
| 53 | Mobilizations emergency erosion control (628.1910) | EACH | 3 | $295.00 | $295.00 | $309.75 | $295.00 | $295.00 | $295.00 |
| 54 | Erosion mat urban class I type A (628.2006) | SY | 7 | $3.25 | $3.25 | $3.41 | $3.25 | $3.25 | $3.25 |
| 55 | Erosion mat urban class I type B (628.2008) | SY | 2,748 | $2.50 | $2.50 | $2.63 | $2.50 | $2.50 | $2.50 |
| 56 | Temporary ditch checks (628.7504) | LF | 26 | $15.00 | $15.00 | $15.75 | $15.00 | $15.00 | $15.00 |
| 57 | Culvert pipe checks (628.7555) | EACH | 108 | $22.00 | $22.00 | $23.10 | $22.00 | $22.00 | $22.00 |
| 58 | Rock bags (628.7570) | EACH | 64 | $8.00 | $8.00 | $8.40 | $8.00 | $8.00 | $8.00 |
| 59 | Fertilizer type B (629.0210) | CWT | 5 | $125.00 | $125.00 | $131.25 | $125.00 | $125.00 | $125.00 |
| 60 | Seeding mixture no. 30 (630.0130) | LB | 132 | $8.95 | $8.95 | $9.40 | $8.95 | $8.95 | $8.95 |
| 61 | Seeding mixture no. 40 (630.0140) | LB | 2 | $100.00 | $100.00 | $105.00 | $100.00 | $100.00 | $100.00 |
| 62 | Seed water (630.0500) | MGAL | 56 | $10.00 | $10.00 | $10.50 | $10.00 | $10.00 | $10.00 |
| 63 | Markers culvert end (633.5200) | EACH | 22 | $85.00 | $85.00 | $89.25 | $85.00 | $85.00 | $85.00 |
| 64 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 23 | $105.00 | $105.00 | $110.25 | $105.00 | $105.00 | $105.00 |
| 65 | Signs type II reflective H (637.2210) | SF | 12.50 | $60.00 | $60.00 | $63.00 | $60.00 | $60.00 | $60.00 |
| 66 | Moving signs type II (638.2102) | EACH | 39 | $125.00 | $125.00 | $131.25 | $125.00 | $125.00 | $125.00 |
| 67 | Removing signs type II (638.2602) | EACH | 2 | $35.00 | $35.00 | $36.75 | $35.00 | $35.00 | $35.00 |
| 68 | Removing small sign supports (638.3000) | EACH | 2 | $35.00 | $35.00 | $36.75 | $35.00 | $35.00 | $35.00 |
| 69 | Field office type B (642.5001) | EACH | 1 | $20,000 | $12,500 | $10,285 | $20,000 | $15,000 | $12,000 |
| 70 | Traffic control drums (643.0300) | DAY | 915 | $0.50 | $0.50 | $0.32 | $0.50 | $0.50 | $0.30 |
| 71 | Traffic control barricades type III (643.0420) | DAY | 1,316 | $0.60 | $0.60 | $0.53 | $0.60 | $0.60 | $0.50 |
| 72 | Traffic control warning lights type A (643.0705) | DAY | 2,712 | $0.10 | $0.10 | $0.01 | $0.10 | $0.10 | $0.01 |
| 73 | Traffic control connected arrow boards (643.0810) | DAY | 10 | $20.00 | $20.00 | $42.00 | $20.00 | $20.00 | $40.00 |
| 74 | Traffic control signs (643.0900) | DAY | 8,165 | $0.72 | $0.72 | $0.37 | $0.72 | $0.72 | $0.35 |
| 75 | Traffic control covering signs type II (643.0920) | EACH | 21 | $20.00 | $20.00 | $36.75 | $20.00 | $20.00 | $35.00 |
| 76 | Traffic control signs fixed message (643.1000) | SF | 36 | $10.90 | $10.90 | $11.03 | $10.90 | $10.90 | $10.50 |
| 77 | Traffic control (643.5000) | EACH | 1 | $4,350.00 | $4,350.00 | $9,817.50 | $4,350.00 | $4,350.00 | $9,350.00 |
| 78 | Geotextile type HR (645.0120) | SY | 300 | $10.00 | $4.00 | $3.72 | $8.81 | $6.00 | $3.90 |
| 79 | Geotextile type R (645.0130) | SY | 23 | $10.00 | $40.00 | $24.38 | $14.12 | $17.00 | $5.00 |
| 80 | Marking line epoxy 6-inch (646.2020) | LF | 500 | $1.00 | $1.00 | $1.05 | $1.00 | $0.75 | $1.00 |
| 81 | Marking line grooved black epoxy 6-inch (646.2025) | LF | 6 | $10.00 | $10.00 | $10.50 | $10.00 | $50.00 | $10.00 |
| 82 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 20,952 | $1.24 | $1.24 | $1.30 | $1.24 | $1.38 | $1.24 |
| 83 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 152 | $2.75 | $2.75 | $2.89 | $2.75 | $2.50 | $2.75 |
| 84 | Marking stop line epoxy 18-inch (646.6120) | LF | 182 | $13.60 | $13.60 | $14.28 | $13.60 | $14.00 | $13.60 |
| 85 | Marking diagonal epoxy 12-inch (646.7120) | LF | 134 | $13.20 | $13.20 | $13.86 | $13.20 | $12.00 | $13.20 |
| 86 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 92 | $11.00 | $11.00 | $11.55 | $11.00 | $11.00 | $11.00 |
| 87 | Locating no-passing zones (648.0100) | MI | 1.51 | $555.70 | $555.70 | $583.49 | $555.70 | $500.00 | $555.70 |
| 88 | Construction staking subgrade (650.4500) | LF | 348 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.75 |
| 89 | Construction staking base (650.5000) | LF | 7,968 | $0.01 | $0.78 | $0.82 | $0.58 | $0.58 | $0.78 |
| 90 | Construction staking pipe culverts (650.6000) | EACH | 11 | $175.00 | $175.00 | $183.75 | $300.00 | $300.00 | $175.00 |
| 91 | Construction staking resurfacing reference (650.8000) | LF | 7,968 | $0.01 | $0.14 | $0.15 | $0.14 | $0.14 | $0.14 |
| 92 | Construction staking electrical installations (project) 01. 6414-01- 74 (650.8501) | EACH | 1 | $550.00 | $550.00 | $577.50 | $300.00 | $300.00 | $550.00 |
| 93 | Construction staking supplemental control (project) 01. 6414-01-74 (650.9911) | EACH | 1 | $850.00 | $850.00 | $892.50 | $1,560.61 | $1,560.61 | $850.00 |
| 94 | Construction staking slope stakes (650.9920) | LF | 881 | $0.01 | $0.79 | $0.83 | $2.95 | $2.95 | $0.79 |
| 95 | Install conduit into existing item (652.0700.S) | EACH | 8 | $420.00 | $125.00 | $441.00 | $420.00 | $420.00 | $125.00 |
| 96 | Conduit loop detector (652.0800) | LF | 566 | $12.15 | $6.00 | $12.76 | $12.15 | $12.15 | $6.00 |
| 97 | Concrete bases type 13 (654.0113) | EACH | 1 | $22,970 | $15,000 | $24,119 | $22,970 | $22,970 | $15,000 |
| 98 | Loop detector lead in cable (655.0700) | LF | 1,352 | $2.27 | $3.00 | $2.38 | $2.27 | $2.27 | $3.00 |
| 99 | Loop detector wire (655.0800) | LF | 1,990 | $1.43 | $1.25 | $1.50 | $1.43 | $1.43 | $1.25 |
| 100 | Poles type 12-over height (657.0356) | EACH | 1 | $19,793 | $16,985 | $20,783 | $19,793 | $19,793 | $16,985 |
| 101 | Monotube arms 15-FT (657.0515) | EACH | 1 | $3,925.00 | $3,095.00 | $4,121.25 | $3,925.00 | $3,925.00 | $3,095.00 |
| 102 | Sawing asphalt (690.0150) | LF | 248 | $1.50 | $1.50 | $1.58 | $1.50 | $1.50 | $3.00 |
| 103 | Sawing concrete (690.0250) | LF | 867 | $2.25 | $2.25 | $2.36 | $2.25 | $2.25 | $4.00 |
| 104 | Incentive iri ride (740.0440) | DOL | 6,040 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 105 | Special 01. 27-inch sanitary plug installation (SPV.0060) | EACH | 1 | $250.00 | $1,300.00 | $559.99 | $1,300.00 | $1,600.00 | $1,637.08 |
| 106 | Special 02. connect to existing sewer (SPV.0060) | EACH | 3 | $1,600.00 | $4,133.00 | $3,813.74 | $4,133.00 | $5,100.00 | $4,252.68 |
| 107 | Special 03. construction staking sanitary sewer (SPV.0060) | EACH | 1 | $180.00 | $180.00 | $189.00 | $375.00 | $375.00 | $180.00 |
| 108 | Special 01. 10-inch PVC sanitary sewer (SPV.0090) | LF | 14 | $250.00 | $710.54 | $94.61 | $710.54 | $280.00 | $268.11 |
| 109 | Special 02. 15-inch PVC sanitary sewer (SPV.0090) | LF | 14 | $260.00 | $726.54 | $110.20 | $726.54 | $300.00 | $294.91 |
| 110 | Special 03. 27-inch PVC sanitary sewer (SPV.0090) | LF | 70 | $300.00 | $807.60 | $165.86 | $807.00 | $240.00 | $397.87 |
| 111 | Special 04. 30-inch PVC sanitary sewer (SPV.0090) | LF | 14 | $330.00 | $801.91 | $187.09 | $801.91 | $380.00 | $422.80 |
| 112 | Special 05. sanitary sewer service 4-inch (SPV.0090) | LF | 10 | $200.00 | $698.11 | $115.64 | $698.11 | $275.00 | $168.36 |
| 113 | Special 01. 60-inch I.D. sanitary sewer drop manhole (SPV.0200) | VF | 18 | $1,300.00 | $1,064.22 | $1,028.98 | $1,064.22 | $2,710.00 | $2,790.17 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of August 11, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.