WisDOT contract 20260512003 bid tabulation
5350-02-65. Let by Wisconsin DOT on May 12, 2026, Rock. 2 bids received; low bid $864,916 by Parisi Construction, LLC.
- Owner
- Wisconsin DOT
- Letting
- 12 MAY 2026
- Pay items
- 125
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Parisi Construction, LLC | $864,916 | Low |
| 2 | Rock Road Companies, Inc. | $1,070,486 | +24% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Parisi Construction, LLC | 2. Rock Road Companies, Inc. |
|---|---|---|---|---|---|
| 1 | Abatement of asbestos containing material (structure) 001. barrier walls (203.0211.S) | EACH | 1 | $12,700 | $11,525 |
| 2 | Removing concrete pavement (204.0100) | SY | 265 | $18.00 | $35.77 |
| 3 | Removing concrete pavement butt joints (204.0105) | SY | 41 | $22.00 | $20.76 |
| 4 | Removing concrete surface partial depth (204.0109.S) | SF | 26,238 | $0.55 | $0.55 |
| 5 | Removing asphaltic surface butt joints (204.0115) | SY | 107 | $22.00 | $20.76 |
| 6 | Removing asphaltic surface milling (204.0120) | SY | 4,348 | $0.55 | $5.08 |
| 7 | Removing curb & gutter (204.0150) | LF | 529 | $15.25 | $17.16 |
| 8 | Removing concrete sidewalk (204.0155) | SY | 340 | $31.25 | $20.77 |
| 9 | Removing concrete barrier (204.0157) | LF | 9 | $140.00 | $174.84 |
| 10 | Excavation common (205.0100) | CY | 83 | $88.00 | $31.08 |
| 11 | Finishing roadway (project) 001. 5350-02-65 (213.0100) | EACH | 1 | $500.00 | $4,934.39 |
| 12 | Finishing roadway (project) 002. 5350-02-75 (213.0100) | EACH | 1 | $500.00 | $4,934.39 |
| 13 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 370 | $28.75 | $34.67 |
| 14 | Concrete base 8-inch (320.0145) | SY | 76 | $140.00 | $100.00 |
| 15 | Concrete base 10-inch (320.0165) | SY | 32 | $170.00 | $125.00 |
| 16 | Drilled tie bars (416.0610) | EACH | 329 | $17.75 | $12.50 |
| 17 | Concrete pavement replacement shes (416.1725) | SY | 67 | $210.00 | $150.00 |
| 18 | Tack coat (455.0605) | GAL | 397 | $0.55 | $3.89 |
| 19 | Incentive density HMA pavement (460.2000) | DOL | 520 | $1.00 | $1.00 |
| 20 | HMA pavement 4 MT 58-28 H (460.6424) | TON | 807 | $130.00 | $124.69 |
| 21 | Asphaltic surface driveways and field entrances (465.0120) | TON | 3 | $280.00 | $230.25 |
| 22 | Protective surface treatment (502.3200) | SY | 383 | $4.40 | $4.00 |
| 23 | Protective surface treatment reseal (502.3215) | SY | 121 | $22.00 | $20.00 |
| 24 | Preparation decks type 1 (509.0301) | SY | 25 | $330.00 | $300.00 |
| 25 | Curb repair (509.1200) | LF | 133 | $130.00 | $120.00 |
| 26 | Concrete surface repair (509.1500) | SF | 10 | $310.00 | $280.00 |
| 27 | Concrete masonry overlay decks (509.2500) | CY | 22 | $4,700.00 | $4,300.00 |
| 28 | Removing asphaltic concrete deck overlay (structure) 001. B-53-135 (509.9010.S) | SY | 383 | $88.00 | $80.00 |
| 29 | Removing and resetting tubular railing (structure) 001. barrier walls (513.9006.S) | EACH | 1 | $8,800.00 | $8,000.00 |
| 30 | Concrete curb & gutter 30-inch type K (601.0417) | LF | 687 | $59.00 | $43.00 |
| 31 | Concrete curb & gutter 30-inch type L (601.0419) | LF | 25 | $75.00 | $43.00 |
| 32 | Concrete curb & gutter 4-inch sloped 36-inch type TBTT (601.0590) | LF | 45 | $69.00 | $50.00 |
| 33 | Concrete curb pedestrian (601.0600) | LF | 79 | $67.00 | $40.00 |
| 34 | Concrete sidewalk 4-inch (602.0405) | SF | 2,741 | $12.25 | $8.00 |
| 35 | Concrete sidewalk 6-inch (602.0415) | SF | 371 | $18.50 | $9.35 |
| 36 | Curb ramp detectable warning field natural patina (602.0515) | SF | 90 | $49.25 | $37.50 |
| 37 | Curb ramp detectable warning field radial natural patina (602.0615) | SF | 16 | $77.00 | $60.00 |
| 38 | Concrete driveway 8-inch (602.0820) | SY | 86 | $120.00 | $90.00 |
| 39 | Concrete barrier single-faced 32- inch (603.0105) | LF | 7 | $780.00 | $1,000.00 |
| 40 | Adjusting manhole covers (611.8110) | EACH | 4 | $610.00 | $1,123.58 |
| 41 | Adjusting inlet covers (611.8115) | EACH | 9 | $740.00 | $1,123.58 |
| 42 | MGS guardrail 3 (614.2300) | LF | 25 | $38.50 | $30.00 |
| 43 | MGS thrie beam transition (614.2500) | LF | 39 | $120.00 | $95.00 |
| 44 | MGS guardrail terminal eat (614.2610) | EACH | 1 | $5,800.00 | $3,700.00 |
| 45 | Mobilization (619.1000) | EACH | 1 | $92,500 | $327,000 |
| 46 | Concrete median sloped nose (620.0300) | SF | 20 | $34.00 | $20.00 |
| 47 | Water (624.0100) | MGAL | 8 | $69.00 | $0.01 |
| 48 | Topsoil (625.0100) | SY | 543 | $17.50 | $0.01 |
| 49 | Mulching (627.0200) | SY | 20 | $11.00 | $1.00 |
| 50 | Mobilizations erosion control (628.1905) | EACH | 5 | $550.00 | $200.00 |
| 51 | Mobilizations emergency erosion control (628.1910) | EACH | 5 | $550.00 | $350.00 |
| 52 | Inlet protection type B (628.7010) | EACH | 12 | $83.00 | $60.00 |
| 53 | Inlet protection type C (628.7015) | EACH | 18 | $83.00 | $70.00 |
| 54 | Fertilizer type B (629.0210) | CWT | 0.36 | $220.00 | $400.00 |
| 55 | Seeding temporary (630.0200) | LB | 1 | $110.00 | $5.00 |
| 56 | Sod water (631.0300) | MGAL | 14 | $44.00 | $75.00 |
| 57 | Sod lawn (631.1000) | SY | 543 | $17.50 | $16.00 |
| 58 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 2 | $170.00 | $110.00 |
| 59 | Posts tubular steel 2X2-inch X 9.5- FT (634.0809) | EACH | 2 | $240.00 | $225.00 |
| 60 | Posts tubular steel 2X2-inch X 11- FT (634.0811) | EACH | 5 | $240.00 | $225.00 |
| 61 | Posts tubular steel 2X2-inch X 14- FT (634.0814) | EACH | 2 | $250.00 | $225.00 |
| 62 | Signs type II reflective H (637.2210) | SF | 77.75 | $49.50 | $19.25 |
| 63 | Signs type II reflective F (637.2230) | SF | 9 | $66.00 | $22.00 |
| 64 | Moving signs type II (638.2102) | EACH | 2 | $140.00 | $100.00 |
| 65 | Removing signs type II (638.2602) | EACH | 4 | $55.00 | $30.00 |
| 66 | Removing small sign supports (638.3000) | EACH | 2 | $55.00 | $30.00 |
| 67 | Moving small sign supports (638.4000) | EACH | 2 | $170.00 | $100.00 |
| 68 | Traffic control drums (643.0300) | DAY | 8,131 | $0.35 | $0.30 |
| 69 | Traffic control barricades type III (643.0420) | DAY | 2,316 | $0.85 | $0.75 |
| 70 | Traffic control flexible tubular marker posts (643.0500) | EACH | 25 | $28.50 | $26.00 |
| 71 | Traffic control flexible tubular marker bases (643.0600) | EACH | 25 | $11.00 | $10.00 |
| 72 | Traffic control warning lights type A (643.0705) | DAY | 4,632 | $0.15 | $0.15 |
| 73 | Traffic control warning lights type C (643.0715) | DAY | 1,105 | $0.15 | $0.15 |
| 74 | Traffic control connected arrow boards (643.0810) | DAY | 160 | $25.25 | $23.00 |
| 75 | Traffic control signs (643.0900) | DAY | 6,252 | $1.00 | $0.90 |
| 76 | Traffic control signs PCMS (643.1050) | DAY | 42 | $44.00 | $40.00 |
| 77 | Traffic control cones 42-inch (643.1070) | DAY | 9,276 | $0.35 | $0.30 |
| 78 | Traffic control connected work zone start and end location markers (643.1220) | DAY | 315 | $14.25 | $13.00 |
| 79 | Temporary marking line paint 6- inch (643.3165) | LF | 4,044 | $0.35 | $0.30 |
| 80 | Temporary marking line removable tape 6-inch (643.3180) | LF | 9,389 | $1.80 | $1.60 |
| 81 | Temporary marking line paint 10- inch (643.3265) | LF | 70 | $1.10 | $1.00 |
| 82 | Temporary marking line removable tape 10-inch (643.3280) | LF | 100 | $4.10 | $3.75 |
| 83 | Temporary marking crosswalk paint 6-inch (643.3305) | LF | 167 | $5.50 | $5.00 |
| 84 | Temporary marking crosswalk removable tape 6-inch (643.3350) | LF | 315 | $8.80 | $8.00 |
| 85 | Temporary marking arrow paint (643.3505) | EACH | 1 | $170.00 | $150.00 |
| 86 | Temporary marking arrow removable tape (643.3550) | EACH | 2 | $390.00 | $350.00 |
| 87 | Temporary marking removable mask out tape 6-inch (643.3960) | LF | 150 | $2.80 | $2.50 |
| 88 | Traffic control (643.5000) | EACH | 1 | $20,500 | $18,600 |
| 89 | Temporary pedestrian surface plate (644.1430) | SF | 50 | $22.00 | $20.00 |
| 90 | Temporary pedestrian surface matting (644.1440) | SF | 80 | $8.80 | $8.00 |
| 91 | Temporary pedestrian curb ramp (644.1601) | DAY | 20 | $9.90 | $9.00 |
| 92 | Temporary pedestrian detectable warning field (644.1605) | SF | 130 | $18.75 | $17.00 |
| 93 | Temporary pedestrian barricade (644.1810) | LF | 935 | $5.50 | $5.00 |
| 94 | Temporary audible message devices (644.1900.S) | DAY | 230 | $7.70 | $7.00 |
| 95 | Marking line epoxy 6-inch (646.2020) | LF | 2,768 | $2.50 | $2.30 |
| 96 | Marking line epoxy 10-inch (646.4020) | LF | 264 | $4.40 | $3.95 |
| 97 | Marking arrow epoxy (646.5020) | EACH | 3 | $360.00 | $325.00 |
| 98 | Marking stop line epoxy 12-inch (646.6020) | LF | 27 | $13.25 | $12.00 |
| 99 | Marking stop line epoxy 18-inch (646.6120) | LF | 135 | $16.50 | $15.00 |
| 100 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 411 | $12.50 | $11.25 |
| 101 | Marking curb epoxy (646.8120) | LF | 26 | $9.90 | $9.00 |
| 102 | Marking island nose epoxy (646.8220) | EACH | 2 | $390.00 | $350.00 |
| 103 | Marking removal line 6-inch (646.9002) | LF | 225 | $1.10 | $1.00 |
| 104 | Construction staking subgrade (650.4500) | LF | 237 | $0.01 | $0.01 |
| 105 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 253 | $2.20 | $2.00 |
| 106 | Construction staking structure layout (structure) 001. B-53-135 (650.6501) | EACH | 1 | $1,300.00 | $1,200.00 |
| 107 | Construction staking resurfacing reference (650.8000) | LF | 1,029 | $0.65 | $0.60 |
| 108 | Construction staking curb ramps (650.9000) | EACH | 12 | $110.00 | $200.00 |
| 109 | Construction staking sidewalk (project) 001. 5350-02-75 (650.9500) | EACH | 1 | $1,200.00 | $1,100.00 |
| 110 | Construction staking supplemental control (project) 001. 5350-02-75 (650.9911) | EACH | 1 | $1,300.00 | $1,200.00 |
| 111 | Construction staking slope stakes (650.9920) | LF | 237 | $3.60 | $3.25 |
| 112 | Sawing asphalt (690.0150) | LF | 68 | $1.40 | $3.45 |
| 113 | Sawing concrete (690.0250) | LF | 1,057 | $2.50 | $2.45 |
| 114 | Incentive strength concrete structures (715.0502) | DOL | 500 | $1.00 | $1.00 |
| 115 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 1,200 | $5.00 | $5.00 |
| 116 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 600 | $5.00 | $5.00 |
| 117 | Special 101. utility line opening (ulo) (SPV.0060) | EACH | 10 | $720.00 | $550.00 |
| 118 | Special 102. adjusting water valve boxes (SPV.0060) | EACH | 3 | $590.00 | $409.53 |
| 119 | Special 103. storm sewer structure repair (SPV.0060) | EACH | 1 | $3,500.00 | $5,833.80 |
| 120 | Special 104. manhole covers type coj (SPV.0060) | EACH | 1 | $2,200.00 | $1,352.71 |
| 121 | Special 105. installing city supplied street name signs (SPV.0060) | EACH | 2 | $550.00 | $150.00 |
| 122 | Special 401. near-surface mounted carbon fiber reinforcement (SPV.0060) | EACH | 22 | $1,400.00 | $1,290.00 |
| 123 | Special 101. concrete curb & gutter 18-inch type K (SPV.0090) | LF | 13 | $110.00 | $40.00 |
| 124 | Special 102. concrete joint and crack plunge milling and patching (SPV.0090) | LF | 568 | $27.50 | $38.93 |
| 125 | Special 103. concrete joint and crack cleaning (SPV.0090) | LF | 1,256 | $16.50 | $38.73 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of May 12, 2026. Compiled by Mirage Metrics.