WisDOT contract 20261013009 bid tabulation
1100-56-70. Let by Wisconsin DOT on October 13, 2026, Fond Du Lac. 3 bids received; low bid $11,293,926 by Vinton Construction Company.
- Owner
- Wisconsin DOT
- Letting
- 13 OCT 2026
- Pay items
- 215
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Vinton Construction Company | $11,293,926 | Low |
| 2 | Zignego Company, Inc. | $11,952,548 | +6.0% |
| 3 | Michels Road & Stone, Inc. | $14,864,514 | +32% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Vinton Construction Company | 2. Zignego Company, Inc. | 3. Michels Road & Stone, Inc. |
|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 13 | $800.00 | $800.00 | $1,650.00 |
| 2 | Grubbing (201.0205) | STA | 13 | $200.00 | $200.00 | $344.00 |
| 3 | Removing small pipe culverts (203.0100) | EACH | 4 | $510.94 | $350.00 | $350.00 |
| 4 | Removing concrete pavement (204.0100) | SY | 620 | $19.50 | $30.00 | $58.00 |
| 5 | Removing asphaltic surface (204.0110) | SY | 4,350 | $0.01 | $5.00 | $14.00 |
| 6 | Removing asphaltic surface butt joints (204.0115) | SY | 89 | $58.70 | $58.70 | $58.70 |
| 7 | Removing asphaltic surface milling (204.0120) | SY | 58,100 | $3.90 | $3.90 | $3.90 |
| 8 | Removing curb & gutter (204.0150) | LF | 477 | $10.00 | $30.00 | $30.00 |
| 9 | Removing concrete sidewalk (204.0155) | SY | 18 | $30.69 | $30.00 | $50.00 |
| 10 | Removing concrete barrier (204.0157) | LF | 314 | $34.06 | $75.00 | $75.00 |
| 11 | Removing guardrail (204.0165) | LF | 4,410 | $1.80 | $1.80 | $1.80 |
| 12 | Removing cable barrier (204.0167) | LF | 17,200 | $4.74 | $4.95 | $4.95 |
| 13 | Removing fence (204.0170) | LF | 270 | $2.00 | $2.00 | $2.00 |
| 14 | Removing concrete slope paving (204.0175) | SY | 924 | $14.72 | $30.00 | $27.00 |
| 15 | Removing delineators and markers (204.0180) | EACH | 15 | $18.00 | $18.00 | $18.00 |
| 16 | Removing surface drains (204.0190) | EACH | 1 | $500.00 | $1,000.00 | $1,300.00 |
| 17 | Removing manholes (204.0210) | EACH | 6 | $539.67 | $950.00 | $950.00 |
| 18 | Removing inlets (204.0220) | EACH | 6 | $400.58 | $375.00 | $375.00 |
| 19 | Removing storm sewer (size) 01. 12-inch (204.0245) | LF | 18 | $19.48 | $16.00 | $16.00 |
| 20 | Removing storm sewer (size) 02. 18-inch (204.0245) | LF | 5 | $42.02 | $17.00 | $17.00 |
| 21 | Removing storm sewer (size) 03. 24-inch (204.0245) | LF | 600 | $17.89 | $26.50 | $26.50 |
| 22 | Removing storm sewer (size) 04. 30-inch (204.0245) | LF | 63 | $22.72 | $22.00 | $22.00 |
| 23 | Removing storm sewer (size) 05. 36-inch (204.0245) | LF | 58 | $23.43 | $23.00 | $23.00 |
| 24 | Removing storm sewer (size) 06. 19-inch X 30-inch (204.0245) | LF | 21 | $25.77 | $23.00 | $23.00 |
| 25 | Removing storm sewer (size) 07. 24-inch X 38-inch (204.0245) | LF | 130 | $19.91 | $26.00 | $26.00 |
| 26 | Removing (item description) 01. crash cushion (204.9060.S) | EACH | 1 | $950.00 | $3,500.00 | $3,500.00 |
| 27 | Excavation common (205.0100) | CY | 3,870 | $38.15 | $75.00 | $30.00 |
| 28 | Borrow (208.0100) | CY | 558 | $28.90 | $20.00 | $20.00 |
| 29 | Finishing roadway (project) 01. 1100-56-70 (213.0100) | EACH | 1 | $3,000.00 | $1,000.00 | $2,500.00 |
| 30 | Finishing roadway (project) 02. 1100-56-71 (213.0100) | EACH | 1 | $3,000.00 | $1,000.00 | $2,500.00 |
| 31 | Base aggregate dense 3/4-inch (305.0110) | TON | 7,130 | $37.91 | $45.00 | $27.00 |
| 32 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 5,420 | $20.61 | $33.00 | $19.00 |
| 33 | Base aggregate dense 3-inch (305.0130) | TON | 2,660 | $20.11 | $33.00 | $15.00 |
| 34 | Coloring concrete wisdot red (405.0100) | CY | 107 | $90.00 | $200.00 | $160.00 |
| 35 | Concrete pavement hes 9-inch (415.1090) | SY | 355 | $98.59 | $115.00 | $330.45 |
| 36 | Concrete truck apron 12-inch (415.2010) | SY | 320 | $108.70 | $150.00 | $125.00 |
| 37 | Drilled tie bars (416.0610) | EACH | 2,063 | $11.00 | $20.00 | $12.14 |
| 38 | Drilled dowel bars (416.0620) | EACH | 3,947 | $19.50 | $25.00 | $16.36 |
| 39 | Concrete pavement repair (416.1710) | SY | 180 | $116.00 | $150.00 | $306.64 |
| 40 | Concrete pavement repair shes (416.1715) | SY | 970 | $160.69 | $160.00 | $306.64 |
| 41 | Concrete pavement replacement (416.1720) | SY | 670 | $120.00 | $150.00 | $307.82 |
| 42 | Concrete pavement replacement shes (416.1725) | SY | 5,910 | $164.69 | $160.00 | $310.08 |
| 43 | Tack coat (455.0605) | GAL | 4,430 | $3.25 | $3.25 | $3.25 |
| 44 | Incentive density HMA pavement (460.2000) | DOL | 4,430 | $1.00 | $1.00 | $1.00 |
| 45 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 6,850 | $114.10 | $114.10 | $144.10 |
| 46 | Asphaltic surface (465.0105) | TON | 725 | $155.30 | $155.30 | $155.30 |
| 47 | Asphaltic surface driveways and field entrances (465.0120) | TON | 165 | $172.40 | $172.40 | $172.40 |
| 48 | Asphaltic surface temporary (465.0125) | TON | 90 | $397.50 | $397.50 | $397.50 |
| 49 | Asphaltic rumble strips, shoulder divided roadway (465.0510) | LF | 38,960 | $0.22 | $0.22 | $0.14 |
| 50 | Pigmented surface sealer reseal (502.3205) | SY | 1,000 | $18.75 | $18.75 | $18.75 |
| 51 | Adhesive anchors no. 4 bar (502.4204) | EACH | 10 | $20.00 | $50.00 | $1,000.00 |
| 52 | Preparation decks type 1 (509.0301) | SY | 1 | $465.00 | $465.00 | $465.00 |
| 53 | Sawing pavement deck preparation areas (509.0310.S) | LF | 10 | $9.00 | $9.00 | $9.00 |
| 54 | Concrete surface repair (509.1500) | SF | 10 | $295.00 | $295.00 | $295.00 |
| 55 | Concrete masonry deck repair (509.2100.S) | CY | 1 | $4,365.00 | $4,365.00 | $4,365.00 |
| 56 | Culvert pipe temporary 18-inch (520.2018) | LF | 254 | $48.59 | $56.00 | $56.00 |
| 57 | Concrete collars for pipe (520.8000) | EACH | 7 | $997.86 | $890.00 | $890.00 |
| 58 | Apron endwalls for culvert pipe steel 12-inch (521.1012) | EACH | 4 | $307.25 | $280.00 | $280.00 |
| 59 | Apron endwalls for culvert pipe steel 18-inch (521.1018) | EACH | 6 | $410.21 | $380.00 | $380.00 |
| 60 | Culvert pipe corrugated steel 12- inch (521.3112) | LF | 154 | $82.84 | $65.00 | $65.00 |
| 61 | Culvert pipe corrugated steel 18- inch (521.3118) | LF | 124 | $99.82 | $70.00 | $70.00 |
| 62 | Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036) | EACH | 1 | $2,592.75 | $2,219.00 | $2,219.00 |
| 63 | Apron endwalls for culvert pipe reinforced concrete 54-inch (522.1054) | EACH | 1 | $4,445.50 | $3,364.00 | $3,364.00 |
| 64 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 19X30-inch (522.2619) | EACH | 1 | $1,928.99 | $1,528.00 | $1,528.00 |
| 65 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 24X38-inch (522.2624) | EACH | 1 | $2,342.75 | $1,928.00 | $1,928.00 |
| 66 | Concrete curb & gutter 6-inch sloped 30-inch type G (601.0413) | LF | 90 | $85.00 | $120.00 | $90.00 |
| 67 | Concrete curb & gutter 4-inch sloped 36-inch type A (601.0551) | LF | 395 | $75.00 | $60.00 | $75.00 |
| 68 | Concrete curb & gutter 4-inch sloped 30-inch type G (601.0574) | LF | 87 | $85.00 | $120.00 | $90.00 |
| 69 | Concrete curb & gutter 4-inch sloped 36-inch type TBTT (601.0590) | LF | 118 | $85.00 | $120.00 | $90.00 |
| 70 | Concrete sidewalk 4-inch (602.0405) | SF | 160 | $15.00 | $20.00 | $16.00 |
| 71 | Concrete surface drains (602.3010) | CY | 8 | $1,500.00 | $1,000.00 | $1,625.00 |
| 72 | Concrete rumble strips, shoulder divided roadway (602.3210) | LF | 20,320 | $0.63 | $0.63 | $0.84 |
| 73 | Concrete barrier single-faced 32- inch (603.0105) | LF | 92 | $272.00 | $300.00 | $350.00 |
| 74 | Concrete barrier type S42 (603.1142) | LF | 215 | $295.00 | $300.00 | $350.00 |
| 75 | Concrete barrier transition type NJ32SF to S32 (603.3111) | EACH | 2 | $6,000.00 | $10,000 | $8,000.00 |
| 76 | Slope paving crushed aggregate (604.0500) | SY | 924 | $30.00 | $49.00 | $49.00 |
| 77 | Riprap medium (606.0200) | CY | 318 | $112.13 | $300.00 | $115.00 |
| 78 | Storm sewer pipe reinforced concrete class III 12-inch (608.0312) | LF | 8 | $233.73 | $141.00 | $141.00 |
| 79 | Storm sewer pipe reinforced concrete class III 24-inch (608.0324) | LF | 12 | $177.87 | $158.00 | $158.00 |
| 80 | Storm sewer pipe reinforced concrete class III 30-inch (608.0330) | LF | 576 | $203.15 | $136.00 | $136.00 |
| 81 | Storm sewer pipe reinforced concrete class III 36-inch (608.0336) | LF | 73 | $259.69 | $162.00 | $162.00 |
| 82 | Storm sewer pipe reinforced concrete class IV 15-inch (608.0415) | LF | 22 | $137.76 | $82.00 | $82.00 |
| 83 | Storm sewer pipe reinforced concrete class IV 18-inch (608.0418) | LF | 125 | $97.49 | $82.00 | $82.00 |
| 84 | Storm sewer pipe reinforced concrete class V 54-inch (608.0554) | LF | 2,194 | $746.57 | $748.00 | $748.00 |
| 85 | Storm sewer pipe reinforced concrete horizontal elliptical class HE-IV 19X30-inch (608.2419) | LF | 175 | $314.81 | $150.00 | $150.00 |
| 86 | Storm sewer pipe reinforced concrete horizontal elliptical class HE-IV 24X38-inch (608.2424) | LF | 84 | $210.49 | $171.00 | $171.00 |
| 87 | Storm sewer pipe reinforced concrete horizontal elliptical class HE-IV 29X45-inch (608.2429) | LF | 155 | $302.75 | $229.00 | $229.00 |
| 88 | Manhole covers type J (611.0530) | EACH | 12 | $517.00 | $548.00 | $548.00 |
| 89 | Inlet covers type C (611.0612) | EACH | 2 | $538.00 | $573.00 | $573.00 |
| 90 | Inlet covers type HM (611.0627) | EACH | 1 | $740.00 | $806.00 | $806.00 |
| 91 | Inlet covers type MS (611.0642) | EACH | 8 | $527.00 | $559.00 | $559.00 |
| 92 | Inlet covers type VV-B (611.0656) | EACH | 6 | $1,950.00 | $2,242.00 | $2,242.00 |
| 93 | Manholes 5-FT diameter (611.2005) | EACH | 4 | $6,145.85 | $5,262.00 | $5,262.00 |
| 94 | Manholes 6-FT diameter (611.2006) | EACH | 2 | $7,117.35 | $6,177.00 | $6,177.00 |
| 95 | Manholes 7-FT diameter (611.2007) | EACH | 1 | $9,758.94 | $8,162.00 | $8,162.00 |
| 96 | Manholes 8-FT diameter (611.2008) | EACH | 3 | $13,304 | $12,784 | $12,784 |
| 97 | Manholes 10-FT diameter (611.2010) | EACH | 1 | $31,961 | $21,952 | $21,952 |
| 98 | Manholes variable tee 4-FT diameter (611.2504) | EACH | 1 | $29,233 | $17,073 | $17,073 |
| 99 | Manholes variable special 4-FT diameter (611.2604) | EACH | 4 | $32,895 | $26,222 | $104,888 |
| 100 | Inlets 2X3.5-FT (611.3260) | EACH | 4 | $3,155.22 | $2,752.00 | $2,752.00 |
| 101 | Inlets median 2 grate (611.3902) | EACH | 2 | $4,093.40 | $3,794.00 | $3,794.00 |
| 102 | Inlets median 4 grate (611.3904) | EACH | 1 | $5,194.44 | $5,901.00 | $5,901.00 |
| 103 | Adjusting inlet covers (611.8115) | EACH | 10 | $650.00 | $274.00 | $274.00 |
| 104 | Pipe grates (size) 01. 36-inch (611.9850.S) | EACH | 1 | $1,519.50 | $1,094.00 | $1,094.00 |
| 105 | Pipe grates (size) 02. 54-inch (611.9850.S) | EACH | 1 | $3,162.00 | $2,369.00 | $2,369.00 |
| 106 | Pipe grates (size) 03. 24X38-inch (611.9850.S) | EACH | 1 | $1,183.50 | $793.00 | $793.00 |
| 107 | Cable barrier type 1 (613.1100.S) | LF | 16,840 | $37.09 | $41.10 | $41.10 |
| 108 | Cable barrier end terminal type 1 (613.1200.S) | EACH | 12 | $9,500.00 | $6,200.00 | $6,200.00 |
| 109 | Steel thrie beam bullnose terminal (614.0220) | EACH | 12 | $13,180 | $13,180 | $13,180 |
| 110 | Steel thrie beam (614.0230) | LF | 1,300 | $32.50 | $32.50 | $325.00 |
| 111 | Crash cushions permanent (614.0800) | EACH | 1 | $31,500 | $31,500 | $31,500 |
| 112 | MGS guardrail 3 (614.2300) | LF | 1,132.50 | $27.00 | $27.00 | $27.00 |
| 113 | MGS thrie beam transition (614.2500) | LF | 395.80 | $88.00 | $88.00 | $88.00 |
| 114 | MGS guardrail terminal eat (614.2610) | EACH | 12 | $3,480.00 | $3,480.00 | $3,480.00 |
| 115 | MGS guardrail terminal type 2 (614.2620) | EACH | 5 | $1,950.00 | $1,950.00 | $1,950.00 |
| 116 | Fence woven wire (height) 01. 4- FT (616.0100) | LF | 263 | $7.00 | $7.00 | $7.00 |
| 117 | Maintenance and repair of haul roads (project) 01. 1100-56-70 (618.0100) | EACH | 1 | $0.01 | $1.00 | $1.00 |
| 118 | Maintenance and repair of haul roads (project) 02. 1100-56-71 (618.0100) | EACH | 1 | $0.01 | $1.00 | $1.00 |
| 119 | Mobilization (619.1000) | EACH | 1 | $685,000 | $974,000 | $2,944,009 |
| 120 | Water (624.0100) | MGAL | 210 | $30.00 | $50.00 | $75.00 |
| 121 | Topsoil (625.0100) | SY | 7,430 | $4.00 | $5.85 | $6.50 |
| 122 | Salvaged topsoil (625.0500) | SY | 21,800 | $3.00 | $6.00 | $4.50 |
| 123 | Mulching (627.0200) | SY | 4,620 | $0.65 | $0.65 | $0.65 |
| 124 | Silt fence (628.1504) | LF | 4,450 | $1.80 | $1.80 | $1.80 |
| 125 | Silt fence maintenance (628.1520) | LF | 4,450 | $0.10 | $0.10 | $0.10 |
| 126 | Mobilizations erosion control (628.1905) | EACH | 10 | $350.00 | $350.00 | $350.00 |
| 127 | Mobilizations emergency erosion control (628.1910) | EACH | 6 | $350.00 | $350.00 | $350.00 |
| 128 | Erosion mat class I type B (628.2004) | SY | 22,800 | $1.18 | $1.18 | $1.18 |
| 129 | Erosion mat urban class I type B (628.2008) | SY | 6,390 | $1.90 | $1.90 | $1.90 |
| 130 | Inlet protection type B (628.7010) | EACH | 71 | $32.00 | $32.00 | $32.00 |
| 131 | Temporary ditch checks (628.7504) | LF | 240 | $10.00 | $10.00 | $10.00 |
| 132 | Culvert pipe checks (628.7555) | EACH | 81 | $22.00 | $22.00 | $22.00 |
| 133 | Tracking pads (628.7560) | EACH | 5 | $3,000.00 | $1.00 | $1,900.00 |
| 134 | Rock bags (628.7570) | EACH | 460 | $22.00 | $22.00 | $22.00 |
| 135 | Fertilizer type B (629.0210) | CWT | 19 | $88.00 | $88.00 | $88.00 |
| 136 | Seeding mixture no. 20 (630.0120) | LB | 760 | $11.00 | $11.00 | $11.00 |
| 137 | Seeding mixture no. 30 (630.0130) | LB | 260 | $13.00 | $13.00 | $13.00 |
| 138 | Seeding mixture no. 40 (630.0140) | LB | 350 | $13.00 | $13.00 | $13.00 |
| 139 | Seeding temporary (630.0200) | LB | 120 | $4.60 | $4.60 | $4.60 |
| 140 | Seed water (630.0500) | MGAL | 690 | $10.00 | $10.00 | $10.00 |
| 141 | Delineator posts steel (633.0100) | EACH | 8 | $78.00 | $78.00 | $78.00 |
| 142 | Delineator reflectors (633.0500) | EACH | 8 | $24.00 | $24.00 | $24.00 |
| 143 | Delineators barrier wall (633.1000) | EACH | 3 | $105.00 | $105.00 | $105.00 |
| 144 | Markers culvert end (633.5200) | EACH | 4 | $60.00 | $60.00 | $60.00 |
| 145 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 1 | $88.00 | $88.00 | $88.00 |
| 146 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 7 | $88.00 | $88.00 | $88.00 |
| 147 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 2 | $88.00 | $88.00 | $88.00 |
| 148 | Posts wood 4X6-inch X 20-FT (634.0620) | EACH | 6 | $88.00 | $88.00 | $88.00 |
| 149 | Moving signs type II (638.2102) | EACH | 15 | $80.00 | $80.00 | $80.00 |
| 150 | Removing small sign supports (638.3000) | EACH | 15 | $22.00 | $22.00 | $22.00 |
| 151 | Moving small sign supports (638.4000) | EACH | 2 | $100.00 | $100.00 | $100.00 |
| 152 | Field office type D (642.5401) | EACH | 1 | $13,500 | $20,000 | $22,000 |
| 153 | Traffic control drums (643.0300) | DAY | 58,095 | $0.14 | $0.14 | $0.14 |
| 154 | Digital speed reduction system (DSRS) (643.0370.S) | DAY | 364 | $95.00 | $95.00 | $95.00 |
| 155 | Traffic control barricades type III (643.0420) | DAY | 1,842 | $0.44 | $0.44 | $0.44 |
| 156 | Traffic control warning lights type A (643.0705) | DAY | 3,036 | $0.10 | $0.10 | $0.10 |
| 157 | Traffic control warning lights type C (643.0715) | DAY | 6,676 | $0.10 | $0.10 | $0.10 |
| 158 | Traffic control connected arrow boards (643.0810) | DAY | 364 | $32.00 | $32.00 | $32.00 |
| 159 | Traffic control signs (643.0900) | DAY | 11,815 | $0.25 | $0.25 | $0.25 |
| 160 | Traffic control covering signs type I (643.0910) | EACH | 91 | $215.00 | $215.00 | $215.00 |
| 161 | Traffic control covering signs type II (643.0920) | EACH | 360 | $41.00 | $41.00 | $41.00 |
| 162 | Traffic control signs PCMS (643.1050) | DAY | 165 | $45.00 | $45.00 | $45.00 |
| 163 | Basic traffic queue warning system (643.1205.S) | DAY | 364 | $155.00 | $155.00 | $155.00 |
| 164 | Traffic control connected work zone start and end location markers (643.1220) | DAY | 364 | $28.00 | $28.00 | $28.00 |
| 165 | Traffic control (643.5000) | EACH | 1 | $179,500 | $179,500 | $179,500 |
| 166 | Temporary pedestrian barricade (644.1810) | LF | 30 | $4.00 | $4.00 | $4.00 |
| 167 | Temporary audible message devices (644.1900.S) | DAY | 15 | $3.00 | $3.00 | $3.00 |
| 168 | Geotextile type HR (645.0120) | SY | 770 | $5.00 | $10.00 | $6.00 |
| 169 | Marking line grooved black epoxy 6-inch (646.2025) | LF | 8,440 | $0.95 | $0.95 | $0.95 |
| 170 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 93,040 | $1.31 | $1.31 | $1.31 |
| 171 | Marking line grooved permanent tape 6-inch (646.2050) | LF | 9,260 | $6.70 | $6.70 | $6.70 |
| 172 | Marking line grooved black epoxy 10-inch (646.4025) | LF | 768 | $1.95 | $1.95 | $1.95 |
| 173 | Marking line grooved permanent tape 10-inch (646.4050) | LF | 16,640 | $11.20 | $11.20 | $11.20 |
| 174 | Marking arrow epoxy (646.5020) | EACH | 9 | $320.00 | $320.00 | $320.00 |
| 175 | Marking word epoxy (646.5120) | EACH | 3 | $330.00 | $330.00 | $330.00 |
| 176 | Marking symbol epoxy (646.5220) | EACH | 2 | $310.00 | $310.00 | $310.00 |
| 177 | Marking stop line epoxy 18-inch (646.6120) | LF | 189 | $11.00 | $11.00 | $11.00 |
| 178 | Marking chevron epoxy 24-inch (646.7220) | LF | 1,090 | $11.50 | $11.50 | $11.50 |
| 179 | Marking parking stall epoxy (646.8320) | LF | 1,010 | $8.25 | $8.25 | $8.25 |
| 180 | Marking removal line 4-inch (646.9000) | LF | 91,600 | $0.26 | $0.40 | $0.26 |
| 181 | Marking removal line grooved contrast permanent tape 4-inch (646.9055) | LF | 8,550 | $0.51 | $2.35 | $0.51 |
| 182 | Marking removal line 8-inch (646.9100) | LF | 10,650 | $0.52 | $1.75 | $0.52 |
| 183 | Marking removal line grooved contrast permanent tape 8-inch (646.9155) | LF | 4,630 | $0.53 | $3.50 | $0.53 |
| 184 | Marking removal line wide (646.9200) | LF | 760 | $0.80 | $2.00 | $0.80 |
| 185 | Marking removal special marking (646.9300) | EACH | 11 | $120.00 | $75.00 | $120.00 |
| 186 | Construction staking storm sewer (650.4000) | EACH | 33 | $46.72 | $125.00 | $46.72 |
| 187 | Construction staking subgrade (650.4500) | LF | 1,955 | $0.01 | $0.01 | $0.01 |
| 188 | Construction staking base (650.5000) | LF | 1,566 | $1.37 | $1.50 | $1.37 |
| 189 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 118 | $2.00 | $5.00 | $2.00 |
| 190 | Construction staking concrete pavement (650.7000) | LF | 389 | $2.50 | $3.00 | $2.50 |
| 191 | Construction staking concrete barrier (650.7500) | LF | 307 | $2.00 | $3.00 | $2.00 |
| 192 | Construction staking resurfacing reference (650.8000) | LF | 52,984 | $0.12 | $0.12 | $0.12 |
| 193 | Construction staking supplemental control (project) 01. 1100-56-70 (650.9911) | EACH | 1 | $476.50 | $10.00 | $476.50 |
| 194 | Construction staking supplemental control (project) 02. 1100-56-71 (650.9911) | EACH | 1 | $476.50 | $10.00 | $476.50 |
| 195 | Construction staking slope stakes (650.9920) | LF | 3,858 | $0.96 | $0.95 | $0.96 |
| 196 | Adjusting pull boxes (653.0900) | EACH | 1 | $500.00 | $1,000.00 | $1,000.00 |
| 197 | Sawing asphalt (690.0150) | LF | 6,586 | $2.00 | $1.39 | $1.39 |
| 198 | Sawing concrete (690.0250) | LF | 15,584 | $2.50 | $4.45 | $2.45 |
| 199 | Incentive strength concrete barrier (715.0603) | DOL | 154 | $1.00 | $1.00 | $1.00 |
| 200 | Incentive compressive strength concrete pavement (715.0720) | DOL | 500 | $1.00 | $1.00 | $1.00 |
| 201 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,400 | $5.00 | $5.00 | $5.00 |
| 202 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 3,650 | $5.00 | $5.00 | $5.00 |
| 203 | Special 01. repair chainlink fence B-20-111 (SPV.0060) | EACH | 1 | $2,900.00 | $1,400.00 | $1,400.00 |
| 204 | Special 02. concrete barrier transition (SPV.0060) | EACH | 1 | $20,000 | $20,000 | $15,000 |
| 205 | Special 03. connect to existing structure (SPV.0060) | EACH | 3 | $1,258.00 | $1,322.00 | $1,322.00 |
| 206 | Special 04. geotechnical instrumentation (SPV.0060) | EACH | 1 | $157,000 | $148,000 | $100,000 |
| 207 | Special 05. inclinometer casing (SPV.0060) | EACH | 3 | $5,000.00 | $1,000.00 | $2,500.00 |
| 208 | Special 06. settlement monitoring point (SPV.0060) | EACH | 4 | $5,000.00 | $5,000.00 | $40,000 |
| 209 | Special 07. structure survey target (SPV.0060) | EACH | 20 | $250.00 | $3,050.00 | $1,000.00 |
| 210 | Special 08. utility line opening (SPV.0060) | EACH | 10 | $980.00 | $1,000.00 | $1,600.00 |
| 211 | Special 09. sawing concrete barrier single faced (SPV.0060) | EACH | 5 | $200.00 | $180.00 | $500.00 |
| 212 | Special 01. joint sealing (SPV.0090) | LF | 4,140 | $4.00 | $9.25 | $10.50 |
| 213 | Special 02. trenchless storm sewer pipe reinforced concrete class V 54-inch (SPV.0090) | LF | 585 | $3,355.00 | $2,800.00 | $1,775.00 |
| 214 | Special 01. excavation, hauling, and disposal of voc contaminated soil (SPV.0195) | TON | 3,610 | $40.00 | $58.00 | $35.50 |
| 215 | Special 02. excavation, hauling, and disposal of pesticide contaminated soil (SPV.0195) | TON | 1,010 | $40.00 | $58.00 | $35.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of October 13, 2026. Compiled by Mirage Metrics.