WisDOT contract 20261110019 bid tabulation

1440-41-71. Let by Wisconsin DOT on November 10, 2026, Sheboygan. 3 bids received; low bid $11,736,119 by Michels Road & Stone, Inc..

Owner
Wisconsin DOT
Letting
10 NOV 2026
Pay items
263
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Michels Road & Stone, Inc.$11,736,119Low
2Northeast Asphalt, Inc$11,795,158+1.0%
3Vinton Construction Company$11,824,966+1.0%
WisDOT contract 20261110019: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Michels Road & Stone, Inc.2. Northeast Asphalt, Inc3. Vinton Construction Company
1Clearing (201.0110)SY5,800$4.50$4.50$4.20
2Grubbing (201.0210)SY5,800$1.25$1.25$1.20
3Removing small pipe culverts (203.0100)EACH10$480.00$480.00$962.51
4Abatement of asbestos containing material (structure) 01. B-59-91 (203.0211.S)EACH1$10,000$10,000$10,000
5Abatement of asbestos containing material (structure) 02. B-59-123 (203.0211.S)EACH1$1.00$1.00$1.00
6Removing structure (structure) 01. B-59-0093 (203.0220)EACH1$27,000$27,000$27,000
7Removing concrete pavement (204.0100)SY4,981$3.00$3.00$1.50
8Removing concrete pavement butt joints (204.0105)SY5,841$10.50$10.50$10.50
9Removing concrete surface partial depth (204.0109.S)SF80,300$0.70$0.70$0.70
10Removing asphaltic surface (204.0110)SY13$20.00$20.00$20.00
11Removing asphaltic surface butt joints (204.0115)SY3,644$5.60$5.60$5.60
12Removing asphaltic surface milling (204.0120)SY54,000$1.30$1.30$1.30
13Removing curb & gutter (204.0150)LF840$4.00$4.00$6.00
14Removing guardrail (204.0165)LF7,936$1.83$1.83$1.83
15Removing fence (204.0170)LF1,540$1.83$1.83$1.83
16Removing delineators and markers (204.0180)EACH1$50.00$50.00$50.00
17Removing surface drains (204.0190)EACH9$200.00$200.00$250.00
18Removing inlets (204.0220)EACH14$425.00$425.00$667.11
19Removing storm sewer (size) 01. 12-inch (204.0245)LF436$10.00$10.00$15.17
20Removing storm sewer (size) 02. 18-inch (204.0245)LF24$18.00$18.00$17.23
21Abandoning sewer (204.0291.S)CY8$507.00$507.00$341.63
22Removing (item description) 01. apron endwalls (204.9060.S)EACH7$500.00$500.00$550.57
23Removing (item description) 01. underdrain 6-inch (204.9090.S)LF715$8.00$8.00$8.21
24Excavation common (205.0100)CY50,669$14.35$14.35$15.35
25Excavation for structures bridges (structure) 01. B-59-0093 (206.1001)EACH1$2,500.00$2,500.00$2,500.00
26Borrow (208.0100)CY5,282$0.01$0.01$0.01
27Select borrow (208.1100)CY650$39.00$39.00$40.00
28Backfill structure type A (210.1500)TON16$100.00$100.00$100.00
29Prepare foundation for asphaltic paving (project) 01. 1440-41-71 (211.0101)EACH1$49,750$49,750$49,750
30Prepare foundation for asphaltic shoulders (211.0400)STA36$395.00$395.00$395.00
31Finishing roadway (project) 01. 1440-41-71 (213.0100)EACH1$2,500.00$3,450.00$5,000.00
32Finishing roadway (project) 02. 1440-41-72 (213.0100)EACH1$2,500.00$3,450.00$5,000.00
33Obliterating old road (214.0100)STA3$750.00$750.00$0.01
34Base aggregate dense 3/4-inch (305.0110)TON13,700$28.60$28.60$27.66
35Base aggregate dense 1 1/4-inch (305.0120)TON20,560$22.90$22.90$20.15
36Base aggregate open-graded (310.0110)TON100$55.00$55.00$36.55
37Select crushed material (312.0110)TON16,750$21.60$21.60$24.77
38Removing pavement for base patching (390.0100)CY369$69.95$69.95$0.01
39Base patching concrete hes (390.0305)CY369$347.65$347.65$495.00
40Concrete pavement 8-inch (415.0080)SY347$97.00$97.00$116.00
41Drilled tie bars (416.0610)EACH723$8.00$8.00$10.00
42Drilled dowel bars (416.0620)EACH2,949$17.00$17.00$18.50
43Concrete pavement repair (416.1710)SY200$125.00$125.00$130.00
44Concrete pavement repair shes (416.1715)SY13$250.00$250.00$250.00
45Concrete pavement replacement (416.1720)SY250$125.00$125.00$133.00
46Concrete pavement replacement shes (416.1725)SY27$250.00$250.00$250.00
47HMA cold weather paving (450.4000)TON11,330$0.01$0.01$0.01
48HMA pavement 4 LT 58-28 S (450.5224)TON9,990$82.10$82.10$82.10
49HMA pavement 3 MT 58-28 S (450.6223)TON4,430$79.20$79.20$79.20
50HMA pavement 4 MT 58-28 S (450.6224)TON29,835$78.90$78.90$78.90
51Tack coat (455.0605)GAL22,970$3.00$3.00$3.00
52Asphaltic surface (465.0105)TON293$144.90$144.90$144.90
53Asphaltic surface temporary (465.0125)TON377$104.90$104.90$104.90
54Asphaltic surface safety islands (465.0305)TON90$194.90$194.90$194.90
55Asphaltic flumes (465.0315)SY104$62.50$62.50$62.50
56Asphaltic rumble strips, shoulder divided roadway (465.0510)LF176,200$0.26$0.26$0.26
57Concrete masonry bridges (502.0100)CY5$3,500.00$3,500.00$3,500.00
58Expansion device (502.3101)LF224$360.00$360.00$360.00
59Protective surface treatment (502.3200)SY139$4.00$4.00$4.00
60Pigmented surface sealer reseal (502.3205)SY799$28.00$28.00$28.00
61Pigmented surface sealer (502.3210)SY22$20.00$20.00$20.00
62Protective surface treatment reseal (502.3215)SY3,729$11.00$11.00$11.00
63Adhesive anchors no. 4 bar (502.4204)EACH10$28.00$28.00$28.00
64Adhesive anchors no. 5 bar (502.4205)EACH244$32.00$32.00$32.00
65Bar steel reinforcement HS structures (505.0400)LB670$1.93$1.93$1.93
66Bar steel reinforcement HS coated structures (505.0600)LB8,010$1.97$1.97$1.97
67Bar couplers no. 5 (505.0905)EACH10$55.00$55.00$55.00
68Bar couplers no. 6 (505.0906)EACH28$70.00$70.00$70.00
69Preparation decks type 1 (509.0301)SY4$500.00$500.00$500.00
70Sawing pavement deck preparation areas (509.0310.S)LF40$15.00$15.00$15.00
71Joint repair (509.1000)SY105$1,700.00$1,700.00$1,700.00
72Concrete surface repair (509.1500)SF161$200.00$200.00$200.00
73Concrete masonry deck repair (509.2100.S)CY36$1,200.00$1,200.00$1,200.00
74Epoxy injection crack repair (509.9025.S)LF15$220.00$220.00$220.00
75Cored holes 2-inch diameter (509.9026.S)EACH4$750.00$750.00$750.00
76Temporary shoring (structure) 01. B-59-0093 (511.1200)SF102$130.00$130.00$130.00
77Rubberized membrane waterproofing (516.0500)SY2$60.00$60.00$60.00
78Preparation and coating of top flanges (structure) 01. B-59-0091 (517.0901.S)EACH1$6,300.00$6,300.00$6,300.00
79Preparation and coating of top flanges (structure) 02. B-59-0093 (517.0901.S)EACH1$4,500.00$4,500.00$4,500.00
80Structure repainting recycled abrasive (structure) 01. B-59-0097 (517.1801.S)EACH1$195,500$199,372$195,500
81Structure overcoating cleaning and priming (structure) 01. B-59-0091 (517.3001.S)EACH1$98,900$98,900$98,900
82Containment and collection of waste materials (structure) 01. B- 59-0091 (517.4001.S)EACH1$13,800$13,800$13,800
83Negative pressure containment and collection of waste materials (structure) 01. B-59-0097 (517.4501.S)EACH1$67,150$67,150$67,150
84Portable decontamination facility (517.6001.S)EACH2$500.00$500.00$500.00
85Apron endwalls for culvert pipe 18- inch (520.1018)EACH8$552.00$552.00$532.62
86Culvert pipe class III-A 18-inch (520.3318)LF136$49.00$49.00$76.98
87Concrete collars for pipe (520.8000)EACH8$700.00$700.00$988.00
88Apron endwalls for culvert pipe steel 12-inch (521.1012)EACH7$410.00$410.00$1,217.26
89Culvert pipe reinforced concrete class IV 18-inch (522.0418)LF48$80.00$80.00$86.83
90Culvert pipe reinforced concrete class IV 24-inch (522.0424)LF101$135.00$135.00$118.33
91Culvert pipe reinforced concrete class IV 36-inch (522.0436)LF108$330.00$330.00$203.35
92Apron endwalls for culvert pipe reinforced concrete 18-inch (522.1018)EACH4$1,736.00$1,736.00$1,616.69
93Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024)EACH5$1,924.00$1,924.00$2,052.37
94Apron endwalls for culvert pipe reinforced concrete 30-inch (522.1030)EACH1$2,301.00$2,301.00$2,180.88
95Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036)EACH2$2,864.00$2,864.00$3,044.20
96Apron endwalls for culvert pipe reinforced concrete 42-inch (522.1042)EACH2$3,895.00$3,895.00$3,487.82
97Culvert pipe reinforced concrete horizontal elliptical class HE-IV 19X30-inch (522.2419)LF528$166.00$166.00$180.04
98Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 19X30-inch (522.2619)EACH14$1,463.00$1,463.00$2,218.59
99Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 29X45-inch (522.2629)EACH2$3,253.00$3,253.00$3,223.19
100Culvert pipe corrugated polyethylene 12-inch (530.0112)LF435$88.00$88.00$91.18
101Concrete curb & gutter 30-inch type D (601.0411)LF120$89.00$89.00$75.00
102Concrete curb & gutter 4-inch sloped 36-inch type D (601.0553)LF2,340$49.00$49.00$32.70
103Concrete curb & gutter 4-inch sloped 36-inch type TBTT (601.0590)LF574$49.00$49.00$75.00
104Concrete sidewalk 4-inch (602.0405)SF2,180$8.85$8.85$12.50
105Curb ramp detectable warning field natural patina (602.0515)SF40$40.00$40.00$36.00
106Concrete surface drains (602.3010)CY5$1,100.00$1,100.00$1,500.00
107Concrete barrier temporary precast delivered (603.8000)LF21,314$9.50$9.50$9.50
108Concrete barrier temporary precast installed (603.8125)LF22,614$4.00$4.00$4.00
109Riprap medium (606.0200)CY199$155.00$106.00$150.00
110Riprap heavy (606.0300)CY498$235.00$235.00$150.00
111Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF169$86.00$86.00$116.43
112Storm sewer pipe reinforced concrete class IV 18-inch (608.0418)LF247$90.00$90.00$192.04
113Storm sewer pipe reinforced concrete horizontal elliptical class HE-III 29X45-inch (608.2329)LF103$236.00$236.00$298.03
114Manhole covers type J-special (611.0535)EACH2$586.00$586.00$558.93
115Inlet covers type HM (611.0627)EACH6$831.00$831.00$775.20
116Inlet covers type MS (611.0642)EACH2$577.00$577.00$551.01
117Inlet covers type V (611.0654)EACH8$771.00$771.00$721.79
118Manholes 5-FT diameter (611.2005)EACH2$5,340.00$5,090.00$6,470.29
119Inlets 4-FT diameter (611.3004)EACH1$3,611.00$3,361.00$4,632.30
120Inlets 2X2-FT (611.3220)EACH8$2,600.00$2,350.00$2,977.44
121Inlets 2X3-FT (611.3230)EACH4$2,850.00$2,600.00$3,259.65
122Inlets median 2 grate (611.3902)EACH2$3,200.00$3,200.00$3,795.90
123Adjusting inlet covers (611.8115)EACH4$864.00$864.00$750.00
124Pipe underdrain 6-inch (612.0106)LF715$16.00$16.00$22.97
125Pipe underdrain unperforated 6- inch (612.0206)LF100$28.00$28.00$28.72
126Pipe underdrain wrapped 6-inch (612.0406)LF15$20.00$4.00$20.00
127Apron endwalls for underdrain reinforced concrete 6-inch (612.0806)EACH4$500.00$500.00$369.76
128Anchor assemblies for steel plate beam guard (614.0150)EACH1$450.00$450.00$450.00
129Steel thrie beam bullnose terminal (614.0220)EACH2$14,000$14,000$14,000
130Steel thrie beam (614.0230)LF175$35.00$35.00$35.00
131Crash cushions temporary (614.0905)EACH5$6,250.00$6,250.00$6,250.00
132MGS guardrail 3 (614.2300)LF6,938.50$26.33$26.33$26.33
133MGS thrie beam transition (614.2500)LF788$88.00$88.00$88.00
134MGS guardrail terminal eat (614.2610)EACH20$3,333.00$3,333.00$3,333.00
135MGS guardrail terminal type 2 (614.2620)EACH2$2,833.00$2,833.00$2,833.00
136Fence woven wire (height) 01. 4- FT (616.0100)LF1,455$8.33$8.33$8.33
137Maintenance and repair of haul roads (project) 01. 1440-41-71 (618.0100)EACH1$1.00$1.00$0.01
138Maintenance and repair of haul roads (project) 02. 1440-41-72 (618.0100)EACH1$1.00$1.00$0.01
139Mobilization (619.1000)EACH1$747,496$798,500$872,000
140Concrete median sloped nose (620.0300)SF430$17.00$17.00$16.00
141Dust control surface treatment (623.0200)SY20,000$0.01$0.80$0.01
142Water (624.0100)MGAL731$60.00$60.00$0.01
143Topsoil (625.0100)SY65,800$2.60$2.60$2.19
144Silt fence (628.1504)LF12,500$1.57$1.57$1.57
145Silt fence maintenance (628.1520)LF25,000$0.03$0.03$0.03
146Mobilizations erosion control (628.1905)EACH14$233.00$233.00$233.00
147Mobilizations emergency erosion control (628.1910)EACH10$333.00$333.00$333.00
148Erosion mat class I type B (628.2004)SY7,700$0.95$0.95$0.95
149Erosion mat urban class I type B (628.2008)SY59,000$1.67$1.67$1.67
150Inlet protection type A (628.7005)EACH27$100.00$100.00$100.00
151Inlet protection type C (628.7015)EACH13$70.00$70.00$70.00
152Inlet protection type D (628.7020)EACH4$250.00$250.00$250.00
153Temporary ditch checks (628.7504)LF1,000$5.03$5.03$5.03
154Culvert pipe checks (628.7555)EACH43$20.00$20.00$20.00
155Rock bags (628.7570)EACH135$5.00$5.00$5.00
156Fertilizer type B (629.0210)CWT43$95.00$95.00$95.00
157Seeding mixture no. 30 (630.0130)LB3,000$6.03$6.03$6.03
158Seeding temporary (630.0200)LB470$4.73$4.73$4.73
159Seed water (630.0500)MGAL1,500$1.00$1.00$1.00
160Markers culvert end (633.5200)EACH20$70.00$70.00$70.00
161Posts wood 4X6-inch X 14-FT (634.0614)EACH23$92.00$92.00$92.00
162Posts wood 4X6-inch X 16-FT (634.0616)EACH27$95.00$95.00$95.00
163Posts wood 4X6-inch X 18-FT (634.0618)EACH42$98.00$98.00$98.00
164Signs type II reflective H (637.2210)SF1,135.60$20.00$20.00$20.00
165Signs type II reflective F (637.2230)SF87.50$25.00$25.00$25.00
166Removing signs type II (638.2602)EACH27$25.00$25.00$25.00
167Removing small sign supports (638.3000)EACH31$25.00$25.00$25.00
168Field office type C (642.5201)EACH1$18,000$19,950$15,000
169Traffic control drums (643.0300)DAY155,809$0.13$0.13$0.13
170Temporary tape rumble strip orange (643.0320.S)LF4,536$11.25$11.25$11.25
171Digital speed reduction system (DSRS) (643.0370.S)DAY446$100.00$100.00$100.00
172Traffic control barricades type III (643.0420)DAY7,312$0.45$0.45$0.45
173Traffic control warning lights type A (643.0705)DAY8,814$0.10$0.10$0.10
174Traffic control warning lights type C (643.0715)DAY15,567$0.10$0.10$0.10
175Traffic control connected arrow boards (643.0810)DAY532$25.00$25.00$25.00
176Traffic control signs (643.0900)DAY23,538$0.25$0.25$0.25
177Traffic control covering signs type II (643.0920)EACH1$45.00$45.00$45.00
178Traffic control signs fixed message (643.1000)SF68$15.00$15.00$15.00
179Traffic control signs PCMS (643.1050)DAY196$45.00$45.00$45.00
180Traffic control cones 42-inch (643.1070)DAY472,100$0.11$0.11$0.11
181Basic traffic queue warning system (643.1205.S)DAY1,218$50.00$50.00$50.00
182Traffic control connected work zone end location marker (643.1222)DAY486$13.50$13.50$13.50
183Temporary marking line removable tape 6-inch (643.3180)LF23,640$1.50$1.50$1.50
184Temporary marking line removable tape 10-inch (643.3280)LF2,600$2.75$2.75$2.75
185Traffic control (643.5000)EACH1$127,500$127,500$127,500
186Temporary pedestrian surface asphalt (644.1410)SF1,900$10.00$7.85$8.50
187Temporary pedestrian barricade (644.1810)LF6,060$3.50$3.50$3.50
188Temporary audible message devices (644.1900.S)DAY110$3.00$3.00$3.00
189Geotextile type DF schedule A (645.0111)SY400$5.00$5.00$5.91
190Geotextile type HR (645.0120)SY1,237$10.00$10.00$4.00
191Geotextile type sas (645.0140)SY1,680$3.70$3.70$3.00
192Marking line epoxy 6-inch (646.2020)LF9,150$0.60$0.60$0.60
193Marking line grooved black epoxy 6-inch (646.2025)LF110,280$0.01$0.01$0.01
194Marking line grooved wet ref epoxy 6-inch (646.2040)LF355,470$1.15$1.15$1.15
195Marking line grooved wet ref epoxy 10-inch (646.4040)LF29,250$3.45$3.45$3.45
196Marking arrow epoxy (646.5020)EACH1$145.00$145.00$145.00
197Marking symbol epoxy (646.5220)EACH1$145.00$145.00$145.00
198Marking outfall epoxy (646.5520)EACH4$70.00$70.00$70.00
199Marking stop line epoxy 18-inch (646.6120)LF55$11.35$11.35$11.35
200Marking yield line epoxy 18-inch (646.6220)EACH60$140.00$140.00$140.00
201Cold weather marking epoxy 6-inch (646.6466)LF89,260$0.32$0.32$0.01
202Cold weather marking epoxy 10- inch (646.6470)LF7,520$0.48$0.48$0.01
203Marking diagonal epoxy 12-inch (646.7120)LF185$10.00$10.00$10.00
204Marking chevron epoxy 24-inch (646.7220)LF740$13.00$13.00$13.00
205Marking chevron epoxy 12-inch (646.7320)LF1,630$10.00$10.00$10.00
206Marking island nose epoxy (646.8220)EACH12$265.00$265.00$265.00
207Marking removal line 4-inch (646.9000)LF5,350$1.00$1.00$1.00
208Marking removal line water blasting 6-inch (646.9012)LF12,810$1.50$1.50$0.55
209Marking removal line grooved contrast permanent tape 10-inch (646.9165)LF1,120$5.25$5.25$0.75
210Marking removal line wide (646.9200)LF130$2.50$2.50$1.05
211Locating no-passing zones (648.0100)MI0.35$800.00$788.41$800.00
212Construction staking storm sewer (650.4000)EACH27$95.00$95.00$95.00
213Construction staking subgrade (650.4500)LF8,100$0.01$0.01$0.01
214Construction staking base (650.5000)LF8,100$0.30$0.30$0.30
215Construction staking curb gutter and curb & gutter (650.5500)LF2,460$0.95$0.95$0.95
216Construction staking pipe culverts (650.6000)EACH12$100.00$100.00$100.00
217Construction staking concrete pavement (650.7000)LF574$2.00$2.00$2.00
218Construction staking resurfacing reference (650.8000)LF114,720$0.13$0.13$0.13
219Construction staking electrical installations (project) 01. 1440-41- 72 (650.8501)EACH1$3,900.00$3,900.00$3,900.00
220Construction staking curb ramps (650.9000)EACH2$100.00$100.00$100.00
221Construction staking sidewalk (project) 01. 1440-41-72 (650.9500)EACH1$100.00$100.00$100.00
222Construction staking supplemental control (project) 01. 1440-41-71 (650.9911)EACH1$10.00$10.00$10.00
223Construction staking supplemental control (project) 02. 1440-41-72 (650.9911)EACH1$10.00$10.00$10.00
224Construction staking slope stakes (650.9920)LF19,460$0.72$0.72$0.72
225Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF4,280$10.00$8.12$10.00
226Conduit rigid nonmetallic schedule 40 3-inch (652.0235)LF10$20.00$10.56$20.00
227Conduit rigid nonmetallic schedule 80 2-inch (652.0325)LF210$24.00$10.02$24.00
228Pull boxes steel 24X42-inch (653.0140)EACH18$1,500.00$1,423.86$1,500.00
229Concrete bases type 5 (654.0105)EACH8$1,750.00$1,174.96$1,750.00
230Electrical wire lighting 12 AWG (655.0610)LF1,500$1.00$1.29$1.00
231Electrical wire lighting 10 AWG (655.0615)LF16,832$1.20$1.63$1.20
232Electrical service meter breaker pedestal (location) 01. STH 23 & CTH TT (656.0201)EACH1$1,850.00$2,904.25$1,850.00
233Transformer bases breakaway 11 1/2-inch bolt circle (657.0255)EACH8$620.00$849.22$620.00
234Poles type 5-aluminum (657.0322)EACH8$1,875.00$2,582.01$1,875.00
235Luminaire arms truss type 4 1/2- inch clamp 12-FT (657.0710)EACH10$750.00$953.22$750.00
236Luminaires utility LED A (659.1115)EACH10$350.00$329.28$350.00
237Sawing asphalt (690.0150)LF2,052$1.20$1.20$2.50
238Sawing concrete (690.0250)LF9,800$2.20$2.20$2.75
239HMA percent within limits (PWL) test strip volumetrics (706.0105)EACH1$2,550.00$2,550.00$2,550.00
240Nuclear gauge correlation strip - HMA, SMA (706.0110)EACH1$3,650.00$3,650.00$3,650.00
241Incentive density PWL HMA pavement (706.2005)DOL21,770$1.00$1.00$1.00
242Incentive density HMA pavement longitudinal joints (706.2007)DOL11,740$1.00$1.00$1.00
243Incentive air voids HMA pavement (706.2010)DOL27,860$1.00$1.00$1.00
244Incentive compressive strength concrete pavement (707.0020)DOL500$1.00$1.00$1.00
245Incentive strength concrete structures (707.0025)DOL500$1.00$1.00$1.00
246Incentive iri ride (740.0440)DOL22,540$1.00$1.00$1.00
247Installing and maintaining bird deterrent system (station) 01. 1250+00EB (999.2000.S)EACH1$20,000$20,000$20,000
248Installing and maintaining bird deterrent system (station) 02. 1357+94WB (999.2000.S)EACH1$1.00$1.00$1.00
249Installing and maintaining bird deterrent system (station) 03. 1607+50WB (999.2000.S)EACH1$4,000.00$4,000.00$4,000.00
250Installing and maintaining bird deterrent system (station) 04. 1607+50EB (999.2000.S)EACH1$4,000.00$4,000.00$4,000.00
251On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,100$5.00$5.00$5.00
252On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS5,760$5.00$5.00$5.00
253Special 01. embedded galvanic anodes (SPV.0060)EACH60$65.00$65.00$65.00
254Special 02. concrete control cabinet bases type 10 NE region special (SPV.0060)EACH1$2,200.00$3,603.91$2,200.00
255Special 03. manholes 7-FT diameter (SPV.0060)EACH1$17,201$16,951$19,084
256Special 04. remove, salvage and replace steel plate beam guard energy absorbing terminal (SPV.0060)EACH1$2,500.00$2,500.00$2,500.00
257Special 05. mounting conduit to exterior of structure (SPV.0060)EACH1$5,875.00$6,070.36$5,875.00
258Special 01. concrete joint and crack cleaning and repair (SPV.0090)LF1,386$10.50$10.50$10.50
259Special 02. removing rumble strips (SPV.0090)LF6,300$2.50$2.50$2.50
260Special 03. pedestrian overhead protection (SPV.0090)LF240$130.00$130.00$130.00
261Special 04. temporary marking wet reflective epoxy 6-inch (SPV.0090)LF281,500$0.76$0.76$0.76
262Special 01. removing loose concrete (SPV.0165)SF50$60.00$60.00$60.00
263Special 01. select crushed material for travel corridor (SPV.0195)TON8$100.00$100.00$100.00
WisDOT contract 20261110019: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of November 10, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy