WisDOT contract 20260310002 bid tabulation

Portage - Packwaukee; STH 78 to USH 51 (IH 039, Columbia County Portage - Packwaukee). Let by Wisconsin DOT on March 10, 2026, Columbia. 5 bids received; low bid $2,192,723 by Parisi Construction, LLC.

Owner
Wisconsin DOT
Letting
10 MAR 2026
Pay items
74
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Parisi Construction, LLC$2,192,723Low
2Michels Road & Stone, Inc.$2,938,613+34%
3Chippewa Concrete Services, Inc.$3,008,708+37%
4Sommers Construction Co., Inc.$3,550,150+62%
5Zignego Company, Inc.$3,591,209+64%
WisDOT contract 20260310002: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Parisi Construction, LLC2. Michels Road & Stone, Inc.3. Chippewa Concrete Services, Inc.4. Sommers Construction Co., Inc.5. Zignego Company, Inc.
1Removing small pipe culverts (203.0100)EACH2$750.00$500.00$1,002.25$1,500.00$1,000.00
2Removing concrete pavement (204.0100)SY370$12.00$35.00$52.75$42.00$100.00
3Removing asphaltic surface (204.0110)SY50$15.00$40.00$52.75$15.00$100.00
4Removing asphaltic surface milling (204.0120)SY1,940$13.65$11.50$15.93$15.10$15.10
5Removing curb & gutter (204.0150)LF135$9.00$15.00$21.10$12.00$100.00
6Removing guardrail (204.0165)LF6,505$2.50$1.95$2.06$1.95$1.95
7Removing delineators and markers (204.0180)EACH185$25.00$10.00$10.55$10.00$10.00
8Removing surface drains (204.0190)EACH3$350.00$500.00$1,055.00$1,500.00$1,000.00
9Removing inlets (204.0220)EACH2$750.00$700.00$633.00$1,500.00$1,000.00
10Prepare foundation for asphaltic shoulders (211.0400)STA48$1.00$25.00$1.06$1.00$1.00
11Finishing roadway (project) 01. 1161-00-78 (213.0100)EACH1$3,057.97$5,000.00$3,692.50$4,500.00$1,000.00
12Base aggregate dense 3/4-inch (305.0110)TON670$41.00$50.00$41.73$39.00$39.00
13Select crushed material (312.0110)TON30$28.00$33.00$85.58$75.00$100.00
14Concrete pavement 10-inch (415.0100)SY50$105.14$125.00$131.88$150.00$200.00
15Concrete pavement approach slab (415.0410)SY120$395.10$270.00$316.50$375.00$280.00
16Rout and seal (415.6000.S)LF4,470$5.05$3.25$3.43$3.25$3.25
17Drilled tie bars (416.0610)EACH1,348$9.33$12.00$8.44$11.00$30.00
18Drilled dowel bars (416.0620)EACH6,624$12.17$23.00$15.83$19.00$30.00
19Concrete pavement partial depth repair surface repair (416.0754.S)SF640$105.19$90.00$263.75$99.00$200.00
20Concrete pavement repair (416.1710)SY2,912$109.79$132.00$158.25$175.00$151.00
21Concrete pavement repair shes (416.1715)SY275$121.00$133.00$226.83$195.00$182.00
22Concrete pavement replacement (416.1720)SY4,562$120.07$133.00$158.25$175.00$151.00
23Concrete pavement replacement shes (416.1725)SY868$122.10$134.00$226.83$195.00$182.00
24Continuous diamond grinding concrete pavement (420.1000)SY1,200$25.06$25.06$26.44$25.06$45.06
25Tack coat (455.0605)GAL136$2.80$4.00$2.95$2.80$2.80
26Incentive density HMA pavement (460.2000)DOL260$1.00$1.00$1.00$1.00$1.00
27HMA pavement 4 LT 58-28 S (460.5224)TON404$107.50$91.00$113.41$107.50$107.50
28Asphaltic rumble strips, shoulder divided roadway (465.0510)LF1,990$2.00$2.00$2.11$2.00$2.00
29Apron endwalls for culvert pipe steel 12-inch (521.1012)EACH2$350.00$2,400.00$2,057.25$1,200.00$2,000.00
30Culvert pipe corrugated steel 12- inch (521.3112)LF20$95.00$185.00$121.33$150.00$600.00
31Concrete curb & gutter 30-inch type A (601.0409)LF80$63.85$57.00$121.33$99.00$200.00
32Concrete curb & gutter 4-inch sloped 30-inch type TBTT (601.0586)LF55$65.54$57.00$121.33$99.00$200.00
33Inlet covers type V (611.0654)EACH2$1,150.00$1,250.00$1,582.50$1,500.00$3,000.00
34Inlets 2X2-FT (611.3220)EACH2$3,675.00$5,200.00$5,802.50$4,500.00$10,000
35Barrier system grading shaping finishing (614.0010)EACH15$1,127.60$2,995.00$7,590.73$695.00$7,695.00
36Steel thrie beam bullnose terminal (614.0220)EACH2$15,500$13,501$14,244$13,501$13,501
37Steel thrie beam (614.0230)LF72$38.00$35.00$36.93$35.00$35.00
38Guardrail mow strip emulsified asphalt (614.0397)SY117$41.06$30.00$31.65$30.00$30.00
39MGS guardrail 3 (614.2300)LF3,264$28.00$26.00$27.43$26.00$26.00
40MGS guardrail 3 K (614.2330)LF2,050$38.00$38.00$40.09$38.00$38.00
41MGS thrie beam transition (614.2500)LF628$90.00$90.00$94.95$90.00$90.00
42MGS guardrail terminal eat (614.2610)EACH9$4,800.00$3,413.00$3,600.72$3,413.00$3,413.00
43MGS guardrail terminal type 2 (614.2620)EACH3$3,200.00$2,713.00$2,862.22$2,713.00$2,713.00
44Maintenance and repair of haul roads (project) 01. 1161-00-78 (618.0100)EACH1$1.00$1.00$1.06$1.00$1.00
45Mobilization (619.1000)EACH1$108,438$675,831$263,043$892,225$829,000
46Water (624.0100)MGAL6$50.00$65.00$26.38$150.00$200.00
47Silt fence (628.1504)LF920$3.00$3.00$3.17$3.00$3.00
48Silt fence maintenance (628.1520)LF920$0.01$0.03$0.03$0.03$0.03
49Mobilizations erosion control (628.1905)EACH2$750.00$401.00$423.06$401.00$401.00
50Mobilizations emergency erosion control (628.1910)EACH2$250.00$402.00$424.11$402.00$402.00
51Delineator posts steel (633.0100)EACH185$50.00$35.00$36.93$35.00$35.00
52Delineator reflectors (633.0500)EACH185$15.00$15.00$15.83$15.00$15.00
53Field office type B (642.5001)EACH1$12,458$8,000.00$7,912.50$18,000$20,000
54Traffic control drums (643.0300)DAY7,460$1.00$1.00$1.06$1.00$1.00
55Traffic control barricades type III (643.0420)DAY554$2.50$2.50$2.64$2.50$2.50
56Traffic control warning lights type A (643.0705)DAY1,098$0.75$0.75$0.79$0.75$0.75
57Traffic control warning lights type C (643.0715)DAY1,790$0.75$0.75$0.79$0.75$0.75
58Traffic control connected arrow boards (643.0810)DAY90$45.00$45.00$47.48$45.00$45.00
59Traffic control signs (643.0900)DAY9,217$0.25$0.25$0.26$0.25$0.25
60Traffic control covering signs type I (643.0910)EACH1$550.00$550.00$580.25$550.00$550.00
61Traffic control covering signs type II (643.0920)EACH38$50.00$50.00$52.75$50.00$50.00
62Traffic control signs PCMS (643.1050)DAY98$45.00$45.00$47.48$45.00$45.00
63Truck or trailer mounted attenuator (643.1055.S)DAY4$2,400.00$2,400.00$2,532.00$2,400.00$2,400.00
64Traffic control (643.5000)EACH1$118,125$118,125$124,622$118,125$118,125
65Marking line epoxy 6-inch (646.2020)LF6,650$0.67$0.67$0.71$0.67$0.67
66Marking line epoxy 10-inch (646.4020)LF400$1.60$1.60$1.69$1.60$1.60
67Marking outfall epoxy (646.5520)EACH145$62.00$62.00$65.41$62.00$62.00
68Construction staking resurfacing reference (650.8000)LF36,144$0.13$0.15$0.16$0.15$0.15
69Construction staking supplemental control (project) 01. 1161-00-78 (650.9911)EACH1$1,750.00$500.00$949.50$900.00$500.00
70Sawing asphalt (690.0150)LF238$1.39$4.00$2.06$1.50$1.95
71Sawing concrete (690.0250)LF22,286$2.75$4.00$2.69$3.00$2.55
72Incentive compressive strength concrete pavement (715.0720)DOL500$1.00$1.00$1.00$1.00$1.00
73Installing and maintaining climbing turtle exclusion fence (999.2100.S)LF600$4.00$5.00$5.28$5.00$5.00
74Special 01. removing raised pavement markers and filling voids (SPV.0060)EACH370$142.86$45.00$100.23$175.00$50.00
WisDOT contract 20260310002: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of March 10, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.