WisDOT contract 20251014010 bid tabulation
1053-07-86. Let by Wisconsin DOT on October 14, 2025, Marathon. 8 bids received; low bid $20,568,560 by James Peterson Sons, Inc..
- Owner
- Wisconsin DOT
- Letting
- 14 OCT 2025
- Pay items
- 157
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | James Peterson Sons, Inc. | $20,568,560 | Low |
| 2 | Trierweiler Construction & Supply Company, Inc. | $20,763,016 | +1.0% |
| 3 | Hoffman Construction Company | $21,696,981 | +5.0% |
| 4 | Mashuda Contractors, Inc. | $22,049,706 | +7.0% |
| 5 | Integrity Grading and Excavating, Inc. | $22,405,866 | +9.0% |
| 6 | Michels Road & Stone, Inc. | $22,566,625 | +10% |
| 7 | Haas Sons, Inc. | $23,181,387 | +13% |
| 8 | Zignego Company, Inc. | $23,298,626 | +13% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. James Peterson Sons, Inc. | 2. Trierweiler Construction & Supply Company, Inc. | 3. Hoffman Construction Company | 4. Mashuda Contractors, Inc. | 5. Integrity Grading and Excavating, Inc. | 6. Michels Road & Stone, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing small pipe culverts (203.0100) | EACH | 7 | $450.00 | $450.00 | $1,250.00 | $400.00 | $226.00 | $650.00 |
| 2 | Removing concrete pavement (204.0100) | SY | 143,893 | $0.50 | $0.65 | $15.00 | $0.76 | $0.65 | $0.65 |
| 3 | Removing asphaltic surface (204.0110) | SY | 19,210 | $1.20 | $1.20 | $1.50 | $2.75 | $2.23 | $2.60 |
| 4 | Removing curb & gutter (204.0150) | LF | 870 | $2.00 | $2.00 | $5.00 | $4.00 | $4.55 | $5.00 |
| 5 | Removing guardrail (204.0165) | LF | 2,040 | $1.85 | $2.75 | $1.85 | $1.85 | $1.85 | $1.85 |
| 6 | Removing delineators and markers (204.0180) | EACH | 207 | $15.00 | $18.00 | $15.00 | $15.00 | $15.00 | $15.00 |
| 7 | Removing inlets (204.0220) | EACH | 14 | $500.00 | $500.00 | $325.00 | $500.00 | $1,146.00 | $500.00 |
| 8 | Removing storm sewer (size) 01. 12-inch (204.0245) | LF | 45 | $20.00 | $20.00 | $9.00 | $30.00 | $27.80 | $30.00 |
| 9 | Removing storm sewer (size) 01. 24-inch (204.0245) | LF | 9 | $100.00 | $100.00 | $9.00 | $75.00 | $26.30 | $35.00 |
| 10 | Abandoning culvert pipes (204.0270) | EACH | 9 | $450.00 | $450.00 | $1,500.00 | $1,500.00 | $723.50 | $850.00 |
| 11 | Removing (item description) 01. apron endwalls (204.9060.S) | EACH | 14 | $450.00 | $450.00 | $400.00 | $400.00 | $291.00 | $750.00 |
| 12 | Removing (item description) 01. buried concrete pavement (204.9180.S) | SY | 10,700 | $0.40 | $0.40 | $5.00 | $6.25 | $0.65 | $4.50 |
| 13 | Excavation common (205.0100) | CY | 236,945 | $8.61 | $8.61 | $20.00 | $8.03 | $7.05 | $10.40 |
| 14 | Excavation for structures bridges (structure) 01. B-37-288 (206.1001) | EACH | 1 | $2,500.00 | $4,500.00 | $30,000 | $8,800.00 | $1,521.00 | $2,500.00 |
| 15 | Borrow (208.0100) | CY | 734 | $13.84 | $13.84 | $0.01 | $0.01 | $0.01 | $10.00 |
| 16 | Backfill structure type A (210.1500) | TON | 182 | $23.50 | $23.50 | $32.00 | $47.65 | $26.30 | $30.00 |
| 17 | Finishing roadway (project) 01. 1053-07-86 (213.0100) | EACH | 1 | $1,500.00 | $500.00 | $100.00 | $725.00 | $500.00 | $2,500.00 |
| 18 | Finishing roadway (project) 02. 1053-07-87 (213.0100) | EACH | 1 | $1,000.00 | $500.00 | $100.00 | $352.00 | $500.00 | $2,500.00 |
| 19 | Base aggregate dense 3/4-inch (305.0110) | TON | 28,307 | $16.79 | $16.79 | $0.01 | $19.95 | $18.30 | $19.70 |
| 20 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 168,310 | $10.20 | $10.43 | $0.01 | $14.28 | $12.25 | $11.80 |
| 21 | Select crushed material (312.0110) | TON | 170,825 | $11.74 | $11.74 | $0.01 | $14.05 | $15.30 | $13.70 |
| 22 | Removing pavement for base patching (390.0100) | CY | 348 | $259.97 | $259.97 | $175.08 | $259.97 | $24.40 | $175.08 |
| 23 | Base patching concrete hes (390.0305) | CY | 348 | $259.97 | $259.97 | $303.16 | $259.97 | $259.97 | $303.16 |
| 24 | Concrete pavement approach slab (415.0410) | SY | 312 | $180.22 | $180.22 | $236.77 | $180.22 | $180.22 | $236.77 |
| 25 | Rout and seal (415.6000.S) | LF | 123,530 | $0.87 | $0.87 | $0.87 | $0.87 | $0.87 | $0.87 |
| 26 | Drilled tie bars (416.0610) | EACH | 220 | $13.13 | $13.13 | $14.28 | $13.13 | $13.13 | $14.28 |
| 27 | Drilled dowel bars (416.0620) | EACH | 98 | $16.59 | $16.59 | $18.33 | $16.59 | $16.59 | $18.33 |
| 28 | HMA cold weather paving (450.4000) | TON | 600 | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 |
| 29 | Tack coat (455.0605) | GAL | 4,268 | $7.25 | $7.25 | $7.25 | $7.25 | $7.25 | $7.25 |
| 30 | Incentive density HMA pavement (460.2000) | DOL | 14,230 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 31 | HMA pavement 4 MT 58-28 S (460.6224) | TON | 17,319 | $108.10 | $108.10 | $108.10 | $108.10 | $108.10 | $108.10 |
| 32 | HMA pavement 5 MT 58-28 S (460.6225) | TON | 2,334 | $112.95 | $112.95 | $112.95 | $112.95 | $112.95 | $112.95 |
| 33 | HMA pavement 3 HT 58-28 S (460.7223) | TON | 3,093 | $117.00 | $117.00 | $117.00 | $117.00 | $117.00 | $117.00 |
| 34 | HMA pavement 4 HT 58-28 H (460.7424) | TON | 1,728 | $125.15 | $125.15 | $125.15 | $125.15 | $125.15 | $125.15 |
| 35 | Asphaltic surface driveways and field entrances (465.0120) | TON | 90 | $225.00 | $225.00 | $225.00 | $225.00 | $225.00 | $225.00 |
| 36 | Asphaltic surface temporary (465.0125) | TON | 700 | $105.40 | $105.40 | $105.40 | $105.40 | $105.40 | $105.40 |
| 37 | Asphaltic flumes (465.0315) | SY | 224 | $84.75 | $84.75 | $84.75 | $84.75 | $84.75 | $84.75 |
| 38 | Asphaltic rumble strips, shoulder divided roadway (465.0510) | LF | 46,950 | $0.13 | $0.24 | $0.40 | $0.13 | $0.40 | $0.40 |
| 39 | Concrete masonry bridges (502.0100) | CY | 10 | $2,000.00 | $1,952.00 | $1,952.00 | $1,952.00 | $2,000.00 | $2,000.00 |
| 40 | Protective surface treatment (502.3200) | SY | 17 | $3.00 | $16.00 | $16.00 | $16.00 | $3.00 | $3.00 |
| 41 | Adhesive anchors no. 5 bar (502.4205) | EACH | 112 | $20.00 | $48.00 | $48.00 | $48.00 | $20.00 | $20.00 |
| 42 | Bar steel reinforcement HS coated structures (505.0600) | LB | 1,180 | $6.50 | $5.00 | $5.00 | $5.00 | $6.50 | $6.50 |
| 43 | Rubberized membrane waterproofing (516.0500) | SY | 4 | $25.00 | $70.00 | $75.00 | $75.00 | $25.00 | $25.00 |
| 44 | Apron endwalls for culvert pipe 12- inch (520.1012) | EACH | 4 | $210.00 | $210.00 | $650.00 | $745.00 | $676.00 | $1,500.00 |
| 45 | Apron endwalls for culvert pipe 18- inch (520.1018) | EACH | 7 | $262.00 | $262.00 | $700.00 | $600.00 | $750.00 | $1,750.00 |
| 46 | Culvert pipe temporary 12-inch (520.2012) | LF | 834 | $52.35 | $52.35 | $32.00 | $51.50 | $35.25 | $70.00 |
| 47 | Culvert pipe class III-A 18-inch (520.3318) | LF | 167 | $51.50 | $51.50 | $42.00 | $57.75 | $62.60 | $81.00 |
| 48 | Concrete collars for pipe (520.8000) | EACH | 3 | $800.00 | $800.00 | $1,200.00 | $1,000.00 | $723.40 | $850.00 |
| 49 | Apron endwalls for culvert pipe steel 12-inch (521.1012) | EACH | 4 | $233.00 | $233.00 | $525.00 | $410.00 | $676.30 | $307.00 |
| 50 | Apron endwalls for culvert pipe steel 24-inch (521.1024) | EACH | 1 | $365.00 | $365.00 | $635.00 | $494.00 | $760.75 | $810.00 |
| 51 | Apron endwalls for culvert pipe steel 36-inch (521.1036) | EACH | 1 | $888.00 | $888.00 | $1,170.00 | $967.00 | $1,754.75 | $1,310.00 |
| 52 | Culvert pipe corrugated steel 24- inch (521.3124) | LF | 8 | $143.00 | $143.00 | $138.00 | $168.50 | $189.00 | $165.00 |
| 53 | Culvert pipe corrugated steel 36- inch (521.3136) | LF | 8 | $172.00 | $172.00 | $172.00 | $197.50 | $226.00 | $210.00 |
| 54 | Apron endwalls for culvert pipe salvaged 18-inch (524.0618) | EACH | 1 | $1,500.00 | $1,500.00 | $400.00 | $1,238.00 | $1,313.00 | $950.00 |
| 55 | Culvert pipe corrugated polyethylene 12-inch (530.0112) | LF | 330 | $66.00 | $66.00 | $32.00 | $51.25 | $55.00 | $75.00 |
| 56 | Concrete curb & gutter 4-inch sloped 36-inch type A (601.0551) | LF | 529 | $36.58 | $36.58 | $53.96 | $36.58 | $36.58 | $53.96 |
| 57 | Concrete curb & gutter 4-inch sloped 36-inch type D (601.0553) | LF | 871 | $37.66 | $37.66 | $53.96 | $37.66 | $37.66 | $53.96 |
| 58 | Concrete curb & gutter 4-inch sloped 36-inch type TBTT (601.0590) | LF | 236 | $37.66 | $37.66 | $53.96 | $37.66 | $37.66 | $53.96 |
| 59 | Concrete rumble strips, shoulder divided roadway (602.3210) | LF | 41,860 | $0.45 | $0.84 | $0.45 | $1.00 | $0.45 | $0.45 |
| 60 | Riprap light (606.0100) | CY | 267 | $80.00 | $80.00 | $70.00 | $80.00 | $96.00 | $156.00 |
| 61 | Storm sewer pipe reinforced concrete class IV 12-inch (608.0412) | LF | 207 | $93.00 | $93.00 | $80.00 | $95.75 | $107.00 | $110.00 |
| 62 | Storm sewer pipe reinforced concrete class IV 18-inch (608.0418) | LF | 200 | $97.00 | $97.00 | $86.00 | $113.50 | $115.00 | $118.00 |
| 63 | Storm sewer pipe reinforced concrete class IV 24-inch (608.0424) | LF | 37 | $203.00 | $203.00 | $136.00 | $226.75 | $153.00 | $191.00 |
| 64 | Inlet covers type MS (611.0642) | EACH | 9 | $665.00 | $665.00 | $1,000.00 | $600.00 | $695.00 | $558.00 |
| 65 | Inlet covers type V (611.0654) | EACH | 4 | $815.00 | $815.00 | $1,100.00 | $870.00 | $857.00 | $746.00 |
| 66 | Inlets 3-FT diameter (611.3003) | EACH | 4 | $2,650.00 | $2,650.00 | $2,100.00 | $3,324.00 | $3,313.00 | $4,550.00 |
| 67 | Inlets median 1 grate (611.3901) | EACH | 3 | $3,725.00 | $3,725.00 | $4,250.00 | $4,534.00 | $4,340.00 | $5,900.00 |
| 68 | Inlets median 2 grate (611.3902) | EACH | 3 | $6,775.00 | $6,775.00 | $7,250.00 | $6,938.00 | $6,300.00 | $9,500.00 |
| 69 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 720 | $3.00 | $3.00 | $9.50 | $15.00 | $11.00 | $6.50 |
| 70 | Steel thrie beam bullnose terminal (614.0220) | EACH | 4 | $15,250 | $14,400 | $15,250 | $15,250 | $15,250 | $15,250 |
| 71 | Steel thrie beam (614.0230) | LF | 300 | $34.00 | $39.00 | $34.00 | $34.00 | $34.00 | $34.00 |
| 72 | Guardrail mow strip emulsified asphalt (614.0397) | SY | 837 | $13.00 | $10.76 | $13.00 | $13.00 | $13.00 | $13.00 |
| 73 | MGS guardrail 3 (614.2300) | LF | 375 | $27.00 | $25.00 | $27.00 | $27.00 | $27.00 | $27.00 |
| 74 | MGS thrie beam transition (614.2500) | LF | 394 | $98.00 | $89.00 | $98.00 | $98.00 | $98.00 | $98.00 |
| 75 | MGS guardrail terminal eat (614.2610) | EACH | 10 | $3,613.00 | $3,650.00 | $3,613.00 | $3,613.00 | $3,613.00 | $3,613.00 |
| 76 | Maintenance and repair of haul roads (project) 01. 1053-07-86 (618.0100) | EACH | 1 | $1,500.00 | $0.01 | $100.00 | $100.00 | $500.00 | $0.01 |
| 77 | Maintenance and repair of haul roads (project) 02. 1053-07-87 (618.0100) | EACH | 1 | $1,500.00 | $0.01 | $100.00 | $100.00 | $500.00 | $0.01 |
| 78 | Mobilization (619.1000) | EACH | 1 | $1,071,681 | $1,105,104 | $995,255 | $1,033,077 | $2,059,000 | $1,005,293 |
| 79 | Water (624.0100) | MGAL | 5,305 | $5.00 | $5.00 | $0.01 | $27.50 | $44.50 | $45.00 |
| 80 | Topsoil (625.0100) | SY | 38,825 | $0.87 | $0.87 | $2.00 | $1.15 | $1.80 | $2.30 |
| 81 | Silt fence (628.1504) | LF | 4,831 | $1.85 | $2.10 | $1.85 | $1.85 | $1.85 | $1.85 |
| 82 | Silt fence maintenance (628.1520) | LF | 9,531 | $0.03 | $0.02 | $0.03 | $0.03 | $0.03 | $0.03 |
| 83 | Mobilizations erosion control (628.1905) | EACH | 25 | $50.00 | $200.00 | $50.00 | $50.00 | $50.00 | $50.00 |
| 84 | Mobilizations emergency erosion control (628.1910) | EACH | 10 | $105.00 | $50.00 | $105.00 | $105.00 | $105.00 | $105.00 |
| 85 | Erosion mat class I type B (628.2004) | SY | 37,165 | $0.95 | $1.07 | $0.95 | $0.95 | $0.95 | $0.95 |
| 86 | Erosion mat urban class I type B (628.2008) | SY | 1,650 | $2.35 | $2.10 | $2.35 | $2.35 | $2.35 | $2.35 |
| 87 | Inlet protection type A (628.7005) | EACH | 27 | $101.00 | $106.00 | $101.00 | $101.00 | $101.00 | $101.00 |
| 88 | Temporary ditch checks (628.7504) | LF | 2,440 | $5.25 | $7.00 | $5.25 | $5.25 | $5.25 | $5.25 |
| 89 | Culvert pipe checks (628.7555) | EACH | 310 | $18.00 | $13.00 | $18.00 | $18.00 | $18.00 | $18.00 |
| 90 | Tracking pads (628.7560) | EACH | 9 | $300.00 | $300.00 | $500.00 | $3,000.00 | $1,000.00 | $1,800.00 |
| 91 | Rock bags (628.7570) | EACH | 50 | $12.50 | $13.00 | $12.50 | $12.50 | $12.50 | $12.50 |
| 92 | Fertilizer type B (629.0210) | CWT | 219.90 | $101.00 | $100.00 | $101.00 | $101.00 | $101.00 | $101.00 |
| 93 | Seeding mixture no. 30 (630.0130) | LB | 7,978 | $6.85 | $7.00 | $6.85 | $6.85 | $6.85 | $6.85 |
| 94 | Seeding borrow pit (630.0300) | LB | 1,078 | $5.95 | $8.00 | $5.95 | $5.95 | $5.95 | $5.95 |
| 95 | Seed water (630.0500) | MGAL | 4,018 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 96 | Delineator posts steel (633.0100) | EACH | 266 | $35.00 | $32.00 | $35.00 | $35.00 | $35.00 | $35.00 |
| 97 | Delineator reflectors (633.0500) | EACH | 306 | $19.00 | $9.00 | $19.00 | $19.00 | $19.00 | $19.00 |
| 98 | Delineators temporary (633.1100) | EACH | 183 | $16.00 | $16.00 | $35.00 | $35.00 | $16.00 | $35.00 |
| 99 | Markers culvert end (633.5200) | EACH | 12 | $85.00 | $65.00 | $85.00 | $85.00 | $85.00 | $85.00 |
| 100 | Markers permanent flexible (633.5350) | EACH | 157 | $31.50 | $31.50 | $55.00 | $55.00 | $31.50 | $31.50 |
| 101 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 1 | $175.00 | $100.00 | $175.00 | $175.00 | $175.00 | $175.00 |
| 102 | Signs type II reflective H (637.2210) | SF | 5.20 | $75.00 | $26.00 | $75.00 | $75.00 | $75.00 | $75.00 |
| 103 | Moving signs type II (638.2102) | EACH | 20 | $175.00 | $155.00 | $175.00 | $175.00 | $175.00 | $175.00 |
| 104 | Removing signs type II (638.2602) | EACH | 5 | $30.00 | $20.00 | $30.00 | $30.00 | $30.00 | $30.00 |
| 105 | Removing small sign supports (638.3000) | EACH | 5 | $30.00 | $20.00 | $30.00 | $30.00 | $30.00 | $30.00 |
| 106 | Field office type D (642.5401) | EACH | 1 | $6,600.00 | $19,526 | $20,000 | $15,000 | $28,000 | $33,000 |
| 107 | Traffic control drums (643.0300) | DAY | 178,116 | $0.10 | $0.10 | $0.10 | $0.10 | $0.10 | $0.10 |
| 108 | Traffic control barricades type III (643.0420) | DAY | 35,746 | $0.35 | $0.35 | $0.35 | $0.35 | $0.35 | $0.35 |
| 109 | Traffic control flexible tubular marker posts (643.0500) | EACH | 1,447 | $24.00 | $24.00 | $24.00 | $24.00 | $24.00 | $24.00 |
| 110 | Traffic control flexible tubular marker bases (643.0600) | EACH | 1,447 | $6.20 | $6.20 | $6.20 | $6.20 | $6.20 | $6.20 |
| 111 | Traffic control warning lights type A (643.0705) | DAY | 44,832 | $0.05 | $0.05 | $0.05 | $0.05 | $0.05 | $0.05 |
| 112 | Traffic control warning lights type C (643.0715) | DAY | 44,792 | $0.05 | $0.05 | $0.05 | $0.05 | $0.05 | $0.05 |
| 113 | Traffic control signs (643.0900) | DAY | 78,123 | $0.30 | $0.30 | $0.30 | $0.30 | $0.30 | $0.30 |
| 114 | Traffic control covering signs type I (643.0910) | EACH | 7 | $425.00 | $425.00 | $425.00 | $425.00 | $425.00 | $425.00 |
| 115 | Traffic control covering signs type II (643.0920) | EACH | 78 | $20.00 | $20.00 | $20.00 | $20.00 | $20.00 | $20.00 |
| 116 | Traffic control signs fixed message (643.1000) | SF | 363 | $10.50 | $10.50 | $10.50 | $10.50 | $10.50 | $10.50 |
| 117 | Temporary marking line epoxy 6- inch (643.3170) | LF | 108,460 | $0.39 | $0.45 | $0.39 | $0.45 | $0.39 | $0.39 |
| 118 | Temporary marking line removable tape 6-inch (643.3180) | LF | 85,415 | $1.65 | $1.65 | $1.65 | $1.65 | $1.65 | $1.65 |
| 119 | Temporary marking line removable tape 10-inch (643.3280) | LF | 630 | $3.40 | $3.40 | $3.40 | $3.40 | $3.40 | $3.40 |
| 120 | Temporary marking stop line removable tape 18-inch (643.3850) | LF | 72 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 121 | Traffic control (643.5000) | EACH | 1 | $6,500.00 | $6,500.00 | $6,500.00 | $6,500.00 | $6,500.00 | $6,500.00 |
| 122 | Geotextile type R (645.0130) | SY | 1,103 | $3.00 | $3.00 | $3.50 | $5.00 | $1.39 | $4.00 |
| 123 | Geotextile type sas (645.0140) | SY | 197,330 | $0.90 | $0.90 | $2.25 | $1.25 | $0.81 | $1.75 |
| 124 | Marking line epoxy 6-inch (646.2020) | LF | 132,960 | $0.43 | $0.60 | $0.43 | $0.60 | $0.43 | $0.43 |
| 125 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 147,662 | $1.30 | $1.48 | $1.30 | $1.48 | $1.30 | $1.30 |
| 126 | Marking line epoxy 10-inch (646.4020) | LF | 4,629 | $0.97 | $1.05 | $0.97 | $1.05 | $0.97 | $0.97 |
| 127 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 6,340 | $2.60 | $2.75 | $2.60 | $2.75 | $2.60 | $2.60 |
| 128 | Marking aerial enforcement bar epoxy (646.5420) | EACH | 10 | $350.27 | $195.00 | $350.27 | $195.00 | $350.27 | $350.27 |
| 129 | Marking outfall epoxy (646.5520) | EACH | 132 | $45.89 | $100.00 | $45.89 | $100.00 | $45.89 | $45.89 |
| 130 | Marking stop line epoxy 18-inch (646.6120) | LF | 486 | $14.77 | $19.75 | $14.77 | $19.75 | $14.77 | $14.77 |
| 131 | Cold weather marking epoxy 6-inch (646.6466) | LF | 15,520 | $0.43 | $0.53 | $0.43 | $0.53 | $0.43 | $0.43 |
| 132 | Cold weather marking epoxy 10- inch (646.6470) | LF | 6,340 | $0.97 | $0.90 | $0.97 | $0.90 | $0.97 | $0.97 |
| 133 | Marking chevron epoxy 24-inch (646.7220) | LF | 326 | $24.24 | $15.50 | $24.24 | $15.50 | $24.24 | $24.24 |
| 134 | Marking removal line water blasting 4-inch (646.9010) | LF | 6,665 | $0.99 | $0.99 | $0.99 | $1.50 | $0.99 | $0.99 |
| 135 | Marking removal line water blasting wide (646.9210) | LF | 20 | $20.97 | $20.97 | $20.97 | $8.25 | $20.97 | $20.97 |
| 136 | Construction staking storm sewer (650.4000) | EACH | 10 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 137 | Construction staking subgrade (650.4500) | LF | 59,748 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 138 | Construction staking base (650.5000) | LF | 16,084 | $0.60 | $0.60 | $0.60 | $0.60 | $0.01 | $0.60 |
| 139 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 871 | $0.75 | $0.75 | $0.75 | $0.75 | $0.75 | $0.75 |
| 140 | Construction staking pipe culverts (650.6000) | EACH | 6 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 141 | Construction staking concrete pavement (650.7000) | LF | 65,599 | $0.36 | $0.36 | $0.36 | $0.36 | $0.36 | $0.36 |
| 142 | Construction staking supplemental control (project) 01. 1053-07-86 (650.9911) | EACH | 1 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 143 | Construction staking supplemental control (project) 02. 1053-07-87 (650.9911) | EACH | 1 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 144 | Construction staking slope stakes (650.9920) | LF | 61,871 | $0.65 | $0.65 | $0.01 | $0.65 | $0.65 | $0.65 |
| 145 | Sawing asphalt (690.0150) | LF | 13,599 | $1.75 | $1.75 | $1.75 | $1.75 | $1.75 | $1.69 |
| 146 | Sawing concrete (690.0250) | LF | 772 | $2.55 | $2.55 | $2.55 | $2.55 | $2.55 | $2.95 |
| 147 | Incentive flexural strength concrete pavement (715.0715) | DOL | 57,085 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 148 | Incentive iri ride (740.0440) | DOL | 41,609 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 149 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,400 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 150 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 1,980 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 151 | Special 01. connected work zone notification system (SPV.0045) | DAY | 688 | $33.00 | $33.00 | $33.00 | $33.00 | $33.00 | $33.00 |
| 152 | Special 01. reestablish section corner monuments (SPV.0060) | EACH | 7 | $500.00 | $500.00 | $500.00 | $500.00 | $500.00 | $500.00 |
| 153 | Special 02. locate and clean existing underdrain outfalls (SPV.0060) | EACH | 132 | $214.00 | $214.00 | $90.00 | $150.00 | $201.00 | $100.00 |
| 154 | Special 03. coring of existing concrete pavement (SPV.0060) | EACH | 60 | $150.00 | $150.00 | $150.00 | $250.00 | $150.00 | $50.00 |
| 155 | Special 01. unbonded concrete overlay 7-inch (SPV.0180) | SY | 41,650 | $31.91 | $31.91 | $33.65 | $31.91 | $31.91 | $33.65 |
| 156 | Special 02. HP concrete pavement 8-inch (SPV.0180) | SY | 16,490 | $54.51 | $54.51 | $55.86 | $54.51 | $54.51 | $55.86 |
| 157 | Special 03. HP concrete pavement 10-inch (SPV.0180) | SY | 131,830 | $44.18 | $44.18 | $45.43 | $44.18 | $44.18 | $45.43 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of October 14, 2025. Compiled by Mirage Metrics.