WisDOT contract 20250211033 bid tabulation

1590-18-71. Let by Wisconsin DOT on February 11, 2025, Forest. 5 bids received; low bid $17,389,817 by Integrity Grading and Excavating, Inc..

Owner
Wisconsin DOT
Letting
11 FEB 2025
Pay items
285
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Integrity Grading and Excavating, Inc.$17,389,817Low
2Northeast Asphalt, Inc$18,647,730+7.0%
3Mashuda Contractors, Inc.$18,775,920+8.0%
4Musson Bros., Inc.$19,603,337+13%
5James Peterson Sons, Inc.$19,828,371+14%
WisDOT contract 20250211033: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Integrity Grading and Excavating, Inc.2. Northeast Asphalt, Inc3. Mashuda Contractors, Inc.4. Musson Bros., Inc.5. James Peterson Sons, Inc.
1Grubbing (201.0205)STA119$329.00$329.00$329.00$329.00$329.06
2Grubbing (201.0215)ACRE0.29$4,150.00$4,150.00$4,150.00$4,150.00$4,150.00
3Roadside clearing (202.0110)SY30$99.00$99.00$99.00$99.00$99.00
4Removing small pipe culverts (203.0100)EACH20$565.00$565.00$970.00$617.00$500.00
5Removing structure over waterway remove debris (structure) 001. C- 21-9703 (203.0250)EACH1$15,000$15,000$15,000$15,000$11,111
6Removing asphaltic surface (204.0110)SY812.60$4.35$10.00$3.00$4.50$10.00
7Removing asphaltic surface butt joints (204.0115)SY905$13.90$13.90$13.90$13.90$13.90
8Removing asphaltic surface milling (204.0120)SY199,310$3.40$3.40$3.40$3.40$3.40
9Removing curb & gutter (204.0150)LF1,527$6.35$6.35$4.50$5.30$3.42
10Removing concrete sidewalk (204.0155)SY107$6.55$6.55$10.00$17.00$15.00
11Removing guardrail (204.0165)LF205$3.00$3.00$3.00$5.00$3.00
12Removing cable barrier (204.0167)LF3,740$3.00$3.00$3.00$5.00$3.00
13Removing fence (204.0170)LF290$2.00$2.00$2.00$5.00$2.06
14Removing storm sewer (size) 001. 15-inch (204.0245)LF37$20.00$20.00$20.00$6.90$20.00
15Abandoning culvert pipes (204.0270)EACH1$10.00$10.00$1,500.00$935.00$2,463.00
16Excavation common (205.0100)CY337,540$10.25$10.25$8.85$8.70$11.14
17Excavation for structures culverts (structure) 001. C-21-9703 (206.2001)EACH1$9,239.00$9,239.00$17,000$5,336.00$13,603
18Excavation for structures culverts (structure) 002. B-21-35 (206.2001)EACH1$46,500$46,500$65,000$37,644$79,925
19Cofferdams (structure) 001. 21008000215 (206.5001)EACH1$500.00$50,000$10,000$15,670$6,500.00
20Select borrow (208.1100)CY1,736$25.00$20.00$18.07$24.00$23.51
21Backfill structure type A (210.1500)TON5,160$20.00$20.00$17.93$13.00$25.00
22Backfill structure type B (210.2500)TON1,270$20.00$19.00$18.93$13.00$22.75
23Prepare foundation for asphaltic paving (project) 001. 1590-18-71 (211.0101)EACH1$28,890$28,890$28,890$28,890$28,890
24Prepare foundation for asphaltic paving (project) 002. 1590-18-81 (211.0101)EACH1$52,750$52,750$52,750$52,750$52,750
25Prepare foundation for asphaltic shoulders (211.0400)STA261$75.10$75.10$75.10$75.10$75.10
26Finishing roadway (project) 001. 1590-18-71 (213.0100)EACH1$500.00$6,250.00$1,000.00$100.00$3,500.00
27Finishing roadway (project) 002. 1590-18-81 (213.0100)EACH1$500.00$6,250.00$1,000.00$100.00$3,500.00
28Base aggregate dense 3/4-inch (305.0110)TON19,657$19.00$19.00$17.28$0.01$23.37
29Base aggregate dense 1 1/4-inch (305.0120)TON35,863$15.50$15.50$14.43$16.00$15.76
30Base aggregate dense 3-inch (305.0130)TON357$26.85$26.85$16.71$17.00$19.79
31Shaping shoulders (305.0500)STA6$562.00$770.00$150.00$198.00$150.00
32Breaker run (311.0110)TON140$32.80$32.80$21.90$37.00$30.19
33Concrete pavement 7-inch (415.0070)SY1,938$95.50$95.50$105.57$105.57$95.50
34HMA cold weather paving (450.4000)TON22,500$3.20$3.20$3.20$3.20$3.20
35Tack coat (455.0605)GAL15,294$3.25$3.25$3.25$3.25$3.25
36HMA percent within limits (PWL) test strip volumetrics (460.0105.S)EACH2$3,150.00$3,150.00$3,150.00$3,150.00$3,150.00
37HMA percent within limits (PWL) test strip density (460.0110.S)EACH3$4,750.00$4,750.00$4,750.00$4,750.00$4,750.00
38Incentive density PWL HMA pavement (460.2005)DOL41,097$1.00$1.00$1.00$1.00$1.00
39Incentive density HMA pavement longitudinal joints (460.2007)DOL29,840$1.00$1.00$1.00$1.00$1.00
40Incentive air voids HMA pavement (460.2010)DOL51,010$1.00$1.00$1.00$1.00$1.00
41HMA pavement 3 MT 58-28 S (460.6223)TON29,490$70.20$70.20$70.20$70.20$70.20
42HMA pavement 4 MT 58-34 S (460.6244)TON21,520$82.90$82.90$82.90$82.90$82.90
43Asphaltic surface (465.0105)TON3,924$121.90$121.90$121.90$121.90$121.90
44Asphaltic surface patching (465.0110)TON525$121.90$121.90$121.90$121.90$121.90
45Asphaltic surface driveways and field entrances (465.0120)TON275$180.00$180.00$180.00$180.00$180.00
46Asphaltic flumes (465.0315)SY130$59.70$59.70$59.70$59.70$75.00
47Asphaltic rumble strips, shoulder (465.0520)LF23,992$0.37$0.37$0.37$0.37$0.37
48Asphaltic rumble strips, centerline (465.0560)LF46,685$0.37$0.37$0.37$0.37$0.37
49Pigmented surface sealer (502.3210)SY121$2.50$2.50$2.50$2.50$3.75
50Adhesive anchors no. 5 bar (502.4205)EACH52$25.00$25.00$25.00$25.00$19.00
51Concrete masonry culverts (504.0100)CY944$745.50$745.50$745.50$745.50$810.00
52Bar steel reinforcement HS structures (505.0400)LB91,920$1.30$1.30$1.30$1.30$0.96
53Bar steel reinforcement HS coated structures (505.0600)LB19,030$1.40$1.40$1.40$1.40$1.06
54Temporary shoring (structure) 001. C-21-9703 (511.1200)SF555$50.00$50.00$50.00$50.00$44.00
55Rubberized membrane waterproofing (516.0500)SY72$18.00$18.00$18.00$18.00$44.00
56Sheet membrane waterproofing for buried structures (516.0610.S)SY646$25.00$25.00$25.00$25.00$44.00
57Concrete staining (structure) 001. B-21-35 (517.1010.S)SF2,997$4.21$4.21$4.21$4.21$2.85
58Concrete staining multi-color (structure) 001. B-21-35 (517.1015.S)SF3,926$5.85$5.85$5.85$5.85$2.10
59Architectural surface treatment (structure) 001. B-21-35 (517.1050.S)SF3,804$10.00$10.00$10.00$10.00$15.35
60Apron endwalls for culvert pipe 24- inch (520.1024)EACH17$882.00$882.00$560.00$543.00$468.00
61Apron endwalls for culvert pipe 30- inch (520.1030)EACH8$1,125.00$1,125.00$795.00$867.00$815.00
62Apron endwalls for culvert pipe 36- inch (520.1036)EACH3$2,038.00$2,038.00$1,150.00$1,659.00$1,148.00
63Culvert pipe class III-A 24-inch (520.3324)LF560$100.00$100.00$89.69$96.00$97.39
64Culvert pipe class III-A 30-inch (520.3330)LF286$110.00$110.00$125.00$135.00$139.35
65Culvert pipe class III-A 36-inch (520.3336)LF106$123.00$123.00$122.00$121.00$236.04
66Concrete collars for pipe (520.8000)EACH6$493.00$493.00$600.00$1,776.00$748.63
67Apron endwalls for culvert pipe steel 48-inch (521.1048)EACH2$2,711.00$2,711.00$1,800.00$2,604.00$1,942.14
68Culvert pipe corrugated steel 48- inch (521.3148)LF93$220.00$220.00$200.00$299.00$218.29
69Culvert pipe reinforced concrete class III 24-inch (522.0124)LF36$162.00$162.00$165.00$161.00$156.05
70Culvert pipe reinforced concrete class III 36-inch (522.0136)LF8$501.00$501.00$245.00$414.00$187.34
71Culvert pipe reinforced concrete class IV 18-inch (522.0418)LF156$129.00$129.00$82.00$115.00$113.18
72Culvert pipe reinforced concrete class IV 24-inch (522.0424)LF68$168.00$168.00$117.00$147.00$140.83
73Culvert pipe reinforced concrete class IV 36-inch (522.0436)LF15$275.00$275.00$240.00$241.00$272.23
74Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012)EACH11$1,205.00$1,205.00$882.00$1,421.00$1,315.00
75Apron endwalls for culvert pipe reinforced concrete 18-inch (522.1018)EACH10$1,352.00$1,352.00$1,050.00$1,591.00$1,516.00
76Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024)EACH10$1,518.00$1,518.00$1,225.00$1,575.00$1,740.00
77Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036)EACH4$3,013.00$3,013.00$2,195.00$2,530.00$2,746.00
78Culvert pipe reinforced concrete horizontal elliptical class HE-III 14X23-inch (522.2314)LF64$173.00$173.00$125.00$168.00$149.74
79Culvert pipe reinforced concrete horizontal elliptical class HE-IV 14X23-inch (522.2414)LF16$199.00$199.00$160.00$208.00$228.35
80Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 14X23-inch (522.2614)EACH4$2,045.00$2,045.00$1,110.00$1,203.00$1,560.00
81Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 29X45-inch (522.2629)EACH1$3,147.00$3,147.00$2,550.00$3,048.00$2,821.00
82Concrete curb & gutter 30-inch type D (601.0411)LF443$72.77$72.77$66.54$66.54$72.77
83Concrete curb & gutter 4-inch sloped 36-inch type D (601.0553)LF20$75.47$75.47$67.51$67.51$75.47
84Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557)LF2,060$42.55$42.55$30.38$30.38$42.55
85Concrete curb & gutter 4-inch sloped 36-inch type T (601.0582)LF12$81.31$81.31$67.51$67.51$81.31
86Concrete curb pedestrian (601.0600)LF43$73.47$73.47$58.98$58.98$73.47
87Concrete sidewalk 5-inch (602.0410)SF5,207$11.19$11.19$15.18$15.18$11.19
88Curb ramp detectable warning field yellow (602.0505)SF10$52.93$52.93$62.51$62.51$52.93
89Curb ramp detectable warning field natural patina (602.0515)SF260$49.05$49.05$60.38$60.38$49.05
90Curb ramp detectable warning field radial yellow (602.0605)SF105$67.82$67.82$67.84$67.84$67.82
91Curb ramp detectable warning field radial natural patina (602.0615)SF145$62.88$62.88$65.71$65.71$62.88
92Concrete surface drains (602.3010)CY1.95$855.20$855.20$1,543.66$1,543.66$855.20
93Riprap medium (606.0200)CY390$192.50$192.50$80.00$308.00$88.34
94Riprap heavy (606.0300)CY45$192.50$192.50$100.00$296.00$98.15
95Riprap extra-heavy (606.0400)CY50$192.50$192.50$100.00$243.00$112.57
96Storm sewer pipe reinforced concrete class III 15-inch (608.0315)LF80$105.00$105.00$87.00$92.00$128.30
97Storm sewer pipe reinforced concrete class III 24-inch (608.0324)LF583$126.00$126.00$110.00$105.00$112.01
98Storm sewer pipe reinforced concrete class III 30-inch (608.0330)LF61$175.00$175.00$154.00$169.00$168.25
99Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF345$93.00$93.00$73.00$86.00$107.88
100Storm sewer pipe reinforced concrete class IV 15-inch (608.0415)LF60$116.00$116.00$89.00$92.00$128.30
101Storm sewer pipe reinforced concrete class IV 18-inch (608.0418)LF103$105.00$105.00$92.00$93.00$113.18
102Storm sewer pipe reinforced concrete class IV 24-inch (608.0424)LF451$137.00$137.00$124.00$119.00$114.43
103Storm sewer pipe reinforced concrete horizontal elliptical class HE-III 29X45-inch (608.2329)LF38$280.00$280.00$255.00$257.00$280.19
104Storm sewer pipe class III-A 18- inch (608.3018)LF571$86.00$86.00$72.00$88.00$85.48
105Manhole covers type J (611.0530)EACH4$644.00$644.00$640.00$1,002.00$1,195.00
106Inlet covers type C (611.0612)EACH8$680.00$680.00$660.00$1,002.00$1,227.00
107Inlet covers type HM (611.0627)EACH7$908.00$908.00$850.00$1,253.00$1,323.00
108Inlet covers type MS (611.0642)EACH26$687.00$687.00$602.00$640.00$600.00
109Manholes 4-FT diameter (611.2004)EACH6$3,963.00$3,963.00$3,700.00$3,585.00$3,380.00
110Manholes 5-FT diameter (611.2005)EACH4$5,131.00$5,131.00$4,500.00$4,288.00$4,562.00
111Manholes 8-FT diameter (611.2008)EACH2$12,636$12,636$12,400$12,482$13,142
112Inlets 4-FT diameter (611.3004)EACH1$3,714.00$3,714.00$3,200.00$2,516.00$2,917.00
113Inlets 2X3-FT (611.3230)EACH6$2,595.00$2,595.00$2,400.00$1,812.00$2,059.00
114Inlets median 1 grate (611.3901)EACH18$3,727.00$3,727.00$2,650.00$2,531.00$2,992.00
115Inlets median 2 grate (611.3902)EACH4$5,150.00$5,150.00$4,900.00$4,164.00$5,025.00
116Pipe underdrain wrapped 6-inch (612.0406)LF207$2.00$2.00$10.00$5.30$18.00
117Insulation board polystyrene (inch) 001. 2 -inch (612.0902.S)SY676$18.08$18.08$38.00$45.00$29.00
118Maintenance and repair of haul roads (project) 001. 1590-18-71 (618.0100)EACH1$500.00$10.00$1.00$1.00$100.00
119Maintenance and repair of haul roads (project) 002. 1590-18-81 (618.0100)EACH1$500.00$10.00$1.00$1.00$100.00
120Mobilization (619.1000)EACH1$678,000$1,832,460$1,191,691$1,662,282$1,697,865
121Water (624.0100)MGAL1,419.80$30.00$50.00$30.00$18.00$45.00
122Topsoil (625.0100)SY151,879$1.65$1.65$2.14$0.40$2.15
123Mulching (627.0200)SY4,758$0.40$0.40$0.40$0.50$0.40
124Silt fence (628.1504)LF14,110$2.00$2.00$2.00$2.05$2.00
125Silt fence maintenance (628.1520)LF16,327$0.01$0.01$0.01$0.05$0.01
126Mobilizations erosion control (628.1905)EACH23$100.00$100.00$100.00$400.00$100.00
127Mobilizations emergency erosion control (628.1910)EACH10$100.00$100.00$100.00$125.00$100.00
128Erosion mat urban class I type A (628.2006)SY6,252$1.75$1.75$1.75$1.98$1.75
129Erosion mat class II type B (628.2023)SY140,720$1.95$1.95$1.95$1.98$1.95
130Soil stabilizer type B (628.6510)ACRE3.39$850.00$850.00$850.00$4,500.00$850.00
131Inlet protection type A (628.7005)EACH24$125.00$125.00$125.00$50.00$125.00
132Inlet protection type C (628.7015)EACH19$50.00$50.00$50.00$75.00$50.00
133Inlet protection type D (628.7020)EACH1$100.00$100.00$100.00$135.00$100.00
134Temporary ditch checks (628.7504)LF1,891$10.00$10.00$10.00$7.25$10.00
135Stone ditch checks (628.7515.S)CY161$80.00$80.00$60.00$463.00$80.00
136Culvert pipe checks (628.7555)EACH155$8.00$8.00$8.00$14.00$8.00
137Tracking pads (628.7560)EACH8$1,000.00$1,000.00$2,650.00$500.00$2,500.00
138Rock bags (628.7570)EACH631$10.00$10.00$10.00$14.00$10.00
139Fertilizer type A (629.0205)CWT14.02$125.00$125.00$125.00$115.00$125.00
140Fertilizer type B (629.0210)CWT91$80.00$80.00$80.00$115.00$80.00
141Seeding mixture no. 20 (630.0120)LB7,644$8.00$8.00$8.00$7.50$8.00
142Seed water (630.0500)MGAL3,028$5.00$5.00$5.00$10.00$5.00
143Markers culvert end (633.5200)EACH55$70.00$70.00$70.00$70.00$70.00
144Posts wood 4X6-inch X 12-FT (634.0612)EACH2$100.00$100.00$100.00$70.00$100.00
145Posts wood 4X6-inch X 16-FT (634.0616)EACH63$125.00$125.00$125.00$78.00$125.00
146Signs type II reflective H (637.2210)SF174.56$35.00$35.00$35.00$22.70$35.00
147Signs type II reflective F (637.2230)SF236.50$35.00$35.00$35.00$24.30$35.00
148Moving signs type II (638.2102)EACH40$100.00$100.00$100.00$80.00$100.00
149Removing signs type II (638.2602)EACH10$25.00$25.00$25.00$40.00$25.00
150Removing small sign supports (638.3000)EACH41$25.00$25.00$25.00$40.00$25.00
151Moving small sign supports (638.4000)EACH5$50.00$50.00$50.00$80.00$50.00
152Field office type B (642.5001)EACH1$22,000$18,740$15,000$15,000$16,000
153Traffic control drums (643.0300)DAY16,510$0.18$0.18$0.18$0.18$0.18
154Traffic control barricades type III (643.0420)DAY27,305$0.34$0.34$0.34$0.34$0.34
155Traffic control warning lights type A (643.0705)DAY47,918$0.11$0.11$0.11$0.11$0.11
156Traffic control warning lights type C (643.0715)DAY5,865$0.11$0.11$0.11$0.11$0.11
157Traffic control arrow boards (643.0800)DAY180$8.56$8.56$8.56$8.56$8.56
158Traffic control signs (643.0900)DAY101,034$0.17$0.17$0.17$0.17$0.17
159Traffic control covering signs type II (643.0920)EACH7$100.00$100.00$100.00$100.00$100.00
160Traffic control signs fixed message (643.1000)SF89.50$30.00$30.00$30.00$30.00$30.00
161Temporary marking line paint 6- inch (643.3165)LF84,407$0.25$0.25$0.33$0.25$0.25
162Temporary marking line removable tape 6-inch (643.3180)LF3,895$2.45$2.45$2.45$2.45$2.45
163Temporary marking crosswalk removable tape 6-inch (643.3350)LF1,094$1.91$1.91$1.91$1.91$1.91
164Traffic control (643.5000)EACH1$3,500.00$3,500.00$3,500.00$3,500.00$3,500.00
165Temporary pedestrian surface plate (644.1430)SF238$3.69$3.69$3.69$3.69$3.69
166Temporary pedestrian curb ramp (644.1601)DAY120$19.44$19.44$19.44$19.44$19.44
167Temporary pedestrian detectable warning field (644.1605)SF56$25.14$25.14$25.14$25.14$25.14
168Temporary pedestrian barricade (644.1810)LF452$6.41$6.41$6.41$6.41$6.41
169Geotextile type C (645.0105)SY275$1.75$1.75$4.90$3.10$7.27
170Geotextile type HR (645.0120)SY951$2.31$2.31$3.70$5.60$4.21
171Geotextile type R (645.0130)SY2,647$1.09$5.00$3.40$6.90$4.53
172Geotextile type SR (645.0135)SY528$1.28$1.28$2.50$2.90$6.63
173Geogrid type SR (645.0220)SY7,926$0.75$0.75$1.65$1.80$2.02
174Marking line grooved wet ref epoxy 6-inch (646.2040)LF217,685$1.35$1.35$1.35$1.35$1.35
175Marking line grooved wet ref epoxy 10-inch (646.4040)LF670$2.60$2.60$2.60$2.60$2.60
176Marking arrow epoxy (646.5020)EACH12$299.00$299.00$299.00$299.00$299.00
177Marking stop line epoxy 18-inch (646.6120)LF65$17.00$17.00$17.00$17.00$17.00
178Cold weather marking epoxy 6-inch (646.6466)LF45,000$0.40$0.40$0.40$0.40$0.40
179Cold weather marking epoxy 10- inch (646.6470)LF400$1.00$1.00$1.00$1.00$1.00
180Marking diagonal epoxy 12-inch (646.7120)LF2,550$7.50$7.50$7.50$7.50$7.50
181Marking crosswalk epoxy transverse line 6-inch (646.7420)LF596$14.00$14.00$14.00$14.00$14.00
182Marking crosswalk epoxy block style 24-inch (646.7520)LF90$22.00$22.00$22.00$22.00$22.00
183Marking removal line 4-inch (646.9000)LF2,915$0.50$0.50$0.50$0.50$0.50
184Locating no-passing zones (648.0100)MI3.33$800.00$800.00$800.00$800.00$800.00
185Construction staking storm sewer (650.4000)EACH65$115.00$115.00$115.00$115.00$115.00
186Construction staking subgrade (650.4500)LF12,165$0.01$0.95$0.50$0.01$0.01
187Construction staking base (650.5000)LF22,640$0.95$0.95$0.95$0.95$0.95
188Construction staking curb gutter and curb & gutter (650.5500)LF2,566$1.44$1.44$1.44$1.44$1.44
189Construction staking pipe culverts (650.6000)EACH41$165.00$165.00$165.00$165.00$165.00
190Construction staking structure layout (structure) 001. C-21-9703 (650.6501)EACH1$3,000.00$3,000.00$3,000.00$3,000.00$3,000.00
191Construction staking structure layout (structure) 002. B-21-35 (650.6501)EACH1$3,000.00$3,000.00$3,000.00$3,000.00$3,000.00
192Construction staking concrete pavement (650.7000)LF1,233$0.92$0.92$0.92$0.92$0.92
193Construction staking resurfacing reference (650.8000)LF53,261$0.07$0.07$0.07$0.07$0.07
194Construction staking curb ramps (650.9000)EACH27$110.00$110.00$110.00$110.00$110.00
195Construction staking sidewalk (project) 001. 1590-18-71 (650.9500)EACH1$500.00$500.00$500.00$500.00$500.00
196Construction staking sidewalk (project) 003. 9813-02-70 (650.9500)EACH1$500.00$500.00$500.00$500.00$500.00
197Construction staking supplemental control (project) 001. 1590-18-71 (650.9911)EACH1$10.00$10.00$10.00$10.00$10.00
198Construction staking supplemental control (project) 002. 1590-18-81 (650.9911)EACH1$10.00$10.00$10.00$10.00$10.00
199Construction staking supplemental control (project) 003. 1590-18-82 (650.9911)EACH1$10.00$10.00$10.00$10.00$10.00
200Construction staking supplemental control (project) 004. 9813-02-70 (650.9911)EACH1$10.00$10.00$10.00$10.00$10.00
201Construction staking slope stakes (650.9920)LF12,565$0.98$0.98$0.98$0.98$0.98
202Conduit rigid metallic 3/4-inch (652.0105)LF25$95.00$95.00$95.00$95.00$95.00
203Conduit rigid metallic 1-inch (652.0110)LF23$180.00$180.00$180.00$180.00$180.00
204Conduit rigid nonmetallic schedule 40 3/4-inch (652.0205)LF94$9.70$9.70$9.70$9.70$9.70
205Conduit rigid nonmetallic schedule 40 1-inch (652.0210)LF471$10.00$10.00$10.00$10.00$10.00
206Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF385$10.00$10.00$10.00$10.00$10.00
207Pull boxes non-conductive 24X42- inch (653.0164)EACH4$2,438.00$2,438.00$2,438.00$2,438.00$2,438.00
208Junction boxes 8X8X8-inch (653.0208)EACH2$1,653.00$1,653.00$1,653.00$1,653.00$1,653.00
209Electrical wire lighting 10 AWG (655.0615)LF1,686$1.30$1.30$1.30$1.30$1.30
210Sawing asphalt (690.0150)LF7,749$1.69$1.75$1.75$1.75$1.80
211Sawing concrete (690.0250)LF123$2.50$2.75$2.75$2.75$2.35
212Incentive strength concrete structures (715.0502)DOL5,618$1.00$1.00$1.00$1.00$1.00
213Incentive compressive strength concrete pavement (715.0720)DOL1,000$1.00$1.00$1.00$1.00$1.00
214Incentive iri ride (740.0440)DOL45,200$1.00$1.00$1.00$1.00$1.00
215On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,100$5.00$5.00$5.00$5.00$5.00
216On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS4,800$5.00$5.00$5.00$5.00$5.00
217Special 201. utility trench rock excavation (SPV.0035)CY500$60.00$60.00$52.50$88.00$200.00
218Special 001. adjusting water valves (SPV.0060)EACH8$780.00$780.00$350.00$1,425.00$534.63
219Special 002. adjusting sanitary manhole covers (SPV.0060)EACH4$580.00$580.00$525.00$860.00$810.79
220Special 003. foam sealant joint repair C-21-9703 (SPV.0060)EACH1$14,213$14,213$14,213$14,213$6,500.00
221Special 101. precast concrete panel (SPV.0060)EACH2$5,000.00$5,000.00$5,000.00$5,000.00$8,911.00
222Special 102. posts wood 4X4-inch X 12-FT (SPV.0060)EACH23$61.00$61.00$61.00$60.00$61.00
223Special 103. posts wood 4X4-inch X 14-FT (SPV.0060)EACH67$61.00$61.00$61.00$64.00$61.00
224Special 104. tunnel luminare (SPV.0060)EACH6$987.00$987.00$987.00$987.00$987.00
225Special 106. electrical service meter breaker pedestal special (SPV.0060)EACH1$8,050.00$8,050.00$8,050.00$8,050.00$8,050.00
226Special 106. precast concrete planter (SPV.0060)EACH8$800.00$800.00$800.00$2,250.00$800.00
227Special 107. kiosks (SPV.0060)EACH4$12,000$12,000$12,000$22,600$12,000
228Special 108. concrete footing (concrete base) (SPV.0060)EACH39$50.00$50.00$50.00$150.00$50.00
229Special 109. benches (SPV.0060)EACH8$900.00$900.00$900.00$2,700.00$900.00
230Special 202. removing sanitary manhole (SPV.0060)EACH1$1,175.00$1,175.00$625.00$1,200.00$500.00
231Special 203. removing sanitary cleanout (SPV.0060)EACH10$250.00$250.00$160.00$500.00$150.00
232Special 204. abandon sanitary manhole (SPV.0060)EACH2$1,386.00$1,386.00$920.00$1,200.00$1,093.11
233Special 205. remove hydrant (SPV.0060)EACH5$1,175.00$1,175.00$645.00$800.00$880.00
234Special 206. remove 6-inch gate valve (SPV.0060)EACH6$250.00$250.00$415.00$800.00$450.00
235Special 207. remove 8-inch gate valve (SPV.0060)EACH1$250.00$250.00$458.00$800.00$600.00
236Special 208. remove 12-inch gate valve (SPV.0060)EACH2$250.00$250.00$645.00$800.00$750.00
237Special 209. remove valve box (SPV.0060)EACH4$250.00$250.00$267.50$800.00$150.00
238Special 210. air release valve manhole (SPV.0060)EACH1$24,000$24,000$33,000$44,300$41,740
239Special 211. connect to existing force main (SPV.0060)EACH3$7,400.00$7,400.00$4,915.00$3,000.00$2,504.67
240Special 212. reconnect existing sanitary lateral (SPV.0060)EACH10$3,550.00$3,550.00$1,125.00$700.00$261.05
241Special 213. temporary 4-inch sanitary connection (SPV.0060)EACH5$5,140.00$5,140.00$3,150.00$1.00$1.00
242Special 214. temporary 6-inch force main connection (SPV.0060)EACH6$5,240.00$5,240.00$3,250.00$1.00$1.00
243Special 215. reconnect existing water service lateral (SPV.0060)EACH1$3,520.00$3,520.00$1,656.00$1,355.00$332.88
244Special 216. temporary water main connection, 6-inch (SPV.0060)EACH7$9,700.00$9,700.00$3,250.00$1.00$1.00
245Special 217. connect to existing water main (SPV.0060)EACH4$4,800.00$4,800.00$5,000.00$4,500.00$2,651.54
246Special 218. 6-inch gate valve and box (SPV.0060)EACH11$1,826.00$1,826.00$2,613.00$2,900.00$2,423.40
247Special 219. 8-inch gate valve and box (SPV.0060)EACH14$2,020.00$2,020.00$3,442.50$3,830.00$3,404.80
248Special 220. fire hydrant (SPV.0060)EACH11$6,546.00$6,546.00$7,230.00$7,160.00$6,406.12
249Special 221. remove and reset gate and post (SPV.0060)EACH1$750.00$750.00$750.00$4,500.00$750.00
250Special 222. utility line openings (SPV.0060)EACH10$1,400.00$1,400.00$925.00$500.00$1,500.00
251Special 247. construction staking sanitary sewer and force main (project) 1590-18-83 (SPV.0060)EACH1$6,500.00$6,500.00$6,500.00$6,500.00$6,500.00
252Special 248. construction staking water main (project) 1590-18-83 (SPV.0060)EACH1$5,000.00$5,000.00$5,000.00$5,000.00$5,000.00
253Special 253. sanitary sewer 8-inch cleanout (SPV.0060)EACH1$520.00$520.00$2,105.00$2,100.00$672.25
254Special 101. railing (SPV.0090)LF3,693$22.05$22.05$22.05$60.00$22.05
255Special 102. profile curb cut (SPV.0090)LF86$34.88$36.35$30.00$30.00$64.50
256Special 103. staked wattles (SPV.0090)LF21,923$7.00$7.00$7.00$5.50$7.00
257Special 223. remove existing sanitary force main 6-inch or smaller (SPV.0090)LF3,648$6.05$6.05$9.70$1.00$19.56
258Special 224. remove existing casing pipe (SPV.0090)LF60$6.05$6.05$25.00$1.00$73.34
259Special 225. remove existing water main 12-inch or smaller (SPV.0090)LF3,346$6.05$6.05$9.70$1.00$22.00
260Special 226. remove 24-inch steel casing (SPV.0090)LF50$6.05$6.05$25.00$1.00$88.00
261Special 227. abandon 6-inch or smaller sanitary or force main (SPV.0090)LF9,863$2.82$2.82$4.50$1.00$1.00
262Special 228. abandon 8-inch or smaller water main (SPV.0090)LF1,287$2.82$2.82$11.25$1.00$1.00
263Special 229. abandon 12-inch water main (SPV.0090)LF1,115$2.82$2.82$18.30$1.00$1.00
264Special 230. 6-inch lift station force main (SPV.0090)LF8,130$45.45$45.45$66.40$105.00$85.54
265Special 231. 6-inch effluent force main (SPV.0090)LF6,682$45.45$45.45$66.40$105.00$84.92
266Special 232. 8-inch sanitary sewer pipe (SPV.0090)LF6,516$73.75$73.75$187.40$169.00$84.42
267Special 233. 8-inch sanitary sewer SDR 26 pipe (SPV.0090)LF400$127.00$127.00$176.75$203.00$84.74
268Special 234. 2-inch sanitary lateral (SPV.0090)LF33$122.00$122.00$168.00$142.00$138.84
269Special 235. 4-inch sanitary laterall (SPV.0090)LF435$62.00$62.00$158.50$119.00$69.47
270Special 236. 6-inch sanitary lateral (SPV.0090)LF54$72.00$72.00$137.25$123.00$111.49
271Special 237. 1-inch water service lateral (SPV.0090)LF43$88.00$88.00$95.25$116.00$110.08
272Special 238. 6-inch water main (includes hydrant leads) (SPV.0090)LF189$80.00$80.00$126.75$154.00$116.80
273Special 239. 8-inch water main (SPV.0090)LF5,862$70.00$70.00$113.00$146.00$88.39
274Special 241. over excavation for pipe bedding 0.5-FT to 1.5-FT (force main) (SPV.0090)LF600$9.00$9.00$12.75$22.00$28.78
275Special 242. over excavation for pipe bedding 1.6-FT to 3.0-FT (force main) (SPV.0090)LF600$18.00$18.00$25.50$33.00$58.01
276Special 243. over excavation for pipe bedding 0.5-FT to 1.5-FT (san 9-FT - 14FT deep) (SPV.0090)LF400$9.00$9.00$12.75$23.00$30.77
277Special 244. over excavation for pipe bedding 1.6-FT to 3.0-FT (san 9-FT - 14FT deep) (SPV.0090)LF400$18.00$18.00$25.50$34.00$58.01
278Special 245. over excavation for pipe bedding 0.5-FT to 1.5-FT (san 14.1-FT - 25FT deep) (SPV.0090)LF400$9.00$9.00$12.75$25.00$35.77
279Special 246. over excavation for pipe bedding 1.6-FT to 3.0-FT (san 14.1-FT - 25FT deep) (SPV.0090)LF400$18.00$18.00$25.50$36.00$72.01
280Special 247. 2-1/2 - inch lift station force main (SPV.0090)LF95$41.00$41.00$151.00$119.00$105.23
281Special 001. protective thermoplastic coating at snowmobile trail crossings (SPV.0180)SY315$100.00$100.00$100.00$100.00$100.00
282Special 249. 4-inch sanitary lateral riser (SPV.0200)VF3$10.25$10.25$227.50$130.00$150.00
283Special 250. 6-inch sanitary lateral riser (SPV.0200)VF3$21.30$21.30$240.00$135.00$150.00
284Special 251. sanitary sewer manhole 4-FT diameter (SPV.0200)VF274.84$480.00$480.00$613.00$885.00$423.94
285Special 252. sanitary sewer outside drop manhole (SPV.0200)VF19.56$1,525.00$1,525.00$1,042.00$950.00$788.68
WisDOT contract 20250211033: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of February 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy