WisDOT contract 20261110018 bid tabulation
3830-01-70. Let by Wisconsin DOT on November 10, 2026, Kenosha. 6 bids received; low bid $6,487,537 by A.W. Oakes & Son, Inc..
- Owner
- Wisconsin DOT
- Letting
- 10 NOV 2026
- Pay items
- 186
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | A.W. Oakes & Son, Inc. | $6,487,537 | Low |
| 2 | Stark Pavement Corporation | $6,775,895 | +4.0% |
| 3 | James Peterson Sons, Inc. | $6,777,944 | +4.0% |
| 4 | Lalonde Contractors Incorporated | $7,850,013 | +21% |
| 5 | Zignego Company, Inc. | $7,866,257 | +21% |
| 6 | Willkomm Excav. & Grading | $8,439,370 | +30% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. A.W. Oakes & Son, Inc. | 2. Stark Pavement Corporation | 3. James Peterson Sons, Inc. | 4. Lalonde Contractors Incorporated | 5. Zignego Company, Inc. | 6. Willkomm Excav. & Grading |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 35 | $850.00 | $858.50 | $850.00 | $850.00 | $850.00 | $981.57 |
| 2 | Grubbing (201.0205) | STA | 35 | $150.00 | $151.50 | $150.00 | $150.00 | $150.00 | $173.22 |
| 3 | Removing small pipe culverts (203.0100) | EACH | 22 | $400.00 | $375.00 | $375.00 | $1,450.00 | $350.00 | $3,798.47 |
| 4 | Removing concrete pavement (204.0100) | SY | 60 | $25.00 | $11.00 | $11.00 | $15.72 | $14.35 | $15.08 |
| 5 | Removing curb & gutter (204.0150) | LF | 220 | $20.00 | $2.50 | $2.50 | $11.07 | $5.71 | $4.64 |
| 6 | Removing concrete sidewalk (204.0155) | SY | 10 | $10.00 | $10.00 | $10.00 | $14.66 | $7.31 | $15.18 |
| 7 | Removing manholes (204.0210) | EACH | 1 | $1,000.00 | $750.00 | $750.00 | $1,481.25 | $1,000.00 | $2,864.88 |
| 8 | Removing inlets (204.0220) | EACH | 2 | $500.00 | $500.00 | $500.00 | $859.13 | $1,000.00 | $2,114.79 |
| 9 | Removing storm sewer (size) 01. 12-inch (204.0245) | LF | 41 | $40.00 | $27.06 | $27.06 | $71.10 | $50.00 | $122.34 |
| 10 | Excavation common (205.0100) | CY | 25,153 | $16.80 | $17.58 | $17.58 | $32.07 | $18.58 | $31.27 |
| 11 | Backfill granular grade 1 (209.1500) | TON | 9,170 | $19.60 | $22.56 | $22.56 | $21.32 | $25.00 | $20.29 |
| 12 | Finishing roadway (project) 01. 3830-01-70 (213.0100) | EACH | 1 | $2,500.00 | $4,000.00 | $5,500.00 | $3,392.00 | $1,000.00 | $3,292.85 |
| 13 | Base aggregate dense 3/4-inch (305.0110) | TON | 24 | $24.00 | $115.07 | $115.07 | $56.83 | $100.00 | $71.15 |
| 14 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 7,274 | $27.00 | $33.45 | $33.45 | $26.38 | $18.56 | $13.66 |
| 15 | Base aggregate open-graded (310.0110) | TON | 4,234 | $35.00 | $19.37 | $19.37 | $38.96 | $50.00 | $36.86 |
| 16 | Coloring concrete wisdot red (405.0100) | CY | 110 | $175.00 | $280.00 | $175.00 | $144.29 | $200.00 | $191.55 |
| 17 | Concrete pavement 7-inch (415.0070) | SY | 15,042 | $57.00 | $56.00 | $57.00 | $56.53 | $66.65 | $62.39 |
| 18 | Concrete pavement gaps (415.0210) | EACH | 19 | $0.01 | $1,400.00 | $0.01 | $1,295.00 | $1,000.00 | $0.01 |
| 19 | Concrete truck apron 12-inch (415.2010) | SY | 317 | $95.00 | $46.00 | $100.00 | $126.67 | $144.13 | $109.46 |
| 20 | Drilled tie bars (416.0610) | EACH | 4 | $30.00 | $30.00 | $30.00 | $29.53 | $100.00 | $32.84 |
| 21 | Drilled dowel bars (416.0620) | EACH | 36 | $30.00 | $30.00 | $30.00 | $32.86 | $30.00 | $32.84 |
| 22 | Tack coat (455.0605) | GAL | 1,167 | $3.15 | $3.15 | $3.15 | $3.15 | $3.15 | $3.45 |
| 23 | Incentive density HMA pavement (460.2000) | DOL | 1,150 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 24 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 191 | $105.00 | $104.15 | $104.15 | $104.15 | $104.15 | $114.00 |
| 25 | HMA pavement 4 LT 58-28 H (460.5424) | TON | 1,635 | $87.00 | $86.95 | $86.95 | $86.95 | $86.95 | $95.17 |
| 26 | Asphaltic surface driveways and field entrances (465.0120) | TON | 20 | $140.00 | $140.00 | $140.00 | $140.00 | $140.00 | $153.24 |
| 27 | Asphaltic surface temporary (465.0125) | TON | 123 | $135.00 | $135.00 | $135.00 | $135.00 | $135.00 | $147.77 |
| 28 | Apron endwalls for culvert pipe 15- inch (520.1015) | EACH | 5 | $325.00 | $305.96 | $305.96 | $1,074.80 | $300.00 | $832.35 |
| 29 | Apron endwalls for culvert pipe 18- inch (520.1018) | EACH | 4 | $375.00 | $354.58 | $354.58 | $1,248.99 | $300.00 | $918.25 |
| 30 | Culvert pipe class III-B 15-inch (520.3515) | LF | 46 | $80.00 | $47.79 | $47.79 | $63.91 | $100.00 | $87.41 |
| 31 | Culvert pipe class III-B 18-inch (520.3518) | LF | 74 | $84.00 | $64.67 | $64.67 | $70.39 | $100.00 | $96.83 |
| 32 | Concrete collars for pipe (520.8000) | EACH | 2 | $900.00 | $770.00 | $770.00 | $1,896.00 | $1,500.00 | $473.42 |
| 33 | Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012) | EACH | 1 | $1,150.00 | $993.35 | $993.35 | $1,632.34 | $850.00 | $1,361.96 |
| 34 | Apron endwalls for culvert pipe reinforced concrete 15-inch (522.1015) | EACH | 1 | $1,250.00 | $1,098.33 | $1,098.33 | $1,806.39 | $850.00 | $1,416.09 |
| 35 | Apron endwalls for culvert pipe reinforced concrete 18-inch (522.1018) | EACH | 1 | $1,375.00 | $1,186.00 | $1,186.00 | $2,007.98 | $900.00 | $1,544.51 |
| 36 | Apron endwalls for culvert pipe reinforced concrete 30-inch (522.1030) | EACH | 1 | $2,700.00 | $1,903.48 | $1,903.48 | $2,461.84 | $1,350.00 | $1,929.05 |
| 37 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 19X30-inch (522.2619) | EACH | 2 | $1,750.00 | $1,589.38 | $1,589.38 | $3,515.01 | $1,350.00 | $1,941.26 |
| 38 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 89 | $75.00 | $46.00 | $75.00 | $56.01 | $47.61 | $85.73 |
| 39 | Concrete sidewalk 4-inch (602.0405) | SF | 375 | $10.00 | $8.00 | $10.00 | $10.80 | $9.55 | $10.95 |
| 40 | Concrete sidewalk 5-inch (602.0410) | SF | 21,360 | $7.50 | $7.00 | $7.50 | $8.74 | $10.38 | $8.21 |
| 41 | Concrete sidewalk 6-inch (602.0415) | SF | 1,510 | $10.00 | $8.00 | $10.00 | $9.21 | $11.20 | $10.95 |
| 42 | Curb ramp detectable warning field yellow (602.0505) | SF | 196 | $55.00 | $48.00 | $55.00 | $51.07 | $60.00 | $60.20 |
| 43 | Concrete driveway 6-inch (602.0810) | SY | 520 | $75.00 | $68.50 | $75.00 | $77.05 | $82.81 | $82.09 |
| 44 | Riprap light (606.0100) | CY | 25 | $180.00 | $208.69 | $208.69 | $139.56 | $300.00 | $172.03 |
| 45 | Riprap medium (606.0200) | CY | 25 | $180.00 | $210.68 | $210.68 | $139.56 | $300.00 | $253.12 |
| 46 | Storm sewer pipe reinforced concrete class III 12-inch (608.0312) | LF | 1,200 | $95.00 | $125.54 | $125.54 | $116.46 | $107.23 | $120.63 |
| 47 | Storm sewer pipe reinforced concrete class III 15-inch (608.0315) | LF | 624 | $92.00 | $86.80 | $86.80 | $121.24 | $109.34 | $120.59 |
| 48 | Storm sewer pipe reinforced concrete class III 18-inch (608.0318) | LF | 284 | $100.00 | $108.38 | $108.38 | $121.84 | $127.62 | $146.94 |
| 49 | Storm sewer pipe reinforced concrete class III 24-inch (608.0324) | LF | 236 | $118.00 | $124.85 | $124.85 | $137.06 | $135.38 | $157.64 |
| 50 | Storm sewer pipe reinforced concrete class III 30-inch (608.0330) | LF | 812 | $183.00 | $167.53 | $167.53 | $177.56 | $257.97 | $252.29 |
| 51 | Storm sewer pipe reinforced concrete class IV 12-inch (608.0412) | LF | 262 | $105.00 | $133.19 | $133.19 | $116.46 | $122.34 | $133.91 |
| 52 | Storm sewer pipe reinforced concrete class IV 15-inch (608.0415) | LF | 42 | $113.00 | $135.12 | $135.12 | $121.24 | $105.25 | $160.35 |
| 53 | Storm sewer pipe reinforced concrete class IV 18-inch (608.0418) | LF | 122 | $117.00 | $115.01 | $115.01 | $123.05 | $123.53 | $151.52 |
| 54 | Storm sewer pipe reinforced concrete class IV 24-inch (608.0424) | LF | 384 | $126.00 | $120.60 | $120.60 | $158.20 | $151.13 | $164.74 |
| 55 | Storm sewer pipe reinforced concrete class IV 30-inch (608.0430) | LF | 350 | $153.00 | $136.55 | $136.55 | $192.36 | $134.69 | $214.44 |
| 56 | Storm sewer pipe reinforced concrete horizontal elliptical class HE-III 19X30-inch (608.2319) | LF | 76 | $178.00 | $168.20 | $168.20 | $196.90 | $105.44 | $185.04 |
| 57 | Storm sewer pipe class III-A 15- inch (608.3015) | LF | 72 | $67.00 | $60.41 | $60.41 | $113.40 | $100.00 | $88.35 |
| 58 | Manhole covers type J (611.0530) | EACH | 15 | $625.00 | $873.59 | $873.59 | $693.46 | $900.00 | $997.03 |
| 59 | Inlet covers type B (611.0606) | EACH | 1 | $905.00 | $1,241.79 | $1,241.79 | $1,128.12 | $1,000.00 | $1,299.60 |
| 60 | Inlet covers type B-A (611.0609) | EACH | 11 | $980.00 | $1,451.92 | $1,451.79 | $1,191.40 | $1,000.00 | $1,274.18 |
| 61 | Inlet covers type H (611.0624) | EACH | 32 | $865.00 | $1,295.12 | $1,295.12 | $1,063.42 | $1,100.00 | $1,254.55 |
| 62 | Inlet covers type H-S (611.0639) | EACH | 11 | $865.00 | $1,295.12 | $1,295.12 | $1,063.42 | $1,100.00 | $1,254.55 |
| 63 | Inlet covers type MS-A (611.0645) | EACH | 2 | $655.00 | $611.80 | $611.80 | $873.35 | $750.00 | $1,030.51 |
| 64 | Manholes 4-FT diameter (611.2004) | EACH | 7 | $3,100.00 | $2,335.98 | $2,335.98 | $4,269.28 | $3,805.31 | $5,057.73 |
| 65 | Manholes 5-FT diameter (611.2005) | EACH | 7 | $4,300.00 | $4,139.75 | $4,139.75 | $6,055.23 | $4,861.31 | $8,853.43 |
| 66 | Manholes 6-FT diameter (611.2006) | EACH | 3 | $6,000.00 | $4,671.53 | $4,671.53 | $6,869.40 | $7,408.71 | $8,410.56 |
| 67 | Inlets 4-FT diameter (611.3004) | EACH | 4 | $3,000.00 | $2,324.90 | $2,324.90 | $4,664.01 | $3,859.34 | $5,235.31 |
| 68 | Inlets 2X2-FT (611.3220) | EACH | 11 | $2,400.00 | $1,371.36 | $1,371.36 | $2,535.79 | $2,456.34 | $3,580.60 |
| 69 | Inlets 2X3-FT (611.3230) | EACH | 38 | $2,600.00 | $1,752.28 | $1,752.28 | $3,058.77 | $2,667.54 | $4,042.71 |
| 70 | Inlets median 2 grate (611.3902) | EACH | 1 | $5,900.00 | $4,939.95 | $4,939.95 | $3,938.35 | $7,512.93 | $6,284.00 |
| 71 | Adjusting manhole covers (611.8110) | EACH | 1 | $600.00 | $660.79 | $660.79 | $888.75 | $1,000.00 | $1,214.86 |
| 72 | Adjusting inlet covers (611.8115) | EACH | 2 | $600.00 | $774.32 | $774.32 | $888.75 | $1,000.00 | $1,214.87 |
| 73 | Pipe underdrain 6-inch (612.0106) | LF | 7,925 | $10.00 | $10.14 | $10.14 | $35.50 | $16.28 | $20.44 |
| 74 | Mobilization (619.1000) | EACH | 1 | $343,200 | $337,970 | $340,850 | $169,048 | $121,000 | $411,165 |
| 75 | Concrete median sloped nose (620.0300) | SF | 493 | $16.00 | $12.00 | $16.00 | $20.75 | $14.60 | $17.51 |
| 76 | Water (624.0100) | MGAL | 254 | $25.00 | $25.00 | $25.00 | $60.00 | $30.00 | $12.13 |
| 77 | Topsoil (625.0100) | SY | 19,750 | $5.00 | $3.56 | $3.56 | $6.30 | $7.15 | $7.07 |
| 78 | Silt fence (628.1504) | LF | 5,970 | $2.25 | $1.62 | $2.25 | $2.18 | $2.25 | $2.19 |
| 79 | Silt fence maintenance (628.1520) | LF | 5,970 | $0.05 | $0.10 | $0.05 | $0.01 | $0.05 | $0.27 |
| 80 | Mobilizations erosion control (628.1905) | EACH | 6 | $150.00 | $325.00 | $150.00 | $200.00 | $150.00 | $218.92 |
| 81 | Mobilizations emergency erosion control (628.1910) | EACH | 6 | $200.00 | $325.00 | $200.00 | $1.00 | $200.00 | $218.92 |
| 82 | Erosion mat urban class I type B (628.2008) | SY | 19,750 | $1.75 | $1.58 | $1.65 | $2.01 | $1.65 | $1.92 |
| 83 | Inlet protection type A (628.7005) | EACH | 53 | $10.00 | $84.00 | $10.00 | $70.00 | $10.00 | $103.99 |
| 84 | Inlet protection type B (628.7010) | EACH | 12 | $65.00 | $32.00 | $65.00 | $70.00 | $65.00 | $71.15 |
| 85 | Inlet protection type C (628.7015) | EACH | 31 | $60.00 | $34.00 | $60.00 | $70.00 | $60.00 | $82.09 |
| 86 | Inlet protection type D (628.7020) | EACH | 14 | $115.00 | $88.00 | $115.00 | $125.00 | $115.00 | $136.82 |
| 87 | Temporary ditch checks (628.7504) | LF | 39 | $8.00 | $13.00 | $8.00 | $8.00 | $8.00 | $13.68 |
| 88 | Culvert pipe checks (628.7555) | EACH | 33 | $20.00 | $26.00 | $20.00 | $20.00 | $20.00 | $38.31 |
| 89 | Fertilizer type B (629.0210) | CWT | 13 | $60.00 | $92.00 | $60.00 | $83.00 | $60.00 | $103.99 |
| 90 | Seeding mixture no. 40 (630.0140) | LB | 1,015 | $7.00 | $9.80 | $6.90 | $11.95 | $6.90 | $10.40 |
| 91 | Seeding temporary (630.0200) | LB | 254 | $2.50 | $4.20 | $2.50 | $4.00 | $2.50 | $3.84 |
| 92 | Seeding borrow pit (630.0300) | LB | 100 | $7.00 | $11.00 | $6.90 | $9.00 | $6.90 | $8.21 |
| 93 | Seed water (630.0500) | MGAL | 404 | $1.00 | $9.00 | $1.00 | $6.00 | $1.00 | $21.89 |
| 94 | Posts wood 4X6-inch X 12-FT (634.0612) | EACH | 10 | $70.00 | $82.00 | $70.00 | $147.00 | $70.00 | $109.46 |
| 95 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 4 | $74.00 | $82.00 | $74.00 | $147.00 | $74.00 | $136.82 |
| 96 | Signs type II reflective H (637.2210) | SF | 90.88 | $25.00 | $22.00 | $24.50 | $21.15 | $24.50 | $27.36 |
| 97 | Moving signs type II (638.2102) | EACH | 3 | $175.00 | $148.00 | $175.00 | $80.00 | $175.00 | $273.65 |
| 98 | Removing signs type II (638.2602) | EACH | 9 | $30.00 | $28.00 | $30.00 | $10.00 | $30.00 | $43.78 |
| 99 | Removing small sign supports (638.3000) | EACH | 9 | $30.00 | $28.00 | $30.00 | $10.00 | $30.00 | $43.78 |
| 100 | Moving small sign supports (638.4000) | EACH | 3 | $50.00 | $55.00 | $50.00 | $80.00 | $50.00 | $273.65 |
| 101 | Pond liner clay (640.1303.S) | CY | 1,820 | $28.00 | $24.18 | $24.18 | $39.04 | $45.00 | $26.53 |
| 102 | Field office type C (642.5201) | EACH | 1 | $12,000 | $25,000 | $18,000 | $20,070 | $20,000 | $16,966 |
| 103 | Traffic control drums (643.0300) | DAY | 6,390 | $0.15 | $0.51 | $0.50 | $0.12 | $0.50 | $0.13 |
| 104 | Traffic control barricades type III (643.0420) | DAY | 1,818 | $0.75 | $0.76 | $0.75 | $0.70 | $0.75 | $0.77 |
| 105 | Traffic control warning lights type A (643.0705) | DAY | 2,572 | $0.10 | $0.05 | $0.05 | $0.07 | $0.05 | $0.08 |
| 106 | Traffic control warning lights type C (643.0715) | DAY | 224 | $0.25 | $0.05 | $0.05 | $0.25 | $0.05 | $0.27 |
| 107 | Traffic control signs (643.0900) | DAY | 17,459 | $0.25 | $0.56 | $0.55 | $0.25 | $0.55 | $0.27 |
| 108 | Traffic control signs PCMS (643.1050) | DAY | 14 | $60.00 | $40.40 | $40.00 | $60.00 | $40.00 | $65.68 |
| 109 | Traffic control (643.5000) | EACH | 1 | $17,000 | $13,130 | $13,000 | $16,657 | $13,000 | $18,232 |
| 110 | Geotextile type DF schedule A (645.0111) | SY | 4,418 | $3.00 | $1.15 | $1.15 | $3.00 | $4.00 | $2.34 |
| 111 | Geotextile type HR (645.0120) | SY | 102 | $5.00 | $9.83 | $9.83 | $6.06 | $10.00 | $20.62 |
| 112 | Geotextile type R (645.0130) | SY | 105 | $5.00 | $6.39 | $6.39 | $5.33 | $10.00 | $6.15 |
| 113 | Marking line epoxy 4-inch (646.1020) | LF | 16,489 | $0.50 | $0.80 | $0.79 | $0.40 | $0.70 | $0.86 |
| 114 | Marking stop line epoxy 18-inch (646.6120) | LF | 30 | $20.00 | $14.14 | $14.00 | $19.75 | $25.00 | $15.32 |
| 115 | Marking dotted extension epoxy 18-inch (646.6320) | LF | 48 | $20.00 | $15.15 | $15.00 | $19.85 | $25.00 | $16.42 |
| 116 | Marking diagonal epoxy 12-inch (646.7120) | LF | 92 | $20.00 | $12.12 | $12.00 | $19.30 | $11.00 | $13.14 |
| 117 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 362 | $16.00 | $11.11 | $11.00 | $15.75 | $14.00 | $12.04 |
| 118 | Marking curb epoxy (646.8120) | LF | 80 | $10.00 | $8.08 | $8.00 | $9.50 | $13.00 | $8.76 |
| 119 | Marking island nose epoxy (646.8220) | EACH | 8 | $375.00 | $353.50 | $350.00 | $353.05 | $340.00 | $383.11 |
| 120 | Construction staking storm sewer (650.4000) | EACH | 71 | $125.00 | $121.20 | $130.00 | $130.00 | $130.00 | $142.30 |
| 121 | Construction staking subgrade (650.4500) | LF | 4,771 | $1.00 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 122 | Construction staking base (650.5000) | LF | 198 | $2.00 | $3.03 | $3.00 | $3.00 | $3.00 | $3.28 |
| 123 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 89 | $4.00 | $6.06 | $3.00 | $3.00 | $3.00 | $3.28 |
| 124 | Construction staking pipe culverts (650.6000) | EACH | 2 | $200.00 | $131.30 | $300.00 | $300.00 | $300.00 | $328.38 |
| 125 | Construction staking concrete pavement (650.7000) | LF | 4,573 | $2.00 | $3.03 | $0.01 | $0.01 | $2.20 | $0.01 |
| 126 | Construction staking curb ramps (650.9000) | EACH | 14 | $350.00 | $202.00 | $200.00 | $200.00 | $200.00 | $218.92 |
| 127 | Construction staking sidewalk (project) 01. 3830-01-70 (650.9500) | EACH | 1 | $5,000.00 | $3,131.00 | $5,500.00 | $5,500.00 | $5,500.00 | $6,020.25 |
| 128 | Construction staking supplemental control (project) 01. 3830-01-70 (650.9911) | EACH | 1 | $2,500.00 | $1,515.00 | $11,200 | $11,200 | $1,200.00 | $12,259 |
| 129 | Construction staking slope stakes (650.9920) | LF | 4,771 | $1.50 | $0.76 | $1.10 | $1.10 | $1.10 | $1.20 |
| 130 | Sawing asphalt (690.0150) | LF | 299 | $2.00 | $2.25 | $2.05 | $2.05 | $1.89 | $2.19 |
| 131 | Sawing concrete (690.0250) | LF | 149 | $5.00 | $3.00 | $2.75 | $2.75 | $2.85 | $3.01 |
| 132 | Incentive compressive strength concrete pavement (715.0720) | DOL | 4,663 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 133 | Incentive iri ride (740.0440) | DOL | 2,960 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 134 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 1,800 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 135 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 4,900 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 136 | Special 01. cored holes 6-inch (SPV.0060) | EACH | 4 | $250.00 | $250.00 | $250.00 | $474.00 | $1,000.00 | $1,504.81 |
| 137 | Special 02. basin riser 48-inch (SPV.0060) | EACH | 2 | $8,200.00 | $12,432 | $12,432 | $1,735.31 | $7,000.00 | $7,640.24 |
| 138 | Special 03. section corner monuments (SPV.0060) | EACH | 1 | $500.00 | $1,600.00 | $2,500.00 | $500.00 | $1,000.00 | $3,092.28 |
| 139 | Special 04. temporary water diversion - station 77+84 (SPV.0060) | EACH | 1 | $2,750.00 | $10,661 | $10,661 | $32,500 | $10,000 | $6,696.09 |
| 140 | Special 05. storm sewer tracer wire access box (SPV.0060) | EACH | 10 | $200.00 | $53.20 | $53.20 | $1,055.84 | $100.00 | $115.86 |
| 141 | Special 06. clay collar (SPV.0060) | EACH | 2 | $500.00 | $2,500.00 | $2,500.00 | $2,192.25 | $500.00 | $730.85 |
| 142 | Special 50. 4-inch sanitary cleanout (SPV.0060) | EACH | 11 | $875.00 | $565.17 | $565.17 | $654.00 | $500.00 | $699.93 |
| 143 | Special 51. connect to existing sanitary manhole (SPV.0060) | EACH | 2 | $2,500.00 | $3,284.50 | $3,284.50 | $1,513.13 | $2,500.00 | $12,835 |
| 144 | Special 52. adjust sanitary manhole (SPV.0060) | EACH | 5 | $2,300.00 | $800.79 | $800.79 | $937.50 | $1,000.00 | $3,051.85 |
| 145 | Special 53. sanitary manhole casting (SPV.0060) | EACH | 5 | $640.00 | $1,395.79 | $1,395.79 | $792.50 | $1,434.00 | $1,015.51 |
| 146 | Special 54. sanitary sewer tracer wire access box (SPV.0060) | EACH | 16 | $200.00 | $53.20 | $53.20 | $301.25 | $100.00 | $115.86 |
| 147 | Special 55. gate valve and box, 8- inch (SPV.0060) | EACH | 1 | $3,500.00 | $3,963.40 | $3,963.40 | $4,522.38 | $3,500.00 | $3,584.76 |
| 148 | Special 56. gate valve and box, 6- inch (SPV.0060) | EACH | 11 | $2,600.00 | $2,901.80 | $2,901.80 | $3,235.38 | $3,500.00 | $2,453.07 |
| 149 | Special 57. butterfly valve and box, 16-inch (SPV.0060) | EACH | 14 | $800.00 | $14,298 | $14,298 | $9,427.13 | $7,500.00 | $7,797.16 |
| 150 | Special 58. butterfly valve and box, 12-inch (SPV.0060) | EACH | 3 | $6,100.00 | $9,619.00 | $9,619.00 | $6,835.31 | $7,500.00 | $5,668.30 |
| 151 | Special 59. hydrant assembly (SPV.0060) | EACH | 9 | $9,000.00 | $11,416 | $11,416 | $9,426.63 | $9,256.93 | $9,540.61 |
| 152 | Special 60. air release hydrant assembly (SPV.0060) | EACH | 3 | $9,000.00 | $11,416 | $11,416 | $9,426.63 | $9,256.93 | $9,101.90 |
| 153 | Special 61. water service corp stop, 1.25-inch (SPV.0060) | EACH | 19 | $1,150.00 | $600.60 | $600.60 | $1,035.94 | $800.00 | $836.07 |
| 154 | Special 62. curb stop and box, 1. 25-inch (SPV.0060) | EACH | 19 | $915.00 | $1,273.20 | $1,273.20 | $795.00 | $600.00 | $574.51 |
| 155 | Special 63. water main tracer wire access box (SPV.0060) | EACH | 19 | $235.00 | $53.20 | $53.20 | $1,090.00 | $100.00 | $115.86 |
| 156 | Special 64. remove and salvage existing hydrant (SPV.0060) | EACH | 9 | $1,100.00 | $1,163.25 | $1,163.25 | $1,656.25 | $2,000.00 | $2,846.36 |
| 157 | Special 65. abandon existing water valve (SPV.0060) | EACH | 17 | $300.00 | $400.00 | $400.00 | $1,062.50 | $1,000.00 | $1,028.65 |
| 158 | Special 66. bulkhead existing water main (SPV.0060) | EACH | 13 | $500.00 | $250.00 | $250.00 | $1,137.50 | $600.00 | $1,624.09 |
| 159 | Special 67. connect to existing water main (SPV.0060) | EACH | 5 | $700.00 | $3,408.01 | $3,408.01 | $2,232.00 | $2,500.00 | $11,502 |
| 160 | Special 68. connect to existing water service (SPV.0060) | EACH | 10 | $600.00 | $260.90 | $260.90 | $104.00 | $600.00 | $278.01 |
| 161 | Special 69. construction staking water main (SPV.0060) | EACH | 1 | $7,500.00 | $4,969.20 | $6,800.00 | $6,800.00 | $6,800.00 | $7,443.21 |
| 162 | Special 70. construction staking sanitary sewer (SPV.0060) | EACH | 1 | $7,500.00 | $3,333.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,189.18 |
| 163 | Special 01. concrete curb & gutter 30-inch type A modified (SPV.0090) | LF | 7,754 | $23.50 | $25.05 | $23.50 | $31.37 | $34.61 | $29.36 |
| 164 | Special 02. concrete curb & gutter 18-inch type A modified (SPV.0090) | LF | 112 | $75.00 | $42.00 | $75.00 | $54.82 | $39.08 | $85.73 |
| 165 | Special 03. concrete curb & gutter 4-inch sloped 36-inch type A modified (SPV.0090) | LF | 340 | $51.75 | $38.00 | $51.75 | $62.23 | $52.96 | $60.28 |
| 166 | Special 04. concrete curb & gutter 3-inch sloped 30-inch type R modified (SPV.0090) | LF | 173 | $43.25 | $46.00 | $43.25 | $59.43 | $47.61 | $50.98 |
| 167 | Special 05. concrete curb & gutter hes 30-inch type A modified (SPV.0090) | LF | 186 | $26.00 | $30.00 | $26.00 | $60.11 | $50.21 | $32.10 |
| 168 | Special 06. storm sewer laterals 4- inch (SPV.0090) | LF | 24 | $72.00 | $90.86 | $90.86 | $88.92 | $200.00 | $179.86 |
| 169 | Special 07. concrete curb pedestrian special (SPV.0090) | LF | 20 | $100.00 | $80.00 | $100.00 | $104.01 | $33.65 | $109.46 |
| 170 | Special 50. sanitary lateral pipe PVC, 4-inch (SPV.0090) | LF | 693 | $152.00 | $149.54 | $149.54 | $103.95 | $181.56 | $220.76 |
| 171 | Special 51. sanitary lateral pipe PVC, 6-inch (SPV.0090) | LF | 42 | $195.00 | $184.02 | $184.02 | $119.54 | $184.20 | $217.36 |
| 172 | Special 52. sanitary sewer pipe PVC, 8-inch (SPV.0090) | LF | 1,867 | $179.00 | $222.10 | $222.10 | $286.56 | $234.60 | $255.93 |
| 173 | Special 53. sanitary sewer pipe PVC, 12-inch (SPV.0090) | LF | 1,145 | $295.00 | $289.54 | $289.54 | $301.48 | $309.83 | $399.61 |
| 174 | Special 54. water main pipe PVC, 6-inch (SPV.0090) | LF | 197 | $130.00 | $155.09 | $155.09 | $113.06 | $156.89 | $356.92 |
| 175 | Special 55. water main pipe PVC, 8-inch (SPV.0090) | LF | 39 | $175.00 | $229.71 | $229.71 | $152.79 | $222.07 | $342.33 |
| 176 | Special 56. water main pipe PVC, 12-inch (SPV.0090) | LF | 266 | $200.00 | $238.24 | $238.24 | $182.64 | $259.03 | $251.59 |
| 177 | Special 57. water main pipe PVC, 16-inch (SPV.0090) | LF | 4,004 | $188.00 | $180.44 | $180.44 | $189.19 | $197.02 | $219.98 |
| 178 | Special 58. water service pipe HDPE, 1.25-inch (SPV.0090) | LF | 762 | $110.00 | $136.74 | $136.74 | $92.68 | $150.54 | $135.81 |
| 179 | Special 59. abandon existing water main W/ flowable fill (SPV.0090) | LF | 4,275 | $13.00 | $17.71 | $17.71 | $46.23 | $60.00 | $18.92 |
| 180 | Special 60. remove existing water main (SPV.0090) | LF | 153 | $40.00 | $10.00 | $10.00 | $62.50 | $50.00 | $128.68 |
| 181 | Special 61. televising sewers (SPV.0090) | LF | 8,211 | $5.50 | $5.95 | $5.95 | $6.99 | $6.25 | $5.93 |
| 182 | Special 50. water main insulation (SPV.0165) | SF | 160 | $10.00 | $6.00 | $6.00 | $15.63 | $20.00 | $20.79 |
| 183 | Special 01. concrete pavement hes 7-inch (SPV.0180) | SY | 500 | $62.00 | $67.00 | $62.00 | $78.55 | $117.27 | $67.86 |
| 184 | Special 50. sanitary manhole 4-FT diameter (SPV.0200) | VF | 132.50 | $665.00 | $461.68 | $461.68 | $840.06 | $2,562.83 | $1,017.28 |
| 185 | Special 51. sanitary manhole outside drop (SPV.0200) | VF | 5.50 | $660.00 | $1,210.33 | $1,210.33 | $940.00 | $5,904.18 | $96.79 |
| 186 | Special 52. 4-inch sanitary riser (SPV.0200) | VF | 62.60 | $150.00 | $149.54 | $149.54 | $380.21 | $532.49 | $427.88 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of November 10, 2026. Compiled by Mirage Metrics.