WisDOT contract 20251111034 bid tabulation
Chippewa Falls - Cornell; Olson Drive to Cashman Drive (STH 178, Chippewa County Chippewa Falls - Cornell). Let by Wisconsin DOT on November 11, 2025, Chippewa. 3 bids received; low bid $1,010,984 by Chippewa Concrete Services, Inc..
- Owner
- Wisconsin DOT
- Letting
- 11 NOV 2025
- Pay items
- 142
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Chippewa Concrete Services, Inc. | $1,010,984 | Low |
| 2 | Haas Sons, Inc. | $1,026,262 | +2.0% |
| 3 | Pember Companies, Inc. | $1,103,298 | +9.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Chippewa Concrete Services, Inc. | 2. Haas Sons, Inc. | 3. Pember Companies, Inc. |
|---|---|---|---|---|---|---|
| 1 | Removing concrete pavement (204.0100) | SY | 2,098 | $11.14 | $4.33 | $15.75 |
| 2 | Removing concrete sidewalk (204.0155) | SY | 19 | $27.29 | $10.79 | $11.65 |
| 3 | Removing inlets (204.0220) | EACH | 1 | $945.35 | $1,084.00 | $880.00 |
| 4 | Excavation common (205.0100) | CY | 1,485 | $17.89 | $26.21 | $35.00 |
| 5 | Finishing roadway (project) 01. 8600-00-74 (213.0100) | EACH | 1 | $5,110.00 | $1.00 | $500.00 |
| 6 | Base aggregate dense 3/4-inch (305.0110) | TON | 14 | $89.94 | $86.60 | $42.00 |
| 7 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 1,328 | $22.13 | $29.24 | $37.20 |
| 8 | Concrete pavement 9-inch (415.0090) | SY | 2,162 | $106.37 | $104.00 | $103.50 |
| 9 | Concrete pavement joint filling (415.4100) | SY | 2,404 | $5.01 | $6.36 | $8.90 |
| 10 | Drilled tie bars (416.0610) | EACH | 220 | $16.38 | $7.00 | $7.00 |
| 11 | Drilled dowel bars (416.0620) | EACH | 40 | $21.04 | $18.00 | $18.00 |
| 12 | Tack coat (455.0605) | GAL | 78 | $11.41 | $11.16 | $11.85 |
| 13 | Asphaltic surface (465.0105) | TON | 224 | $193.29 | $189.13 | $198.60 |
| 14 | Concrete collars for pipe (520.8000) | EACH | 2 | $1,410.36 | $858.00 | $1,500.00 |
| 15 | Apron endwalls for culvert pipe salvaged 24-inch (524.0624) | EACH | 1 | $1,083.32 | $943.00 | $1,000.00 |
| 16 | Concrete curb type G (601.0115) | LF | 181 | $97.91 | $38.00 | $38.00 |
| 17 | Concrete curb & gutter 6-inch sloped 30-inch type G (601.0413) | LF | 62 | $69.94 | $41.40 | $41.40 |
| 18 | Concrete curb & gutter 6-inch sloped 36-inch type A (601.0555) | LF | 444 | $71.62 | $52.30 | $52.30 |
| 19 | Concrete sidewalk 5-inch (602.0410) | SF | 2,033 | $10.59 | $7.70 | $7.70 |
| 20 | Curb ramp detectable warning field yellow (602.0505) | SF | 40 | $61.32 | $66.00 | $66.00 |
| 21 | Curb ramp detectable warning field radial yellow (602.0605) | SF | 67 | $76.65 | $79.00 | $79.00 |
| 22 | Storm sewer pipe reinforced concrete class III 24-inch (608.0324) | LF | 4 | $383.25 | $265.50 | $242.00 |
| 23 | Storm sewer pipe reinforced concrete class IV 12-inch (608.0412) | LF | 10 | $250.39 | $164.40 | $143.65 |
| 24 | Inlet covers type HM-S (611.0636) | EACH | 1 | $1,124.20 | $1,099.00 | $1,220.00 |
| 25 | Inlets 2X3-FT (611.3230) | EACH | 1 | $3,449.25 | $3,212.00 | $2,650.00 |
| 26 | Adjusting manhole covers (611.8110) | EACH | 2 | $674.52 | $720.63 | $690.00 |
| 27 | Adjusting inlet covers (611.8115) | EACH | 2 | $602.98 | $720.63 | $622.00 |
| 28 | Mobilization (619.1000) | EACH | 1 | $33,573 | $87,748 | $73,305 |
| 29 | Concrete median sloped nose (620.0300) | SF | 53 | $14.87 | $16.00 | $16.00 |
| 30 | Water (624.0100) | MGAL | 17 | $44.97 | $1.00 | $117.00 |
| 31 | Topsoil (625.0100) | SY | 683 | $10.22 | $9.95 | $14.90 |
| 32 | Mulching (627.0200) | SY | 785 | $0.63 | $0.62 | $0.65 |
| 33 | Silt fence (628.1504) | LF | 1,070 | $2.35 | $2.30 | $2.45 |
| 34 | Silt fence maintenance (628.1520) | LF | 1,070 | $0.08 | $0.08 | $0.08 |
| 35 | Mobilizations erosion control (628.1905) | EACH | 7 | $306.60 | $300.00 | $320.00 |
| 36 | Mobilizations emergency erosion control (628.1910) | EACH | 7 | $51.10 | $50.00 | $50.00 |
| 37 | Erosion mat urban class I type A (628.2006) | SY | 683 | $2.24 | $2.19 | $2.30 |
| 38 | Inlet protection type A (628.7005) | EACH | 4 | $108.33 | $106.00 | $112.40 |
| 39 | Inlet protection type C (628.7015) | EACH | 4 | $73.58 | $72.00 | $76.35 |
| 40 | Culvert pipe checks (628.7555) | EACH | 12 | $21.77 | $21.30 | $22.60 |
| 41 | Fertilizer type B (629.0210) | CWT | 0.95 | $112.42 | $110.00 | $116.65 |
| 42 | Seeding mixture no. 20 (630.0120) | LB | 66.05 | $8.94 | $8.75 | $9.30 |
| 43 | Seed water (630.0500) | MGAL | 16.53 | $25.55 | $25.00 | $26.50 |
| 44 | Markers permanent flexible (633.5350) | EACH | 8 | $75.63 | $74.00 | $78.50 |
| 45 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 22 | $118.55 | $116.00 | $123.00 |
| 46 | Sign flags permanent type II (637.0620) | EACH | 16 | $214.62 | $210.00 | $222.70 |
| 47 | Signs type II reflective H (637.2210) | SF | 147.25 | $29.13 | $28.50 | $30.20 |
| 48 | Signs type II reflective H folding (637.2215) | SF | 50 | $31.99 | $31.30 | $33.20 |
| 49 | Signs type II reflective F (637.2230) | SF | 72 | $28.62 | $28.00 | $29.70 |
| 50 | Moving signs type II (638.2102) | EACH | 2 | $121.62 | $119.00 | $126.20 |
| 51 | Removing signs type II (638.2602) | EACH | 24 | $41.90 | $41.00 | $43.50 |
| 52 | Removing small sign supports (638.3000) | EACH | 10 | $35.05 | $34.30 | $36.40 |
| 53 | Moving small sign supports (638.4000) | EACH | 2 | $127.75 | $125.00 | $132.60 |
| 54 | Field office type B (642.5001) | EACH | 1 | $7,665.00 | $13,300 | $9,600.00 |
| 55 | Traffic control drums (643.0300) | DAY | 5,532 | $0.61 | $0.60 | $0.65 |
| 56 | Traffic control barricades type III (643.0420) | DAY | 592 | $1.02 | $1.00 | $1.05 |
| 57 | Traffic control warning lights type A (643.0705) | DAY | 775 | $0.10 | $0.10 | $0.10 |
| 58 | Traffic control warning lights type C (643.0715) | DAY | 605 | $0.15 | $0.15 | $0.15 |
| 59 | Traffic control connected arrow boards (643.0810) | DAY | 119 | $17.37 | $17.00 | $18.00 |
| 60 | Traffic control signs (643.0900) | DAY | 1,118 | $1.02 | $1.00 | $1.05 |
| 61 | Traffic control covering signs type II (643.0920) | EACH | 8 | $30.66 | $30.00 | $31.85 |
| 62 | Traffic control signs PCMS (643.1050) | DAY | 104 | $30.66 | $30.00 | $31.85 |
| 63 | Traffic control connected work zone start and end location markers (643.1220) | DAY | 119 | $13.03 | $12.75 | $13.50 |
| 64 | Traffic control (643.5000) | EACH | 1 | $2,700.12 | $2,642.00 | $15,000 |
| 65 | Temporary pedestrian surface matting (644.1440) | SF | 220 | $5.11 | $5.00 | $5.30 |
| 66 | Temporary pedestrian barricade (644.1810) | LF | 580 | $5.11 | $5.00 | $5.30 |
| 67 | Marking line epoxy 6-inch (646.2020) | LF | 1,460 | $0.77 | $0.75 | $0.80 |
| 68 | Marking arrow epoxy (646.5020) | EACH | 1 | $332.15 | $325.00 | $344.65 |
| 69 | Marking stop line epoxy 18-inch (646.6120) | LF | 198 | $18.19 | $17.80 | $18.90 |
| 70 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 298 | $10.73 | $10.50 | $11.15 |
| 71 | Marking curb epoxy (646.8120) | LF | 20 | $13.08 | $12.80 | $13.60 |
| 72 | Marking island nose epoxy (646.8220) | EACH | 2 | $357.70 | $350.00 | $371.20 |
| 73 | Marking removal line 6-inch (646.9002) | LF | 419 | $7.92 | $4.00 | $5.00 |
| 74 | Construction staking storm sewer (650.4000) | EACH | 1 | $275.94 | $270.00 | $285.00 |
| 75 | Construction staking base (650.5000) | LF | 110 | $0.01 | $0.01 | $0.01 |
| 76 | Construction staking concrete pavement (650.7000) | LF | 362 | $2.30 | $2.25 | $2.40 |
| 77 | Construction staking electrical installations (project) 01. 8600-00- 74 (650.8501) | EACH | 1 | $792.05 | $775.00 | $822.00 |
| 78 | Construction staking curb ramps (650.9000) | EACH | 4 | $224.84 | $220.00 | $233.30 |
| 79 | Construction staking sidewalk (project) 01. 8600-00-74 (650.9500) | EACH | 1 | $792.05 | $775.00 | $822.00 |
| 80 | Construction staking supplemental control (project) 01. 8600-00-74 (650.9911) | EACH | 1 | $1,737.40 | $1,700.00 | $1,800.00 |
| 81 | Construction staking slope stakes (650.9920) | LF | 300 | $0.01 | $0.01 | $0.01 |
| 82 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 3,086 | $7.15 | $7.00 | $7.40 |
| 83 | Conduit rigid nonmetallic schedule 40 3-inch (652.0235) | LF | 304 | $8.69 | $8.50 | $8.95 |
| 84 | Install conduit into existing item (652.0700.S) | EACH | 14 | $281.05 | $275.00 | $289.00 |
| 85 | Conduit loop detector (652.0800) | LF | 1,367 | $7.15 | $7.00 | $7.40 |
| 86 | Pull boxes steel 24X36-inch (653.0135) | EACH | 18 | $1,277.50 | $1,250.00 | $1,310.00 |
| 87 | Pull boxes steel 24X42-inch (653.0140) | EACH | 19 | $1,328.60 | $1,300.00 | $1,365.00 |
| 88 | Adjusting pull boxes (653.0900) | EACH | 3 | $153.30 | $150.00 | $157.50 |
| 89 | Removing pull boxes (653.0905) | EACH | 22 | $153.30 | $150.00 | $157.50 |
| 90 | Concrete bases type 1 (654.0101) | EACH | 8 | $970.90 | $950.00 | $997.50 |
| 91 | Concrete bases type 2 (654.0102) | EACH | 2 | $1,481.90 | $1,450.00 | $1,522.50 |
| 92 | Concrete bases type 5 (654.0105) | EACH | 16 | $1,226.40 | $1,200.00 | $1,260.00 |
| 93 | Concrete bases type 10-special (654.0120) | EACH | 2 | $11,804 | $11,550 | $12,130 |
| 94 | Concrete control cabinet bases type 9 special (654.0217) | EACH | 1 | $1,967.35 | $1,925.00 | $2,020.00 |
| 95 | Concrete control cabinet bases type L30 (654.0230) | EACH | 1 | $1,635.20 | $1,600.00 | $1,680.00 |
| 96 | Cable traffic signal 5-14 AWG (655.0230) | LF | 1,023 | $2.04 | $2.00 | $2.10 |
| 97 | Cable traffic signal 7-14 AWG (655.0240) | LF | 719 | $2.56 | $2.50 | $2.65 |
| 98 | Cable traffic signal 12-14 AWG (655.0260) | LF | 1,629 | $3.68 | $3.60 | $3.80 |
| 99 | Cable type UF 2-12 AWG grounded (655.0305) | LF | 2,612 | $2.30 | $2.25 | $2.35 |
| 100 | Cable type UF 2-10 AWG grounded (655.0320) | LF | 4,076 | $3.07 | $3.00 | $3.15 |
| 101 | Electrical wire traffic signals 10 AWG (655.0515) | LF | 1,584 | $1.43 | $1.40 | $1.50 |
| 102 | Electrical wire lighting 12 AWG (655.0610) | LF | 2,880 | $1.28 | $1.25 | $1.30 |
| 103 | Loop detector lead in cable (655.0700) | LF | 6,971 | $1.53 | $1.50 | $1.60 |
| 104 | Loop detector wire (655.0800) | LF | 4,618 | $1.33 | $1.30 | $1.40 |
| 105 | Traffic signal evp detector cable (655.0900) | LF | 1,037 | $1.33 | $1.30 | $1.40 |
| 106 | Electrical service meter breaker pedestal (location) 01. STH 178 & cashman drive (656.0201) | EACH | 1 | $2,146.20 | $2,100.00 | $2,205.00 |
| 107 | Electrical service meter breaker pedestal (location) 02. STH 178 & olson drive (656.0201) | EACH | 1 | $2,146.20 | $2,100.00 | $2,205.00 |
| 108 | Pedestal bases (657.0100) | EACH | 8 | $357.70 | $350.00 | $367.50 |
| 109 | Transformer bases breakaway 11 1/2-inch bolt circle (657.0255) | EACH | 18 | $730.73 | $715.00 | $750.00 |
| 110 | Poles type 3 (657.0310) | EACH | 2 | $3,699.64 | $3,620.00 | $3,800.00 |
| 111 | Poles type 5-aluminum (657.0322) | EACH | 16 | $2,197.30 | $2,150.00 | $2,260.00 |
| 112 | Poles type 10-special (657.0352) | EACH | 2 | $12,673 | $12,400 | $13,020 |
| 113 | Traffic signal standards aluminum 15-FT (657.0425) | EACH | 8 | $991.34 | $970.00 | $1,020.00 |
| 114 | Monotube arms 45-FT-special (657.0546) | EACH | 2 | $7,154.00 | $7,000.00 | $7,350.00 |
| 115 | Trombone arms 25-FT (657.0595) | EACH | 2 | $2,483.46 | $2,430.00 | $2,550.00 |
| 116 | Luminaire arms truss type 4-inch clamp 15-FT (657.0714) | EACH | 2 | $889.14 | $870.00 | $915.00 |
| 117 | Luminaire arms truss type 4 1/2- inch clamp 15-FT (657.0715) | EACH | 16 | $873.81 | $855.00 | $900.00 |
| 118 | Luminaire arms steel 15-FT (657.0815) | EACH | 2 | $1,154.86 | $1,130.00 | $1,185.00 |
| 119 | Traffic signal face 3S 12-inch (658.0173) | EACH | 14 | $924.91 | $905.00 | $950.00 |
| 120 | Traffic signal face 4S 12-inch (658.0174) | EACH | 6 | $1,328.60 | $1,300.00 | $1,365.00 |
| 121 | Pedestrian signal face 16-inch (658.0416) | EACH | 2 | $613.20 | $600.00 | $630.00 |
| 122 | Signal mounting hardware (location) 01. STH 178 & olson drive (658.5070) | EACH | 1 | $4,813.62 | $4,710.00 | $4,950.00 |
| 123 | Luminaires utility LED A (659.1115) | EACH | 12 | $378.14 | $370.00 | $390.00 |
| 124 | Luminaires utility LED C (659.1125) | EACH | 8 | $413.91 | $405.00 | $425.00 |
| 125 | Lighting control cabinets 120/240 30-inch (659.2130) | EACH | 1 | $8,610.35 | $8,425.00 | $8,845.00 |
| 126 | Sawing asphalt (690.0150) | LF | 99 | $1.99 | $1.80 | $3.95 |
| 127 | Sawing concrete (690.0250) | LF | 1,050 | $2.61 | $2.35 | $5.40 |
| 128 | Incentive compressive strength concrete pavement (715.0720) | DOL | 650 | $1.00 | $1.00 | $1.00 |
| 129 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 300 | $5.00 | $5.00 | $5.00 |
| 130 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 300 | $5.00 | $5.00 | $5.00 |
| 131 | Special 01. install state furnished evp detector heads (SPV.0060) | EACH | 1 | $255.50 | $250.00 | $265.00 |
| 132 | Special 02. adjusting water valves (SPV.0060) | EACH | 4 | $321.93 | $396.50 | $265.00 |
| 133 | Special 03. adjusting sanitary manhole covers (SPV.0060) | EACH | 1 | $674.52 | $743.00 | $810.00 |
| 134 | Special 04. abandoning sanitary manholes (SPV.0060) | EACH | 1 | $2,227.96 | $1,204.00 | $4,055.00 |
| 135 | Special 05. utility line opening (SPV.0060) | EACH | 8 | $924.91 | $1,500.00 | $675.00 |
| 136 | Special 06. install state furnished APS push button stations (SPV.0060) | EACH | 2 | $127.75 | $125.00 | $131.30 |
| 137 | Special 07. clean existing pull boxes (SPV.0060) | EACH | 8 | $127.75 | $125.00 | $131.30 |
| 138 | Special 08. bell ends for rigid non- metallic conduit (SPV.0060) | EACH | 55 | $1.02 | $1.00 | $1.05 |
| 139 | Special 09. test existing loops (SPV.0060) | EACH | 16 | $178.85 | $175.00 | $185.00 |
| 140 | Special 01. concrete curb & gutter 18-inch type G special (SPV.0090) | LF | 292 | $59.75 | $46.00 | $46.00 |
| 141 | Special 02. install cat-5E cable (SPV.0090) | LF | 453 | $1.02 | $1.00 | $1.05 |
| 142 | Special 03. clean and proof existing conduit (SPV.0090) | LF | 1,495 | $3.07 | $3.00 | $3.15 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of November 11, 2025. Compiled by Mirage Metrics.