WisDOT contract 20251111034 bid tabulation

Chippewa Falls - Cornell; Olson Drive to Cashman Drive (STH 178, Chippewa County Chippewa Falls - Cornell). Let by Wisconsin DOT on November 11, 2025, Chippewa. 3 bids received; low bid $1,010,984 by Chippewa Concrete Services, Inc..

Owner
Wisconsin DOT
Letting
11 NOV 2025
Pay items
142
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Chippewa Concrete Services, Inc.$1,010,984Low
2Haas Sons, Inc.$1,026,262+2.0%
3Pember Companies, Inc.$1,103,298+9.0%
WisDOT contract 20251111034: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Chippewa Concrete Services, Inc.2. Haas Sons, Inc.3. Pember Companies, Inc.
1Removing concrete pavement (204.0100)SY2,098$11.14$4.33$15.75
2Removing concrete sidewalk (204.0155)SY19$27.29$10.79$11.65
3Removing inlets (204.0220)EACH1$945.35$1,084.00$880.00
4Excavation common (205.0100)CY1,485$17.89$26.21$35.00
5Finishing roadway (project) 01. 8600-00-74 (213.0100)EACH1$5,110.00$1.00$500.00
6Base aggregate dense 3/4-inch (305.0110)TON14$89.94$86.60$42.00
7Base aggregate dense 1 1/4-inch (305.0120)TON1,328$22.13$29.24$37.20
8Concrete pavement 9-inch (415.0090)SY2,162$106.37$104.00$103.50
9Concrete pavement joint filling (415.4100)SY2,404$5.01$6.36$8.90
10Drilled tie bars (416.0610)EACH220$16.38$7.00$7.00
11Drilled dowel bars (416.0620)EACH40$21.04$18.00$18.00
12Tack coat (455.0605)GAL78$11.41$11.16$11.85
13Asphaltic surface (465.0105)TON224$193.29$189.13$198.60
14Concrete collars for pipe (520.8000)EACH2$1,410.36$858.00$1,500.00
15Apron endwalls for culvert pipe salvaged 24-inch (524.0624)EACH1$1,083.32$943.00$1,000.00
16Concrete curb type G (601.0115)LF181$97.91$38.00$38.00
17Concrete curb & gutter 6-inch sloped 30-inch type G (601.0413)LF62$69.94$41.40$41.40
18Concrete curb & gutter 6-inch sloped 36-inch type A (601.0555)LF444$71.62$52.30$52.30
19Concrete sidewalk 5-inch (602.0410)SF2,033$10.59$7.70$7.70
20Curb ramp detectable warning field yellow (602.0505)SF40$61.32$66.00$66.00
21Curb ramp detectable warning field radial yellow (602.0605)SF67$76.65$79.00$79.00
22Storm sewer pipe reinforced concrete class III 24-inch (608.0324)LF4$383.25$265.50$242.00
23Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF10$250.39$164.40$143.65
24Inlet covers type HM-S (611.0636)EACH1$1,124.20$1,099.00$1,220.00
25Inlets 2X3-FT (611.3230)EACH1$3,449.25$3,212.00$2,650.00
26Adjusting manhole covers (611.8110)EACH2$674.52$720.63$690.00
27Adjusting inlet covers (611.8115)EACH2$602.98$720.63$622.00
28Mobilization (619.1000)EACH1$33,573$87,748$73,305
29Concrete median sloped nose (620.0300)SF53$14.87$16.00$16.00
30Water (624.0100)MGAL17$44.97$1.00$117.00
31Topsoil (625.0100)SY683$10.22$9.95$14.90
32Mulching (627.0200)SY785$0.63$0.62$0.65
33Silt fence (628.1504)LF1,070$2.35$2.30$2.45
34Silt fence maintenance (628.1520)LF1,070$0.08$0.08$0.08
35Mobilizations erosion control (628.1905)EACH7$306.60$300.00$320.00
36Mobilizations emergency erosion control (628.1910)EACH7$51.10$50.00$50.00
37Erosion mat urban class I type A (628.2006)SY683$2.24$2.19$2.30
38Inlet protection type A (628.7005)EACH4$108.33$106.00$112.40
39Inlet protection type C (628.7015)EACH4$73.58$72.00$76.35
40Culvert pipe checks (628.7555)EACH12$21.77$21.30$22.60
41Fertilizer type B (629.0210)CWT0.95$112.42$110.00$116.65
42Seeding mixture no. 20 (630.0120)LB66.05$8.94$8.75$9.30
43Seed water (630.0500)MGAL16.53$25.55$25.00$26.50
44Markers permanent flexible (633.5350)EACH8$75.63$74.00$78.50
45Posts wood 4X6-inch X 16-FT (634.0616)EACH22$118.55$116.00$123.00
46Sign flags permanent type II (637.0620)EACH16$214.62$210.00$222.70
47Signs type II reflective H (637.2210)SF147.25$29.13$28.50$30.20
48Signs type II reflective H folding (637.2215)SF50$31.99$31.30$33.20
49Signs type II reflective F (637.2230)SF72$28.62$28.00$29.70
50Moving signs type II (638.2102)EACH2$121.62$119.00$126.20
51Removing signs type II (638.2602)EACH24$41.90$41.00$43.50
52Removing small sign supports (638.3000)EACH10$35.05$34.30$36.40
53Moving small sign supports (638.4000)EACH2$127.75$125.00$132.60
54Field office type B (642.5001)EACH1$7,665.00$13,300$9,600.00
55Traffic control drums (643.0300)DAY5,532$0.61$0.60$0.65
56Traffic control barricades type III (643.0420)DAY592$1.02$1.00$1.05
57Traffic control warning lights type A (643.0705)DAY775$0.10$0.10$0.10
58Traffic control warning lights type C (643.0715)DAY605$0.15$0.15$0.15
59Traffic control connected arrow boards (643.0810)DAY119$17.37$17.00$18.00
60Traffic control signs (643.0900)DAY1,118$1.02$1.00$1.05
61Traffic control covering signs type II (643.0920)EACH8$30.66$30.00$31.85
62Traffic control signs PCMS (643.1050)DAY104$30.66$30.00$31.85
63Traffic control connected work zone start and end location markers (643.1220)DAY119$13.03$12.75$13.50
64Traffic control (643.5000)EACH1$2,700.12$2,642.00$15,000
65Temporary pedestrian surface matting (644.1440)SF220$5.11$5.00$5.30
66Temporary pedestrian barricade (644.1810)LF580$5.11$5.00$5.30
67Marking line epoxy 6-inch (646.2020)LF1,460$0.77$0.75$0.80
68Marking arrow epoxy (646.5020)EACH1$332.15$325.00$344.65
69Marking stop line epoxy 18-inch (646.6120)LF198$18.19$17.80$18.90
70Marking crosswalk epoxy transverse line 6-inch (646.7420)LF298$10.73$10.50$11.15
71Marking curb epoxy (646.8120)LF20$13.08$12.80$13.60
72Marking island nose epoxy (646.8220)EACH2$357.70$350.00$371.20
73Marking removal line 6-inch (646.9002)LF419$7.92$4.00$5.00
74Construction staking storm sewer (650.4000)EACH1$275.94$270.00$285.00
75Construction staking base (650.5000)LF110$0.01$0.01$0.01
76Construction staking concrete pavement (650.7000)LF362$2.30$2.25$2.40
77Construction staking electrical installations (project) 01. 8600-00- 74 (650.8501)EACH1$792.05$775.00$822.00
78Construction staking curb ramps (650.9000)EACH4$224.84$220.00$233.30
79Construction staking sidewalk (project) 01. 8600-00-74 (650.9500)EACH1$792.05$775.00$822.00
80Construction staking supplemental control (project) 01. 8600-00-74 (650.9911)EACH1$1,737.40$1,700.00$1,800.00
81Construction staking slope stakes (650.9920)LF300$0.01$0.01$0.01
82Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF3,086$7.15$7.00$7.40
83Conduit rigid nonmetallic schedule 40 3-inch (652.0235)LF304$8.69$8.50$8.95
84Install conduit into existing item (652.0700.S)EACH14$281.05$275.00$289.00
85Conduit loop detector (652.0800)LF1,367$7.15$7.00$7.40
86Pull boxes steel 24X36-inch (653.0135)EACH18$1,277.50$1,250.00$1,310.00
87Pull boxes steel 24X42-inch (653.0140)EACH19$1,328.60$1,300.00$1,365.00
88Adjusting pull boxes (653.0900)EACH3$153.30$150.00$157.50
89Removing pull boxes (653.0905)EACH22$153.30$150.00$157.50
90Concrete bases type 1 (654.0101)EACH8$970.90$950.00$997.50
91Concrete bases type 2 (654.0102)EACH2$1,481.90$1,450.00$1,522.50
92Concrete bases type 5 (654.0105)EACH16$1,226.40$1,200.00$1,260.00
93Concrete bases type 10-special (654.0120)EACH2$11,804$11,550$12,130
94Concrete control cabinet bases type 9 special (654.0217)EACH1$1,967.35$1,925.00$2,020.00
95Concrete control cabinet bases type L30 (654.0230)EACH1$1,635.20$1,600.00$1,680.00
96Cable traffic signal 5-14 AWG (655.0230)LF1,023$2.04$2.00$2.10
97Cable traffic signal 7-14 AWG (655.0240)LF719$2.56$2.50$2.65
98Cable traffic signal 12-14 AWG (655.0260)LF1,629$3.68$3.60$3.80
99Cable type UF 2-12 AWG grounded (655.0305)LF2,612$2.30$2.25$2.35
100Cable type UF 2-10 AWG grounded (655.0320)LF4,076$3.07$3.00$3.15
101Electrical wire traffic signals 10 AWG (655.0515)LF1,584$1.43$1.40$1.50
102Electrical wire lighting 12 AWG (655.0610)LF2,880$1.28$1.25$1.30
103Loop detector lead in cable (655.0700)LF6,971$1.53$1.50$1.60
104Loop detector wire (655.0800)LF4,618$1.33$1.30$1.40
105Traffic signal evp detector cable (655.0900)LF1,037$1.33$1.30$1.40
106Electrical service meter breaker pedestal (location) 01. STH 178 & cashman drive (656.0201)EACH1$2,146.20$2,100.00$2,205.00
107Electrical service meter breaker pedestal (location) 02. STH 178 & olson drive (656.0201)EACH1$2,146.20$2,100.00$2,205.00
108Pedestal bases (657.0100)EACH8$357.70$350.00$367.50
109Transformer bases breakaway 11 1/2-inch bolt circle (657.0255)EACH18$730.73$715.00$750.00
110Poles type 3 (657.0310)EACH2$3,699.64$3,620.00$3,800.00
111Poles type 5-aluminum (657.0322)EACH16$2,197.30$2,150.00$2,260.00
112Poles type 10-special (657.0352)EACH2$12,673$12,400$13,020
113Traffic signal standards aluminum 15-FT (657.0425)EACH8$991.34$970.00$1,020.00
114Monotube arms 45-FT-special (657.0546)EACH2$7,154.00$7,000.00$7,350.00
115Trombone arms 25-FT (657.0595)EACH2$2,483.46$2,430.00$2,550.00
116Luminaire arms truss type 4-inch clamp 15-FT (657.0714)EACH2$889.14$870.00$915.00
117Luminaire arms truss type 4 1/2- inch clamp 15-FT (657.0715)EACH16$873.81$855.00$900.00
118Luminaire arms steel 15-FT (657.0815)EACH2$1,154.86$1,130.00$1,185.00
119Traffic signal face 3S 12-inch (658.0173)EACH14$924.91$905.00$950.00
120Traffic signal face 4S 12-inch (658.0174)EACH6$1,328.60$1,300.00$1,365.00
121Pedestrian signal face 16-inch (658.0416)EACH2$613.20$600.00$630.00
122Signal mounting hardware (location) 01. STH 178 & olson drive (658.5070)EACH1$4,813.62$4,710.00$4,950.00
123Luminaires utility LED A (659.1115)EACH12$378.14$370.00$390.00
124Luminaires utility LED C (659.1125)EACH8$413.91$405.00$425.00
125Lighting control cabinets 120/240 30-inch (659.2130)EACH1$8,610.35$8,425.00$8,845.00
126Sawing asphalt (690.0150)LF99$1.99$1.80$3.95
127Sawing concrete (690.0250)LF1,050$2.61$2.35$5.40
128Incentive compressive strength concrete pavement (715.0720)DOL650$1.00$1.00$1.00
129On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS300$5.00$5.00$5.00
130On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS300$5.00$5.00$5.00
131Special 01. install state furnished evp detector heads (SPV.0060)EACH1$255.50$250.00$265.00
132Special 02. adjusting water valves (SPV.0060)EACH4$321.93$396.50$265.00
133Special 03. adjusting sanitary manhole covers (SPV.0060)EACH1$674.52$743.00$810.00
134Special 04. abandoning sanitary manholes (SPV.0060)EACH1$2,227.96$1,204.00$4,055.00
135Special 05. utility line opening (SPV.0060)EACH8$924.91$1,500.00$675.00
136Special 06. install state furnished APS push button stations (SPV.0060)EACH2$127.75$125.00$131.30
137Special 07. clean existing pull boxes (SPV.0060)EACH8$127.75$125.00$131.30
138Special 08. bell ends for rigid non- metallic conduit (SPV.0060)EACH55$1.02$1.00$1.05
139Special 09. test existing loops (SPV.0060)EACH16$178.85$175.00$185.00
140Special 01. concrete curb & gutter 18-inch type G special (SPV.0090)LF292$59.75$46.00$46.00
141Special 02. install cat-5E cable (SPV.0090)LF453$1.02$1.00$1.05
142Special 03. clean and proof existing conduit (SPV.0090)LF1,495$3.07$3.00$3.15
WisDOT contract 20251111034: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of November 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy