Temporary lane shift during culvert work, WisDOT 208.1500.S

Low bidders on WisDOT contracts carried a median of $3,675.00 per EACH for this item, over the 24 months to 10 NOV 2026, across 18 low bids. Half of all 49 bids fell between $2,055.00 and $6,810.50.

Owner
Wisconsin DOT
Item
208.1500.S
Unit
EACH
Data through
10 NOV 2026

WisDOT prints this item as “Temporary Lane Shift During Culvert Work”.

$3,675.00Low bidder's median, per EACH
$5,000.00Median of all bids, per EACH
20Contracts in the window

By year of letting

Temporary lane shift during culvert work, WisDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20221817$5,000.0037$5,000.00
20231816$2,448.0536$2,475.00
2024119$3,030.0020$3,057.14
202598$2,180.5016$2,380.50
202698$5,766.0026$5,996.00

Bid prices as published, not adjusted for inflation.

By quantity

Quantity (EACH)Low bidsLow-bid median
1 to 24$3,777.50
3 to 55$5,000.00
7 to 134$4,146.50
21 to 465$2,100.00
Temporary lane shift during culvert work, WisDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

Temporary lane shift during culvert work, WisDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
13 OCT 202620261013026Taylor4$3,250.00$3,250.001American Asphalt of WisconsinWisDOT
13 OCT 202620261013028Polk21$11,549$11,5491Monarch Paving CompanyWisDOT
15 SEP 202620260915014Waupaca13$6,032.00$6,032.002Northeast Asphalt, IncWisDOT
15 SEP 202620260915019Oneida33$741.13$741.134Musson Bros., Inc.WisDOT
11 AUG 202620260811004Richland2$2,000.00$10,8763Mathy Construction CompanyWisDOT
11 AUG 202620260811005Vernon11n/a$4,867.304Hoffman Construction CompanyWisDOT
12 MAY 202620260512015Barron7$10,036$10,0361Monarch Paving CompanyWisDOT
10 MAR 202620260310012Dane2$5,500.00$5,500.005Parisi Construction, LLCWisDOT
13 JAN 202620260113055Bayfield1$6,810.50$7,860.005Northern Interstate Construction, Inc.WisDOT
09 DEC 202520251209042Polk2$2,055.00$2,055.001Monarch Paving CompanyWisDOT
11 NOV 202520251111028Ashland46$3,500.00$1,628.003James Peterson Sons, Inc.WisDOT
14 OCT 202520251014003Lafayette6n/a$2,700.001Zignego Company, Inc.WisDOT
12 AUG 202520250812019Oneida42$1,772.86$1,772.862Pitlik & Wick, Inc.WisDOT
10 JUN 202520250610008Vilas26$2,100.00$2,500.003Pitlik & Wick, Inc.WisDOT
08 APR 202520250408019Price7$2,261.00$2,261.001American Asphalt of WisconsinWisDOT
Latest WisDOT contracts carrying Temporary lane shift during culvert work

Filter this item by your own quantity, county and period, or check your price against it, in the WisDOT explorer.

How these prices were read

WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WisDOT's own: this item is compared with WisDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the WisDOT letting of 10 NOV 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy