| 1 | Removing small pipe culverts (203.0100) | EACH | 34 | $327.00 |
| 2 | Removing concrete surface partial depth (204.0109.S) | SF | 7,090 | $2.21 |
| 3 | Removing asphaltic surface butt joints (204.0115) | SY | 3,200 | $6.96 |
| 4 | Removing asphaltic surface milling (204.0120) | SY | 36,000 | $6.04 |
| 5 | Removing curb & gutter (204.0150) | LF | 962 | $11.00 |
| 6 | Removing concrete sidewalk (204.0155) | SY | 301 | $11.40 |
| 7 | Removing guardrail (204.0165) | LF | 9,348 | $2.00 |
| 8 | Excavation common (205.0100) | CY | 5,591 | $9.05 |
| 9 | Cofferdams (structure) 01. culvert 10 (206.5001) | EACH | 1 | $27,241 |
| 10 | Cofferdams (structure) 02. culvert 11 (206.5001) | EACH | 1 | $27,241 |
| 11 | Borrow (208.0100) | CY | 5,372 | $20.00 |
| 12 | Temporary lane shift during culvert work (208.1500.S) | EACH | 2 | $2,055.00 |
| 13 | Backfill granular grade 1 (209.1100) | CY | 1,730 | $20.60 |
| 14 | Prepare foundation for asphaltic paving (project) 01. 8030-00-70 (211.0101) | EACH | 1 | $47,395 |
| 15 | Prepare foundation for cir base layer (project) 01. 8030-00-70 (211.0700.S) | EACH | 1 | $42,688 |
| 16 | Base repair for cir layer (211.0800.S) | CY | 750 | $119.36 |
| 17 | Finishing roadway (project) 01. 8030-00-70 (213.0100) | EACH | 1 | $4,988.00 |
| 18 | Base aggregate dense 3/4-inch (305.0110) | TON | 6,760 | $31.15 |
| 19 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 2,640 | $26.05 |
| 20 | Shaping shoulders (305.0500) | STA | 568 | $29.10 |
| 21 | Select crushed material (312.0110) | TON | 930 | $32.20 |
| 22 | Cir asphaltic base layer (327.1000.S) | SY | 204,090 | $3.58 |
| 23 | Tack coat (455.0605) | GAL | 33,830 | $3.08 |
| 24 | Asphalt stabilizing agent (455.0770.S) | TON | 1,060 | $350.00 |
| 25 | HMA percent within limits (PWL) test strip volumetrics (460.0105.S) | EACH | 1 | $12,230 |
| 26 | HMA percent within limits (PWL) test strip density (460.0110.S) | EACH | 1 | $2,220.00 |
| 27 | Incentive density HMA pavement (460.2000) | DOL | 2,380 | $1.00 |
| 28 | Incentive density PWL HMA pavement (460.2005) | DOL | 22,935 | $1.00 |
| 29 | Incentive density HMA pavement longitudinal joints (460.2007) | DOL | 22,340 | $1.00 |
| 30 | Incentive air voids HMA pavement (460.2010) | DOL | 32,460 | $1.00 |
| 31 | HMA pavement 5 MT 58-28 S (460.6225) | TON | 36,890 | $97.45 |
| 32 | Material transfer vehicle 01. 8030- 00-70 (460.9000.S) | EACH | 1 | $22,600 |
| 33 | Asphaltic surface (465.0105) | TON | 500 | $128.97 |
| 34 | Asphaltic surface patching (465.0110) | TON | 150 | $251.23 |
| 35 | Asphaltic surface driveways and field entrances (465.0120) | TON | 375 | $175.21 |
| 36 | Asphaltic rumble strips, shoulder (465.0520) | LF | 69,150 | $0.28 |
| 37 | Asphaltic rumble strips, centerline (465.0560) | LF | 47,765 | $0.30 |
| 38 | Concrete collars for pipe (520.8000) | EACH | 3 | $2,855.00 |
| 39 | Cleaning culvert pipes (520.8700) | EACH | 17 | $2,850.00 |
| 40 | Culvert pipe liners (size) 01. 24- inch (520.9700.S) | LF | 292 | $137.00 |
| 41 | Culvert pipe liners (size) 02. 30- inch (520.9700.S) | LF | 320 | $162.50 |
| 42 | Culvert pipe liners (size) 03. 36- inch (520.9700.S) | LF | 160 | $248.00 |
| 43 | Cleaning culvert pipes for liner verification (520.9750.S) | EACH | 5 | $250.00 |
| 44 | Apron endwalls for culvert pipe steel 24-inch (521.1024) | EACH | 23 | $521.00 |
| 45 | Apron endwalls for culvert pipe steel 30-inch (521.1030) | EACH | 2 | $802.50 |
| 46 | Apron endwalls for culvert pipe steel 36-inch (521.1036) | EACH | 4 | $1,025.00 |
| 47 | Apron endwalls for culvert pipe steel 48-inch (521.1048) | EACH | 2 | $1,855.00 |
| 48 | Culvert pipe corrugated steel 24- inch (521.3124) | LF | 218 | $139.50 |
| 49 | Culvert pipe reinforced concrete class IV 24-inch (522.0424) | LF | 148 | $179.50 |
| 50 | Culvert pipe reinforced concrete class IV 30-inch (522.0430) | LF | 64 | $220.50 |
| 51 | Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012) | EACH | 1 | $1,152.00 |
| 52 | Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024) | EACH | 26 | $1,533.00 |
| 53 | Apron endwalls for culvert pipe reinforced concrete 30-inch (522.1030) | EACH | 2 | $1,876.00 |
| 54 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 962 | $67.64 |
| 55 | Concrete curb pedestrian (601.0600) | LF | 124 | $49.44 |
| 56 | Concrete sidewalk 5-inch (602.0410) | SF | 3,090 | $13.45 |
| 57 | Curb ramp detectable warning field yellow (602.0505) | SF | 180 | $62.51 |
| 58 | Curb ramp detectable warning field radial yellow (602.0605) | SF | 58 | $67.84 |
| 59 | Riprap medium (606.0200) | CY | 40 | $97.50 |
| 60 | Riprap heavy (606.0300) | CY | 722 | $70.00 |
| 61 | Adjusting manhole covers (611.8110) | EACH | 10 | $985.00 |
| 62 | Adjusting inlet covers (611.8115) | EACH | 11 | $808.00 |
| 63 | Cover plates temporary (611.8120.S) | EACH | 20 | $10.00 |
| 64 | MGS guardrail 3 (614.2300) | LF | 1,925 | $22.05 |
| 65 | MGS guardrail 3 K (614.2330) | LF | 5,350 | $35.75 |
| 66 | MGS guardrail 3 L (614.2340) | LF | 187.50 | $26.05 |
| 67 | MGS guardrail terminal eat (614.2610) | EACH | 32 | $3,470.00 |
| 68 | Maintenance and repair of haul roads (project) 01. 8030-00-70 (618.0100) | EACH | 1 | $1.00 |
| 69 | Mobilization (619.1000) | EACH | 1 | $429,744 |
| 70 | Water (624.0100) | MGAL | 140 | $31.07 |
| 71 | Salvaged topsoil (625.0500) | SY | 15,509 | $1.55 |
| 72 | Mulching (627.0200) | SY | 500 | $1.00 |
| 73 | Erosion bales (628.1104) | EACH | 120 | $15.00 |
| 74 | Silt fence (628.1504) | LF | 2,838 | $4.50 |
| 75 | Silt fence maintenance (628.1520) | LF | 2,838 | $0.01 |
| 76 | Mobilizations erosion control (628.1905) | EACH | 5 | $700.00 |
| 77 | Mobilizations emergency erosion control (628.1910) | EACH | 2 | $10.00 |
| 78 | Erosion mat urban class I type B (628.2008) | SY | 16,474 | $1.74 |
| 79 | Turbidity barriers (628.6005) | SY | 1,440 | $42.45 |
| 80 | Inlet protection type C (628.7015) | EACH | 9 | $40.00 |
| 81 | Temporary ditch checks (628.7504) | LF | 374 | $6.95 |
| 82 | Culvert pipe checks (628.7555) | EACH | 155 | $15.00 |
| 83 | Rock bags (628.7570) | EACH | 100 | $15.00 |
| 84 | Fertilizer type B (629.0210) | CWT | 9.80 | $88.00 |
| 85 | Seeding mixture no. 30 (630.0130) | LB | 418.70 | $15.55 |
| 86 | Seed water (630.0500) | MGAL | 100 | $1.00 |
| 87 | Markers culvert end (633.5200) | EACH | 73 | $58.00 |
| 88 | Moving signs type II (638.2102) | EACH | 12 | $73.00 |
| 89 | Moving small sign supports (638.4000) | EACH | 11 | $73.00 |
| 90 | Field office type B (642.5001) | EACH | 1 | $23,940 |
| 91 | Traffic control drums (643.0300) | DAY | 144,772 | $0.24 |
| 92 | Traffic control barricades type III (643.0420) | DAY | 2,059 | $0.50 |
| 93 | Traffic control warning lights type A (643.0705) | DAY | 2,952 | $0.10 |
| 94 | Traffic control warning lights type C (643.0715) | DAY | 1,000 | $0.10 |
| 95 | Traffic control signs (643.0900) | DAY | 12,900 | $0.47 |
| 96 | Traffic control covering signs type II (643.0920) | EACH | 10 | $30.00 |
| 97 | Traffic control signs fixed message (643.1000) | SF | 54 | $9.60 |
| 98 | Traffic control speed feedback trailer (643.1500) | DAY | 540 | $26.00 |
| 99 | Temporary marking line paint 6- inch (643.3165) | LF | 181,227 | $0.22 |
| 100 | Temporary marking line epoxy 6- inch (643.3170) | LF | 34,134 | $0.55 |
| 101 | Temporary marking crosswalk removable tape 6-inch (643.3350) | LF | 460 | $1.69 |
| 102 | Traffic control (643.5000) | EACH | 1 | $231,947 |
| 103 | Temporary pedestrian surface matting (644.1440) | SF | 800 | $5.00 |
| 104 | Temporary pedestrian curb ramp (644.1601) | DAY | 450 | $4.00 |
| 105 | Temporary pedestrian barricade (644.1810) | LF | 90 | $4.00 |
| 106 | Temporary audible message devices (644.1900.S) | DAY | 222 | $4.00 |
| 107 | Geotextile type R (645.0130) | SY | 3,250 | $2.85 |
| 108 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 202,663 | $1.23 |
| 109 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 547 | $2.00 |
| 110 | Marking arrow epoxy (646.5020) | EACH | 4 | $325.00 |
| 111 | Marking word epoxy (646.5120) | EACH | 2 | $330.00 |
| 112 | Marking stop line epoxy 18-inch (646.6120) | LF | 318 | $20.00 |
| 113 | Marking yield line epoxy 18-inch (646.6220) | EACH | 40 | $140.00 |
| 114 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 1,046 | $14.00 |
| 115 | Marking curb epoxy (646.8120) | LF | 1,157 | $6.00 |
| 116 | Marking parking stall epoxy (646.8320) | LF | 950 | $10.00 |
| 117 | Locating no-passing zones (648.0100) | MI | 11.40 | $315.00 |
| 118 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 962 | $1.20 |
| 119 | Construction staking pipe culverts (650.6000) | EACH | 8 | $225.00 |
| 120 | Construction staking resurfacing reference (650.8000) | LF | 60,409 | $0.05 |
| 121 | Construction staking curb ramps (650.9000) | EACH | 16 | $175.00 |
| 122 | Construction staking supplemental control (project) 01. 8030-00-70 (650.9911) | EACH | 1 | $573.65 |
| 123 | Construction staking slope stakes (650.9920) | LF | 7,463 | $0.50 |
| 124 | Sawing asphalt (690.0150) | LF | 1,300 | $1.95 |
| 125 | Sawing concrete (690.0250) | LF | 120 | $2.95 |
| 126 | Incentive iri ride (740.0440) | DOL | 45,680 | $1.00 |
| 127 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,500 | $5.00 |
| 128 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 2,000 | $5.00 |
| 129 | Special 01. resetting pipe end sections (SPV.0060) | EACH | 41 | $1,150.00 |
| 130 | Special 02. adjusting water valves (SPV.0060) | EACH | 21 | $785.00 |
| 131 | Special 01. ditch cleaning (SPV.0090) | LF | 400 | $12.15 |