WisDOT contract 20260811005 bid tabulation

5865-02-64. Let by Wisconsin DOT on August 11, 2026, Vernon. 5 bids received; low bid $7,123,105 by Hoffman Construction Company.

Owner
Wisconsin DOT
Letting
11 AUG 2026
Pay items
200
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Hoffman Construction Company$7,123,105Low
2James Peterson Sons, Inc.$7,390,553+4.0%
3Gerke Excavating Inc$7,531,737+6.0%
4A-1 Excavating LLC$7,654,321+7.0%
5Integrity Grading and Excavating, Inc.$8,830,433+24%
WisDOT contract 20260811005: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Hoffman Construction Company2. James Peterson Sons, Inc.3. Gerke Excavating Inc4. A-1 Excavating LLC5. Integrity Grading and Excavating, Inc.
1Clearing (201.0105)STA26$1,150.00$1,150.00$1,207.50$1,200.00$1,150.00
2Grubbing (201.0205)STA26$650.00$650.00$682.50$700.00$650.00
3Removing small pipe culverts (203.0100)EACH12$1,000.00$1,430.00$229.02$700.00$1,750.86
4Removing structure (structure) 01. C-62-302 (203.0220)EACH1$10,695$17,883$11,230$8,000.00$10,695
5Removing structure (structure) 02. B-62-984 (203.0220)EACH1$92,000$92,000$96,600$95,000$92,000
6Removing asphaltic surface (204.0110)SY357$5.00$10.10$6.43$9.00$16.01
7Removing asphaltic surface butt joints (204.0115)SY1,138$3.00$3.00$3.44$4.00$3.00
8Removing curb & gutter (204.0150)LF650$4.00$10.00$7.06$6.00$8.67
9Removing concrete sidewalk (204.0155)SY199$7.50$10.00$10.79$12.00$16.55
10Removing guardrail (204.0165)LF8,364$2.65$2.50$2.78$2.75$2.65
11Removing cable barrier (204.0167)LF1,460$3.00$3.50$3.15$3.50$3.00
12Excavation common (205.0100)CY15,754$20.50$26.34$15.84$28.00$38.57
13Excavation for structures bridges (structure) 01. B-62-984 (206.1001)EACH1$1,505.00$28,000$29,400$30,000$28,000
14Excavation for structures culverts (structure) 01. C-62-335 (206.2001)EACH1$75,000$13,000$25,578$38,500$27,360
15Temporary lane shift during culvert work (208.1500.S)EACH11$0.01$8,200.00$7,588.61$500.00$2,145.99
16Backfill granular grade 2 (209.2500)TON4,650$26.50$17.28$33.65$38.00$36.16
17Backfill structure type A (210.1500)TON171$30.00$90.00$94.50$100.00$90.00
18Backfill structure type B (210.2500)TON1,153$25.00$29.17$22.05$35.00$21.00
19Prepare foundation for asphaltic paving (project) 01. 5865-02-64 (211.0101)EACH1$68,914$68,914$72,360$69,414$68,914
20Prepare foundation for asphaltic shoulders (211.0400)STA487$57.83$57.83$60.72$63.00$57.83
21Finishing roadway (project) 01. 5865-02-64 (213.0100)EACH1$100.00$10,000$6,885.89$500.00$500.00
22Base aggregate dense 3/4-inch (305.0110)TON3,279$35.00$22.22$28.76$27.00$52.31
23Base aggregate dense 1 1/4-inch (305.0120)TON11,018$21.25$26.46$20.94$21.00$33.81
24Base aggregate open-graded (310.0110)TON440$0.01$45.63$25.20$56.00$63.43
25Breaker run (311.0110)TON11,995$30.00$21.06$20.53$20.00$29.12
26Tack coat (455.0605)GAL6,260$3.00$3.00$3.15$3.50$3.00
27HMA percent within limits (PWL) test strip volumetrics (460.0105.S)EACH1$10,000$10,000$10,500$10,500$10,000
28HMA percent within limits (PWL) test strip density (460.0110.S)EACH2$10,000$10,000$10,500$10,500$10,000
29Incentive density HMA pavement (460.2000)DOL210$1.00$1.00$1.00$1.00$1.00
30Incentive density PWL HMA pavement (460.2005)DOL17,790$1.00$1.00$1.00$1.00$1.00
31Incentive density HMA pavement longitudinal joints (460.2007)DOL7,540$1.00$1.00$1.00$1.00$1.00
32Incentive air voids HMA pavement (460.2010)DOL22,699$1.00$1.00$1.00$1.00$1.00
33HMA pavement 4 LT 58-28 S (460.5224)TON22,808$89.58$89.58$94.06$90.00$89.58
34Asphaltic surface driveways and field entrances (465.0120)TON78$209.15$209.15$219.61$230.00$209.15
35Asphaltic flumes (465.0315)SY260$60.12$60.12$63.13$65.00$60.12
36Asphaltic rumble strips, centerline (465.0560)LF31,293$0.33$0.95$0.27$0.30$0.28
37Concrete masonry bridges (502.0100)CY35$1,525.00$1,525.00$1,601.25$1,575.00$1,525.00
38Protective surface treatment (502.3200)SY994$4.00$4.00$24.15$5.00$4.00
39Pigmented surface sealer reseal (502.3205)SY203$23.00$23.00$24.15$26.00$23.00
40Pigmented surface sealer (502.3210)SY47$13.00$13.00$13.65$23.00$13.00
41Protective surface treatment reseal (502.3215)SY24$295.00$295.00$309.75$305.00$295.00
42Adhesive anchors no. 5 bar (502.4205)EACH72$29.50$29.50$30.98$35.00$29.50
43Concrete masonry culverts (504.0100)CY121$819.00$1,376.00$859.95$1,527.00$819.00
44Bar steel reinforcement HS structures (505.0400)LB19,350$2.50$2.50$1.31$3.00$1.24
45Bar steel reinforcement HS coated structures (505.0600)LB3,090$2.85$2.85$2.35$3.00$2.24
46Preparation decks type 1 (509.0301)SY404$185.00$185.00$194.25$188.00$185.00
47Preparation decks type 2 (509.0302)SY161$276.00$276.00$289.80$281.00$276.00
48Cleaning decks (509.0500)SY144$46.00$46.00$48.30$51.00$46.00
49Cleaning decks to reapply concrete masonry overlay (509.0505.S)SY850$16.00$16.00$55.79$17.00$16.00
50Concrete surface repair (509.1500)SF483$172.00$172.00$180.60$175.00$172.00
51Concrete masonry overlay decks (509.2500)CY106$1,115.00$1,115.00$1,170.75$1,120.00$1,115.00
52Removing concrete masonry deck overlay (structure) 01. B-62-29 (509.9005.S)SY850$53.13$53.13$55.79$56.00$53.13
53Temporary shoring (structure) 01. B-62-984 (511.1200)SF640$69.00$69.00$72.45$73.00$69.00
54Rubberized membrane waterproofing (516.0500)SY34$63.00$63.00$55.50$69.00$52.86
55Apron endwalls for culvert pipe 24- inch (520.1024)EACH7$900.00$634.06$932.92$770.00$1,112.78
56Culvert pipe class III-A 24-inch (520.3324)LF182$80.00$298.75$115.80$142.00$126.80
57Apron endwalls for culvert pipe steel 18-inch (521.1018)EACH1$550.00$276.04$853.48$480.00$1,033.66
58Culvert pipe corrugated steel 18- inch (521.3118)LF6$200.00$257.96$301.84$116.00$327.57
59Culvert pipe reinforced concrete horizontal elliptical class HE-III 19X30-inch (522.2319)LF160$155.00$416.19$244.09$176.00$348.63
60Culvert pipe reinforced concrete horizontal elliptical class HE-III 24X38-inch (522.2324)LF36$180.00$461.44$308.07$280.00$379.07
61Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 19X30-inch (522.2619)EACH7$1,650.00$1,879.30$2,062.57$1,850.00$3,037.81
62Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 24X38-inch (522.2624)EACH2$2,150.00$2,299.20$2,502.66$2,360.00$3,438.65
63Piling cip concrete 14 X 0.375-inch (550.2146)LF420$135.00$135.00$141.75$138.00$135.00
64Concrete curb & gutter 30-inch type D (601.0411)LF1,920$20.39$20.39$21.41$21.00$20.39
65Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557)LF2,435$21.98$21.98$23.08$22.50$21.98
66Concrete sidewalk 4-inch (602.0405)SF3,685$8.11$8.11$8.52$8.65$8.11
67Curb ramp detectable warning field yellow (602.0505)SF40$60.34$60.34$63.36$61.50$60.34
68Concrete driveway 6-inch (602.0810)SY205$81.04$81.04$85.09$87.00$81.04
69Concrete barrier temporary precast delivered (603.8000)LF508$12.52$12.52$13.15$62.00$12.52
70Concrete barrier temporary precast installed (603.8125)LF1,016$7.40$7.40$7.77$7.00$7.40
71Riprap medium (606.0200)CY17$185.00$71.26$118.06$100.00$166.76
72Riprap heavy (606.0300)CY187$150.00$71.26$71.14$100.00$166.76
73Storm sewer pipe class III-A 12- inch (608.3012)LF147$48.50$111.91$78.48$78.00$110.03
74Storm sewer pipe class III-A 15- inch (608.3015)LF134$52.00$68.36$62.47$82.00$114.61
75Storm sewer pipe class III-A 18- inch (608.3018)LF825$56.50$59.46$67.82$89.00$102.24
76Storm sewer pipe class III-A 24- inch (608.3024)LF621$67.50$68.72$80.35$102.00$119.93
77Manhole covers type J (611.0530)EACH6$450.00$1,257.63$902.39$930.00$842.26
78Inlet covers type F (611.0615)EACH4$2,250.00$3,167.93$2,214.47$2,200.00$1,071.15
79Inlet covers type H (611.0624)EACH8$1,050.00$1,832.77$1,168.78$1,190.00$1,071.15
80Inlet covers type MS (611.0642)EACH6$800.00$630.75$905.85$950.00$877.06
81Inlet covers type MS-A (611.0645)EACH2$800.00$658.75$953.87$975.00$1,015.26
82Manholes 4-FT diameter (611.2004)EACH6$2,800.00$2,891.21$3,228.18$3,210.00$4,682.02
83Inlets 3-FT diameter (611.3003)EACH2$2,050.00$1,954.19$2,751.46$2,280.00$4,130.74
84Inlets 4-FT diameter (611.3004)EACH8$2,450.00$2,472.03$3,097.28$2,860.00$4,448.62
85Inlets 2.5X3-FT (611.3253)EACH2$2,050.00$2,031.94$2,926.79$2,600.00$4,290.87
86Inlets median 1 grate (611.3901)EACH4$3,050.00$2,525.12$4,937.43$3,900.00$4,992.86
87Inlets median 2 grate (611.3902)EACH2$4,000.00$3,987.63$5,523.52$4,650.00$5,529.50
88Pipe underdrain 6-inch (612.0106)LF75$25.00$20.00$44.29$30.00$18.04
89Crash cushions temporary (614.0905)EACH2$3,550.00$4,750.00$3,727.50$4,050.00$3,800.00
90MGS guardrail 3 (614.2300)LF2,450$26.00$30.00$27.30$26.50$26.00
91MGS guardrail 3 K (614.2330)LF5,900$37.00$42.00$38.85$37.50$37.00
92MGS guardrail 3 L (614.2340)LF112.50$33.00$30.00$34.65$36.00$33.00
93MGS guardrail short radius (614.2350)LF112.50$37.90$40.00$39.80$41.00$37.90
94MGS thrie beam transition (614.2500)LF630.40$92.00$95.00$96.60$93.00$92.00
95MGS guardrail terminal eat (614.2610)EACH38$3,755.00$4,000.00$3,942.75$3,855.00$3,755.00
96MGS guardrail terminal type 2 (614.2620)EACH2$2,900.00$3,000.00$3,045.00$3,400.00$2,900.00
97MGS guardrail short radius terminal (614.2630)EACH1$2,300.00$2,200.00$2,415.00$2,800.00$2,300.00
98Maintenance and repair of haul roads (project) 01. 5865-02-64 (618.0100)EACH1$100.00$1.00$1.16$500.00$500.00
99Mobilization (619.1000)EACH1$479,065$461,933$653,518$508,618$822,285
100Water (624.0100)MGAL143.20$140.00$75.00$27.50$50.00$63.83
101Topsoil (625.0100)SY1,651$5.00$11.19$9.14$7.00$12.47
102Salvaged topsoil (625.0500)SY10,380$5.00$1.65$0.96$5.00$5.38
103Mulching (627.0200)SY5,411$0.45$0.50$0.47$0.70$0.45
104Silt fence (628.1504)LF11,800$2.15$2.00$2.26$2.25$2.15
105Silt fence maintenance (628.1520)LF23,600$0.01$0.01$0.01$0.01$0.01
106Mobilizations erosion control (628.1905)EACH8$500.00$100.00$525.00$550.00$500.00
107Mobilizations emergency erosion control (628.1910)EACH4$100.00$100.00$105.00$150.00$100.00
108Erosion mat urban class I type B (628.2008)SY8,200$2.10$1.70$2.21$2.25$2.10
109Erosion mat class II type B (628.2023)SY500$2.20$2.25$2.31$2.50$2.20
110Inlet protection type A (628.7005)EACH24$106.00$125.00$111.30$116.00$106.00
111Inlet protection type B (628.7010)EACH5$73.00$70.00$76.65$83.00$73.00
112Inlet protection type C (628.7015)EACH15$72.00$75.00$75.60$82.00$72.00
113Temporary ditch checks (628.7504)LF348$8.95$9.00$9.40$10.00$8.95
114Culvert pipe checks (628.7555)EACH45$16.00$22.00$16.80$26.00$16.00
115Fertilizer type B (629.0210)CWT14.50$93.00$100.00$97.65$100.00$93.00
116Seeding mixture no. 30 (630.0130)LB663$8.80$9.00$9.24$10.00$8.80
117Seeding mixture no. 40 (630.0140)LB175$12.00$12.00$12.60$13.00$12.00
118Seeding mixture no. 75 (630.0175)LB21.80$115.00$200.00$120.75$120.00$115.00
119Seeding temporary (630.0200)LB510$3.55$4.00$3.73$4.00$3.55
120Seed water (630.0500)MGAL493$0.01$10.00$0.01$0.01$0.01
121Markers culvert end (633.5200)EACH16$71.00$65.00$74.55$81.00$71.00
122Posts wood 4X6-inch X 12-FT (634.0612)EACH8$92.00$85.00$96.60$102.00$92.00
123Posts wood 4X6-inch X 14-FT (634.0614)EACH31$95.00$90.00$99.75$105.00$95.00
124Posts wood 4X6-inch X 16-FT (634.0616)EACH11$97.00$95.00$101.85$107.00$97.00
125Posts wood 4X6-inch X 18-FT (634.0618)EACH6$105.00$100.00$110.25$115.00$105.00
126Moving signs type II (638.2102)EACH57$119.00$150.00$124.95$124.00$119.00
127Field office type C (642.5201)EACH1$5,000.00$22,763$10,215$15,000$20,000
128Traffic control drums (643.0300)DAY24,500$0.20$0.20$0.21$0.25$0.50
129Traffic control barricades type III (643.0420)DAY10,207$0.45$0.45$0.47$0.50$1.00
130Traffic control warning lights type A (643.0705)DAY20,414$0.01$0.01$0.01$0.05$0.10
131Traffic control warning lights type C (643.0715)DAY975$0.01$0.01$0.01$1.00$0.25
132Traffic control signs (643.0900)DAY54,504$0.25$0.25$0.26$0.30$0.25
133Traffic control covering signs type II (643.0920)EACH9$45.00$45.00$47.25$65.00$25.00
134Traffic control signs PCMS (643.1050)DAY14$60.00$60.00$63.00$70.00$100.00
135Temporary marking line removable tape 4-inch (643.3150)LF5,152$2.50$2.50$2.63$3.00$1.50
136Temporary marking line paint 6- inch (643.3165)LF74,182$0.42$0.42$0.44$0.50$0.18
137Temporary marking stop line removable tape 18-inch (643.3850)LF22$8.00$8.00$8.40$18.00$10.00
138Traffic control (643.5000)EACH1$45,200$45,200$47,460$65,200$30,000
139Temporary pedestrian surface matting (644.1440)SF240$1.00$1.00$1.05$3.00$7.00
140Temporary pedestrian barricade (644.1810)LF517$2.00$2.00$2.10$4.00$5.00
141Temporary audible message devices (644.1900.S)DAY120$4.00$4.00$4.20$9.00$10.00
142Geotextile type C (645.0105)SY252$6.50$5.95$4.73$3.00$4.50
143Geotextile type HR (645.0120)SY424$5.30$3.45$3.94$4.00$1.89
144Marking line grooved wet ref epoxy 6-inch (646.2040)LF150,482$1.05$1.05$1.10$1.10$1.19
145Marking removal line 4-inch (646.9000)LF1,564$1.75$1.75$1.84$2.00$1.25
146Locating no-passing zones (648.0100)MI7.20$625.00$625.00$656.25$800.00$532.93
147Construction staking storm sewer (650.4000)EACH23$350.00$350.00$367.50$400.00$350.00
148Construction staking subgrade (650.4500)LF7,856$0.01$0.01$0.26$0.01$0.01
149Construction staking base (650.5000)LF7,856$0.01$1.00$1.05$1.20$1.00
150Construction staking curb gutter and curb & gutter (650.5500)LF4,355$5.00$5.00$5.25$5.20$5.00
151Construction staking pipe culverts (650.6000)EACH9$300.00$300.00$315.00$350.00$300.00
152Construction staking structure layout (structure) 01. C-62-335 (650.6501)EACH1$2,000.00$2,000.00$1,050.00$2,500.00$2,000.00
153Construction staking structure layout (structure) 02. B-62-984 (650.6501)EACH1$3,000.00$3,000.00$2,100.00$3,500.00$3,000.00
154Construction staking resurfacing reference (650.8000)LF38,150$0.12$0.12$0.13$0.15$0.12
155Construction staking curb ramps (650.9000)EACH4$200.00$200.00$210.00$250.00$200.00
156Construction staking sidewalk (project) 01. 5865-02-64 (650.9500)EACH1$1,000.00$1,000.00$1,050.00$1,100.00$1,000.00
157Construction staking supplemental control (project) 01.5865-02-64 (650.9911)EACH1$2,000.00$2,000.00$2,100.00$2,500.00$2,000.00
158Construction staking slope stakes (650.9920)LF7,856$0.75$0.75$0.79$0.80$0.75
159Sawing asphalt (690.0150)LF5,482$1.64$1.64$2.05$2.00$1.64
160Sawing concrete (690.0250)LF78$3.95$3.95$3.25$6.00$3.95
161Incentive strength concrete structures (715.0502)DOL936$1.00$1.00$1.00$1.00$1.00
162Incentive iri ride (740.0440)DOL28,800$1.00$1.00$1.00$1.00$1.00
163Installing and maintaining bird deterrent system (station) 01. 132+17.1 (999.2000.S)EACH1$10,500$10,500$11,025$100.00$10,500
164Installing and maintaining bird deterrent system (station) 02. 184+01.4 (999.2000.S)EACH1$2,550.00$1,500.00$2,677.50$100.00$2,550.00
165Installing and maintaining bird deterrent system (station) 03. 252+98.5 (999.2000.S)EACH1$2,600.00$2,600.00$2,730.00$100.00$2,600.00
166Installing and maintaining bird deterrent system (station) 04. 431+53.0 (999.2000.S)EACH1$2,900.00$2,900.00$3,045.00$100.00$2,900.00
167Installing and maintaining climbing turtle exclusion fence (999.2100.S)LF7,200$2.55$5.00$2.68$2.75$2.55
168On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,400$5.00$5.00$5.00$5.00$5.00
169On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS3,200$5.00$5.00$5.00$5.00$5.00
170Special 001. verify landmark reference monuments (SPV.0060)EACH1$1,000.00$1,000.00$1,000.00$1,200.00$1,000.00
171Special 200. remove existing sanitary manhole (SPV.0060)EACH4$1,200.00$500.00$734.70$750.00$1,806.79
172Special 201. 48" sanitary sewer manhole (SPV.0060)EACH3$4,500.00$4,808.66$4,118.54$5,460.00$5,432.78
173Special 202. 8" X 6" PVC wye (SPV.0060)EACH1$500.00$131.60$1,427.74$400.00$94.00
174Special 203. 8" X 4" PVC wye (SPV.0060)EACH21$250.00$110.60$501.08$300.00$79.00
175Special 204. connect to existing sanitary sewer main (SPV.0060)EACH2$2,000.00$2,181.44$1,329.66$2,200.00$10,590
176Special 206. connect to existing sanitary sewer service (SPV.0060)EACH22$125.00$282.80$700.30$200.00$1,837.85
177Special 207. remove & salvage existing hydrants & valves (SPV.0060)EACH6$1,500.00$1,787.26$1,245.50$500.00$2,626.30
178Special 209. 8" gate valves & boxes (SPV.0060)EACH5$4,200.00$3,805.20$3,499.20$3,750.00$2,718.00
179Special 210. 6" gate valves & boxes (SPV.0060)EACH5$3,400.00$2,707.60$2,544.58$2,750.00$1,934.00
180Special 211. fire hydrant (SPV.0060)EACH3$7,000.00$8,163.00$8,099.27$7,950.00$8,420.59
181Special 212. 8" tapping saddle (SPV.0060)EACH22$400.00$250.42$620.82$160.00$179.00
182Special 213. 1" corporation stop (SPV.0060)EACH21$180.00$141.40$394.91$730.00$103.00
183Special 214. 2" corporation stop (SPV.0060)EACH1$420.00$522.20$1,641.04$1,260.00$374.00
184Special 215. 1" curb stop & box (SPV.0060)EACH21$330.00$431.20$577.10$530.00$310.00
185Special 216. connect to existing main (SPV.0060)EACH5$2,000.00$2,990.64$1,707.91$2,400.00$10,745
186Special 217. connect to existing service (SPV.0060)EACH22$200.00$295.90$715.53$200.00$1,783.64
187Special 218. temporary water services (SPV.0060)EACH1$8,500.00$16,500$14,769$13,255$71,532
188Special 200. special fittings (SPV.0085)LB1,200$10.00$7.20$11.31$1.00$5.14
189Special 200. remove existing sanitary sewer pipe (SPV.0090)LF834$8.00$2.00$16.43$5.00$27.41
190Special 201. 8" sanitary sewer main (SPV.0090)LF906$80.00$61.78$83.12$97.00$197.67
191Special 202. 2" HDPE sanitary sewer forcemain (SPV.0090)LF96$100.00$46.67$49.96$93.00$474.73
192Special 203. 6" sanitary sewer service pipe (SPV.0090)LF37$110.00$45.44$59.28$98.00$229.33
193Special 204. 4" sanitary sewer service pipe (SPV.0090)LF495$50.00$43.91$43.73$74.00$224.99
194Special 205. remove existing watermain (SPV.0090)LF1,121$10.00$2.00$5.91$9.00$29.50
195Special 206. 8" watermain (SPV.0090)LF1,039$87.00$80.61$97.89$144.00$136.45
196Special 207. 6" watermain (SPV.0090)LF64$100.00$102.49$95.12$157.00$148.62
197Special 208. 6" class 52 ductile iron pipe hydrant lead (SPV.0090)LF40$100.00$105.87$156.05$160.00$152.87
198Special 209. 1" copper water service (SPV.0090)LF484$54.00$55.45$48.71$90.00$235.66
199Special 210. 2" copper water service (SPV.0090)LF19$200.00$88.84$110.70$142.00$284.54
200Special 001. removing asphaltic surface milling (SPV.0180)SY100,500$2.00$2.00$2.21$2.10$2.00
WisDOT contract 20260811005: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of August 11, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way