WisDOT contract 20260915014 bid tabulation
New London - Clintonville; Church Road to Reinke Road (USH 045, Waupaca County New London - Clintonville). Let by Wisconsin DOT on September 15, 2026, Waupaca. 3 bids received; low bid $6,970,115 by Northeast Asphalt, Inc.
- Owner
- Wisconsin DOT
- Letting
- 15 SEP 2026
- Pay items
- 99
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Northeast Asphalt, Inc | $6,970,115 | Low |
| 2 | American Asphalt of Wisconsin | $7,343,408 | +5.0% |
| 3 | Rock Road Companies, Inc. | $8,024,147 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Northeast Asphalt, Inc | 2. American Asphalt of Wisconsin | 3. Rock Road Companies, Inc. |
|---|---|---|---|---|---|---|
| 1 | Removing small pipe culverts (203.0100) | EACH | 10 | $1,357.00 | $2,318.00 | $1,357.00 |
| 2 | Removing structure (structure) 01. sta. 198+33 (203.0220) | EACH | 1 | $1,200.00 | $11,910 | $1,200.00 |
| 3 | Removing structure (structure) 02. sta. 316+40 (203.0220) | EACH | 1 | $1,000.00 | $10,820 | $1,000.00 |
| 4 | Removing structure (structure) 03. sta. 607+85 (203.0220) | EACH | 1 | $1,000.00 | $10,885 | $1,000.00 |
| 5 | Removing concrete pavement (204.0100) | SY | 2,000 | $13.09 | $3.00 | $13.09 |
| 6 | Removing asphaltic surface (204.0110) | SY | 689 | $15.00 | $2.20 | $15.00 |
| 7 | Removing asphaltic surface butt joints (204.0115) | SY | 1,042 | $7.70 | $6.25 | $13.19 |
| 8 | Removing asphaltic surface milling (204.0120) | SY | 255,030 | $1.80 | $2.65 | $3.28 |
| 9 | Removing curb & gutter (204.0150) | LF | 344 | $22.00 | $10.00 | $22.00 |
| 10 | Excavation common (205.0100) | CY | 8,917 | $19.92 | $22.24 | $19.92 |
| 11 | Temporary lane shift during culvert work (208.1500.S) | EACH | 13 | $6,032.00 | $0.01 | $6,032.00 |
| 12 | Prepare foundation for asphaltic paving (project) 01. 1140-00-78 (211.0101) | EACH | 1 | $95,450 | $50,000 | $0.01 |
| 13 | Prepare foundation for asphaltic shoulders (211.0400) | STA | 1,062 | $51.40 | $10.95 | $12.03 |
| 14 | Finishing roadway (project) 01. 1140-00-78 (213.0100) | EACH | 1 | $2,900.00 | $100.00 | $5,384.04 |
| 15 | Base aggregate dense 3/4-inch (305.0110) | TON | 5,640 | $28.76 | $29.70 | $28.76 |
| 16 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 6,710 | $21.08 | $23.59 | $21.08 |
| 17 | Shaping shoulders (305.0500) | STA | 1,062 | $13.25 | $15.10 | $12.03 |
| 18 | Tack coat (455.0605) | GAL | 39,330 | $3.00 | $3.50 | $0.01 |
| 19 | HMA percent within limits (PWL) test strip volumetrics (460.0105.S) | EACH | 1 | $2,170.00 | $5,000.00 | $3,500.00 |
| 20 | HMA percent within limits (PWL) test strip density (460.0110.S) | EACH | 2 | $1,650.00 | $5,000.00 | $3,500.00 |
| 21 | Incentive density PWL HMA pavement (460.2005) | DOL | 31,790 | $1.00 | $1.00 | $1.00 |
| 22 | Incentive density HMA pavement longitudinal joints (460.2007) | DOL | 11,280 | $1.00 | $1.00 | $1.00 |
| 23 | Incentive air voids HMA pavement (460.2010) | DOL | 53,520 | $1.00 | $1.00 | $1.00 |
| 24 | HMA pavement 4 MT 58-28 S (460.6224) | TON | 53,520 | $69.80 | $79.15 | $82.00 |
| 25 | Asphaltic surface (465.0105) | TON | 2,834 | $95.90 | $117.90 | $137.04 |
| 26 | Asphaltic surface patching (465.0110) | TON | 860 | $114.70 | $92.60 | $113.97 |
| 27 | Asphaltic surface driveways and field entrances (465.0120) | TON | 50 | $430.00 | $213.10 | $201.66 |
| 28 | Asphaltic flumes (465.0315) | SY | 28 | $49.90 | $65.85 | $72.50 |
| 29 | Asphaltic rumble strips, shoulder (465.0520) | LF | 85,610 | $0.28 | $0.19 | $0.13 |
| 30 | Asphaltic rumble strips, centerline (465.0560) | LF | 47,810 | $0.28 | $0.27 | $0.16 |
| 31 | Culvert pipe reinforced concrete class IV 24-inch (522.0424) | LF | 80 | $190.31 | $134.07 | $190.31 |
| 32 | Culvert pipe reinforced concrete class IV 30-inch (522.0430) | LF | 56 | $253.75 | $161.84 | $253.75 |
| 33 | Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024) | EACH | 2 | $1,259.61 | $3,331.57 | $1,259.61 |
| 34 | Apron endwalls for culvert pipe reinforced concrete 30-inch (522.1030) | EACH | 2 | $1,527.13 | $3,586.88 | $1,527.13 |
| 35 | Culvert pipe reinforced concrete horizontal elliptical class HE-IV 24X38-inch (522.2424) | LF | 96 | $297.83 | $231.93 | $297.83 |
| 36 | Culvert pipe reinforced concrete horizontal elliptical class HE-IV 29X45-inch (522.2429) | LF | 72 | $368.85 | $295.54 | $368.85 |
| 37 | Culvert pipe reinforced concrete horizontal elliptical class HE-IV 34X53-inch (522.2434) | LF | 256 | $431.43 | $356.60 | $431.43 |
| 38 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 24X38-inch (522.2624) | EACH | 4 | $1,941.48 | $2,425.00 | $1,941.48 |
| 39 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 29X45-inch (522.2629) | EACH | 2 | $2,511.93 | $2,425.00 | $2,511.93 |
| 40 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 34X53-inch (522.2634) | EACH | 8 | $3,081.80 | $2,425.00 | $3,081.80 |
| 41 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 38X60-inch (522.2638) | EACH | 4 | $4,224.99 | $3,080.20 | $4,224.99 |
| 42 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 43X68-inch (522.2643) | EACH | 4 | $5,335.33 | $3,365.00 | $5,335.33 |
| 43 | Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557) | LF | 627 | $67.86 | $67.86 | $67.86 |
| 44 | Riprap medium (606.0200) | CY | 15 | $108.06 | $250.00 | $108.06 |
| 45 | Adjusting inlet covers (611.8115) | EACH | 21 | $1,743.76 | $300.00 | $1,743.76 |
| 46 | Maintenance and repair of haul roads (project) 01. 1140-00-78 (618.0100) | EACH | 1 | $1.00 | $100.00 | $0.01 |
| 47 | Mobilization (619.1000) | EACH | 1 | $251,500 | $26,050 | $415,747 |
| 48 | Water (624.0100) | MGAL | 250 | $75.00 | $25.00 | $75.00 |
| 49 | Topsoil (625.0100) | SY | 5,386 | $2.70 | $4.73 | $2.70 |
| 50 | Silt fence (628.1504) | LF | 5,514 | $2.00 | $2.00 | $2.00 |
| 51 | Silt fence maintenance (628.1520) | LF | 5,514 | $0.01 | $0.01 | $0.01 |
| 52 | Mobilizations erosion control (628.1905) | EACH | 5 | $200.00 | $200.00 | $200.00 |
| 53 | Mobilizations emergency erosion control (628.1910) | EACH | 5 | $100.00 | $100.00 | $100.00 |
| 54 | Erosion mat class I type B (628.2004) | SY | 420 | $1.75 | $1.75 | $1.75 |
| 55 | Erosion mat urban class I type B (628.2008) | SY | 4,926 | $1.80 | $1.80 | $1.80 |
| 56 | Temporary ditch checks (628.7504) | LF | 40 | $8.00 | $8.00 | $8.00 |
| 57 | Culvert pipe checks (628.7555) | EACH | 78 | $15.00 | $15.00 | $15.00 |
| 58 | Rock bags (628.7570) | EACH | 150 | $15.00 | $15.00 | $15.00 |
| 59 | Fertilizer type B (629.0210) | CWT | 4.90 | $90.00 | $90.00 | $90.00 |
| 60 | Seeding mixture no. 30 (630.0130) | LB | 111 | $7.50 | $7.50 | $7.50 |
| 61 | Seed water (630.0500) | MGAL | 54.50 | $5.00 | $5.00 | $5.00 |
| 62 | Markers culvert end (633.5200) | EACH | 26 | $68.00 | $68.00 | $68.00 |
| 63 | Moving signs type II (638.2102) | EACH | 13 | $75.00 | $75.00 | $75.00 |
| 64 | Moving small sign supports (638.4000) | EACH | 13 | $75.00 | $75.00 | $75.00 |
| 65 | Field office type C (642.5201) | EACH | 1 | $11,220 | $10,000 | $6,000.00 |
| 66 | Traffic control drums (643.0300) | DAY | 1,720 | $1.00 | $0.20 | $0.20 |
| 67 | Traffic control barricades type III (643.0420) | DAY | 100 | $2.50 | $1.00 | $1.00 |
| 68 | Traffic control warning lights type A (643.0705) | DAY | 200 | $0.50 | $0.15 | $0.15 |
| 69 | Traffic control warning lights type C (643.0715) | DAY | 140 | $0.50 | $0.15 | $0.15 |
| 70 | Traffic control connected arrow boards (643.0810) | DAY | 10 | $50.00 | $75.00 | $75.00 |
| 71 | Traffic control signs (643.0900) | DAY | 3,670 | $1.25 | $0.25 | $0.25 |
| 72 | Traffic control signs fixed message (643.1000) | SF | 36 | $25.00 | $14.00 | $14.00 |
| 73 | Traffic control connected work zone start and end location markers (643.1220) | DAY | 10 | $25.00 | $55.00 | $55.00 |
| 74 | Temporary marking line paint 6- inch (643.3165) | LF | 128,802 | $0.23 | $0.23 | $0.23 |
| 75 | Traffic control (643.5000) | EACH | 1 | $21,500 | $42,225 | $42,225 |
| 76 | Geotextile type HR (645.0120) | SY | 26 | $35.22 | $5.00 | $35.22 |
| 77 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 192,980 | $1.14 | $1.14 | $1.14 |
| 78 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 2,330 | $2.67 | $2.67 | $2.67 |
| 79 | Marking arrow epoxy (646.5020) | EACH | 16 | $207.62 | $207.62 | $207.62 |
| 80 | Marking word epoxy (646.5120) | EACH | 14 | $277.27 | $277.27 | $277.27 |
| 81 | Marking stop line epoxy 18-inch (646.6120) | LF | 114 | $14.24 | $14.24 | $14.24 |
| 82 | Marking diagonal epoxy 12-inch (646.7120) | LF | 185 | $13.83 | $13.83 | $13.83 |
| 83 | Marking curb epoxy (646.8120) | LF | 483 | $8.08 | $8.08 | $8.08 |
| 84 | Marking island nose epoxy (646.8220) | EACH | 17 | $301.74 | $301.74 | $301.74 |
| 85 | Locating no-passing zones (648.0100) | MI | 10.68 | $540.72 | $540.72 | $540.72 |
| 86 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 627 | $0.75 | $0.75 | $0.75 |
| 87 | Construction staking pipe culverts (650.6000) | EACH | 13 | $75.00 | $75.00 | $75.00 |
| 88 | Construction staking resurfacing reference (650.8000) | LF | 56,375 | $0.19 | $0.19 | $0.19 |
| 89 | Construction staking supplemental control (project) 01. 1140-00-78 (650.9911) | EACH | 1 | $10.00 | $10.00 | $10.00 |
| 90 | Construction staking slope stakes (650.9920) | LF | 3,525 | $0.15 | $0.15 | $0.15 |
| 91 | Public land survey monument verify and reset (680.0100) | EACH | 9 | $800.00 | $800.00 | $800.00 |
| 92 | Sawing asphalt (690.0150) | LF | 3,999 | $1.69 | $4.45 | $2.00 |
| 93 | Sawing concrete (690.0250) | LF | 462 | $2.25 | $3.50 | $2.75 |
| 94 | Incentive iri ride (740.0440) | DOL | 44,000 | $1.00 | $1.00 | $1.00 |
| 95 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,400 | $5.00 | $5.00 | $5.00 |
| 96 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 2,760 | $5.00 | $5.00 | $5.00 |
| 97 | Special 01.culvert pipe reinforced concrete horizontal elliptical class HE-IV 38X60-inch (SPV.0090) | LF | 160 | $491.49 | $449.26 | $491.49 |
| 98 | Special 02.culvert pipe reinforced concrete horizontal elliptical class HE-IV 43X68-inch (SPV.0090) | LF | 184 | $568.24 | $546.78 | $568.24 |
| 99 | Special 01. removing distressed asphaltic surface milling (SPV.0180) | SY | 7,651 | $6.70 | $8.05 | $7.21 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of September 15, 2026. Compiled by Mirage Metrics.