WisDOT contract 20251014007 bid tabulation

C Greenfield/Milwaukee, S 27th St; W Bottsford Ave to W Howard Ave (STH 241, Milwaukee County C Greenfield/Milwauke, S 27th St). Let by Wisconsin DOT on October 14, 2025, Milwaukee. 4 bids received; low bid $1,677,377 by Lalonde Contractors Incorporated.

Owner
Wisconsin DOT
Letting
14 OCT 2025
Pay items
132
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Lalonde Contractors Incorporated$1,677,377Low
2Rock Road Companies, Inc.$1,860,808+11%
3Stark Pavement Corporation$1,876,309+12%
4Payne and Dolan, Inc$1,935,723+15%
WisDOT contract 20251014007: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Lalonde Contractors Incorporated2. Rock Road Companies, Inc.3. Stark Pavement Corporation4. Payne and Dolan, Inc
1CPM progress schedule (108.4400)EACH1$2,500.00$0.01$5,000.00$2,525.25
2Clearing (201.0105)STA1$4,750.00$4,750.00$4,750.00$4,797.98
3Grubbing (201.0205)STA1$500.00$500.00$500.00$505.05
4Removing asphaltic surface (204.0110)SY850$17.20$7.80$7.00$7.80
5Removing asphaltic surface butt joints (204.0115)SY82$18.00$10.63$42.00$21.25
6Removing asphaltic surface milling (204.0120)SY29,800$2.60$4.97$3.30$2.60
7Removing curb & gutter (204.0150)LF1,140$17.18$8.70$15.00$8.70
8Removing concrete sidewalk (204.0155)SY680$9.39$24.45$15.00$24.45
9Removing fence (204.0170)LF14$10.00$55.00$25.00$25.25
10Removing concrete bases (204.0195)EACH5$346.00$346.00$346.00$350.00
11Removing (item description) 01. loop detector wire and lead-in cable STH 241 & coldspring RD (204.9060.S)EACH1$799.00$799.00$799.00$4,488.00
12Removing (item description) 02. loop detector wire and lead-in cable STH 241 & W. howard ave (204.9060.S)EACH1$799.00$799.00$799.00$1,122.00
13Removing (item description) 03. electrical service meter breaker pedestal (204.9060.S)EACH1$160.00$160.00$160.00$764.00
14Cofferdams (structure) 01. C-40-42 (206.5001)EACH1$7,909.00$7,909.00$7,909.00$175,000
15Prepare foundation for asphaltic paving (project) 01. 2265-11-72 (211.0101)EACH1$1,000.00$0.01$5,050.00$1,450.00
16Finishing roadway (project) 01. 2265-11-72 (213.0100)EACH1$2,610.00$8,414.81$6,650.00$1,450.00
17Removing pavement for base patching (390.0100)CY120$62.33$74.35$200.00$74.35
18Base patching concrete hes (390.0305)CY128$329.00$289.85$350.00$289.85
19Drilled tie bars (416.0610)EACH66$14.00$15.75$15.00$15.75
20Drilled dowel bars (416.0620)EACH328$18.55$20.00$30.00$20.00
21Tack coat (455.0605)GAL4,363$2.30$2.99$3.00$2.30
22Incentive density HMA pavement (460.2000)DOL4,720$1.00$1.00$1.00$1.00
23HMA pavement 3 MT 58-28 S (460.6223)TON4,140$66.70$86.32$91.00$70.30
24HMA pavement 4 MT 58-28 H (460.6424)TON3,220$81.60$101.84$99.90$85.10
25Asphaltic surface (465.0105)TON67$195.00$192.05$221.20$195.00
26Asphaltic surface patching (465.0110)TON76$195.00$192.05$221.20$195.00
27Asphaltic surface temporary (465.0125)TON101$195.00$192.05$179.00$195.00
28Concrete surface repair (509.1500)SF94$80.00$80.00$80.00$600.00
29Concrete curb & gutter 31-inch (601.0331)LF1,012$66.55$64.00$50.00$64.00
30Concrete curb pedestrian (601.0600)LF185$65.48$35.25$75.00$35.25
31Concrete sidewalk 5-inch (602.0410)SF5,830$9.82$9.25$9.50$9.25
32Curb ramp detectable warning field natural patina (602.0515)SF300$41.70$48.50$55.00$48.50
33Inlet covers type WM (611.0660)EACH2$2,000.00$1,613.40$1,900.00$1,919.95
34Adjusting manhole covers (611.8110)EACH2$1,905.00$300.00$2,000.00$665.38
35Adjusting inlet covers (611.8115)EACH5$1,090.00$300.00$1,500.00$665.38
36Pipe underdrain 6-inch (612.0106)LF44$58.44$61.29$20.00$71.11
37Fence chain link 6-FT (616.0206)LF10$85.00$328.00$250.00$328.00
38Gates chain link (width) 01. 4-FT (616.0329)EACH1$2,600.00$3,788.00$3,000.00$3,788.00
39Maintenance and repair of haul roads (project) 01. 2265-11-72 (618.0100)EACH1$0.01$0.01$1.00$1.00
40Mobilization (619.1000)EACH1$133,542$118,940$85,319$173,500
41Concrete median sloped nose (620.0300)SF367$20.81$19.95$15.00$19.95
42Mobilizations erosion control (628.1905)EACH3$100.00$250.00$250.00$252.53
43Mobilizations emergency erosion control (628.1910)EACH3$100.00$125.00$250.00$252.53
44Inlet protection type B (628.7010)EACH10$55.00$45.00$50.00$50.51
45Inlet protection type C (628.7015)EACH55$55.00$45.00$60.00$60.61
46Inlet protection type D (628.7020)EACH40$95.00$88.00$125.00$126.26
47Posts wood 4X6-inch X 18-FT (634.0618)EACH67$130.00$94.10$100.00$101.01
48Posts tubular steel 2X2-inch X 12- FT (634.0812)EACH10$220.00$170.00$200.00$202.02
49Signs type II reflective H (637.2210)SF780.38$21.00$20.10$18.50$18.69
50Signs type II reflective F (637.2230)SF78.25$24.00$21.25$21.00$21.21
51Removing signs type II (638.2602)EACH110$28.00$18.00$35.00$35.35
52Removing small sign supports (638.3000)EACH70$28.00$18.00$35.00$35.35
53Field office type D (642.5401)EACH1$11,064$11,000$16,000$5,800.00
54Traffic control drums (643.0300)DAY96,265$0.14$0.14$0.14$0.14
55Traffic control barricades type III (643.0420)DAY11,050$0.48$0.48$0.48$0.48
56Traffic control warning lights type A (643.0705)DAY22,590$0.11$0.11$0.11$0.11
57Traffic control warning lights type C (643.0715)DAY6,870$0.12$0.12$0.12$0.12
58Connected arrow board (643.0810.S)DAY663$6.18$6.18$6.18$6.18
59Traffic control signs (643.0900)DAY34,680$0.17$0.17$0.17$0.17
60Traffic control signs PCMS (643.1050)DAY27$60.00$60.00$60.00$60.00
61Connected work zone start and end location markers (643.1220.S)DAY825$4.27$4.27$4.27$4.27
62Temporary marking line paint 6- inch (643.3165)LF14,420$1.00$1.00$1.00$1.00
63Temporary marking line removable tape 6-inch (643.3180)LF27,280$2.24$2.24$2.24$2.24
64Temporary marking removable mask out tape 6-inch (643.3960)LF3,938$2.49$2.49$2.49$2.49
65Traffic control (643.5000)EACH1$5,605.62$5,605.62$5,605.62$5,605.62
66Temporary pedestrian surface asphalt (644.1410)SF3,063$6.74$10.35$5.50$4.40
67Temporary pedestrian surface matting (644.1440)SF1,600$2.20$2.20$2.20$2.20
68Temporary pedestrian curb ramp (644.1601)DAY282$12.09$12.09$12.09$12.09
69Temporary pedestrian detectable warning field (644.1605)SF338$5.48$5.48$5.48$5.48
70Temporary pedestrian barricade (644.1810)LF2,975$4.11$4.11$4.11$4.11
71Temporary audible message devices (644.1900.S)DAY745$1.54$1.54$1.54$1.54
72Marking line epoxy 4-inch (646.1020)LF130$1.00$1.00$1.00$1.00
73Marking line grooved black epoxy 6-inch (646.2025)LF3,080$1.35$1.35$1.35$1.20
74Marking line grooved wet ref epoxy 6-inch (646.2040)LF14,500$1.60$1.60$1.60$1.70
75Marking line epoxy 8-inch (646.3020)LF370$2.00$2.00$2.00$1.99
76Marking line grooved wet ref epoxy 10-inch (646.4040)LF2,900$2.60$2.60$2.60$3.30
77Marking arrow epoxy (646.5020)EACH13$285.00$285.00$285.00$320.00
78Marking word epoxy (646.5120)EACH4$325.00$325.00$325.00$350.00
79Marking stop line epoxy 18-inch (646.6120)LF240$16.00$16.00$16.00$18.00
80Marking crosswalk epoxy transverse line 6-inch (646.7420)LF870$10.00$10.00$10.00$15.00
81Marking curb epoxy (646.8120)LF870$8.00$8.00$8.00$7.50
82Marking island nose epoxy (646.8220)EACH13$300.00$300.00$300.00$475.00
83Construction staking curb gutter and curb & gutter (650.5500)LF1,197$2.00$2.00$1.95$2.02
84Construction staking resurfacing reference (650.8000)LF13,400$0.20$0.20$0.25$0.20
85Construction staking electrical installations (project) 01. 2265-11- 72 (650.8501)EACH1$1,500.00$1,500.00$1,850.00$1,515.15
86Construction staking curb ramps (650.9000)EACH32$200.00$200.00$265.00$202.02
87Construction staking sidewalk (project) 01. 2265-11-72 (650.9500)EACH1$1,000.00$1,000.00$3,250.00$1,010.10
88Construction staking supplemental control (project) 01. 2265-11-72 (650.9911)EACH1$1,800.00$1,800.00$4,595.00$1,818.18
89Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF88$1.91$1.91$1.91$8.48
90Conduit rigid nonmetallic schedule 40 3-inch (652.0235)LF220$2.88$2.88$2.88$9.68
91Conduit special 2-inch (652.0605)LF655$18.38$18.38$18.38$21.65
92Conduit loop detector (652.0800)LF2,310$7.37$7.37$7.37$9.34
93Pull boxes steel 24X36-inch (653.0135)EACH1$1,287.00$1,287.00$1,287.00$1,248.00
94Pull boxes steel 24X42-inch (653.0140)EACH4$1,288.00$1,288.00$1,288.00$1,356.00
95Adjusting pull boxes (653.0900)EACH1$218.00$218.00$218.00$257.00
96Removing pull boxes (653.0905)EACH2$176.00$176.00$176.00$195.00
97Concrete bases type 1 (654.0101)EACH3$901.00$901.00$901.00$1,338.00
98Cable traffic signal 5-14 AWG (655.0230)LF80$1.79$1.79$1.79$2.12
99Cable traffic signal 7-14 AWG (655.0240)LF200$2.11$2.11$2.11$2.52
100Cable traffic signal 12-14 AWG (655.0260)LF590$3.27$3.27$3.27$3.79
101Electrical wire traffic signals 10 AWG (655.0515)LF520$1.20$1.20$1.20$1.52
102Loop detector lead in cable (655.0700)LF9,979$1.91$1.91$1.91$2.02
103Loop detector wire (655.0800)LF9,525$1.26$1.26$1.26$1.18
104Pedestal bases (657.0100)EACH3$347.00$347.00$347.00$272.00
105Traffic signal standards aluminum 3.5-FT (657.0405)EACH1$356.00$356.00$356.00$302.00
106Traffic signal standards aluminum 15-FT (657.0425)EACH2$857.00$857.00$857.00$656.00
107Traffic signal face 4S 12-inch (658.0174)EACH2$1,171.00$1,171.00$1,171.00$1,446.00
108Pedestrian signal face 16-inch (658.0416)EACH2$611.00$611.00$611.00$701.20
109Pedestrian push buttons (658.0500)EACH7$430.00$430.00$430.00$408.00
110Signal mounting hardware (location) 01. STH 241 & coldspring RD (658.5070)EACH1$1,664.00$1,664.00$1,664.00$3,783.00
111Lamp, ballast, LED, switch disposal by contractor (659.5000.S)EACH4$19.00$19.00$19.00$18.00
112Sawing asphalt (690.0150)LF1,676$1.75$1.45$5.00$1.75
113Sawing concrete (690.0250)LF766$2.35$2.95$5.00$2.35
114Incentive iri ride (740.0440)DOL7,600$1.00$1.00$1.00$1.00
115On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS250$5.00$5.00$5.00$5.00
116On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS900$5.00$5.00$5.00$5.00
117Special 01. pedestrian push button extension (SPV.0060)EACH2$441.00$441.00$441.00$642.20
118Special 02. modify traffic signal STH 241 & coldspring (SPV.0060)EACH1$1,860.00$1,860.00$1,860.00$6,320.00
119Special 03. adjusting cuc manhole cover (SPV.0060)EACH2$2,561.00$387.50$2,300.00$1,523.77
120Special 04. adjusting sanitary manhole with internal/external seal (SPV.0060)EACH8$2,022.27$805.15$1,800.00$1,376.47
121Special 05. adjusting water valve boxes (SPV.0060)EACH6$559.00$166.67$500.00$294.60
122Special 06. temporary bus stop (SPV.0060)EACH8$1,529.00$2,874.88$3,200.00$750.00
123Special 07. curb ramp grading, shaping, and finishing (SPV.0060)EACH32$737.24$500.00$1,500.00$500.00
124Special 08. cleaning storm sewer structure & pipes (SPV.0060)EACH5$785.00$514.00$750.00$801.02
125Special 09. section corner monument (SPV.0060)EACH1$1,652.00$1,350.00$1,000.00$1.00
126Special 10. tuck point storm sewer structure (SPV.0060)EACH4$557.00$462.50$600.00$558.72
127Special 302. pullboxes 13" X 24" X 24" (SPV.0060)EACH12$1,111.00$1,111.00$1,111.00$884.00
128Special 01. construction staking fence (SPV.0090)LF10$10.00$10.00$8.50$10.10
129Special 351. split duct conduit (SPV.0090)LF10$16.48$16.48$16.48$152.20
130Special 01. concrete surface repair full-depth (SPV.0165)SF15$558.00$558.00$558.00$900.00
131Special 02. remove, salvage, and reinstall landscaping rocks (SPV.0165)SF60$10.00$40.00$25.00$25.25
132Special 01. asphaltic repair (SPV.0195)TON368$160.00$185.32$145.00$150.00
WisDOT contract 20251014007: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of October 14, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy