WisDOT contract 20260210003 bid tabulation

5627-00-71. Let by Wisconsin DOT on February 10, 2026, Dane. 6 bids received; low bid $2,717,944 by James Peterson Sons, Inc..

Owner
Wisconsin DOT
Letting
10 FEB 2026
Pay items
93
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1James Peterson Sons, Inc.$2,717,944Low
2Integrity Grading and Excavating, Inc.$3,125,672+15%
3Rock Road Companies, Inc.$3,253,988+20%
4Fischer Excavating, Inc.$3,461,526+27%
5Parisi Construction, LLC$3,999,038+47%
6Speedway Sand & Gravel, Inc.$4,018,135+48%
WisDOT contract 20260210003: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. James Peterson Sons, Inc.2. Integrity Grading and Excavating, Inc.3. Rock Road Companies, Inc.4. Fischer Excavating, Inc.5. Parisi Construction, LLC6. Speedway Sand & Gravel, Inc.
1Clearing (201.0120)ID24$65.00$65.00$65.00$65.00$68.00$65.00
2Grubbing (201.0220)ID24$65.00$65.00$65.00$65.00$68.00$65.00
3Removing concrete pavement (204.0100)SY596$3.50$3.55$11.76$7.00$8.30$4.50
4Removing asphaltic surface (204.0110)SY19,960$0.01$2.00$0.01$1.55$0.01$0.01
5Removing curb & gutter (204.0150)LF5,310$2.00$5.30$5.72$3.50$7.70$4.00
6Removing concrete sidewalk (204.0155)SY2,656$3.50$2.25$10.90$18.00$23.50$9.20
7Removing catch basins (204.0215)EACH4$300.00$620.00$378.68$500.00$740.00$440.00
8Removing storm sewer (size) 01. 12-inch through 18-inch (204.0245)LF120$31.55$26.00$24.53$20.00$32.00$13.80
9Excavation common (205.0100)CY6,000$11.23$22.25$23.19$25.00$27.00$22.94
10Finishing roadway (project) 01. 5627-00-71 (213.0100)EACH1$5,000.00$1,000.00$5,149.47$15,000$420.00$678.00
11Base aggregate dense 3/4-inch (305.0110)TON740$25.98$35.75$25.71$20.00$24.00$28.20
12Base aggregate dense 1 1/4-inch (305.0120)TON2,210$20.86$31.75$16.53$20.00$15.25$20.00
13Base aggregate dense 3-inch (305.0130)TON4,650$13.14$19.00$15.88$20.00$14.50$15.05
14Breaker run (311.0115)CY1,603$12.42$40.00$29.76$35.00$26.00$30.50
15Drilled tie bars (416.0610)EACH24$15.00$15.00$14.00$14.00$11.25$13.00
16Tack coat (455.0605)GAL497$0.10$0.10$3.50$0.10$0.10$0.10
17Incentive density HMA pavement (460.2000)DOL1,390$1.00$1.00$1.00$1.00$1.00$1.00
18HMA pavement 3 LT 58-28 S (460.5223)TON1,216$68.50$68.50$68.82$68.50$72.00$68.50
19HMA pavement 4 LT 58-28 S (460.5224)TON945$69.50$69.50$73.58$69.50$73.00$69.50
20Asphaltic surface driveways and field entrances (465.0120)TON40$120.00$120.00$237.32$120.00$130.00$120.00
21Concrete curb & gutter 30-inch type D (601.0411)LF5,310$19.50$19.50$19.70$20.00$20.00$29.52
22Concrete sidewalk 5-inch (602.0410)SF22,840$5.60$5.60$5.10$8.00$5.55$7.20
23Concrete sidewalk 7-inch (602.0420)SF4,221$6.60$6.60$8.00$10.00$8.00$9.70
24Curb ramp detectable warning field natural patina (602.0515)SF180$50.00$50.00$45.00$45.00$45.00$60.00
25Concrete driveway 7-inch (602.0815)SY886$60.00$60.00$72.00$94.00$70.00$83.00
26Storm sewer pipe reinforced concrete class V 15-inch (608.0515)LF1,943$69.07$83.00$91.78$73.00$85.00$110.30
27Storm sewer pipe reinforced concrete class V 18-inch (608.0518)LF48$92.96$93.50$117.93$82.00$104.00$117.45
28Manhole covers type J (611.0530)EACH8$1,127.79$675.00$986.88$485.00$440.00$1,065.00
29Inlet covers type H (611.0624)EACH18$1,563.32$925.00$1,228.44$745.00$680.00$1,156.00
30Catch basins 2X3-FT (611.1230)EACH18$2,387.83$3,325.00$3,238.59$2,500.00$3,000.00$2,905.00
31Manholes 6X6-FT (611.2066)EACH1$7,158.72$8,800.00$7,412.13$12,000$10,000$11,437
32Adjusting catch basin covers (611.8105)EACH27$774.32$1,100.00$1,342.13$725.00$870.00$100.00
33Adjusting manhole covers (611.8110)EACH6$660.79$1,100.00$1,342.13$725.00$680.00$550.00
34Pipe underdrain unperforated 8- inch (612.0208)LF4,416$42.93$15.50$24.01$30.00$20.75$34.54
35Mobilization (619.1000)EACH1$37,039$447,692$270,909$200,000$504,000$511,632
36Water (624.0100)MGAL137.10$50.00$45.00$0.01$5.00$41.75$1.00
37Topsoil (625.0100)SY4,790$8.17$14.00$0.01$5.00$12.75$4.95
38Mulching (627.0200)SY4,790$0.50$0.50$0.50$0.35$2.10$0.45
39Mobilizations erosion control (628.1905)EACH1$250.00$250.00$250.00$200.00$1,500.00$200.00
40Mobilizations emergency erosion control (628.1910)EACH3$250.00$250.00$250.00$250.00$160.00$200.00
41Inlet protection type D (628.7020)EACH31$130.00$130.00$130.00$65.00$130.00$90.00
42Tracking pads (628.7560)EACH3$3,700.00$2,475.00$750.00$1,800.00$900.00$980.00
43Fertilizer type A (629.0205)CWT3$70.00$70.00$70.00$80.00$160.00$90.00
44Seeding mixture no. 40 (630.0140)LB161$11.00$11.00$11.00$10.00$21.00$12.95
45Seed water (630.0500)MGAL100$1.00$1.00$1.00$2.00$0.01$12.00
46Moving signs type II (638.2102)EACH27$200.00$200.00$200.00$40.00$260.00$110.00
47Traffic control drums (643.0300)DAY6,260$0.25$0.25$0.25$0.25$0.25$0.25
48Traffic control barricades type III (643.0420)DAY3,690$0.50$0.50$0.50$0.50$0.55$0.50
49Traffic control warning lights type A (643.0705)DAY732$0.25$0.25$0.25$0.25$0.25$0.25
50Traffic control signs (643.0900)DAY8,792$0.25$0.25$0.25$0.25$0.25$0.25
51Traffic control signs fixed message (643.1000)SF8$18.00$18.00$18.00$18.00$19.00$18.00
52Traffic control signs PCMS (643.1050)DAY20$69.99$69.99$69.99$70.00$73.00$69.99
53Traffic control (643.5000)EACH1$4,500.00$4,500.00$4,500.00$4,500.00$5,000.00$4,500.00
54Temporary audible message devices (644.1900.S)DAY3,618$2.00$2.00$2.00$2.00$2.10$2.00
55Marking stop line paint 18-inch (646.6105)LF198$12.25$5.95$9.90$5.95$10.50$5.95
56Marking crosswalk paint transverse line 6-inch (646.7405)LF790$5.75$1.95$9.70$1.95$10.25$1.95
57Marking crosswalk paint block style 24-inch (646.7505)LF930$18.50$7.95$16.45$7.95$17.25$7.95
58Construction staking storm sewer (650.4000)EACH19$150.00$150.00$150.00$200.00$0.01$150.00
59Construction staking subgrade (650.4500)LF2,796$0.01$0.01$0.01$0.01$0.01$0.01
60Construction staking base (650.5000)LF2,796$1.50$1.50$1.50$1.00$0.01$1.50
61Construction staking curb gutter and curb & gutter (650.5500)LF5,310$1.50$1.50$1.50$1.00$0.01$1.50
62Construction staking curb ramps (650.9000)EACH20$300.00$300.00$300.00$250.00$0.01$300.00
63Construction staking sidewalk (project) 01. 5627-00-71 (650.9500)EACH1$4,000.00$4,000.00$4,000.00$5,000.00$0.01$4,000.00
64Construction staking supplemental control (project) 01. 5627-00-71 (650.9911)EACH1$1,500.00$1,500.00$1,500.00$2,000.00$0.01$1,500.00
65Construction staking supplemental control (project) 02. 5627-00-72 (650.9911)EACH1$1,000.00$1,000.00$1,000.00$2,000.00$0.01$1,000.00
66Sawing asphalt (690.0150)LF493$2.00$2.00$2.00$2.00$1.60$2.50
67Sawing concrete (690.0250)LF459$2.00$2.00$2.00$2.00$2.90$0.50
68Incentive iri ride (740.0440)DOL1,000$1.00$1.00$1.00$1.00$1.00$1.00
69On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,000$5.00$5.00$5.00$5.00$5.00$5.00
70On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS1,320$5.00$5.00$5.00$5.00$5.00$5.00
71Special 01. hydrant assembly (SPV.0060)EACH7$10,899$8,700.00$10,154$10,000$13,000$10,631
72Special 02. water valve 8-inch (SPV.0060)EACH11$3,956.40$2,750.00$3,747.30$3,500.00$5,100.00$4,100.00
73Special 03. 1-inch curb stop and box (SPV.0060)EACH12$347.20$310.00$1,224.25$550.00$630.00$918.00
74Special 04. 1-inch tap and corporation valve (SPV.0060)EACH52$287.20$75.00$764.63$300.00$3,600.00$1,538.00
75Special 05. adjust sanitary manhole (SPV.0060)EACH9$611.45$1,075.00$888.22$1,000.00$680.00$485.00
76Special 07. adjust water valve box (SPV.0060)EACH24$150.00$635.00$500.14$1,000.00$580.00$250.00
77Special 08. water main vertical offset (SPV.0060)EACH2$5,015.16$5,470.00$4,969.86$2,800.00$7,400.00$5,607.00
78Special 09. storm main crossing (SPV.0060)EACH11$2,600.00$1,135.00$1,159.34$1,400.00$1,500.00$900.00
79Special 10. external sanitary manhole seal (SPV.0060)EACH7$474.60$800.00$735.57$415.00$600.00$623.00
80Special 11. manhole sanitary 4FT (SPV.0060)EACH7$6,022.58$4,545.00$5,311.01$7,400.00$6,000.00$6,141.00
81Special 12. connect to existing water main (SPV.0060)EACH7$2,153.41$5,010.00$3,842.44$3,200.00$3,200.00$2,570.00
82Special 13. connect to existing sanitary sewer (SPV.0060)EACH6$1,873.75$7,500.00$3,217.27$1,800.00$4,600.00$1,205.00
83Special 14. construction staking sanitary sewer system (SPV.0060)EACH1$4,000.00$4,000.00$4,000.00$5,000.00$0.01$4,000.00
84Special 15. construction staking water main system (SPV.0060)EACH1$4,000.00$4,000.00$4,000.00$5,000.00$0.01$4,000.00
85Special 16. remove sanitary manholes (SPV.0060)EACH10$500.00$1,225.00$544.15$700.00$750.00$750.00
86Special 01. 8-inch ductile iron water main (SPV.0090)LF2,706$144.48$119.00$149.73$100.00$146.00$168.15
87Special 02. 6-inch ductile iron hydrant lead (SPV.0090)LF110$160.85$165.00$118.05$90.00$151.00$135.00
88Special 03. 1-inch water service pipe (SPV.0090)LF1,242$93.76$87.00$136.28$100.00$36.00$97.50
89Special 04. sanitary sewer lateral (SPV.0090)LF1,540$82.90$90.00$120.39$110.00$190.00$183.13
90Special 05. sanitary sewer PVC, 8- inch (SPV.0090)LF368$116.74$100.00$126.19$145.00$192.00$216.40
91Special 06. sanitary sewer PVC, 10-inch (SPV.0090)LF980$136.02$100.00$162.42$330.00$207.00$261.75
92Special 07. sanitary sewer PVC, 12-inch (SPV.0090)LF1,293$190.53$100.00$198.80$365.00$320.00$308.53
93Special 08. remove existing sanitary sewer main (SPV.0090)LF2,655$2.00$24.00$3.58$0.01$33.25$1.00
WisDOT contract 20260210003: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of February 10, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy